CN110608052A - Tunnel segment based on high-performance cement-based composite material and construction method thereof - Google Patents

Tunnel segment based on high-performance cement-based composite material and construction method thereof Download PDF

Info

Publication number
CN110608052A
CN110608052A CN201911006042.5A CN201911006042A CN110608052A CN 110608052 A CN110608052 A CN 110608052A CN 201911006042 A CN201911006042 A CN 201911006042A CN 110608052 A CN110608052 A CN 110608052A
Authority
CN
China
Prior art keywords
tunnel
segment
based composite
composite material
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911006042.5A
Other languages
Chinese (zh)
Inventor
杨才千
田宝晴
周泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Dream Bridge Sensing Technology Co Ltd
Xiangtan University
Original Assignee
Nanjing Dream Bridge Sensing Technology Co Ltd
Xiangtan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Dream Bridge Sensing Technology Co Ltd, Xiangtan University filed Critical Nanjing Dream Bridge Sensing Technology Co Ltd
Priority to CN201911006042.5A priority Critical patent/CN110608052A/en
Publication of CN110608052A publication Critical patent/CN110608052A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/086Methods of making concrete lining segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Ceramic Engineering (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a duct piece based on a high-performance cement-based composite material and a construction method thereof. The invention has the advantages that the segment steel bars are reliably anchored and then poured with the high-strength high-performance cement-based composite material, so that the overall performance and the seismic performance of the segment are obviously improved.

