CN210031914U - Assembled inspection shaft - Google Patents
Assembled inspection shaft Download PDFInfo
- Publication number
- CN210031914U CN210031914U CN201920466441.9U CN201920466441U CN210031914U CN 210031914 U CN210031914 U CN 210031914U CN 201920466441 U CN201920466441 U CN 201920466441U CN 210031914 U CN210031914 U CN 210031914U
- Authority
- CN
- China
- Prior art keywords
- section
- well
- well chamber
- rabbet
- standard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Sewage (AREA)
Abstract
本实用新型公开了一种装配式检查井,包括井室、井筒(2)、井室盖板(3)和相互匹配的上企口(4)与下企口(5),井室包括顶节(11)、一节或若干节标准节(12)和底节(13);底节顶部设有上企口,标准节顶部和底部设有上企口和下企口,标准节(12)通过上企口和下企口依次拼接成埋深标准节,埋深标准节通过下企口经上企口与底节匹配安装;顶节底部设有下企口,顶节通过下企口经上企口匹配安装在埋深标准节上;井室盖板匹配安装在顶节的顶部,井筒设在井室盖板上并与井室连通。本实用新型能将预制的井室、井筒和井室盖板采用装配式施工,提高施工效率和质量,能满足井室埋深要求,降低施工成本。
The utility model discloses an assembled inspection well, which comprises a well chamber, a wellbore (2), a well chamber cover plate (3) and an upper groove (4) and a lower groove (5) matched with each other. The well chamber comprises a top Section (11), one or several standard sections (12) and bottom section (13); the top of the bottom section is provided with upper and lower grooves, the top and bottom of the standard section are provided with upper and lower grooves, and the standard section (12) ) The upper and lower tongues are spliced to form a buried depth standard section, and the buried depth standard section is installed through the lower tongue and the upper tongue and the bottom section; the bottom of the top section is provided with a lower tongue, and the top section passes through the lower tongue. It is installed on the standard section of buried depth by matching the upper groove and mouth; the well chamber cover is matched and installed on the top of the top section, and the wellbore is set on the well chamber cover and communicated with the well chamber. The utility model can adopt the prefabricated well chamber, the well bore and the well chamber cover plate to adopt the prefabricated construction, improve the construction efficiency and quality, can meet the well chamber buried depth requirement, and reduce the construction cost.
Description
技术领域technical field
本实用新型涉及市政给排水施工领域,尤其涉及一种装配式检查井。The utility model relates to the field of municipal water supply and drainage construction, in particular to an assembled inspection well.
背景技术Background technique
检查井是为城市地下基础设施的供电、给水、排水、排污、通讯、有线电视、煤气管、路灯线路等维修,安装方便而设置的,每个一定距离设置检查井,便于定期检查附属构筑物。Inspection wells are installed for the maintenance of power supply, water supply, drainage, sewage, communication, cable television, gas pipes, and street light lines of urban underground infrastructure. They are installed for convenient installation. Inspection wells are set at a certain distance to facilitate regular inspection of auxiliary structures.
目前,给排水及其他管道工程的检查井在施工时,均为土方开挖后采用砖砌或者钢筋混凝土现浇。此类传统方法主要存在以下问题:At present, the inspection wells for water supply and drainage and other pipeline projects are constructed with brickwork or reinforced concrete cast-in-place after earthwork excavation. Such traditional methods mainly have the following problems:
1)、检查井埋深较深时需要进行基坑支护,否则容易造成边坡坍塌,危险系数高。1) When the inspection well is buried deep, foundation pit support is required, otherwise it is easy to cause the slope to collapse and the risk factor is high.
2)、检查井采用现浇钢筋混凝土结构或者砖砌结构,材料组织困难,施工质量差,功效低。2) The inspection well adopts the cast-in-place reinforced concrete structure or the brick structure, the material organization is difficult, the construction quality is poor, and the efficiency is low.
发明内容SUMMARY OF THE INVENTION
本实用新型的目的在于提供一种装配式检查井,能将预制的井室、井筒和井室盖板采用装配式施工,提高施工效率和质量,能满足井室埋深要求,降低施工成本。The purpose of the utility model is to provide a prefabricated inspection well, which can use prefabricated well chamber, wellbore and well chamber cover for prefabricated construction, improve construction efficiency and quality, meet well chamber buried depth requirements, and reduce construction costs.
