CN109958272A - High altitude operation operating platform bracket and its hooking method for being articulated on girder steel - Google Patents

High altitude operation operating platform bracket and its hooking method for being articulated on girder steel Download PDF

Info

Publication number
CN109958272A
CN109958272A CN201910289344.1A CN201910289344A CN109958272A CN 109958272 A CN109958272 A CN 109958272A CN 201910289344 A CN201910289344 A CN 201910289344A CN 109958272 A CN109958272 A CN 109958272A
Authority
CN
China
Prior art keywords
operating platform
support frame
vertical bar
hook
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910289344.1A
Other languages
Chinese (zh)
Inventor
文腾
杨猛
甘彬
谢慧智
林巍
魏超
雷金玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201910289344.1A priority Critical patent/CN109958272A/en
Publication of CN109958272A publication Critical patent/CN109958272A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention discloses the high altitude operation operating platform brackets and its hooking method for being articulated on girder steel, solve the hanging technical problem for being inconvenient to cause operating efficiency low and high-altitude hanging operation safety coefficient is not high in prior art high-altitude.High altitude operation operating platform bracket includes support frame, hook and operating platform;Support frame includes support frame vertical bar and support frame cross bar.Hooking method is main are as follows: high altitude operation operating platform bracket is carried at girder steel and is mounted on it, high altitude operation operating platform backing positions are adjusted later, finally two chains are bypassed into steel beam bottom respectively and be wound on respective support frame vertical bar and locked chain and respective support frame vertical bar with lock, that is, completes the firm mounting of high altitude operation operating platform bracket.The present invention can effectively improve the safety coefficient of worker's high altitude operation efficiency and high altitude operation, and hooking method is simple and easy to do.

