CN108867814A - It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method - Google Patents

It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method Download PDF

Info

Publication number
CN108867814A
CN108867814A CN201810791487.8A CN201810791487A CN108867814A CN 108867814 A CN108867814 A CN 108867814A CN 201810791487 A CN201810791487 A CN 201810791487A CN 108867814 A CN108867814 A CN 108867814A
Authority
CN
China
Prior art keywords
existing sewage
sewage network
branch pipe
well
newly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810791487.8A
Other languages
Chinese (zh)
Inventor
韩龙伟
文杰
田锦虎
刘正刚
张彤炜
周书东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 7 Co Ltd
Original Assignee
Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 7 Co Ltd filed Critical Sinohydro Bureau 7 Co Ltd
Priority to CN201810791487.8A priority Critical patent/CN108867814A/en
Publication of CN108867814A publication Critical patent/CN108867814A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F5/025Manhole shafts or other inspection chambers; Snow-filling openings; accessories provided with a liner

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

The present invention provide it is a kind of newly-built cut dirty branch pipe and existing sewage network is plugged into engineering method, include the following steps:(1) physical prospecting verification is carried out to existing sewage network, determines the structure of the existing sewage network;(2) it constructs to active well and received well, the received well uses reverse construction;(3) dirty branch pipe newly-built will be cut by the active well push pipe to the received well, then be plugged into the existing sewage network;(4) after the completion of described newly-built section dirty branch pipe is plugged into the existing sewage network, the existing sewage network is subjected to water conservancy diversion, water conservancy diversion carries out notch after the completion, it is ensured that the existing sewage network is connected to the newly-built dirt time branch pipe that cuts.Engineering method provided by the invention of plugging into, both the normal water flowing of existing sewage network had been can guarantee, the influence to ambient enviroment can be reduced again, and generally process is simple, construction efficiency is high, construction cost is low, is of great significance to newly-built section of dirty branch pipe with plugging into for existing sewage network.

