CN112095748A - Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline - Google Patents

Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline Download PDF

Info

Publication number
CN112095748A
CN112095748A CN202010916997.0A CN202010916997A CN112095748A CN 112095748 A CN112095748 A CN 112095748A CN 202010916997 A CN202010916997 A CN 202010916997A CN 112095748 A CN112095748 A CN 112095748A
Authority
CN
China
Prior art keywords
pipeline
open caisson
newly
construction
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010916997.0A
Other languages
Chinese (zh)
Inventor
王震
王玉良
王天乐
陈忠良
倪同荣
胡腾云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BCEG Civil Engineering Co Ltd
Original Assignee
BCEG Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BCEG Civil Engineering Co Ltd filed Critical BCEG Civil Engineering Co Ltd
Priority to CN202010916997.0A priority Critical patent/CN112095748A/en
Publication of CN112095748A publication Critical patent/CN112095748A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/16Jointing caissons to the foundation soil, specially to uneven foundation soil

Abstract

The invention relates to the relevant field of municipal engineering pipeline construction, in particular to a quick construction method for non-stop touch joint of a newly-built sewage pipeline and an operating pipeline, which comprises the following steps: excavating a working pit and processing a side slope; prefabricating the open caisson; positioning the open caisson; sinking the open caisson; pouring the bottom of the open caisson and performing anti-seepage treatment; the newly-built pipeline is installed on the open caisson; and cutting the pipeline running in the open caisson and backfilling earthwork to restore the ground. According to the method, the problem of how to quickly touch and connect the newly-built pipeline and the operated pipeline under the condition of not stopping water is solved, the touch and connection work can be effectively ensured to be quickly completed on schedule, the construction cost is reduced in the construction process, the influence on surrounding production and life is reduced, and the potential safety hazard of cracking and water leakage of the operated pipeline is eliminated; in addition, the method has the advantages of high construction speed, capability of ensuring the construction period of the butting connection, safety guarantee, good economic effect and small influence.