本实用新型是这样实现的:The utility model is realized in this way:
一种装配式检查井,包括井室、井筒、井室盖板和相互匹配的上企口与下企口,井室包括顶节、一节或若干节标准节和底节;底节上预留U型槽口,底节作为基坑支护固定在井底,底节的顶部设有上企口;标准节的顶部和底部分别设有上企口和下企口,一节或若干节标准节通过上企口和下企口依次匹配拼接成埋深标准节,埋深标准节的底部通过下企口经上企口与底节匹配安装;顶节的底部设有下企口,顶节通过下企口经上企口匹配安装在埋深标准节上;井室盖板匹配安装在顶节的顶部,井筒固定设置在井室盖板上并与井室连通。A prefabricated inspection well, comprising a well chamber, a well bore, a well chamber cover, and matching upper and lower grooves, the well chamber includes a top section, one section or several standard sections and a bottom section; U-shaped notch is reserved, the bottom section is fixed at the bottom of the well as the foundation pit support, and the top of the bottom section is provided with an upper groove; the top and bottom of the standard section are respectively provided with an upper groove and a lower groove, one or several sections. The standard section is matched and spliced into a buried depth standard section through the upper tongue and the lower tongue in turn, and the bottom of the buried depth standard section is installed through the lower tongue and the upper tongue and the bottom section; the bottom of the top section is provided with a lower tongue, and the top The joint is installed on the buried depth standard section through the lower tongue and the upper tongue matching; the well chamber cover is matched and installed on the top of the top section, and the wellbore is fixed on the well chamber cover and communicated with the well chamber.
所述的底节的内壁底部设有浇筑企口,底板及流槽浇筑在底节内,底板通过浇筑企口嵌入检查井的井室底部。The bottom of the inner wall of the bottom section is provided with a pouring groove, the bottom plate and the launder are cast in the bottom section, and the bottom plate is embedded in the bottom of the well chamber of the inspection well through the pouring groove.
所述的井筒的底部设有防水凸缘,井室盖板上设有与防水凸缘匹配的防水凹槽,防使井筒匹配安装在井室盖板上。The bottom of the wellbore is provided with a waterproof flange, and the well chamber cover plate is provided with a waterproof groove matched with the waterproof flange to prevent the wellbore from being matched and installed on the well chamber cover plate.
所述的井室盖板与井室的顶部之间设有防水砂浆。Waterproof mortar is provided between the well chamber cover and the top of the well chamber.
所述的防水砂浆的厚度为5cm。The thickness of the waterproof mortar is 5cm.
所述的上企口与下企口的拼接缝内设有止水圈。A water stop ring is arranged in the seam between the upper tongue and the lower tongue.
所述的顶节、标准节、底节、井筒和井室盖板均为工厂预制件。The top section, standard section, bottom section, wellbore and well cover are all factory prefabricated parts.
本实用新型与现有技术相比,具有如下有益效果:Compared with the prior art, the utility model has the following beneficial effects:
1、本实用新型采用沉井方法施工安装,井室兼做沉井支护,不需要单独施工基坑支护,节约工程造价。1. The utility model adopts the caisson method for construction and installation, and the well chamber also serves as the caisson support, so it is not necessary to construct the foundation pit support separately, which saves the project cost.
2、本实用新型采用的井室、井室盖板及井筒均在工厂预制,可采用现场装配式施工,安装便捷,工期短,施工质量好。2. The well chamber, well chamber cover and wellbore adopted by the utility model are all prefabricated in the factory, and can be constructed by on-site assembly, with convenient installation, short construction period and good construction quality.
3、本实用新型通过井室标准节调整检查井的高度,可以适应不同深度的检查井要求。3. The utility model adjusts the height of the inspection well through the standard section of the well room, and can adapt to the requirements of inspection wells of different depths.