Description

It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method
Technical field
It plugs into field the invention belongs to sewage pipe, more particularly to a kind of newly-built cut a dirty branch pipe and plug into existing sewage network Engineering method.
Background technique
Most domestic Urban Underground sewage network project under construction is to cut dirty branch pipeline network construction at present, need to be with city early period The built existing sewage network connection in city, and sewage is concentrated to sewage treatment plant, handle rear discharge or recycling up to standard.It is conventional Connection modes are that open caisson is plugged into technique, but tradition technique of plugging into has the disadvantages that:
(1) existing pipeline can not be protected during plain sequence open caisson, is easy to damage surrounding buildings and pipeline;
(2) building platform is needed when constructing, construction speed is slow, the construction time is long, security risk is high;
(3) sewage guide project amount is huge, and construction cost is high;
(4) construction noise is big, travel fatigue is more, is affected to surrounding resident life.
Therefore, the work of plugging into that a kind of process is simple, work efficiency is high, security risk is small, small to surrounding resident life interference is needed Method.
Summary of the invention
That the purpose of the present invention is to provide a kind of processes is simple, work efficiency is high, security risk is small it is newly-built cut dirty branch pipe with The engineering method of plugging into of existing sewage network.
To achieve the above object, the present invention, which provides, a kind of newly-built cuts dirty branch pipe and existing sewage network is plugged into engineering method, packet Include following steps:
(1) physical prospecting verification is carried out to existing sewage network, determines the structure of existing sewage network;
(2) it constructs to active well and received well, the received well uses reverse construction, and the active well is for pushing up Pipe is newly-built to cut dirty branch pipe to the received well, the received well be used to receive with the existing sewage network plug into it is described newly It builds and cuts dirty branch pipe;
(3) by it is described it is newly-built cut dirty branch pipe by the active well push pipe to the received well, then with the existing dirt Pipe network is plugged into;
(4) after the completion of described newly-built section dirty branch pipe and the existing sewage network are plugged into, by the existing sewage pipe Net carries out water conservancy diversion, and notch is carried out after the completion of water conservancy diversion, it is ensured that the existing sewage network is connected to described newly-built section dirty branch pipe.Tool Body, use the cooperation of diamond rope saw and diamond water drilling to carry out notch to connection under the conditions of the interim support top of I-steel, Compare static blasting, manually abolish, engineering one-time investment has been reduced to a great extent.
Preferably, further including between step (1) and step (2):
(11) geological state of the existing sewage network is verified in analysis, understands the details of underground utilities;
(12) surveying setting-out, it is ensured that the position of active well and received well;
(13) foundation pit construction is carried out deep pit monitor and is gone along with sb. to guard him.
It reconnoitres geological state, raw data acquisition is carried out to existing sewage network, such as buried depth, trend, cross dimensions, material Deng, so as to determine it is newly-built cut smoothly plugging into for dirty branch pipe and existing sewage network, improve work efficiency of plugging into.
Preferably, the foundation pit surrounding is provided with gutter in step (13).Specifically, the gutter is according to the base Pit edge is no less than 2m.
Preferably, the trapezoidal structure of the retaining wall of the received well.The retaining wall of trapezium structure facilitates constructor and is pacifying It when full accident, is quickly withdrawn by the step between each trapezoidal retaining wall, improves safety coefficient.
Preferably, in step (2), the received well construction method includes:
(2a) carries out Construction of High Pressure Jet Grouting Pile, forms the seepproof screen of the received well outer wall;
(2b) is protected in the seepproof screen inner excavation first segment heatable adobe sleeping platform in first segment heatable adobe sleeping platform inner wall setting first segment Wall;
(2c) repeats step (2b), in the second section of seepproof screen inner excavation heatable adobe sleeping platform, in the second section heatable adobe sleeping platform inner wall Second section retaining wall is set, is so repeated, until completing final section retaining wall;
After the completion of (2d) all panelling constructions, back cover is carried out, the received well is formed.
Received well uses reverse construction, and construction efficiency is high, construction cost is low.Using Construction of High Pressure Jet Grouting Pile, construction is accounted for Ground less, with small vibration, low noise, it is smaller to surrounding environment influence.
Preferably, the construction procedure of the retaining wall includes:Reinforcing bar is installed in each heatable adobe sleeping platform inner wall, is set at reinforcement location Template is set, the casting concrete at template carries out concrete curing after the completion of pouring, form removable is finally formed retaining wall.
Preferably, bottom sealing method described in step (2d) includes:Final section heatable adobe sleeping platform bottom be successively laid with bottoming, Concrete bed course and reinforced concrete floor carry out back cover.
Preferably, status well is not contained in the existing sewage network, described newly-built section dirty branch pipe and the existing dirt Plugging into for pipe network is a little located in the received well.
Preferably, step (3) specifically includes:
(3a) broken hole formation on the received well is plugged into hole, it is described plug into hole for receive and the existing sewage Described newly-built section dirty branch pipe that pipe network is plugged into;
(3b) by it is described it is newly-built cut dirty branch pipe by the active well push pipe to the hole of plugging into, then directly and institute Existing sewage network is stated to plug into.
Preferably, containing status well in the existing sewage network, is created described in the active well push pipe and cut dirty branch pipe After to the received well, push pipe is further continued for the status well until plugging into the existing sewage network.
Preferably, step (3) specifically includes:
(3a ') described on the received well newly-built cuts dirty branch pipe and the existing sewage network is plugged into and broken at position Hole forms hole of plugging into, and the hole of plugging into is connected to the received well;
(3b ') opens up reserved connecting port on the status well, and the newly-built dirt time branch pipe that cuts may pass through the hole of plugging into Mouthful to the reserved connecting port, and plug into the existing sewage network;
(3c ') carries out closure and guide to the existing sewage network in the status well;
It is created described in (3d ') push pipe and cuts a dirty branch pipe and pass through the hole of plugging into the reserved connecting port, then and institute Existing sewage network is stated to plug into.
Preferably, further including between step (3a ') and step (3b '):It pours to form chute in the reception bottom, slip Slot can be used for transport concrete, carry out closure and guide to existing pipe network so as to subsequent.
Compared with prior art, it is provided by the invention it is newly-built cut dirty branch pipe and existing sewage network is plugged into engineering method, opening Begin to carry out physical prospecting verification before construction to job location, understand the structure of existing sewage network, with determine it is newly-built cut dirty branch pipe with The connection modes of existing sewage network, guarantee to plug into goes on smoothly.Received well uses reverse construction, can preferably protect Existing pipeline, reduces the construction guide time, and construction efficiency is high;Do not need that building platform, workload are small, labor intensity is low; Process is simple, security risk is small, noise is few, influences on surrounding resident life less;Construction material is simple and easy to get, and the time is short, applies Work is at low cost.Engineering method provided by the invention of plugging into not only can guarantee the normal water flowing of existing sewage network, but also can reduce to ring around The influence in border, generally process are simple, construction efficiency is high, construction cost is low, cut dirty branch pipe and existing sewage network to newly-built Plug into and be of great significance.
Detailed description of the invention
Fig. 1, which is that the present invention is newly-built, cuts dirty branch pipe and existing sewage network is plugged into the flow chart of engineering method;
Fig. 2, which is that the embodiment of the present invention 1 is newly-built, cuts dirty branch pipe and existing sewage network connecting structure schematic diagram;
Fig. 3, which is that the embodiment of the present invention 2 is newly-built, cuts dirty branch pipe and existing sewage network connecting structure schematic diagram.
Specific embodiment
For the technical solution, construction feature, the technical effect realized that the present invention will be described in detail, below in conjunction with specific implementation Mode simultaneously cooperates attached drawing to be explained in detail.
Referring to Fig. 1, the newly-built engineering method of plugging into for cutting dirty branch pipe and existing sewage network provided by the present application, including step:
(1) physical prospecting verification is carried out to existing sewage network, determines the structure of existing sewage network;Consult previously existing sewage The related data of pipe network, and carry out verifying on the spot and investigate, the structure of existing sewage network is determined, for example, it is determined whether containing There is status well, to formulate subsequent operating method of specifically plugging into.Status well is draining, the blowdown for Urban Underground infrastructure Maintenance, it is easy for installation and setting.It is generally located at pipeline intersection, turning, caliber or gradient change and straight line pipeline section On locate at a certain distance, be easy for the auxiliary construction inspected periodically.
(2) it constructs to active well and received well, vertical transport, equipment peace is used as in active well, that is, construction by pipeline jacking method The shaft structure that dress, water and electricity supply, personnel enter and leave, specifically, active well, to received well, connect for the newly-built dirt time branch pipe that cuts of push pipe It receives well and is used to receive the newly-built section of dirty branch pipe plugged into existing sewage network, received well uses reverse construction.Active well is used In the newly-built dirt time branch pipe that cuts of push pipe to received well, newly-built section of dirty branch pipe can be passed through buried pipe without excavating ground in this way The barriers such as line are delivered to received well, can largely reduce the influence to ambient enviroment;Received well uses reverse construction, Compared to traditional sequence open caisson engineering method, contrary sequence method can be very good to protect existing subterranean pipe line structure, and process is simple, and pacify Overall coefficient is high.
(3) dirty branch pipe newly-built will be cut by active well push pipe to received well, then be plugged into existing sewage network;Root The factually structure of the existing sewage network in border newly-built will first cut dirty branch pipe by active well push pipe to received well, then according to reality Demand of plugging into, determine and plug into position, cut a dirty branch pipe so that newly-built and plug into existing sewage network.
(4) after the completion of newly-built section of dirty branch pipe and existing sewage network are plugged into, existing sewage network is subjected to water conservancy diversion, is led Notch is carried out after the completion of stream, it is ensured that existing sewage network is connected to newly-built section of dirty branch pipe.Notch is carried out again after the completion of water conservancy diversion, really Guarantor plugs into precision, and guarantee is plugged into quality.
In the construction process, to improve construction precision, further include between step (1) and step (2):
(11) geological state of existing sewage network is verified in analysis, understands the details of underground utilities;Determining work It before well and received well position, needs to analyze local geological state, for the heavy of geologic feature and different geological stratifications The features such as product time, select suitable construction method and construction tool.The survey of underground utilities is carried out simultaneously, it is ensured that is being applied The normal operation of underground utilities during work.
(12) surveying setting-out, it is ensured that the position of active well and received well;The work such as shaft centerline measurement are carried out, active well is set With the construction location of received well.
(13) foundation pit construction is carried out deep pit monitor and is gone along with sb. to guard him.According to geological state and the architectural environment of surrounding, excavation pit, And the safety for carrying out foundation pit goes along with sb. to guard him work, and gutter is arranged in foundation pit surrounding, provides basic working space for subsequent construction engineering method.
With reference to the accompanying drawing, for different existing sewage networks, newly-built section of dirty branch pipe and existing sewage is described in detail The engineering method of plugging into of pipe network.
Embodiment 1
In the present embodiment, existing sewage network does not contain status well.
Referring to fig. 2, the engineering method of plugging into for creating the existing sewage network for cutting dirt time branch pipe and not containing status well specifically includes Following steps:
(1) physical prospecting verification is carried out to existing sewage network, determines the structure of existing sewage network 100, especially determines existing Whether contain status well in sewage network.
(11) geological state of existing sewage network is verified in analysis, understands the details of underground utilities.
(12) surveying setting-out, it is ensured that the position of active well 200 and received well 300.In the present embodiment, existing sewage network Status well is not contained in 100, therefore, the setting of the position of received well 300 cuts dirty branch pipe 400 and both whether there is or not sewage networks newly-built At 100 plug into, a little it is located in received well 300 so that plugging into.
(13) foundation pit construction is carried out deep pit monitor and is gone along with sb. to guard him.
(2) it constructs to active well 200 and received well 300, received well 300 uses reverse construction, and active well 200 is used Dirty branch pipe 400 is cut to received well 300 in push pipe is newly-built, received well 300 for receive plug into existing sewage network 100 it is new It builds and cuts dirty branch pipe 400.In the present embodiment, it is provided with reserved opening 201 on active well 200, cuts dirty branch for push pipe is newly-built Pipe 400 is used.The trapezoidal structure of the retaining wall of received well 300.The detailed process of reverse construction received well 300 includes:(2a) is carried out Construction of High Pressure Jet Grouting Pile forms the seepproof screen 301 of 300 outer wall of received well;(2b) is in 301 inner excavation first segment soil of seepproof screen Hole excavates heatable adobe sleeping platform and uses mechanical excavation, machine dig less than place hand excavation can be used, manual cleaning soil after the completion of excavation First segment retaining wall 302 then is arranged in first segment heatable adobe sleeping platform inner wall, wherein the construction procedure of retaining wall includes in hole:In each heatable adobe sleeping platform inner wall Reinforcing bar is installed, template is set at reinforcement location, the casting concrete at template carries out concrete curing after the completion of pouring, supports Shield need to be completed to carry out in 12h pouring, and curing time is no less than 28 round the clock, and form removable is finally formed retaining wall, and template is torn open Except rear concrete surface should add covering, prevent solar exposure and cold wave from attacking;(2c) repeats step (2b), in seepproof screen 301 Portion continues to excavate the second section heatable adobe sleeping platform, and the second section retaining wall 303 is arranged in the second section heatable adobe sleeping platform inner wall, so repeats, until completing last One section retaining wall;After the completion of (2d) all panelling constructions, back cover is carried out, forms received well;When the form removable of final section retaining wall After can carry out back cover, when back cover, be successively laid with bottoming, concrete bed course and reinforced concrete floor in final section heatable adobe sleeping platform bottom Complete back cover, it should be noted that before back cover, final section heatable adobe sleeping platform substrate need to be dug to designed elevation, exclude well internal water accumulation, To backbreaking, part should backfill sandstone, to meet construction requirement.
(3) newly-built will cut dirty branch pipe 400 by 200 push pipe of active well to received well 300, then with existing sewage network 100 plug into.Concrete operation step includes:(3a) broken hole on received well 300 forms hole 304 of plugging into, and broken hole is used and taken Core drilling machine or pneumatic pick abolish hole by size of pipe and tubing, and hole 304 of plugging into is created for receiving with what existing sewage network 100 was plugged into Cut dirty branch pipe 400;(3b) cuts dirty branch pipe 400 by 200 push pipe of active well to hole 304 of plugging into, then directly for newly-built It plugs into existing sewage network 100.
(4) it is newly-built cut a dirty branch pipe 400 and plug into existing sewage network 100 after the completion of, by existing sewage network 100 into Row water conservancy diversion, water conservancy diversion carry out notch after the completion, it is ensured that existing sewage network 100 is connected to the newly-built dirt time branch pipe 400 that cuts.
Embodiment 2
Referring to Fig. 3, in the present embodiment, existing sewage network 100 ' contains status well 500, the present embodiment and embodiment phase Than in addition to position is arranged in received well 300 ' and step (3) concrete operations are different, remaining is all the same.
In the present embodiment, since existing sewage network 100 ' contains status well 500, the setting of received well 300 ' exists Near status well 500, which, which can be reduced, destroys 500 structure of status well, greatly shorten existing pipe network 100 ' block or The guide time, construction cost is effectively reduced.Active well 200 ' by after newly-built 400 ' push pipe to received well 300 ' of sewage network, followed by Continuous push pipe is to status well 500, until can plug into existing sewage network 100 '.
In the present embodiment, step (3) newly-built will cut dirty branch pipe 400 ' by 200 ' push pipe of active well to received well 300 ', Then plug into existing sewage network 100 '.Concrete operation step includes:The newly-built section of dirt of (3a ') on received well 300 ' The broken hole formation at position of plugging into of secondary branch pipe 400 ' and existing sewage network 100 ' is plugged into hole 304 ', and hole 304 ' of plugging into is set as Two, and two holes 304 ' of plugging into are connected to received well 300 ', pass through received well 200 ' for the newly-built dirt time branch pipe 400 ' that cuts; (3b ') opens up reserved connecting port 501 on status well 500, newly-built to cut a dirty branch pipe 400 ' and may pass through hole 304 ' of plugging into pre- Connecting port 501 is stayed, and is plugged into existing sewage network 100 ';(3c ') is to the existing sewage network 100 ' in status well 500 Carry out closure and guide;(3d ') push pipe creates a section dirty branch pipe 100 ' and extremely reserves connecting port 501 across hole 304 ' of plugging into, with It plugs into afterwards with existing sewage network 100 '.It should be noted that before carrying out step (3b '), it is suitable to guarantee to plug into Benefit carries out, and after it will create section dirty 400 ' push pipe to received well 300 ' of branch pipe, is being received according to push pipe pipeline absolute altitude and the gradient 300 ' bottom of well pours to form chute 305, and chute 305 can be used for transport concrete, blocks so as to subsequent to existing pipe network And guide.
The engineering method in conclusion newly-built section of dirty branch pipe provided by the invention and existing sewage network are plugged into, is starting to construct Before, physical prospecting verification is carried out to job location, understands the structure of existing sewage network, to determine newly-built section of dirty branch pipe and existing dirt The connection modes of pipe network, guarantee to plug into goes on smoothly.Received well uses reverse construction, can preferably protect existing pipe Road, reduces the construction guide time, and construction efficiency is high;Do not need that building platform, workload are small, labor intensity is low;Process letter List, security risk is small, noise is few, influences on surrounding resident life less;Construction material is simple and easy to get, and the time is short, construction cost It is low.Engineering method provided by the invention of plugging into not only can guarantee the normal water flowing of existing sewage network, but also can reduce the shadow to ambient enviroment It rings, generally process is simple, construction efficiency is high, construction cost is low, plugs into newly-built section of dirty branch pipe with existing sewage network It is of great significance.
The above disclosure is only a preferred example of the present invention, and the scope of the invention cannot be limited thereby, Therefore equivalent changes made in accordance with the claims of the present invention belong to the range that the present invention is covered.

Claims (12)

  1. The engineering method 1. newly-built section of dirty branch pipe of one kind and existing sewage network are plugged into, which is characterized in that include the following steps:
    (1) physical prospecting verification is carried out to existing sewage network, determines the structure of the existing sewage network;
    (2) it constructs to active well and received well, the received well uses reverse construction, and the active well is new for push pipe It builds and cuts dirt time branch pipe to the received well, the received well is used to receive described newly-built section to plug into the existing sewage network Dirty branch pipe;
    (3) by it is described it is newly-built cut dirty branch pipe by the active well push pipe to the received well, then with the existing sewage pipe Net is plugged into;
    (4) it is described it is newly-built cut a dirty branch pipe and after the completion of the existing sewage network is plugged into, by the existing sewage network into Row water conservancy diversion, water conservancy diversion carry out notch after the completion, it is ensured that the existing sewage network is connected to the newly-built dirt time branch pipe that cuts.
  2. 2. engineering method of plugging into as described in claim 1, wherein further include between step (1) and step (2):
    (11) geological state of the existing sewage network is verified in analysis, understands the details of underground utilities;
    (12) surveying setting-out, it is ensured that the position of active well and received well;
    (13) foundation pit construction is carried out deep pit monitor and is gone along with sb. to guard him.
  3. 3. engineering method of plugging into as claimed in claim 2, wherein in step (13), the foundation pit surrounding is provided with gutter.
  4. 4. engineering method of plugging into as described in claim 1, wherein the trapezoidal structure of the retaining wall of the received well.
  5. 5. engineering method of plugging into as described in claim 1, wherein in step (2), the received well construction method includes:
    (2a) carries out Construction of High Pressure Jet Grouting Pile, forms the seepproof screen of the received well outer wall;
    First segment retaining wall is arranged in the seepproof screen inner excavation first segment heatable adobe sleeping platform, in the first segment heatable adobe sleeping platform inner wall in (2b);
    (2c) repeats step (2b), in the second section of seepproof screen inner excavation heatable adobe sleeping platform, is arranged in the second section heatable adobe sleeping platform inner wall Second section retaining wall so repeats, until completing final section retaining wall;
    After the completion of (2d) all panelling constructions, back cover is carried out, the received well is formed.
  6. 6. plugging into engineering method as claimed in claim 5, wherein the construction procedure of the retaining wall includes:In each heatable adobe sleeping platform inner wall Reinforcing bar is installed, template is set at reinforcement location, the casting concrete at template carries out concrete curing after the completion of pouring, most Form removable is formed into retaining wall afterwards.
  7. 7. plugging into engineering method as claimed in claim 6, wherein bottom sealing method described in step (2d) includes:In final section soil Hole bottom is successively laid with bottoming, concrete bed course and reinforced concrete floor and carries out back cover.
  8. 8. engineering method of plugging into as described in claim 1, wherein status well is not contained in the existing sewage network, it is described newly-built It cuts dirty branch pipe and plugging into for the existing sewage network is a little located in the received well.
  9. 9. engineering method of plugging into as claimed in claim 8, wherein step (3) specifically includes:
    (3a) broken hole formation on the received well is plugged into hole, it is described plug into hole for receive and the existing sewage network The described newly-built section dirty branch pipe plugged into;
    (3b) by it is described it is newly-built cut dirty branch pipe by the active well push pipe to the hole of plugging into, then directly with it is described both There is sewage network to plug into.
  10. 10. engineering method of plugging into as described in claim 1, wherein contain status well, the active well in the existing sewage network It is created described in push pipe after cutting dirty branch pipe to the received well, is further continued for push pipe to the status well until with the existing sewage Pipe network is plugged into.
  11. 11. engineering method of plugging into as claimed in claim 10, wherein step (3) specifically includes:
    (3a ') described on the received well newly-built cuts dirty branch pipe and the existing sewage network is plugged into broken hole shape at position At hole of plugging into, the hole of plugging into is connected to the received well;
    (3b ') opens up reserved connecting port on the status well, it is described it is newly-built cut a dirty branch pipe and may pass through described plug into hole extremely The reserved connecting port, and plug into the existing sewage network;
    (3c ') carries out closure and guide to the existing sewage network in the status well;
    Created described in (3d ') push pipe and cut a dirty branch pipe and pass through the hole of plugging into the reserved connecting port, then with it is described both There is sewage network to plug into.
  12. 12. engineering method of plugging into as claimed in claim 11, wherein further include between step (3a ') and step (3b '):Described Bottom is received to pour to form chute.
CN201810791487.8A 2018-07-18 2018-07-18 It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method Pending CN108867814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810791487.8A CN108867814A (en) 2018-07-18 2018-07-18 It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810791487.8A CN108867814A (en) 2018-07-18 2018-07-18 It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method

Publications (1)

Publication Number Publication Date
CN108867814A true CN108867814A (en) 2018-11-23

Family

ID=64303028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810791487.8A Pending CN108867814A (en) 2018-07-18 2018-07-18 It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method

Country Status (1)

Country Link
CN (1) CN108867814A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736416A (en) * 2019-01-24 2019-05-10 安徽省公路桥梁工程有限公司 The old and new's sewage conduct deep well point connection structure and construction method
CN110080369A (en) * 2019-05-20 2019-08-02 中国二十冶集团有限公司 A kind of intersection blowdown pipeline construction method for not interrupting blowdown
CN110306581A (en) * 2019-07-31 2019-10-08 广东省源天工程有限公司 One kind new old pipeline connection well and its construction method in water rich strata
CN111236387A (en) * 2020-01-17 2020-06-05 中铁十二局集团有限公司 Construction method for connecting newly-built sewage pipe with existing sewage pipe
CN111853418A (en) * 2020-07-02 2020-10-30 深圳市市政工程总公司 Construction method for pipeline repair
CN112095748A (en) * 2020-09-03 2020-12-18 北京建工土木工程有限公司 Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
CN112095747A (en) * 2020-09-03 2020-12-18 北京建工土木工程有限公司 Safe construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
CN112282029A (en) * 2020-11-05 2021-01-29 上海交通建设总承包有限公司 Connection construction method for urban high-water-level large-diameter reinforced concrete sewage pipeline
CN112982425A (en) * 2021-02-01 2021-06-18 中国电建集团市政规划设计研究院有限公司 Method for reinforcing open caisson and existing channel
CN113309900A (en) * 2021-06-24 2021-08-27 江苏广吴建设园林有限公司 Non-water-cut-off construction method for connecting branch pipe of concrete water supply pipeline
CN116290282A (en) * 2023-04-23 2023-06-23 中铁一局集团市政环保工程有限公司 Construction method for connecting new and old pipelines

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07216921A (en) * 1994-01-28 1995-08-15 Sanpori:Kk Catch basin
CN204876019U (en) * 2015-08-20 2015-12-16 宁波市新亚建设有限公司 Reverse construction method well that old and new's pipeline was linked up
CN107859145A (en) * 2017-11-17 2018-03-30 广州市自来水工程公司 A kind of drainpipe is plugged into construction method under water

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07216921A (en) * 1994-01-28 1995-08-15 Sanpori:Kk Catch basin
CN204876019U (en) * 2015-08-20 2015-12-16 宁波市新亚建设有限公司 Reverse construction method well that old and new's pipeline was linked up
CN107859145A (en) * 2017-11-17 2018-03-30 广州市自来水工程公司 A kind of drainpipe is plugged into construction method under water

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
朱小宁: "兰州市污水全收集工程管道施工工艺及顶管技术研究", 《中国优秀硕士学位论文全文数据库(电子期刊) 工程科技II辑》 *
河海大学《水利大辞典》编辑修订委员会: "《水利大辞典》", 31 October 2015, 上海辞书出版社 *
田瑛: "《沉井施工在工程中的应用》", 《科技情报开发与经济》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736416A (en) * 2019-01-24 2019-05-10 安徽省公路桥梁工程有限公司 The old and new's sewage conduct deep well point connection structure and construction method
CN110080369A (en) * 2019-05-20 2019-08-02 中国二十冶集团有限公司 A kind of intersection blowdown pipeline construction method for not interrupting blowdown
CN110306581A (en) * 2019-07-31 2019-10-08 广东省源天工程有限公司 One kind new old pipeline connection well and its construction method in water rich strata
CN111236387A (en) * 2020-01-17 2020-06-05 中铁十二局集团有限公司 Construction method for connecting newly-built sewage pipe with existing sewage pipe
CN111853418A (en) * 2020-07-02 2020-10-30 深圳市市政工程总公司 Construction method for pipeline repair
CN111853418B (en) * 2020-07-02 2022-06-03 深圳市市政工程总公司 Construction method for pipeline repair
CN112095747A (en) * 2020-09-03 2020-12-18 北京建工土木工程有限公司 Safe construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
CN112095748A (en) * 2020-09-03 2020-12-18 北京建工土木工程有限公司 Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
CN112282029A (en) * 2020-11-05 2021-01-29 上海交通建设总承包有限公司 Connection construction method for urban high-water-level large-diameter reinforced concrete sewage pipeline
CN112982425A (en) * 2021-02-01 2021-06-18 中国电建集团市政规划设计研究院有限公司 Method for reinforcing open caisson and existing channel
CN113309900A (en) * 2021-06-24 2021-08-27 江苏广吴建设园林有限公司 Non-water-cut-off construction method for connecting branch pipe of concrete water supply pipeline
CN113309900B (en) * 2021-06-24 2022-04-08 江苏广吴建设园林有限公司 Non-water-cut-off construction method for connecting branch pipe of concrete water supply pipeline
CN116290282A (en) * 2023-04-23 2023-06-23 中铁一局集团市政环保工程有限公司 Construction method for connecting new and old pipelines

Similar Documents

Publication Publication Date Title
CN108867814A (en) It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN106837353A (en) Filling karst constructing tunnel processing method
CN106837352A (en) Fault belt surrounding rock tunnel construction method
CN109723065A (en) Deep basal pit freezing partly reinforced construction method in bracing means and rich water sandy pear variety
CN102352757B (en) Method for controlling upward floating of pipe piece during shield machine air pushing through mining tunnel
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN103938617A (en) Super-deep underground continuous wall and construction method thereof
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN102635119A (en) Supporting method for construction of swirl well
CN108952732A (en) A kind of excavation construction method suitable for rich water fault belt large cross-section tunnel
CN113216832B (en) Construction method for water milling and drilling of pile holes in karst areas
CN106761776A (en) Existing pipeline construction method is worn under super shallow-buried tunnel shield
CN107014262A (en) A kind of construction method of subway station artificial digging pile carbon dioxide explosion
CN111852515A (en) Tunnel stratum pre-reinforcement comprehensive grouting method
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN113006733A (en) Deep grouting process for ground surface
CN110259490A (en) A kind of Underground Subway Station construction method
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN103806444A (en) Soft soil layer rotary excavating pile construction method
CN104315251B (en) Artificial pipe jacking construction method under soil stone combination geological conditions
Xu et al. Construction of 8.0-m diameter rock-socketed piles in a large-scale deep excavation
CN205618170U (en) Protective structure of no template punishment rock mass cavity in tunnel engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181123