Description

Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
Technical Field
The invention relates to the field related to municipal engineering pipeline construction, in particular to a quick construction method for non-stop touch connection of a newly-built sewage pipeline and an operating pipeline.
Background
In the construction of a newly-built sewage pipeline, the collision connection of a newly-built small pipeline and a large pipeline in operation is a common condition in the pipeline construction process, the operated pipeline is in a water-flowing state at the moment, if the two pipelines can be quickly collided, the construction cost can be reduced, the adverse effects on surrounding production and life are reduced, and the potential safety hazard in the construction process can also be reduced.
The existing touch joint construction method has two kinds, the first method is to stop the water supply of the existing pipeline and carry out touch joint construction, the water supply of the running large pipeline is required to be stopped in the method to influence the surrounding production and life, and the local water cut-off in the large pipeline is difficult to realize if an overrunning mode is adopted; the second method is the frogman underwater breaking operation, in a large pipeline, due to the fact that the pipeline water volume and flow velocity are large, visibility is low and the like, the frogman underwater operation difficulty is large, safety risk is high, construction uncertainty is increased, and construction period cannot be guaranteed invisibly.
Therefore, a quick construction method for non-stop water collision connection of the newly-built sewage pipeline and the running pipeline is provided.
Disclosure of Invention
The invention aims to provide a quick construction method for non-stop water touch joint of a newly-built sewage pipeline and an operating pipeline, which aims to solve the problems in the prior art.
In order to achieve the purpose, the invention adopts the following technical scheme:
a quick construction method for non-stop touch joint of a newly-built sewage pipeline and an operation pipeline comprises the following steps:
s1, excavating a working pit and processing a side slope;
s2, prefabricating the open caisson according to a construction drawing, and reserving an inverted U-shaped groove and a reserved opening of a new pipeline on the side wall of the bottom of the prefabricated open caisson;
s3, positioning the open caisson, and temporarily plugging the reserved port of the new pipeline;
s4, sinking the open caisson to a required position;
s5, carrying out bottom sealing treatment on the bottom of the working pit, and pouring construction joints at the bottom of the open caisson and the top of the bottom seal by using impervious concrete after the concrete for bottom sealing treatment is solidified;
s6, plugging a gap between the inverted U-shaped clamping groove and a contact part of a running pipeline;
s7, performing seal breaking treatment on the reserved opening of the new pipeline, and completing installation and plugging treatment of the newly-built pipeline;
s8, waiting for the time when the water quantity in the running pipeline is small, adopting a proper water reducing measure, installing a lifting point at the top of the running pipeline positioned in the open caisson, and utilizing frogman to carry out breaking operation on the running pipeline;
s9, lifting the broken pipeline out of the open caisson;
and S10, backfilling earthwork and recovering the ground.
Preferably, the bottom of the edge angle of the caisson is reinforced after the caisson is prefabricated, and the reinforcing treatment of the bottom of the edge angle of the caisson is performed by double-fluid grouting.
Preferably, the open caisson prefabrication procedure can be performed in the process of working pit excavation and slope treatment.
Preferably, the top of the open caisson is prefabricated with an inspection well.
Preferably, the inspection shaft is a masonry inspection shaft, the top of the inspection shaft is flush with the ground, and the top of the inspection shaft is provided with a concrete well ring and a well cover.
Preferably, during the process of digging the working pit, a crane and a sling are used for carrying out vertical hoisting stabilization on the pipeline dug by the working pit in operation.
Preferably, the sinking position of the open caisson needs to ensure that the pipeline in operation is positioned in the inverted U-shaped groove.
Preferably, the concrete used for the back cover in S5 is quick-setting concrete.
Preferably, the broken pipeline is lifted out of the open caisson in S9 by means of a crane and a sling.
Preferably, when the running pipeline is cut, the number of the hoisting points at the top of the running pipeline is not less than two.
Preferably, the top of the open caisson is surrounded by a rammed bed of coarse sand.
Preferably, the pipe in operation and the open caisson are subjected to roughening treatment.
Compared with the prior art, the invention has the beneficial effects that:
according to the method, the problem of how to quickly touch and connect the newly-built pipeline and the operated pipeline under the condition of not stopping water is solved, the touch and connection work can be effectively ensured to be quickly completed on schedule, the construction cost is reduced in the construction process, the influence on surrounding production and life is reduced, and the potential safety hazard of cracking and water leakage of the operated pipeline is eliminated; in addition, the method has the advantages of high construction speed, capability of ensuring the construction period of the butting connection, safety guarantee, good economic effect and small influence.
Drawings
FIG. 1 is a plan layout view of an inspection well in a rapid construction method for non-stop butting of a newly-built sewage pipeline and an operating pipeline, which is provided by the invention;
FIG. 2 is a cross-sectional view of inspection well operation in the fast construction method of non-stop water collision of the newly-built sewage pipeline and the operation pipeline.
1. An in-service pipeline; 2. quick-setting concrete; 3. sinking a well; 4. a new pipeline reserved port; 5. a medium coarse sand ramming layer; 6. an inspection well; 7. a well cover is provided.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-2, the invention also provides a quick construction method for non-stop touch joint of a newly-built sewage pipeline and an operating pipeline, which comprises the following steps:
s1, excavating a working pit and processing a side slope;
s2, prefabricating the open caisson 3 according to a construction drawing, and reserving an inverted U-shaped groove and a new pipeline reserved opening 4 on the side wall of the bottom of the prefabricated open caisson 3;
s3, positioning the open caisson 3, and temporarily plugging the reserved port 4 of the new pipeline;
s4, sinking the open caisson 3 to a required position;
s5, carrying out bottom sealing treatment on the bottom of the working pit, and pouring construction joints at the bottom of the open caisson 3 and the top of the bottom seal by using impervious concrete after the concrete subjected to the bottom sealing treatment is solidified;
s6, plugging a gap between the inverted U-shaped clamping groove and a contact part of the running pipeline 1;
s7, performing seal breaking treatment on the reserved opening 4 of the new pipeline, and completing installation and plugging treatment of the newly-built pipeline;
s8, waiting for the time when the water quantity in the pipeline 1 is small, adopting proper water reducing measures, installing a lifting point at the top of the pipeline 1 which is positioned in the caisson 3 and is in operation, and utilizing frogman to carry out breaking operation on the pipeline 1 which is in operation;
s9, lifting the broken pipeline out of the open caisson 3;
and S10, backfilling earthwork and recovering the ground.
The purpose of temporarily plugging the new pipeline reserved opening 4 is to prevent the inside of the pipeline reserved opening 4 from being blocked by concrete and influencing the use of the new pipeline reserved opening 4.
Wherein, the inverted U-shaped clamping groove is used for sleeving the open caisson 3 above the pipeline 1 in operation.
In S6, the pouring of the impervious concrete on the construction joint between the bottom of the open caisson 3 and the top of the bottom cover is to prevent the water in the running pipeline 1 from seeping out of the open caisson 3 and causing leakage.
And in the step S8, the sealing of the reserved opening 4 of the new pipeline is broken, the installation and the sealing treatment of the new pipeline are completed, the purpose is to install the new pipeline on the side wall of the open caisson 3, and the condition that sewage leakage does not occur between the new pipeline and the open caisson 3 is ensured.
In this embodiment, further, an inverted U-shaped slot is reserved at the bottom of the open caisson 3 corresponding to the position of the running pipeline 1, so that the open caisson 3 can sink without damaging the running pipeline 1.
In this embodiment, further, a newly-built pipeline can be constructed after the bottom sealing of the open caisson 3 and the plugging of the gap between the reserved inverted U-shaped groove and the running pipeline 1. And after the gap is blocked, the position of the open caisson 3 does not need to be lifted, and related lifting equipment can be removed.
In this embodiment, further, the sunk well 3 is reinforced at the bottom of the cutting edge of the sunk well 3 after the completion of prefabrication, and the reinforcement treatment of the bottom of the cutting edge of the sunk well 3 is performed by means of double-fluid grouting.
The purpose of reinforcing the bottom of the cutting edge of the open caisson 3 by grouting is to prevent the open caisson 3 from sinking at the position of the open caisson 3 in the bottom sealing process and prevent the pipeline 1 in operation from being influenced.
Preferably, the bottom of the cutting edge of the open caisson 3 is reinforced by grouting to prevent the open caisson 3 from sinking in the bottom sealing process.
In this embodiment, further, the open caisson 3 prefabricating process can be performed in the process of working pit excavation and slope treatment.
In this embodiment, further, the top of the open caisson 3 is prefabricated with an inspection well 6.
Preferably, the manhole 6 is a masonry manhole, the top of the manhole 6 is flush with the ground, and the top of the manhole 6 is provided with a concrete well ring and a well cover 7.
In the embodiment, further, in the process of digging the pit in the working pit, the pipeline 1 dug by the working pit is stably vertically hoisted by using a crane and a hanging belt.
In this embodiment, further, the sinking position of the open caisson 3 needs to ensure that the pipeline 1 in operation is located in the inverted U-shaped groove.
In this embodiment, the concrete used for the back cover in S5 is quick-setting concrete 2.
In this embodiment, further, the broken pipeline may be lifted out of the caisson 3 in S9 by using a crane and a sling.
Preferably, the number of hanging points at the top of the running pipe 1 is not less than two when the running pipe 1 is cut.
In this embodiment, further, the top of the open caisson 3 is surrounded by a rammed layer of coarse sand 5. So as to protect the top outer sidewall of the open caisson 3.
In this embodiment, further, the pipe 1 and the open caisson 3 in operation are subjected to roughening treatment, so as to improve the connection stability between the pipe 1 and the open caisson 3 in operation.
The method solves the problem of how to realize the construction method of fast butting between the newly-built small-diameter pipeline and the operated large-diameter pipeline without water supply interruption, reduces the construction cost in the construction process, reduces the influence on surrounding production and life, and has the advantages of high construction speed, safety guarantee, good economic effect and small influence. The sewage pipeline joint device is particularly suitable for the butt joint of a newly-built small-pipe-diameter sewage pipeline and an operated large-pipe-diameter sewage pipeline under the condition of not stopping water. The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (10)

1. A quick construction method for non-stop touch joint of a newly-built sewage pipeline and an operation pipeline is characterized by comprising the following steps:
s1, excavating a working pit and processing a side slope;
s2, prefabricating the open caisson according to a construction drawing, and reserving an inverted U-shaped groove and a reserved opening of a new pipeline on the side wall of the bottom of the prefabricated open caisson;
s3, positioning the open caisson, and temporarily plugging the reserved port of the new pipeline;
s4, sinking the open caisson to a required position;
s5, carrying out bottom sealing treatment on the bottom of the working pit, and pouring construction joints at the bottom of the open caisson and the top of the bottom seal by using impervious concrete after the concrete for bottom sealing treatment is solidified;
s6, plugging a gap between the inverted U-shaped clamping groove and a contact part of a running pipeline;
s7, performing seal breaking treatment on the reserved opening of the new pipeline, and completing installation and plugging treatment of the newly-built pipeline;
s8, waiting for the time when the water quantity in the running pipeline is small, adopting a proper water reducing measure, installing a lifting point at the top of the running pipeline positioned in the open caisson, and utilizing frogman to carry out breaking operation on the running pipeline;
s9, lifting the broken pipeline out of the open caisson;
and S10, backfilling earthwork and recovering the ground.
2. The rapid construction method for the non-stop water collision connection of the newly-built sewage pipeline and the operation pipeline according to claim 1, wherein the sunk well is subjected to reinforcement treatment on the bottom of the sunk well cutting edge after the completion of prefabrication, and the reinforcement treatment on the bottom of the sunk well cutting edge adopts a double-fluid grouting reinforcement treatment mode.
3. The method of claim 1, wherein the open caisson prefabrication process is performed during excavation and slope treatment of the working pit.
4. The rapid construction method for the non-stop water collision of the newly-built sewage pipeline and the operation pipeline according to claim 1, wherein an inspection well is prefabricated at the top of the open caisson.
5. The method of claim 1, wherein the vertical hoisting of the newly-built sewage pipeline is stabilized by a crane and a sling during the excavation of the pit.
6. The method of claim 1, wherein the sinking position of the open caisson is determined so that the pipeline in operation is located in the inverted U-shaped groove.
7. The method of claim 1, wherein the concrete used for sealing the bottom in S5 is quick-setting concrete.
8. The method of claim 1, wherein the broken sewage pipes are lifted out of the caisson in step S9 by a crane and a sling.
9. The method of claim 1, wherein the top of the open caisson is surrounded by a rammed coarse sand layer.
10. The method as claimed in claim 1, wherein the piping is roughened to the open caisson.
CN202010916997.0A 2020-09-03 2020-09-03 Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline Pending CN112095748A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010916997.0A CN112095748A (en) 2020-09-03 2020-09-03 Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010916997.0A CN112095748A (en) 2020-09-03 2020-09-03 Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline

Publications (1)

Publication Number Publication Date
CN112095748A true CN112095748A (en) 2020-12-18

Family

ID=73757652

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010916997.0A Pending CN112095748A (en) 2020-09-03 2020-09-03 Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline

Country Status (1)

Country Link
CN (1) CN112095748A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113833085A (en) * 2021-11-12 2021-12-24 中建七局安装工程有限公司 Maintenance method for inspection well without stopping water supply

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2146127A2 (en) * 2008-07-17 2010-01-20 Shonan Gosei - Jushi Seisakusho K.K. Rehabilitating pipe segment and existing pipe rehabilitation method using same
CN108222223A (en) * 2017-11-20 2018-06-29 杭州市市政工程集团有限公司 A kind of inspection shaft and method for cutting over for having pressure sewage conduct cutover for Large Diameter Pipeline
CN108222220A (en) * 2018-01-31 2018-06-29 杭州市市政工程集团有限公司 The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation
CN108867814A (en) * 2018-07-18 2018-11-23 中国水利水电第七工程局有限公司 It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method
CN109403444A (en) * 2018-11-26 2019-03-01 广西建工集团第建筑工程有限责任公司 The underground reinforced concrete supplying drainage of major diameter is not cut off the water connecting device and method
CN109736416A (en) * 2019-01-24 2019-05-10 安徽省公路桥梁工程有限公司 The old and new's sewage conduct deep well point connection structure and construction method
CN109972719A (en) * 2019-03-15 2019-07-05 上海宇联给水工程有限公司 A kind of pipe device of paying wages of not cutting off the water supply for drainage pipeline
CN210031914U (en) * 2019-04-08 2020-02-07 中国建筑第八工程局有限公司 Assembled inspection shaft

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2146127A2 (en) * 2008-07-17 2010-01-20 Shonan Gosei - Jushi Seisakusho K.K. Rehabilitating pipe segment and existing pipe rehabilitation method using same
CN108222223A (en) * 2017-11-20 2018-06-29 杭州市市政工程集团有限公司 A kind of inspection shaft and method for cutting over for having pressure sewage conduct cutover for Large Diameter Pipeline
CN108222220A (en) * 2018-01-31 2018-06-29 杭州市市政工程集团有限公司 The construction method of new and old sewage pipe connection in a kind of sewage pipe displacement transformation
CN108867814A (en) * 2018-07-18 2018-11-23 中国水利水电第七工程局有限公司 It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method
CN109403444A (en) * 2018-11-26 2019-03-01 广西建工集团第建筑工程有限责任公司 The underground reinforced concrete supplying drainage of major diameter is not cut off the water connecting device and method
CN109736416A (en) * 2019-01-24 2019-05-10 安徽省公路桥梁工程有限公司 The old and new's sewage conduct deep well point connection structure and construction method
CN109972719A (en) * 2019-03-15 2019-07-05 上海宇联给水工程有限公司 A kind of pipe device of paying wages of not cutting off the water supply for drainage pipeline
CN210031914U (en) * 2019-04-08 2020-02-07 中国建筑第八工程局有限公司 Assembled inspection shaft

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113833085A (en) * 2021-11-12 2021-12-24 中建七局安装工程有限公司 Maintenance method for inspection well without stopping water supply
CN113833085B (en) * 2021-11-12 2023-06-20 中建七局安装工程有限公司 Maintenance method for inspection well without stopping water

Similar Documents

Publication Publication Date Title
US11143027B2 (en) Rectangular working well with preset pipe jacking hole and sliding back wall in water-rich stratum and construction method thereof
CN103334444B (en) A kind of method for blocking of foundation pit dewatering well pressure release type
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN102797266B (en) Well sealing waterproof construction method for dewatering well
CN109778992B (en) Horse riding well device for pipeline construction and construction method thereof
CN110485468B (en) Permanent circular working well with water-rich stratum preset jacking pipe door opening and construction method thereof
CN103015456A (en) Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure
CN114150749A (en) Construction method for non-stop connection of new and old sewage wells
CN104929135A (en) Deep foundation pit underground diaphragm wall enclosure structure and chemical churning pile water stop construction method thereof
CN103628507A (en) Anti-floating construction method for passing through seabed shallow buried soil for pipe jacking
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN112095748A (en) Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
CN211816279U (en) New and old ground is wall interface processing structure even
CN212641468U (en) Pit-in-pit rapid construction structure
CN104846837B (en) The construction method of ultra-deep well in a kind of bright draining foundation ditch
CN108035357B (en) Filling pile construction scheme and its funnel
CN204456228U (en) A kind of diaphragm wall fast plugging device
CN105332382A (en) River-adjacent-foundation-pit island-building cofferdam clay sealing construction method
KR100880367B1 (en) Process for constructing diffuser in the water
CN112095747A (en) Safe construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
CN110485465B (en) Circular working well with water-rich stratum with preset pipe jacking door opening and construction method of circular working well
CN114197508A (en) Easy-sealing water draining device, manufacturing method and using method thereof
CN113175058A (en) Existing underground jacking pipe access construction method
CN110565692A (en) construction method for steel bar and formwork of reverse construction method construction joint
CN111894103A (en) Pipe jacking connection guide row structure and pipe jacking connection method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201218

RJ01 Rejection of invention patent application after publication