Description

High altitude operation operating platform bracket and its hooking method for being articulated on girder steel
Technical field
The present invention relates to the high altitude operation operating platform brackets and its hooking method for being articulated on girder steel.
Background technique
Site construction, it is often necessary to welding or roof boarding laying construction are vacantly carried out in high-altitude, under normal circumstances, at this A little places are constructed, and worker does not increase, and machine can't reach again, at this time worker can only body fasten the safety belt and lift up into row from top to bottom and hang Idle job, operation is inconvenient, and operating efficiency is low, and safety coefficient is not also high.Therefore, a height for being articulated on girder steel is designed Idle job operating platform bracket and its hooking method are become with improving worker's high altitude operation efficiency and high-altitude working safety coefficient Skilled artisan's technical problem urgently to be resolved.
Summary of the invention
The technical problem to be solved by the present invention is provide high altitude operation operating platform bracket for being articulated on girder steel and Its hooking method, solves that prior art high-altitude is hanging is inconvenient to cause operating efficiency low and high-altitude hanging operation safety coefficient Not high technical problem.
To achieve the above object, The technical solution adopted by the invention is as follows:
High altitude operation operating platform bracket for being articulated on girder steel, including support frame, are fixed on support frame as described above Top is used for the hook being articulated on girder steel, and is fixed on operation of the bottom of support frame as described above for worker's standing at work and puts down Platform;Support frame as described above is frame structure, support frame vertical bar and two or more equidistant fixations including the distribution of a pair of of parallel vertical In this between support frame as described above vertical bar and in the support frame cross bar of horizontal distribution, the hook is fixed on this to support frame as described above The top of vertical bar, the operating platform are fixed on the bottom to support frame as described above vertical bar.
Further, it is described hook include two in horizontal distribution connecting rod, two in be distributed vertically hook vertical bar, And at least two be in horizontal distribution hook cross bar, one end of two connecting rods respectively with two support frame as described above vertical bars Top mutually fix, two hook vertical bars are mutually fixed with the other end of two connecting rods respectively, all hooks Cross bar is equidistantly fixed between two hook vertical bars, the hook vertical bar, the connecting rod and support frame as described above vertical bar The hook structure for being articulated on girder steel is collectively formed.
Further, the hook cross bar has two, and it is perpendicular that a hook cross bar level is fixed on two hooks The top of bar, another hook cross bar level are fixed on the bottom end of two hook vertical bars.
Further, the bottom of each hook vertical bar is respectively and fixedly provided with a chain, and the length of the chain is greater than The length of the connecting rod.
Further, support frame as described above vertical bar and support frame as described above cross bar are stainless steel square tube, and all branch Support cross bar is welded and fixed with a pair of of support frame as described above vertical bar respectively;
The connecting rod, the hook vertical bar and the hook cross bar are stainless steel square tube, and the chain is not using Rust Steel material is made, and the connecting rod is welded and fixed with support frame as described above vertical bar, the connecting rod and the hook vertical bar It is welded and fixed, the hook vertical bar and the hook cross bar are welded and fixed, and the chain and the corresponding hook vertical bar welding are solid It is fixed.
Further, the operating platform includes the behaviour be fixed on a pair of of support frame as described above vertical bar bottom and be in horizontal distribution Make platform framework and level is fixed in the operating platform frame people from station platform for being used to support worker's standing at work, institute State the side that operating platform frame is located at support frame as described above.
Further, the operating platform frame is in isosceles triangle, and the first stainless steel tube of You Lianggen and one second are not Rust steel pipe head and the tail are welded, and first stainless steel tube is longer than second stainless steel tube, two first stainless steel tubes Pad also mutually welded with the bottom end of a support frame as described above vertical bar simultaneously, and the bottom end of another support frame as described above vertical bar In the operating platform frame.
Further, people from station platform is the stainless steel cloth or stainless steel being welded in the operating platform frame Plate, and at least two reinforcement steel pipes are equidistantly welded between two first stainless steel tubes, all reinforcement steel pipes are equal It is parallel with second stainless steel tube, and bottom end be located at support frame as described above vertical bar in the operating platform frame with wherein A piece interphase welding for reinforcing steel pipe.
Further, the operating platform further includes having operating platform guardrail, and the operating platform guardrail includes using one Root steel pipe bending and molding is simultaneously in isosceles triangle and is in the guardrail frame of horizontal distribution, the reinforcing being welded in the guardrail frame Steel pipe and two or more are equidistantly welded in the operating platform guardrail connecting rod of the operating platform guardrail bottom vertically, own The operating platform guardrail connecting rod was distributed around the operating platform guardrail bottom one week, the guardrail frame and the operation Platform framework size is identical and the distribution of upper and lower face, the bottom end of all operating platform guardrail connecting rods with the operation The top of platform framework is mutually welded, by the guardrail frame and the operating platform frame Joint, the guardrail frame Tip and the lower part of a support frame as described above vertical bar are mutually welded, and the lower part of another support frame as described above vertical bar is located at the shield It is welded in column frame and with the interphase for reinforcing steel pipe.
The hooking method of high altitude operation operating platform bracket for being articulated on girder steel, comprising the following steps:
Step 1: high altitude operation operating platform bracket is carried at the girder steel for needing hanging operation, high altitude operation is grasped The hook structure for making platform support is articulated on girder steel;
Step 2: adjustment high altitude operation operating platform backing positions, are located at operating platform and are suitable for hanging operation point;
Step 3: two chains are bypassed steel beam bottom respectively and are wound on respective support frame vertical bar, while with lock Chain and respective support frame vertical bar are locked, that is, complete the firm mounting of high altitude operation operating platform bracket.
Compared with prior art, the invention has the following advantages:
The configuration of the present invention is simple, design is scientific and reasonable, easy to use, can effectively improve worker's high altitude operation efficiency and high-altitude The safety coefficient of operation.
High altitude operation operating platform bracket of the present invention includes support frame, hook and operating platform, and welding hook is in support frame The front or the back side on top, and hook structure is collectively formed with support frame top, when needing high altitude operation, this high-altitude is made Industry operating platform bracket includes that support frame is transported to girder steel, and hook structure is articulated on girder steel, and support frame and operation Platform is then located at girder steel hereinafter, operating platform is then welded on the side of support frame, in this way, worker can then stand on the operational platform High altitude operation is carried out, and while worker stands progress high altitude operation on the operational platform, also by the safety with tying up to Band ties up on girder steel, and the operating efficiency of such worker will be greatly enhanced, and fastens the safety belt hanging operation relative to body, Its safety coefficient can be also improved.
Be welded with chain on the hook vertical bar of invention hook, after hook structure is articulated on girder steel, by chain from The lower section of girder steel is bypassed and is locked with support frame vertical bar using lock, prevents hook because high altitude operation operating platform bracket is laterally put It moves and breaks off relations with girder steel, such hook structure can be more firmly articulated on girder steel, further increase worker's high altitude operation Safety coefficient.
Operation of the present invention platform framework is welded into isosceles triangle using stainless steel tube, the tip of the triangle and a branch Support vertical bar mutually welds, another support frame vertical bar be located in operating platform frame and be welded in two first stainless steel tubes it Between reinforcement steel pipe interphase welding, in this way, operating platform frame i.e. be bonded with support frame, structure is simply firm, simultaneously Working space is big, and people's platform of standing uses stainless steel cloth or stainless steel plate, then is aided with and reinforces steel pipe and hold stainless steel cloth or not Become rusty steel plate, so not only light but also durable, and worker stands quite safe thereon.
Operation of the present invention platform is additionally provided with the operating platform guardrail with operating platform frame Joint, operating platform guardrail packet Guardrail frame and operating platform guardrail connecting rod are included, guardrail frame is using a steel pipe bending and molding and is in isosceles triangle and is in Horizontal distribution is distributed with operating platform frame in upper and lower face, and flat by several operating platform guardrail connecting rods and operation Table frame mutually welds, the stable connection with operating platform frame, meanwhile, the tip of guardrail frame is also mutually welded with support frame vertical bar It connects, being bonded for whole operation platform and support frame can be further strengthened, further increase the safety system of worker's high altitude operation Number.
High altitude operation operating platform bracket of the present invention uses steel pipe and stainless steel square tube welding fabrication substantially, material easily takes, Structure is simple, easily fabricated, and suitable for the high altitude operation of every profession and trade, hooking method is simple and easy to do, and worker grasps this high altitude operation As platform support mount to girder steel after again by the safety belt of carry-on frenulum tie up to girder steel can stand carried out in station people's platform it is high Idle job, it is practical, application can be widelyd popularize in the industry.
Detailed description of the invention
Fig. 1 is schematic structural view of the invention.
Fig. 2 is top view of the present invention.
Fig. 3 is that chain and support frame vertical bar latch rearview.
Wherein, the corresponding title of appended drawing reference are as follows:
1- support frame, 2- hook, 3- operating platform, 11- support frame vertical bar, 12- support frame cross bar, 21- connecting rod, 22- Link up with vertical bar, 23- hook cross bar, 24- chain, 31- operating platform frame, people from the station 32- platform, the first stainless steel tube of 33-, 34- Second stainless steel tube, 35- reinforce steel pipe, 36- operating platform guardrail, 37- guardrail frame, 38- and reinforce steel pipe, 39- operating platform Guardrail connecting rod.
Specific embodiment
The invention will be further described with embodiment for explanation with reference to the accompanying drawing, and mode of the invention includes but not only limits In following embodiment.
As shown in Figure 1-3, provided by the present invention for the high altitude operation operating platform bracket being articulated on girder steel, structure letter List, design is scientific and reasonable, easy to use, can effectively improve the safety coefficient of worker's high altitude operation efficiency and high altitude operation.This hair Bright includes support frame 1, is fixed on the hook 2 that the top of support frame as described above 1 is used to be articulated on girder steel, and be fixed on the branch The bottom of support 1 is used for the operating platform 3 of worker's standing at work;Support frame as described above 1 is frame structure, including a pair of of parallel vertical The support frame vertical bar 11 of distribution and two or more are equidistantly fixed on this between support frame as described above vertical bar 11 and in horizontal distribution Support frame cross bar 12, the hook 2 is fixed on the top to support frame as described above vertical bar 11, and the operating platform 3 is fixed on The bottom to support frame as described above vertical bar 11.
High altitude operation operating platform bracket of the present invention includes support frame, hook and operating platform, and welding hook is in support frame The front or the back side on top, and hook structure is collectively formed with support frame top, when needing high altitude operation, this high-altitude is made Industry operating platform bracket includes that support frame is transported to girder steel, and hook structure is articulated on girder steel, and support frame and operation Platform is then located at girder steel hereinafter, operating platform is then welded on the side of support frame, in this way, worker can then stand on the operational platform High altitude operation is carried out, and while worker stands progress high altitude operation on the operational platform, also by the safety with tying up to Band ties up on girder steel, and the operating efficiency of such worker will be greatly enhanced, and fastens the safety belt hanging operation relative to body, Its safety coefficient can be also improved.
Hook 2 of the present invention includes two connecting rod 21, two in horizontal distribution in the hook vertical bar being distributed vertically 22 and at least two be in horizontal distribution hook cross bar 23, one end of two connecting rods 21 respectively with two branch The top of support vertical bar 11 is mutually fixed, and two hook vertical bars 22 are mutually solid with the other end of two connecting rods 21 respectively Fixed, all hook cross bars 23 are equidistantly fixed between two hook vertical bars 22, the hook vertical bar 22, the connection The hook structure for being articulated on girder steel is collectively formed in bar 21 and support frame as described above vertical bar 11.The hook cross bar 23 There are two, hook 23 level of cross bar is fixed on the top of two hook vertical bars 22, and another hook is horizontal 23 level of bar is fixed on the bottom end of two hook vertical bars 22.The bottom of each hook vertical bar 22 is respectively and fixedly provided with one Chain 24, the length of the chain 24 are greater than the length of the connecting rod 21.
Support frame vertical bar 11 and support frame as described above cross bar 12 of the present invention are stainless steel square tube, and all branch Support cross bar 12 is welded and fixed with a pair of of support frame as described above vertical bar 11 respectively;The connecting rod 21, the hook vertical bar 22 and The hook cross bar 23 is stainless steel square tube, and the chain 24 is made of stainless steel, and the connecting rod 21 with Support frame as described above vertical bar 11 is welded and fixed, and the connecting rod 21 and the hook vertical bar 22 are welded and fixed, the hook vertical bar 22 It is welded and fixed with the hook cross bar 23, the chain 24 is welded and fixed with the corresponding hook vertical bar 22.
Be welded with chain on the hook vertical bar of invention hook, after hook structure is articulated on girder steel, by chain from The lower section of girder steel is bypassed and is locked with support frame vertical bar using lock, prevents hook because high altitude operation operating platform bracket is laterally put It moves and breaks off relations with girder steel, such hook structure can be more firmly articulated on girder steel, further increase worker's high altitude operation Safety coefficient.
Operating platform 3 of the present invention includes the behaviour be fixed on a pair of of 11 bottom of support frame as described above vertical bar and be in horizontal distribution Make platform framework 31 and level is fixed in the operating platform frame 31 people from station platform for being used to support worker's standing at work 32, the operating platform frame 31 is located at the side of support frame as described above 1.The operating platform frame 31 is in isosceles triangle, by Two first stainless steel tubes 33 and 34 head and the tail of the second stainless steel tube are welded, and first stainless steel tube 33 is longer than described Second stainless steel tube 34, the pad of two first stainless steel tubes 33 also bottom with a support frame as described above vertical bar 11 simultaneously End is mutually welded, and the bottom end of another support frame as described above vertical bar 11 is located in the operating platform frame 31.The people from station is flat Platform 32 is the stainless steel cloth or stainless steel plate being welded in the operating platform frame 31, and two first stainless steels Equidistantly be welded at least two reinforcement steel pipes 35 between pipe 33, all reinforcement steel pipes 35 with second stainless steel tube 34 It is parallel, and bottom end is located at support frame as described above vertical bar 11 and a wherein reinforcement steel in the operating platform frame 31 The interphase of pipe 35 is welded.
Operation of the present invention platform framework is welded into isosceles triangle using stainless steel tube, the tip of the triangle and a branch Support vertical bar mutually welds, another support frame vertical bar be located in operating platform frame and be welded in two first stainless steel tubes it Between reinforcement steel pipe interphase welding, in this way, operating platform frame i.e. be bonded with support frame, structure is simply firm, simultaneously Working space is big, and people's platform of standing uses stainless steel cloth or stainless steel plate, then is aided with and reinforces steel pipe and hold stainless steel cloth or not Become rusty steel plate, so not only light but also durable, and worker stands quite safe thereon.
Operating platform 3 of the present invention further includes having operating platform guardrail 36, and the operating platform guardrail 36 includes using A piece steel pipe bending and molding is simultaneously in isosceles triangle and is in the guardrail frame 37 of horizontal distribution, is welded in the guardrail frame 37 Reinforcing steel pipe 38 and two or more the operating platform guardrails for being equidistantly welded in 36 bottom of operating platform guardrail vertically connect Extension bar 39, all operating platform guardrail connecting rods 39 are distributed for one week around 36 bottom of operating platform guardrail, the shield The face distribution identical and upper and lower with 31 size of operating platform frame of column frame 37, all operating platform guardrail connections Top of the bottom end of bar 39 with the operating platform frame 31 is mutually welded, by the guardrail frame 37 and the operating platform 31 Joint of frame, the tip of the guardrail frame 37 are mutually welded with the lower part of a support frame as described above vertical bar 11, and another The lower part of root support frame as described above vertical bar 11 is located in the guardrail frame 37 and welds with the interphase for reinforcing steel pipe 38.
Operation of the present invention platform is additionally provided with the operating platform guardrail with operating platform frame Joint, operating platform guardrail packet Guardrail frame and operating platform guardrail connecting rod are included, guardrail frame is using a steel pipe bending and molding and is in isosceles triangle and is in Horizontal distribution is distributed with operating platform frame in upper and lower face, and flat by several operating platform guardrail connecting rods and operation Table frame mutually welds, the stable connection with operating platform frame, meanwhile, the tip of guardrail frame is also mutually welded with support frame vertical bar It connects, being bonded for whole operation platform and support frame can be further strengthened, further increase the safety system of worker's high altitude operation Number.
Provided by the present invention for the hooking method for the high altitude operation operating platform bracket being articulated on girder steel, including it is following Step:
Step 1: high altitude operation operating platform bracket is carried at the girder steel for needing hanging operation, high altitude operation is grasped The hook structure for making platform support is articulated on girder steel;
Step 2: adjustment high altitude operation operating platform backing positions, are located at operating platform and are suitable for hanging operation point;
Step 3: two chains are bypassed steel beam bottom respectively and are wound on respective support frame vertical bar, while with lock Chain and respective support frame vertical bar are locked, that is, complete the firm mounting of high altitude operation operating platform bracket.
High altitude operation operating platform bracket of the present invention uses steel pipe and stainless steel square tube welding fabrication substantially, material easily takes, Structure is simple, easily fabricated, and suitable for the high altitude operation of every profession and trade, hooking method is simple and easy to do, and worker grasps this high altitude operation As platform support mount to girder steel after again by the safety belt of carry-on frenulum tie up to girder steel can stand carried out in station people's platform it is high Idle job, it is practical, application can be widelyd popularize in the industry.
Above-described embodiment is only one of the preferred embodiment of the present invention, should not be taken to limit protection model of the invention It encloses, as long as that in body design thought of the invention and mentally makes has no the change of essential meaning or polishing, is solved The technical issues of it is still consistent with the present invention, should all be included within protection scope of the present invention.

Claims (10)

1. the high altitude operation operating platform bracket for being articulated on girder steel, which is characterized in that including support frame (1), be fixed on The top of support frame as described above (1) is used for the hook (2) being articulated on girder steel, and is fixed on the bottom use of support frame as described above (1) In the operating platform (3) of worker's standing at work;Support frame as described above (1) is frame structure, the branch including the distribution of a pair of of parallel vertical Support vertical bar (11) and two or more be equidistantly fixed on this between support frame as described above vertical bar (11) and be in horizontal distribution branch Support cross bar (12), the hook (2) are fixed on the top to support frame as described above vertical bar (11), and the operating platform (3) is solid Due to the bottom to support frame as described above vertical bar (11).
2. the high altitude operation operating platform bracket according to claim 1 for being articulated on girder steel, which is characterized in that institute State hook (2) include two in horizontal distribution connecting rod (21), two in the hook vertical bar (22) that is distributed vertically and at least Two be in horizontal distribution hook cross bar (23), one end of two connecting rods (21) respectively with two support frame as described above vertical bars (11) top is mutually fixed, and the other end of two hooks vertical bar (22) respectively with two connecting rods (21) is mutually fixed, All hook cross bars (23) are equidistantly fixed between two hook vertical bars (22), the hook vertical bar (22), described The hook structure for being articulated on girder steel is collectively formed in connecting rod (21) and support frame as described above vertical bar (11).
3. the high altitude operation operating platform bracket according to claim 2 for being articulated on girder steel, which is characterized in that institute Stating hook cross bar (23) has two, and hook cross bar (23) level is fixed on the top of two hooks vertical bar (22) End, another described hook cross bar (23) level are fixed on the bottom end of two hooks vertical bar (22).
4. the high altitude operation operating platform bracket according to claim 3 for being articulated on girder steel, which is characterized in that every The bottom of piece hook vertical bar (22) is respectively and fixedly provided with a chain (24), and the length of the chain (24) is greater than the connection The length of bar (21).
5. the high altitude operation operating platform bracket according to claim 4 for being articulated on girder steel, which is characterized in that institute It states support frame vertical bar (11) and support frame as described above cross bar (12) is stainless steel square tube, and all support frame as described above cross bars (12) It is welded and fixed respectively with a pair of of support frame as described above vertical bar (11);
The connecting rod (21), the hook vertical bar (22) and the hook cross bar (23) are stainless steel square tube, the chain Item (24) is made of stainless steel, and the connecting rod (21) is welded and fixed with support frame as described above vertical bar (11), described Connecting rod (21) and the hook vertical bar (22) are welded and fixed, and the hook vertical bar (22) and the hook cross bar (23) welding are solid Fixed, the chain (24) is welded and fixed with the corresponding hook vertical bar (22).
6. the high altitude operation operating platform bracket according to claim 5 for being articulated on girder steel, which is characterized in that institute Stating operating platform (3) includes the operating platform frame for being fixed on a pair of of support frame as described above vertical bar (11) bottom and being in horizontal distribution (31) and level is fixed in the operating platform frame (31) people from station platform (32) for being used to support worker's standing at work, The operating platform frame (31) is located at the side of support frame as described above (1).
7. the high altitude operation operating platform bracket according to claim 6 for being articulated on girder steel, which is characterized in that institute Operating platform frame (31) are stated in isosceles triangle, the first stainless steel tube of You Lianggen (33) the second stainless steel tube of He Yigen (34) is first Tail is welded, and first stainless steel tube (33) is longer than second stainless steel tube (34), two first stainless steel tubes (33) pad is also mutually welded with the bottom end of a support frame as described above vertical bar (11) simultaneously, and another support frame as described above is perpendicular The bottom end of bar (11) is located in the operating platform frame (31).
8. the high altitude operation operating platform bracket according to claim 7 for being articulated on girder steel, which is characterized in that institute Stating people from station platform (32) is the stainless steel cloth or stainless steel plate being welded in the operating platform frame (31), and two institutes State and be equidistantly welded at least two reinforcement steel pipes (35) between the first stainless steel tube (33), all reinforcement steel pipes (35) with Second stainless steel tube (34) is parallel, and bottom end is located at the support frame as described above vertical bar in the operating platform frame (31) (11) it is welded with wherein one interphase for reinforcing steel pipe (35).
9. the high altitude operation operating platform bracket according to claim 8 for being articulated on girder steel, which is characterized in that institute Stating operating platform (3) further includes having operating platform guardrail (36), and the operating platform guardrail (36) includes using a steel pipe folding Roll forming is simultaneously in isosceles triangle and is in the guardrail frame (37) of horizontal distribution, the reinforcing being welded in the guardrail frame (37) Steel pipe (38) and two or more are equidistantly welded in the operating platform guardrail connection of operating platform guardrail (36) bottom vertically Bar (39), all operating platform guardrail connecting rods (39) are distributed for one week around operating platform guardrail (36) bottom, institute State guardrail frame (37) face distribution identical and upper and lower with operating platform frame (31) size, all operating platforms Top of the bottom end of guardrail connecting rod (39) with the operating platform frame (31) is mutually welded, by the guardrail frame (37) With operating platform frame (31) Joint, the tip of the guardrail frame (37) and support frame as described above vertical bar (11) Lower part is mutually welded, and the lower part of another support frame as described above vertical bar (11) is located in the guardrail frame (37) and adds with described Gu the interphase of steel pipe (38) is welded.
10. the mounting side of the high altitude operation operating platform bracket described in claim 1-9 any one for being articulated on girder steel Method, which comprises the following steps:
Step 1: high altitude operation operating platform bracket is carried at the girder steel for needing hanging operation, high altitude operation is operated flat The hook structure of platform bracket is articulated on girder steel;
Step 2: adjustment high altitude operation operating platform backing positions, are located at operating platform and are suitable for hanging operation point;
Step 3: two chains are bypassed steel beam bottom respectively and are wound on respective support frame vertical bar, while with lock by chain Item and respective support frame vertical bar are locked, that is, complete the firm mounting of high altitude operation operating platform bracket.
CN201910289344.1A 2019-04-11 2019-04-11 High altitude operation operating platform bracket and its hooking method for being articulated on girder steel Pending CN109958272A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910289344.1A CN109958272A (en) 2019-04-11 2019-04-11 High altitude operation operating platform bracket and its hooking method for being articulated on girder steel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910289344.1A CN109958272A (en) 2019-04-11 2019-04-11 High altitude operation operating platform bracket and its hooking method for being articulated on girder steel

Publications (1)

Publication Number Publication Date
CN109958272A true CN109958272A (en) 2019-07-02

Family

ID=67025996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910289344.1A Pending CN109958272A (en) 2019-04-11 2019-04-11 High altitude operation operating platform bracket and its hooking method for being articulated on girder steel

Country Status (1)

Country Link
CN (1) CN109958272A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096042A (en) * 2020-09-22 2020-12-18 中国十七冶集团有限公司 Aerial work platform for construction on steel beam and use method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203441073U (en) * 2013-08-23 2014-02-19 广州建筑股份有限公司 Hoop-type high-altitude guard platform suitable for super high-rise building outline boarder structural column
CN204552054U (en) * 2015-03-04 2015-08-12 杭州建工集团有限责任公司 A kind of telescopic work high above the ground hanger bracket
CN204983608U (en) * 2015-10-09 2016-01-20 多维联合集团有限公司 Hanging flower basket is used in installation
US20160177583A1 (en) * 2013-01-23 2016-06-23 Eric William Kurtz Modular Roof Mounted Staging Bracket With Safety Rails
CN206053276U (en) * 2016-07-19 2017-03-29 中建钢构有限公司 Steel construction high altitude operation platform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20160177583A1 (en) * 2013-01-23 2016-06-23 Eric William Kurtz Modular Roof Mounted Staging Bracket With Safety Rails
CN203441073U (en) * 2013-08-23 2014-02-19 广州建筑股份有限公司 Hoop-type high-altitude guard platform suitable for super high-rise building outline boarder structural column
CN204552054U (en) * 2015-03-04 2015-08-12 杭州建工集团有限责任公司 A kind of telescopic work high above the ground hanger bracket
CN204983608U (en) * 2015-10-09 2016-01-20 多维联合集团有限公司 Hanging flower basket is used in installation
CN206053276U (en) * 2016-07-19 2017-03-29 中建钢构有限公司 Steel construction high altitude operation platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096042A (en) * 2020-09-22 2020-12-18 中国十七冶集团有限公司 Aerial work platform for construction on steel beam and use method
CN112096042B (en) * 2020-09-22 2022-06-10 中国十七冶集团有限公司 Aerial work platform for construction on steel beam and use method

Similar Documents

Publication Publication Date Title
CN103206074B (en) Elevator shaft template construction method, platform and support
CN104948211A (en) Large mining height end-mining net hanging process
US2136696A (en) Scaffold
CN205875666U (en) A platform suspends in midair that is used for building eaves oral area position to be under construction
CN109958272A (en) High altitude operation operating platform bracket and its hooking method for being articulated on girder steel
CN205908004U (en) Special hoist and mount fixing device of hanging flower basket
CN211173007U (en) Novel tripod of encorbelmenting
CN105952130B (en) A kind of suspension platform installation method for the construction of building cornice position
CN102182324A (en) Anti-falling safety net
JP2018193731A (en) Simple type scaffold for steel tower
CN213268819U (en) Platform of standing is assisted in aerial work
CN102704692A (en) Reinforcing steel bar hanging stool and using method thereof
CN208518308U (en) Soft operation platform for daylighting roof construction
CN208220148U (en) A kind of construction safety scaffold that stability is good
CN2267294Y (en) Hanging scaffolds made of steel rope
CN208039041U (en) Travelling cradle for bridge construction
CN207749810U (en) A kind of Novel moveable scaffold
CN109488098A (en) A kind of vertical electric power steel pole of segmentation group
CN206646838U (en) Self-interacting type steel plate wall corrects trivet
CN221001896U (en) Bracket
CN213204918U (en) High altitude eaves construction protector that encorbelments
CN215107207U (en) Hanging flower basket after-poppet fixed component
CN218438161U (en) Slidable ladder-type hanging basket
CN213626573U (en) Higher scaffold of security
CN206844628U (en) Multi-use architecture security protection scaffold plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190702