附图说明Description of drawings
图1是本实用新型装配式检查井的剖视图;Fig. 1 is the sectional view of the utility model assembled inspection well;
图2是本实用新型装配式检查井的顶节的剖视图;Fig. 2 is the sectional view of the top section of the assembled inspection well of the present invention;
图3是本实用新型装配式检查井的标准节的剖视图;Fig. 3 is the sectional view of the standard section of the assembled inspection well of the present utility model;
图4是本实用新型装配式检查井的底节的剖视图;4 is a cross-sectional view of the bottom section of the assembled inspection well of the present invention;
图5是本实用新型装配式检查井的井筒的剖视图;5 is a cross-sectional view of the wellbore of the fabricated inspection well of the present utility model;
图6是本实用新型装配式检查井的井室盖板的俯视图。Fig. 6 is a top view of the well cover plate of the assembled inspection well of the present invention.
图中,11顶节,12标准节,13底节,131U型槽口,2井筒,21防水凸缘,3井室盖板,31防水凹槽,4上企口,5下企口,6浇筑企口,7底板及流槽。In the figure, 11 top section, 12 standard section, 13 bottom section, 131 U-shaped notch, 2 wellbore, 21 waterproof flange, 3 well chamber cover, 31 waterproof groove, 4 upper tongue, 5 lower tongue, 6 Pouring tongue and groove, 7 base plates and launders.
具体实施方式Detailed ways
下面结合附图和具体实施例对本实用新型作进一步说明。The present utility model will be further described below in conjunction with the accompanying drawings and specific embodiments.
请参见附图1至附图3,一种装配式检查井,包括井室、井筒2、井室盖板3和相互匹配的上企口4与下企口5,井室包括顶节11、一节或若干节标准节12和底节13;请参见附图4,底节13上根据管道直径预留两个向下的U型槽口131,底节13作为基坑支护固定在井底,底节13的顶部设有上企口4;标准节12的顶部和底部分别设有上企口4和下企口5,根据埋深要求采用一节或若干节标准节12通过上企口4和下企口5依次匹配拼接成埋深标准节,埋深标准节的底部通过下企口5经上企口4与底节13匹配安装;顶节11的底部设有下企口5,顶节11通过下企口5经上企口4匹配安装在埋深标准节上,完成井室的安装;井室盖板3匹配安装在顶节11的顶部,井筒2固定设置在井室盖板3上并与井室连通。Please refer to accompanying drawings 1 to 3, an assembled inspection well, including a well chamber, a
请参见附图1和附图4,所述的底节13的内壁底部设有浇筑企口6,底板及流槽7通过素砼二次浇筑在底节13内,底板通过浇筑企口6嵌入检查井的井室底部,起到防水的作用。优选的,浇筑企口6的高度为15cm。Please refer to accompanying drawing 1 and accompanying
请参见附图5和附图6,所述的井筒2的底部设有防水凸缘21,井室盖板3上设有与防水凸缘21匹配的防水凹槽31,防使井筒2匹配安装在井室盖板3上,起到防水的作用。优选的,防水凸缘21的高度为3cm,厚度为3cm。5 and 6, the bottom of the
所述的井室盖板3与井室的顶部之间设有防水砂浆(图中未示出),可起到防水的作用,优选的,防水砂浆的厚度为5cm。Waterproof mortar (not shown in the figure) is provided between the well
所述的上企口4与下企口5的拼接缝内设有止水圈(图中未示出),优选的,可采用橡胶材质的止水圈,起到防水的作用。A water stop ring (not shown in the figure) is provided in the splicing seam between the
所述的顶节11、标准节12、底节13、井筒2和井室盖板3均为工厂预制件,加工、运输方便,运送至现场后即可根据检查井的埋深要求进行下沉安装,根据不同的检查井埋深要求选择合适数量的标准节12,以满足施工要求。The
本实用新型装配式检查井的具体施工工艺如下:The concrete construction technology of the assembled inspection well of the present utility model is as follows:
1、检查井的井室、井筒及井室盖板在工厂预制完成以后运送至现场,检查井采用沉井施工方法下沉安装。井室的管壁厚度为20cm。1. The well room, wellbore and well cover plate of the inspection well shall be transported to the site after the prefabrication in the factory, and the inspection well shall be installed by means of the caisson construction method. The wall thickness of the well chamber is 20cm.