Description

Tunnel segment based on high-performance cement-based composite material and construction method thereof
Technical Field
The invention relates to the technical field of high-performance cement-based composite materials and tunnel segments, in particular to a tunnel segment based on a high-performance cement-based composite material and a construction method thereof.
Background
In recent years, due to the rapid development of urban rail transit and the acceleration of urbanization process, the demand of China on underground space resources is increasing, and the shield tunnel segment construction technology is widely adopted in urban subway tunnels and large tunnel projects at present due to the advantages of high mechanization degree, high construction speed, small environmental influence and the like. The shield method tunnel is a structure formed by assembling a plurality of prefabricated pipe pieces on site through bolt connection, and due to the bolt connection, the water leakage phenomenon easily occurs at the joint (circular seam and longitudinal seam) and the bolt hole position formed between the pipe pieces, and in order to prevent the underground water from leaking into the pipe pieces, a rubber waterproof sealing gasket is usually arranged at the joint of the pipe pieces, a water-swelling rubber sealing ring is arranged at the bolt hole position, and grouting, caulking treatment and the like are performed.
The bolt connection is basically manual operation, so that a large amount of time and labor are consumed, the construction speed is low, and the construction period is long. After the bolt adopts waterproof rubber circle and carries out slip casting and caulking treatment among the actual engineering, the phenomenon that appears the percolating water still ubiquitous, in case the seepage appears in the section of jurisdiction, will seriously threaten safety and operation in the tunnel, will cause immeasurable life and property loss especially to electric power tunnel and subway tunnel.
Application number 201610708866.7 discloses a shield method tunnel segment bolt hole waterproof structure and a construction method, waterproof pressure of bolt holes is improved through two waterproof gaskets, and the structure has better durability, but the construction of the connection form is complex, and the aging problem of the waterproof gaskets cannot be avoided.
At present, most of domestic bolt holes are enabled to enhance the waterproof capacity through additional measures, and the bolt connection cannot be avoided. Therefore, the problem to be solved at present is to find a novel tunnel segment connection mode and a construction method which are not connected through bolts, have convenient construction, good anti-permeability performance and durability, reliable connection and low manufacturing cost and can effectively solve the waterproof problem of the bolt holes.
Disclosure of Invention
The invention aims to provide a tunnel segment based on a high-performance cement-based composite material, aiming at the defects in the prior art.
The invention also aims to provide a tunnel segment splicing construction method based on the high-performance cement-based composite material.
The purpose of the invention is realized by the following technical scheme:
the utility model provides a tunnel segment based on high performance cement based composite, it is a plurality of the tunnel segment is assembled and is constituted round tunnel ring, both ends confined recess has been seted up respectively to tunnel segment both sides limit, laid a set of embedded bar in the recess, embedded bar stretch out in outside the recess, when the tunnel is assembled, the corresponding lock of recess of two adjacent tunnel segments forms confined segment spread groove, and grout hole and grout outlet have been seted up to the terminal surface of segment spread groove, through grout outlet and grout outlet to pour high performance cement based composite in the segment spread groove, embedded bar carries out dislocation overlap joint in the segment spread groove.
In a further design scheme of the invention, the groove is a V-shaped groove, a U-shaped groove or an arc-shaped groove.
In a further design scheme of the invention, the diameter of the embedded steel bar is not less than 6mm, and the extending anchoring length is not less than 5 times of the diameter of the embedded steel bar.
In a further design scheme of the invention, the grouting hole is positioned at the lowest point of the segment connecting groove, and the grout outlet hole is positioned at the highest point of the segment connecting groove.
In a further design scheme of the invention, a layer of water stop pad is adhered to the periphery of the groove openings of the two tunnel pipe pieces which are buckled and spliced with each other.
In a further design scheme of the invention, the high-performance cement-based composite material comprises the following components in percentage by weight: fly ash: silica fume: quartz sand: water: water reducing agent: steel fiber =690:240:172:187.34:991.8:22.04:120, wherein the water reducing agent content is 2.0%, the steel fiber volume content is 1.5%, the sand-cement ratio is 0.9, and the water-cement ratio is 0.17.
The construction method of the tunnel segment based on the high-performance cement-based composite material comprises the following specific steps:
step one, designing and manufacturing a tunnel duct piece mold, placing a reinforcement cage in the tunnel duct piece mold, reserving reinforcement extending out of a groove, and adhering a thin water stop pad around the opening of the groove.
And step two, sequentially assembling the tunnel pipe pieces from the lower right to the upper right, correspondingly buckling and tightly contacting groove openings of the tunnel pipe pieces to form a closed pipe piece connecting groove, forming a grouting hole and a grout outlet at one end of the pipe piece connecting groove, wherein the grouting hole is arranged at the lowest position, and the grout outlet is arranged at the highest position.
And step three, injecting the high-performance cement-based composite material into the segment connecting groove from the grouting hole by adopting a high-pressure grouting machine, stopping grouting when slurry of the high-performance cement-based composite material flows out from the upper slurry outlet hole, blocking the open hole part in time, and splicing the rest tunnel segments by using the same method.
In a further design scheme of the invention, the high-performance cement-based composite material comprises the following components in percentage by weight: fly ash: silica fume: quartz sand: water: water reducing agent: steel fiber =690:240:172:187.34:991.8:22.04:120, wherein the water reducing agent content is 2.0%, the steel fiber volume content is 1.5%, the sand-cement ratio is 0.9, and the water-cement ratio is 0.17.
The invention has the following outstanding advantages:
the invention does not need bolt connection, and overcomes the problems of large time and labor consumption, low construction speed, long construction period and the like because the bolt connection needs manual tightening. The problems that water is easy to leak from a bolt hole, a bolt water-stopping sealing ring is easy to age, the difficulty of later maintenance is high and the like in bolt connection are solved.
The high-performance cement-based composite material has the characteristics of high toughness, high durability and low permeability, and the impermeability and the durability of the segment joints are greatly improved by pouring the high-performance cement-based composite material for connection, so that the waterproof effect is good, and the later maintenance cost is low.
According to the invention, the steel bars are connected in a staggered overlapping manner, accurate positioning is not needed, construction is convenient, and the duct piece steel bars are reliably anchored and then poured with the high-strength high-performance cement-based composite material, so that the overall performance and the anti-seismic performance of the duct piece are obviously improved.
Drawings
FIG. 1 is a schematic structural diagram of a tunnel segment based on a high-performance cement-based composite material in an embodiment;
FIG. 2 is a bottom sectional view of a tunnel segment in an embodiment;
FIG. 3 is a ring diagram of tunnel segments assembled in the embodiment;
fig. 4 is a schematic view of the opening on the segment connecting groove at different splicing positions in the embodiment
In the figure, 1-embedded steel bar, 4-groove, 5-tunnel segment, 7-grouting hole, 8-grout outlet, 9-steel bar cage, 10-grouting hole, 11-grout outlet, 12-tunnel segment, 13-tunnel segment, 14-tunnel segment, 15-segment connecting groove, 16-segment connecting groove, 17-segment connecting groove, 18-grouting hole, and 19-grout outlet.
Detailed Description
The invention is further explained below with reference to the drawings and examples.
Examples
Referring to the attached figure 1, a tunnel segment based on a high-performance cement-based composite material is formed by splicing a plurality of tunnel segments 5 to form a circle of tunnel ring, two side edges of each tunnel segment are respectively provided with a V-shaped groove 4 with two closed ends, a group of embedded steel bars 1 with the diameter not less than 6mm are distributed in the grooves 4, the embedded steel bars 1 extend out of the grooves 4, and the extending anchoring length is not less than 5 times of the diameter of the embedded steel bars; the extended anchoring length refers to the portion of the precast segment that extends out of the interior of the precast segment and is not encased by concrete. When the tunnel is assembled, the openings of the grooves 4 of the two adjacent tunnel segments 5 are correspondingly buckled to form a closed segment connecting groove, and a water stop pad is adhered around the groove openings of the two tunnel segments which are buckled and spliced. The end face of the segment connecting groove is provided with a grouting hole and a grout outlet, the grouting hole is located at the lowest point of the segment connecting groove, and the grout outlet is located at the highest point of the segment connecting groove. High-performance cement-based composite materials are poured into the segment connecting grooves through the grouting holes and the grout outlet holes, and embedded steel bars in the segment connecting grooves are connected in a staggered lap joint mode. The staggered lap joint connection is the meaning that the reinforcing steel bars are mutually staggered, staggered and not contacted. The purpose of this is to eliminate the need for precise positioning between the bars, which also takes advantage of the confined space. The high-performance cement-based composite material comprises the following components in parts by mass: fly ash: silica fume: quartz sand: water: water reducing agent: steel fiber =690:240:172:187.34:991.8:22.04:120, wherein the water reducing agent content is 2.0%, the steel fiber volume content is 1.5% (volume ratio), the sand-cement ratio is 0.9 (ratio of quartz sand mass to all the gelled materials mass), and the water-cement ratio is 0.17 (ratio of water mass to all the gelled materials mass).
When the tunnel duct piece is used for assembly construction, bolt connection is not needed, the openings of the grooves of two adjacent tunnel duct pieces are correspondingly buckled to form a closed rhombic duct piece connecting groove, embedded steel bars in the grooves can be connected in a staggered lap joint mode, and high-performance cement-based composite materials are injected into the grooves for connection. Taking 3 tunnel segments to form a ring of tunnel rings as an example, referring to fig. 2-4, the method specifically comprises the following steps:
step one, designing and manufacturing a tunnel segment mould, placing a reinforcement cage 9 in the tunnel segment mould, reserving a reinforcement 1 extending out of a groove 4, and pasting a thin water stop pad around the opening of the groove 4 to ensure that the contact part of the tunnel segment has a better waterproof effect. Tunnel segment 12, tunnel segment 13 and tunnel segment 14 are obtained.
And step two, sequentially assembling the tunnel pipe pieces from bottom to top, assembling the tunnel pipe piece 12 and the tunnel pipe piece 13 at the bottom, after the tunnel pipe pieces are assembled and tightly connected, forming a rhombic pipe piece connecting groove 15 in the contact part, forming two grouting holes 7 and a grout outlet hole 8 on one side of the pipe piece connecting groove 15, wherein the grouting hole 7 is at the lowest position, and the grout outlet hole 8 is at the highest position. After the tunnel segment 12 and the tunnel segment 13 are assembled, the tunnel segment 14 is assembled by the same method, the tunnel segment 14 is respectively buckled with the tunnel segment 12 and the tunnel segment 13 to form a rhombic segment connecting groove 17 and a rhombic segment connecting groove 16, a grouting hole 10 and a grout outlet hole 11 are formed in one end of the segment connecting groove 16, and a grouting hole 18 and a grout outlet hole 19 are formed in one end of the segment connecting groove 17.
And step three, injecting the high-performance cement-based composite material into the segment connecting grooves 15 from the grouting holes 7 by using a high-pressure grouting machine, stopping grouting when slurry of the high-performance cement-based composite material flows out of the upper slurry outlet 8, blocking the grouting holes 7 and the slurry outlet 8 in time, and sequentially filling the rest segment connecting grooves by using the same method.
The high-performance cement-based composite material comprises the following components in percentage by weight: fly ash: silica fume: quartz sand: water: water reducing agent: steel fiber =690:240:172:187.34:991.8:22.04:120, wherein the water reducing agent content is 2.0%, the steel fiber volume content is 1.5%, the sand-cement ratio is 0.9, and the water-cement ratio is 0.17.
The above are preferred embodiments of the present invention, and all changes made according to the technical scheme of the present invention that produce functional effects do not exceed the scope of the technical scheme of the present invention belong to the protection scope of the present invention.

Claims (8)

1. The utility model provides a tunnel segment based on high performance cement-based composite, it is a plurality of the tunnel segment is assembled and is constituted round tunnel ring, its characterized in that, both ends confined recess has been seted up respectively to tunnel segment both sides limit, lay a set of embedded bar in the recess, embedded bar stretch out in outside the recess, when the tunnel is assembled, the corresponding lock of recess of two adjacent tunnel segments forms confined segment spread groove, and grout hole and grout outlet have been seted up to the terminal surface of segment spread groove, through grout hole and grout outlet to pour high performance cement-based composite in the segment spread groove, embedded bar carries out dislocation overlap joint in the segment spread groove.
2. The high performance cement-based composite based tunnel segment of claim 1, wherein the grooves are V-shaped grooves or U-shaped grooves or arc-shaped grooves.
3. The high-performance cement-based composite material-based tunnel segment as claimed in claim 1, wherein the diameter of the embedded steel bars is not less than 6mm, and the extended anchoring length is not less than 5 times the diameter of the embedded steel bars.
4. The high performance cement-based composite material-based tunnel segment of claim 1, wherein said grouting holes are located at the lowest point of segment connecting grooves, and said grout outlet holes are located at the highest point of segment connecting grooves.
5. The tunnel segment based on the high-performance cement-based composite material as claimed in claim 1, wherein a water stop pad is adhered around the groove openings of the two tunnel segments which are buckled and spliced.
6. The high performance cement-based composite material-based tunnel segment of claim 1, wherein the high performance cement-based composite material is cement: fly ash: silica fume: quartz sand: water: water reducing agent: steel fiber =690:240:172:187.34:991.8:22.04:120, wherein the water reducing agent content is 2.0%, the steel fiber volume content is 1.5%, the sand-cement ratio is 0.9, and the water-cement ratio is 0.17.
7. A tunnel segment assembling construction method based on a high-performance cement-based composite material is characterized by comprising the following specific steps:
step one, designing and manufacturing a tunnel duct piece mold, placing a reinforcement cage in the tunnel duct piece mold, reserving reinforcement extending out of a groove, and sticking a thin water stop pad around the opening of the groove;
step two, sequentially assembling tunnel pipe pieces from the right bottom to the top, correspondingly buckling groove openings of the tunnel pipe pieces, tightly contacting the groove openings, forming a closed pipe piece connecting groove, forming a grouting hole and a grout outlet at one end of the pipe piece connecting groove, wherein the grouting hole is arranged at the lowest position, and the grout outlet is arranged at the highest position;
and step three, injecting the high-performance cement-based composite material into the segment connecting groove from the grouting hole by adopting a high-pressure grouting machine, stopping grouting when slurry of the high-performance cement-based composite material flows out from the upper slurry outlet hole, blocking the open hole part in time, and splicing the rest tunnel segments by using the same method.
8. The tunnel segment assembling construction method based on the high-performance cement-based composite material as claimed in claim 7, wherein the high-performance cement-based composite material is prepared from cement: fly ash: silica fume: quartz sand: water: water reducing agent: steel fiber =690:240:172:187.34:991.8:22.04:120, wherein the water reducing agent content is 2.0%, the steel fiber volume content is 1.5%, the sand-cement ratio is 0.9, and the water-cement ratio is 0.17.
CN201911006042.5A 2019-10-22 2019-10-22 Tunnel segment based on high-performance cement-based composite material and construction method thereof Pending CN110608052A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911006042.5A CN110608052A (en) 2019-10-22 2019-10-22 Tunnel segment based on high-performance cement-based composite material and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911006042.5A CN110608052A (en) 2019-10-22 2019-10-22 Tunnel segment based on high-performance cement-based composite material and construction method thereof

Publications (1)

Publication Number Publication Date
CN110608052A true CN110608052A (en) 2019-12-24

Family

ID=68893294

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911006042.5A Pending CN110608052A (en) 2019-10-22 2019-10-22 Tunnel segment based on high-performance cement-based composite material and construction method thereof

Country Status (1)

Country Link
CN (1) CN110608052A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111677526A (en) * 2020-05-15 2020-09-18 中国路桥工程有限责任公司 Tunnel anti-seismic structure and method under complex geological condition
CN114198118A (en) * 2021-12-25 2022-03-18 中铁工程装备集团有限公司 Underground engineering node processing structure and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080068210A (en) * 2007-01-18 2008-07-23 김현경 The tunnel second lining construction work method and that equipment
EP2239416A2 (en) * 2009-04-02 2010-10-13 Herold Kunststofftechnik Concrete tubing and method for manufacturing the same
CN203271763U (en) * 2013-02-07 2013-11-06 广东省水利电力勘测设计研究院 Lining segment for sea-crossing shield tunnel
CN203669880U (en) * 2013-12-31 2014-06-25 西南交通大学 Assembly type tunnel lining segment
KR101809032B1 (en) * 2016-12-22 2017-12-14 주식회사 대산이엔씨 A precast arc segment and a connection structure and a method for engaging the segments each other
CN108678775A (en) * 2018-07-06 2018-10-19 浙江大学城市学院 A kind of anti-horizontal ovalizing deflection shield tunnel ruggedized construction of pre-embedded steel slab and construction method
CN108825269A (en) * 2018-05-30 2018-11-16 宁波大学 Mechanical Method service channel T socket part position adaptive waterproof construction
CN109505624A (en) * 2018-09-27 2019-03-22 中铁隧道局集团有限公司 A kind of section of jurisdiction mortise and tenon formula shield tunnel construction
CN211692480U (en) * 2019-10-22 2020-10-16 湘潭大学 Tunnel segment based on high-performance cement-based composite material

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080068210A (en) * 2007-01-18 2008-07-23 김현경 The tunnel second lining construction work method and that equipment
EP2239416A2 (en) * 2009-04-02 2010-10-13 Herold Kunststofftechnik Concrete tubing and method for manufacturing the same
CN203271763U (en) * 2013-02-07 2013-11-06 广东省水利电力勘测设计研究院 Lining segment for sea-crossing shield tunnel
CN203669880U (en) * 2013-12-31 2014-06-25 西南交通大学 Assembly type tunnel lining segment
KR101809032B1 (en) * 2016-12-22 2017-12-14 주식회사 대산이엔씨 A precast arc segment and a connection structure and a method for engaging the segments each other
CN108825269A (en) * 2018-05-30 2018-11-16 宁波大学 Mechanical Method service channel T socket part position adaptive waterproof construction
CN108678775A (en) * 2018-07-06 2018-10-19 浙江大学城市学院 A kind of anti-horizontal ovalizing deflection shield tunnel ruggedized construction of pre-embedded steel slab and construction method
CN109505624A (en) * 2018-09-27 2019-03-22 中铁隧道局集团有限公司 A kind of section of jurisdiction mortise and tenon formula shield tunnel construction
CN211692480U (en) * 2019-10-22 2020-10-16 湘潭大学 Tunnel segment based on high-performance cement-based composite material

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
潘国庆;: "西藏南路越江隧道工程管片设计及特点", 中国市政工程, no. 1, pages 125 - 127 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111677526A (en) * 2020-05-15 2020-09-18 中国路桥工程有限责任公司 Tunnel anti-seismic structure and method under complex geological condition
CN114198118A (en) * 2021-12-25 2022-03-18 中铁工程装备集团有限公司 Underground engineering node processing structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN103643966B (en) A kind of assembling tunnel lining segment
CN107387123B (en) The construction method of pressure grouting leak stopping is carried out for shield duct piece piece leakage phenomenon
CN204690783U (en) A kind of prefabricated assembled single cabin municipal administration synthesis pipe gallery
CN104947709A (en) Pre-assembled single-compartment municipal tunnel and construction method thereof
CN203669880U (en) Assembly type tunnel lining segment
CN102808414B (en) Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
CN203161259U (en) Buried-in type rubber water-stop belt of double-layer waterproof structure and construction-joint water drainage structure formed by buried-in type rubber water-stop belt
CN105862990A (en) Prefabricated assembly well wall structure and construction method thereof
CN110608052A (en) Tunnel segment based on high-performance cement-based composite material and construction method thereof
CN207079627U (en) A kind of assembled underground pipe gallery member connecting structure
CN110762287A (en) Curved pipe jacking interface water stop structure suitable for high water pressure condition
CN211692480U (en) Tunnel segment based on high-performance cement-based composite material
CN109881661A (en) Assembled underground continuous wall transverse connection structure
CN212248356U (en) Waterproof connection structure for prefabricated comprehensive pipe gallery connector
CN109026067A (en) A kind of circumferential intelligent ruggedized construction of shield tunnel and reinforcement means
CN208295326U (en) Full corrosion-proof lining formula Prestressed concrete cylinder pipe
CN105064411B (en) Method for building post-pouring expansion reinforcing band of wallboard of underground structure
CN210033461U (en) Segment lining grouting system based on externally-embedded channel and stretchable bag
CN210978736U (en) Curved pipe jacking interface water stop structure suitable for high water pressure condition
CN210262964U (en) Grout stopping structure of hydraulic tunnel
CN114370275A (en) Bedrock bolting-grouting impervious supporting structure and construction method thereof
CN112726667A (en) Semi-rigid assembly type comprehensive pipe gallery and construction method thereof
CN107989272A (en) One kind three and muscle are in a row connected with full grout sleeve and three and muscle connection method in a row
CN218540895U (en) Use alpine region center ditch of bamboo winding pipeline
CN218933204U (en) Prefabricated assembled underground works multilayer waterproof prefabricated section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 411105 No.5 Gaoling Road, yanggutang, Xijiao, Xiangtan City, Hunan Province

Applicant after: XIANGTAN University

Applicant after: Jiangsu menglianqiao Technology Co.,Ltd.

Address before: 411105 No.5 Gaoling Road, yanggutang, Xijiao, Xiangtan City, Hunan Province

Applicant before: XIANGTAN University

Applicant before: NANJING MENGLIANQIAO SENSING TECHNOLOGY Co.,Ltd.