2、先定位下沉井室的底节13,土方在井内开挖,井室兼做沉井支护,通过安装一节或多节标准节12来调整检查井的高度,直至符合设计要求。底节13上预留U型槽口131,使其能匹配管径为100cm的管道安装。2. First locate the
井室的底节13、标准节12、顶节11均采用上企口4和下企口5的连接方式,上企口4和下企口5中间安放橡胶止水圈防水,大大简化了施工工艺。下企口5位于管壁的外侧,上企口4位于管壁的内侧,上企口4和下企口5的厚度均为10cm并匹配卡接,使底节13、标准节12、顶节11在安装时保持内外壁的重合。The
3、井室下沉到设计标高以后开始施工底板及流槽7,底板及流槽7采用混凝土二次浇筑,底节13的管壁下部内侧设置15cm高的浇筑企口6,使底板可以嵌入井室从而起到防水作用,流槽的高度及形式符合相关图集要求即可。3. After the well room sinks to the design elevation, start the construction of the bottom plate and the runner 7. The bottom plate and the runner 7 are made of concrete for secondary pouring, and a 15cm-high pouring
4、安装井室盖板3,井室盖板3的直径与井室的直径相当,井室盖板3与井室之间设置5cm厚的防水砂浆,可在井室与井室盖板3之间起到较好的防水作用。4. Install the
5、在井室盖板3上安装井筒2,井筒2的直径小于井室的直径,位于井室盖板3的侧部,井筒2的底部中间位置设置3*3cm的防水凸缘21,嵌入井室盖板3相应位置的防水凹槽31中,安装时,防水凸缘21插入在防水凹槽31内,起到防水作用。5. Install the
以上仅为本实用新型的较佳实施例而已,并非用于限定实用新型的保护范围,因此,凡在本实用新型的精神和原则之内所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above are only the preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present utility model shall include within the scope of protection of the present invention.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201920466441.9U CN210031914U (en) | 2019-04-08 | 2019-04-08 | Assembled inspection shaft |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201920466441.9U CN210031914U (en) | 2019-04-08 | 2019-04-08 | Assembled inspection shaft |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN210031914U true CN210031914U (en) | 2020-02-07 |
Family
ID=69358257
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201920466441.9U Expired - Fee Related CN210031914U (en) | 2019-04-08 | 2019-04-08 | Assembled inspection shaft |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN210031914U (en) |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111535363A (en) * | 2020-05-15 | 2020-08-14 | 中铁四局集团第三建设有限公司 | Non-excavation pipeline middle section inspection well construction system and construction method thereof |
| CN111764435A (en) * | 2020-06-24 | 2020-10-13 | 安徽华路畅安建材有限公司 | A concrete prefabricated grouting sealed assembly inspection well |
| CN112095747A (en) * | 2020-09-03 | 2020-12-18 | 北京建工土木工程有限公司 | Safe construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline |
| CN112095748A (en) * | 2020-09-03 | 2020-12-18 | 北京建工土木工程有限公司 | Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline |
| CN112112249A (en) * | 2020-09-15 | 2020-12-22 | 北京建工土木工程有限公司 | Rapid construction method for non-stop water touch connection of newly-built sewage pipeline and main pipeline |
| CN112302051A (en) * | 2020-11-06 | 2021-02-02 | 中铁工程装备集团有限公司 | A mechanical shaft structure and its construction method |
| CN112663675A (en) * | 2020-12-21 | 2021-04-16 | 福建鑫远建工有限公司 | Anti-settling inspection well chamber structure and construction method thereof |
| CN114319433A (en) * | 2021-12-22 | 2022-04-12 | 深圳市市政工程总公司 | Work well reverse method prefabricated construction method |
| CN115045379A (en) * | 2022-07-20 | 2022-09-13 | 无锡市政设计研究院有限公司 | Assembled rectangular rainwater inspection well and construction method thereof |
| CN115075365A (en) * | 2022-07-20 | 2022-09-20 | 无锡地铁集团有限公司 | Assembly type circular rainwater inspection well with shallow pipeline burial depth and construction method thereof |
-
2019
- 2019-04-08 CN CN201920466441.9U patent/CN210031914U/en not_active Expired - Fee Related
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111535363A (en) * | 2020-05-15 | 2020-08-14 | 中铁四局集团第三建设有限公司 | Non-excavation pipeline middle section inspection well construction system and construction method thereof |
| CN111764435A (en) * | 2020-06-24 | 2020-10-13 | 安徽华路畅安建材有限公司 | A concrete prefabricated grouting sealed assembly inspection well |
| CN112095747A (en) * | 2020-09-03 | 2020-12-18 | 北京建工土木工程有限公司 | Safe construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline |
| CN112095748A (en) * | 2020-09-03 | 2020-12-18 | 北京建工土木工程有限公司 | Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline |
| CN112112249A (en) * | 2020-09-15 | 2020-12-22 | 北京建工土木工程有限公司 | Rapid construction method for non-stop water touch connection of newly-built sewage pipeline and main pipeline |
| CN112112249B (en) * | 2020-09-15 | 2022-03-11 | 北京建工土木工程有限公司 | Rapid construction method for non-stop water touch connection of newly-built sewage pipeline and main pipeline |
| CN112302051A (en) * | 2020-11-06 | 2021-02-02 | 中铁工程装备集团有限公司 | A mechanical shaft structure and its construction method |
| CN112663675A (en) * | 2020-12-21 | 2021-04-16 | 福建鑫远建工有限公司 | Anti-settling inspection well chamber structure and construction method thereof |
| CN114319433A (en) * | 2021-12-22 | 2022-04-12 | 深圳市市政工程总公司 | Work well reverse method prefabricated construction method |
| CN115045379A (en) * | 2022-07-20 | 2022-09-13 | 无锡市政设计研究院有限公司 | Assembled rectangular rainwater inspection well and construction method thereof |
| CN115075365A (en) * | 2022-07-20 | 2022-09-20 | 无锡地铁集团有限公司 | Assembly type circular rainwater inspection well with shallow pipeline burial depth and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10030792B2 (en) | Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall and manufacturing method thereof | |
| CN104404983B (en) | A kind of ride well device and construction method thereof for jacking construction | |
| CN102162253B (en) | Precipitation construction method employing pipe embedded in deep foundation pits | |
| CN104674847A (en) | Novel assembling type precast concrete urban comprehensive pipe gallery and construction method thereof | |
| CN205530280U (en) | Novel prefabricated two walls unification foundation ditch enclosure system | |
| CN107023061B (en) | Assembled plastic municipal drainage inspection well and construction method | |
| CN214143998U (en) | A layout structure of household sewage collection pipe network along the river | |
| CN207672609U (en) | A kind of foundation pit supporting construction also serves as the pipe gallery of main body | |
| Macaulay | Underground | |
| CN112726784A (en) | Fully-prefabricated PC sewer inspection well component assembly type structure and construction method | |
| CN110924438A (en) | Prefabricated member of assembled rectangular inspection well | |
| JP2001207515A (en) | Underground communal space | |
| CN204401756U (en) | The drop well that reverse construction is set up on original gutter | |
| CN106592635A (en) | Integrated inspection shaft and installation method thereof | |
| CN115075365A (en) | Assembly type circular rainwater inspection well with shallow pipeline burial depth and construction method thereof | |
| CN109797988A (en) | A kind of co-layer draining hard-cover precast block toilet of outer wall provided pipe line groove hole | |
| CN108777470A (en) | A kind of cable duct bank and its construction method | |
| CN217399865U (en) | Assembled precast concrete inspection shaft | |
| CN107152034A (en) | A kind of pipe gallery and its construction method | |
| CN218933931U (en) | A reinforcement structure for deep foundation pit adjacent to existing buildings | |
| CN206090623U (en) | Prefabricated inspection shaft of construction efficient | |
| CN116446514A (en) | Multifunctional drainage inspection well and construction method | |
| CN204532379U (en) | The pre-buried gutter structure of subway sectional tunnel waste water pump house | |
| CN204163178U (en) | Push pipe interval combinations manhole | |
| CN211312560U (en) | A Simple Core Tube Staged Diversion and Drainage Structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200207 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |