CN205908004U - Special hoist and mount fixing device of hanging flower basket - Google Patents

Special hoist and mount fixing device of hanging flower basket Download PDF

Info

Publication number
CN205908004U
CN205908004U CN201620918289.XU CN201620918289U CN205908004U CN 205908004 U CN205908004 U CN 205908004U CN 201620918289 U CN201620918289 U CN 201620918289U CN 205908004 U CN205908004 U CN 205908004U
Authority
CN
China
Prior art keywords
hanging basket
supporting rod
column
fixing device
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201620918289.XU
Other languages
Chinese (zh)
Inventor
孙英棋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Nuclear Engineering Co Ltd
Original Assignee
PowerChina Group Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Group Environmental Engineering Co Ltd filed Critical PowerChina Group Environmental Engineering Co Ltd
Priority to CN201620918289.XU priority Critical patent/CN205908004U/en
Application granted granted Critical
Publication of CN205908004U publication Critical patent/CN205908004U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

本实用新型公开了一种吊篮专用吊装固定装置,安装在屋面女儿墙的立柱之间,包括两个悬挑固定架,两个悬挑固定架的悬挑端之间固定安装有横梁,横梁上安装有位置可调的吊篮拉绳,吊篮拉绳的端部与吊篮连接;所述悬挑固定架包括竖支撑杆,所述竖支撑杆上固定安装有两组与所述立柱固定连接的抱立柱装置,所述竖支撑杆的顶端固定安装有横支撑杆,所述立柱的上端面抵靠在所述横支撑杆的下方,所述横支撑杆的自由端与所述横梁固定连接;本实用新型采用抱立柱设计,连接牢固,安全可靠;悬挑固定架轻便可移动、拆卸,可以轻松实现重复利用;悬挑固定架结构简单、合理、安全性能高、方便安装和操作,解决了吊篮在其复杂工作面不易吊装及移动的难题。

The utility model discloses a special hoisting and fixing device for a hanging basket, which is installed between upright columns of a roof parapet, and comprises two cantilevered fixing frames, and a beam is fixedly installed between the cantilevered ends of the two cantilevered fixing frames. A hanging basket pull rope with adjustable position is installed on it, and the end of the hanging basket pull rope is connected with the hanging basket; An upright column device fixedly connected, the top end of the vertical support bar is fixedly installed with a horizontal support bar, the upper end surface of the column is against the bottom of the horizontal support bar, and the free end of the horizontal support bar is connected to the cross beam Fixed connection; the utility model adopts the design of holding columns, the connection is firm, safe and reliable; the cantilevered fixed frame is light, removable and disassembled, and can be easily reused; the cantilevered fixed frame has a simple and reasonable structure, high safety performance, and is convenient for installation and operation , which solves the problem that the hanging basket is not easy to hoist and move on its complex working surface.

Description

吊篮专用吊装固定装置Special hoisting and fixing device for hanging basket

技术领域technical field

本实用新型涉及高空吊装技术领域,尤其涉及一种用于吊篮吊装及固定的吊装工具。The utility model relates to the technical field of high-altitude hoisting, in particular to a hoisting tool used for hoisting and fixing a hanging basket.

背景技术Background technique

安全生产现已是工程施工中的重中之重,而随着社会的不断发展,越来越多的高风险施工项目的出现,必须要有新的施工方案和相应的设备以满足工程施工的需要及现场施工的安全保证。Safety production is now the top priority in engineering construction, and with the continuous development of society, more and more high-risk construction projects appear, and new construction plans and corresponding equipment must be available to meet the requirements of engineering construction. Needs and safety guarantees for on-site construction.

抱女儿墙立柱悬挑架安装主要有以下施工方案:The installation of the cantilever frame of the column of the parapet wall mainly has the following construction schemes:

早期电力建设领域大型设备的吊装主要使用卷扬机提升方案,该方案存在以下缺点:①由于卷扬机起重能力有限,使用此方案需要在被吊件上设置多个吊点,使用多台卷扬机同时工作,而各台卷扬机同步动作难以实现,因此吊装过程冲击很大,安全性能差;②为实现被吊件的移动,确保拖拽过程中设备不受额外载荷的影响,需要保证拖拽钢丝绳走向与被吊件移动方向的夹角不大于设计要求,这就需要在被吊件移动沿途的构筑物上为拖拽钢丝绳布置多个转向滑轮,对构筑物的强度等力学性能提出了许多附加要求,施工成本增加;③施工占用场地大,由于需要通过多级滑轮组和钢丝绳等,导致整个系统危险点多、环节复杂,可控性差;④卷扬机操控对于电源依赖程度高,吊装过程中不能失去电力,否则无法制动,导致吊装存在重大安全隐患。The hoisting scheme of large-scale equipment in the field of electric power construction in the early days mainly used the hoisting scheme. This scheme has the following disadvantages: ①Due to the limited lifting capacity of the hoisting machine, using this scheme requires setting multiple lifting points on the hoisted parts and using multiple hoisting machines to work at the same time. However, it is difficult to realize the synchronous action of each hoist, so the hoisting process has a large impact and poor safety performance; The included angle of the moving direction of the hanger is not greater than the design requirement, which requires arranging multiple diverting pulleys for the dragging wire rope on the structure along the way the hanger moves, which puts forward many additional requirements for the strength and other mechanical properties of the structure, and increases the construction cost ; ③The construction site is large, and because it needs to pass through multi-stage pulley blocks and wire ropes, etc., the whole system has many dangerous points, complicated links, and poor controllability; movement, resulting in major safety hazards in hoisting.

由于以上缺点,卷扬机提升方案已经基本淘汰,为确保安全的前提下同时满足现场的施工需要,悬挑固定架则更适用于现在的施工现场。Due to the above shortcomings, the lifting scheme of the hoist has been basically eliminated. In order to meet the construction needs of the site while ensuring safety, the cantilever fixing frame is more suitable for the current construction site.

实用新型内容Utility model content

本实用新型所要解决的技术问题是提供一种使用方便、安全可靠且成本低的吊篮专用吊装固定装置。The technical problem to be solved by the utility model is to provide a special hoisting and fixing device for hanging baskets which is convenient to use, safe, reliable and low in cost.

为解决上述技术问题,本实用新型的技术方案是:吊篮专用吊装固定装置,安装在屋面女儿墙的立柱之间,包括两个悬挑固定架,两个所述悬挑固定架的悬挑端之间固定安装有横梁,所述横梁上安装有位置可调的吊篮拉绳,所述吊篮拉绳的端部与吊篮连接;In order to solve the above-mentioned technical problems, the technical solution of the utility model is: a special hoisting and fixing device for hanging baskets, installed between the columns of the roof parapet, including two cantilevered fixing frames, and the cantilevered parts of the two cantilevered fixing frames A crossbeam is fixedly installed between the ends, and a position-adjustable hanging basket stay rope is installed on the crossbeam, and the end of the hanging basket stay rope is connected with the hanging basket;

所述悬挑固定架包括竖支撑杆,所述竖支撑杆上固定安装有两组与所述立柱固定连接的抱立柱装置,所述竖支撑杆的顶端固定安装有横支撑杆,所述立柱的上端面抵靠在所述横支撑杆的下方,所述横支撑杆的自由端与所述横梁固定连接。The cantilevered fixing frame includes a vertical support rod, on which two sets of upright column devices fixedly connected with the upright column are fixedly installed, and a horizontal support rod is fixedly installed on the top of the vertical support rod, and the upright column The upper end surface of the upper end is against the lower part of the horizontal support rod, and the free end of the horizontal support rod is fixedly connected with the cross beam.

作为一种优选的技术方案,所述横支撑杆与所述横梁连接的一端固定连接有吊物耳,所述吊物耳上设置有至少一个吊物孔。As a preferred technical solution, one end of the horizontal support rod connected to the cross beam is fixedly connected with an object hanging ear, and at least one object hanging hole is provided on the object hanging ear.

作为一种优选的技术方案,所述横支撑杆远离所述横梁的一端设置有分重过孔。As a preferred technical solution, the end of the cross support bar away from the cross beam is provided with a weight-dividing through hole.

作为一种优选的技术方案,所述抱立柱装置包括两个平行设置且与所述竖支撑杆固定连接的抱臂,两个所述抱臂延伸至所述立柱的另一侧且两个所述抱臂之间固定连接有加固螺栓,两个所述抱臂之间焊接有位于所述立柱一侧的加固钢板。As a preferred technical solution, the device for holding a column includes two arms arranged in parallel and fixedly connected with the vertical support bar, the two arms extend to the other side of the column and the two arms Reinforcement bolts are fixedly connected between the arms, and a reinforced steel plate on one side of the column is welded between the two arms.

作为一种优选的技术方案,所述吊篮拉绳为钢丝绳。As a preferred technical solution, the stay rope of the hanging basket is a steel wire rope.

作为一种优选的技术方案,所述横梁上安装有U型卡箍,所述U型卡箍的两个自由端部与所述横支撑杆固定连接。As a preferred technical solution, a U-shaped clamp is installed on the beam, and the two free ends of the U-shaped clamp are fixedly connected to the horizontal support rod.

由于采用了上述技术方案,吊篮专用吊装固定装置,安装在屋面女儿墙的立柱之间,包括两个悬挑固定架,两个所述悬挑固定架的悬挑端之间固定安装有横梁,所述横梁上安装有位置可调的吊篮拉绳,所述吊篮拉绳的端部与吊篮连接;所述悬挑固定架包括竖支撑杆,所述竖支撑杆上固定安装有两组与所述立柱固定连接的抱立柱装置,所述竖支撑杆的顶端固定安装有横支撑杆,所述立柱的上端面抵靠在所述横支撑杆的下方,所述横支撑杆的自由端与所述横梁固定连接;本实用新型采用抱立柱设计,连接牢固,安全可靠;悬挑固定架轻便可移动、拆卸,可以轻松实现重复利用;悬挑固定架结构简单、合理、安全性能高、方便安装和操作,解决了吊篮在其复杂工作面不易吊装及移动的难题。Due to the adoption of the above-mentioned technical scheme, the special hoisting and fixing device for the hanging basket is installed between the columns of the roof parapet, including two cantilevered fixing frames, and a beam is fixedly installed between the cantilevered ends of the two cantilevered fixing frames , a position-adjustable hanging basket stay rope is installed on the beam, and the end of the hanging basket stay rope is connected with the hanging basket; Two sets of column holding devices fixedly connected with the column, the top of the vertical support bar is fixedly installed with a horizontal support bar, the upper end surface of the column is against the bottom of the horizontal support bar, and the top of the horizontal support bar The free end is fixedly connected with the beam; the utility model adopts the design of holding a column, which is firmly connected, safe and reliable; the cantilevered fixed frame is light, removable and disassembled, and can be easily reused; the cantilevered fixed frame has a simple, reasonable and safe structure High, easy to install and operate, it solves the problem that the hanging basket is not easy to lift and move on the complex working surface.

附图说明Description of drawings

以下附图仅旨在于对本实用新型做示意性说明和解释,并不限定本实用新型的范围。其中:The following drawings are only intended to illustrate and explain the utility model schematically, and do not limit the scope of the utility model. in:

图1是本实用新型实施例的结构示意图;Fig. 1 is the structural representation of the utility model embodiment;

图2是图1中A-A向剖视图;Fig. 2 is A-A to sectional view among Fig. 1;

图中:1-立柱;2-横梁;31-竖支撑杆;32-抱臂;33-加固钢板;34-横支撑杆;4-U型卡箍;51-吊物耳;52-吊物孔;6-分重过孔。In the figure: 1-column; 2-beam; 31-vertical support rod; 32-arm; 33-reinforced steel plate; 34-horizontal support rod; 4-U-shaped clamp; Holes; 6-point heavy vias.

具体实施方式detailed description

下面结合附图和实施例,进一步阐述本实用新型。在下面的详细描述中,只通过说明的方式描述了本实用新型的某些示范性实施例。毋庸置疑,本领域的普通技术人员可以认识到,在不偏离本实用新型的精神和范围的情况下,可以用各种不同的方式对所描述的实施例进行修正。因此,附图和描述在本质上是说明性的,而不是用于限制权利要求的保护范围。Below in conjunction with accompanying drawing and embodiment, further set forth the utility model. In the following detailed description, certain exemplary embodiments of the present invention are described by way of illustration only. Needless to say, those skilled in the art would realize that the described embodiments may be modified in various different ways, all without departing from the spirit and scope of the present invention. Accordingly, the drawings and description are illustrative in nature and not intended to limit the scope of the claims.

如图1和图2所示,吊篮专用吊装固定装置,安装在屋面女儿墙的立柱1之间,包括两个悬挑固定架,两个所述悬挑固定架的悬挑端之间固定安装有横梁2,所述横梁2上安装有位置可调的吊篮拉绳(图中未示出),所述吊篮拉绳为钢丝绳,所述吊篮拉绳的端部与吊篮连接;As shown in Figure 1 and Figure 2, the special hoisting and fixing device for the hanging basket is installed between the columns 1 of the roof parapet, including two cantilevered fixing frames, and the cantilevered ends of the two cantilevered fixing frames are fixed A crossbeam 2 is installed, and a position-adjustable hanging basket stay rope (not shown) is installed on the crossbeam 2, and the hanging basket stay rope is a steel wire rope, and the end of the hanging basket stay rope is connected with the hanging basket ;

所述悬挑固定架包括竖支撑杆31,所述竖支撑杆31上固定安装有两组与所述立柱1固定连接的抱立柱1装置,所述抱立柱1装置包括两个平行设置且与所述竖支撑杆31固定连接的抱臂32,两个所述抱臂32延伸至所述立柱1的另一侧且两个所述抱臂32之间固定连接有加固螺栓(图中未示出),两个所述抱臂32之间焊接有位于所述立柱1一侧的加固钢板33。The cantilevered fixed frame includes a vertical support bar 31, and two groups of embracing column 1 devices fixedly connected with the column 1 are fixedly installed on the vertical support bar 31, and the embracing column 1 device includes two parallel arrangements and The arms 32 fixedly connected to the vertical support bar 31, the two arms 32 extend to the other side of the column 1 and the two arms 32 are fixedly connected with reinforcing bolts (not shown in the figure). Out), a reinforcement steel plate 33 on one side of the column 1 is welded between the two arms 32 .

所述竖支撑杆31的顶端固定安装有横支撑杆34,所述立柱1的上端面抵靠在所述横支撑杆34的下方,所述横支撑杆34的自由端与所述横梁2固定连接,所述横梁2上安装有U型卡箍4,所述U型卡箍4的两个自由端部与所述横支撑杆34固定连接。所述横支撑杆34与所述横梁2连接的一端固定连接有吊物耳51,所述吊物耳51上设置有至少一个吊物孔52,例如设置两个吊物孔52,更加方便吊篮拉绳的挂设。所述横支撑杆34远离所述横梁2的一端设置有分重过孔6,在现场复杂的情况下为钢丝绳穿孔预留,大大提高了悬挑固定架的安全和稳定性。The top end of the vertical support rod 31 is fixedly equipped with a horizontal support rod 34, the upper end surface of the column 1 is against the below of the horizontal support rod 34, and the free end of the horizontal support rod 34 is fixed to the cross beam 2 The crossbeam 2 is connected with a U-shaped clamp 4, and the two free ends of the U-shaped clamp 4 are fixedly connected with the horizontal support rod 34. One end of the cross support rod 34 connected to the crossbeam 2 is fixedly connected with a hanging object ear 51, and the hanging object ear 51 is provided with at least one hanging object hole 52, for example, two hanging object holes 52 are set, which is more convenient for hanging objects. Basket drawstring hanger. The end of the cross support bar 34 far away from the cross beam 2 is provided with a sub-weight through hole 6, which is reserved for the steel wire rope perforation in complex situations on site, which greatly improves the safety and stability of the cantilevered fixing frame.

本实用新型采用的原材料可以采用生产过程中产生的余料,节约能源、降本提效,例如,横梁2采用10#工字钢,横支撑杆34采用20#工字钢,竖支撑杆31和抱臂32均可采用10#槽钢。The raw material that the utility model adopts can adopt the surplus material that produces in the production process, saves energy, reduces cost and improves efficiency, for example, crossbeam 2 adopts 10# I-beam, horizontal support bar 34 adopts 20# I-beam, and vertical support bar 31 And embracing arm 32 all can adopt 10# channel steel.

本实用新型采用抱立柱1设计,连接牢固,安全可靠;悬挑固定架轻便可移动、拆卸,可以轻松实现重复利用;悬挑固定架结构简单、合理、安全性能高、方便安装和操作,解决了吊篮在其复杂工作面不易吊装及移动的难题。The utility model adopts the design of the holding column 1, which is firmly connected, safe and reliable; the cantilevered fixed frame is light and movable, disassembled, and can be easily reused; the cantilevered fixed frame has a simple and reasonable structure, high safety performance, convenient installation and operation, and solves the problem of It solves the problem that the hanging basket is not easy to hoist and move on its complex working surface.

悬挑固定架以抱女儿墙立柱1的形式固定,在两个悬挑固定架端头加上10#工字钢固定,吊绳固定在10#工字钢上,保证两吊绳间距可调。The cantilevered fixing frame is fixed in the form of holding the parapet column 1, and the ends of the two cantilevered fixing frames are fixed with 10# I-beam, and the hanging rope is fixed on the 10# I-beam to ensure that the distance between the two hanging ropes can be adjusted .

本实用新型相关的计算公式如下:The calculation formula related to the utility model is as follows:

1.吊篮计算:1. Basket calculation:

吊篮风荷载计算:Qwk=wk×F=0.5kN/m2×4.046m2=2.023kNCalculation of wind load on hanging basket: Q wk =w k ×F=0.5kN/m 2 ×4.046m 2 =2.023kN

式中:Qwk——吊篮的风荷载标准值(kN);In the formula: Q wk —— wind load standard value of hanging basket (kN);

wk——风荷载标准值,wk=500Pa=0.5kN/m2;w k — standard value of wind load, w k = 500Pa = 0.5kN/m 2 ;

F——吊篮受风面积,F=4.046m2。F——The wind-receiving area of the hanging basket, F=4.046m 2 .

2、钢丝绳承载力验算2. Check calculation of steel wire rope bearing capacity

根据GB19155-2003《高处作业吊篮》第5.4.6.2条要求,钢丝绳安全系数不应小于9。According to the requirements of Article 5.4.6.2 of GB19155-2003 "Basket for Working at Heights", the safety factor of the wire rope should not be less than 9.

选用钢丝绳:<6×19W+IWS-8.60>规格,最小破断拉力为67kN。Select steel wire rope: <6×19W+IWS-8.60> specification, the minimum breaking force is 67kN.

1)吊篮动力钢丝绳所受竖向荷载:1) The vertical load on the dynamic wire rope of the hanging basket:

Q1=(Gk+Qk)/2=(6.76+7)/2=6.88kNQ 1 =(G k +Q k )/2=(6.76+7)/2=6.88kN

式中:Q1——吊篮动力钢丝绳竖向荷载标准值(kN);In the formula: Q 1 ——Standard value of the vertical load of the dynamic steel wire rope of the hanging basket (kN);

Gk——吊篮及钢丝绳自重标准值,G k ——Standard value of self-weight of hanging basket and steel wire rope,

Gk=(120+20+332+174+10+20)×10=6760N=6.76kNG k = (120+20+332+174+10+20)×10=6760N=6.76kN

其中:钢丝绳重量:0.3kg/m×4根×100m=120kgAmong them: wire rope weight: 0.3kg/m×4×100m=120kg

电缆线重量:0.2kg/m×1根×100m=20kgCable weight: 0.2kg/m x 1 x 100m = 20kg

平台总重量:332kg(以最长的6m平台计算)Total platform weight: 332kg (calculated on the longest 6m platform)

提升机重量:53kg×2=174kgHoist weight: 53kg×2=174kg

安全锁重量:5kg×2=10kgSafety lock weight: 5kg×2=10kg

电控箱重量:20kg;Electric control box weight: 20kg;

Qk——施工活荷载标准值,Qk=700×10=7000N=7kNQ k — Standard value of construction live load, Q k = 700 × 10 = 7000N = 7kN

其中:吊篮最大安全载重量为700kg。Among them: the maximum safe load capacity of the hanging basket is 700kg.

2)吊篮动力钢丝绳所受水平荷载:2) The horizontal load on the dynamic wire rope of the hanging basket:

Q2=Qwk/2=2.023/2=1.012kNQ 2 =Q wk /2=2.023/2=1.012kN

式中:Qwk——吊篮的风荷载标准值,Qwk=2.023kN。In the formula: Q wk —— wind load standard value of the hanging basket, Q wk = 2.023kN.

3)吊篮在使用时,动力钢丝绳所受拉力为:3) When the hanging basket is in use, the tension on the dynamic wire rope is:

QQ DD. == KK QQ 11 22 ++ QQ 22 22 == 99 6.886.88 22 ++ 1.0121.012 22 == 62.5962.59 kk NN << 6767 kk NN

式中:QD——动力钢丝绳所受拉力的施工核算值(kN);In the formula: Q D —— the construction calculation value of the tensile force on the dynamic steel wire rope (kN);

K——安全系数,选取9。K——safety factor, choose 9.

经计算证明,施工中6×19W+IWS-8.6规格钢丝绳符合GB19155-2003吊篮标准5.4.6.2的安全要求。It is proved by calculation that the 6×19W+IWS-8.6 steel wire rope in construction meets the safety requirements of GB19155-2003 Hanging Basket Standard 5.4.6.2.

2.抱女儿墙立柱1吊篮悬挑架计算:2. The calculation of the cantilever frame of the parapet column 1 hanging basket:

20#工字钢抗弯强度验算:M=FL=5500×800=4400000N·mmBending strength check calculation of 20# I-beam: M=FL=5500×800=4400000N·mm

σ=M/W=4400000/237×103=18.6N/mm2<205N/mm2,满足要求。σ=M/W=4400000/237×103=18.6N/mm2<205N/mm2, meeting the requirements.

挠度验算:ω=(Fa2L/12EI)×(3+4a/l)=(55000×2002×800/12×2.06×105×245×104)×(3+4×200/800)=0.25mm<800/400=2mm,满足要求。Deflection checking: ω=(Fa2L/12EI)×(3+4a/l)=(55000×2002×800/12×2.06×105×245×104)×(3+4×200/800)=0.25mm< 800/400=2mm, which meets the requirements.

焊缝受剪验算:τ=F/A=7000/(400×8+40*8)=1.99N/mm2<120N/mm2。Weld shear check calculation: τ=F/A=7000/(400×8+40*8)=1.99N/mm2<120N/mm2.

20#工字钢与槽钢焊缝受拉验算:σ=F/A=7000/((100+68+68)*2)=14.83N/mm2<205N/mm2。20# I-beam and channel steel weld tension check: σ=F/A=7000/((100+68+68)*2)=14.83N/mm2<205N/mm2.

吊耳焊缝受拉验算:σ=F/A=7000/(400×8)=2.2N/mm2<205N/mm2。Tensile check of lug weld: σ=F/A=7000/(400×8)=2.2N/mm2<205N/mm2.

10#工字钢抗弯验算:以最大弯矩处进行计算,当吊篮处在工字钢中间位置处时,M=F*L/8=14000*3000/8=5250000N·mm。Bending calculation of 10# I-beam: Calculate at the maximum bending moment, when the hanging basket is in the middle of the I-beam, M=F*L/8=14000*3000/8=5250000N·mm.

σ=M/W=5250000/49×103=107.5N/mm2<205N/mm2,满足要求。σ=M/W=5250000/49×103=107.5N/mm2<205N/mm2, meeting the requirements.

挠度验算:ω=FL3/192EI=14000×8003/192×2.06×105×245×104=0.07mm<3000/400=7.5mm满足要求。Deflection checking calculation: ω=FL3/192EI=14000×8003/192×2.06×105×245×104=0.07mm<3000/400=7.5mm meets the requirements.

10#工字钢与20#工字钢之间焊缝强度验算:σ=F/A=7000/(468×8)=1.87N/mm2<205N/mm2,满足要求。Check calculation of weld strength between 10# I-beam and 20# I-beam: σ=F/A=7000/(468×8)=1.87N/mm2<205N/mm2, which meets the requirements.

20mm厚背楞加固抗弯验算:σ=M/W=7000*1000/(2×102/6+7.8)×103=170.2N/mm2<205N/mm2,满足要求20mm thick back corrugated reinforced bending calculation: σ=M/W=7000*1000/(2×102/6+7.8)×103=170.2N/mm2<205N/mm2, meeting the requirements

以上显示和描述了本实用新型的基本原理、主要特征及本实用新型的优点。本行业的技术人员应该了解,本实用新型不受上述实施例的限制,上述实施例和说明书中描述的只是说明本实用新型的原理,在不脱离本实用新型精神和范围的前提下,本实用新型还会有各种变化和改进,这些变化和改进都落入要求保护的本实用新型范围内。本实用新型要求保护范围由所附的权利要求书及其等效物界定。The basic principles, main features and advantages of the present utility model have been shown and described above. Those skilled in the art should understand that the utility model is not limited by the above-mentioned embodiments. The above-mentioned embodiments and descriptions only illustrate the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model The new model also has various changes and improvements, and these changes and improvements all fall within the scope of the claimed utility model. The scope of protection required by the utility model is defined by the appended claims and their equivalents.

Claims (6)

1. hanging basket special hoisting fixing device, be arranged between the column of parapet of roofing it is characterised in that: include two encorbelment Fixed mount, encorbelmenting of fixed mount of encorbelmenting described in two is installed with crossbeam between end, described crossbeam is provided with position adjustable Hanging basket drawstring, the end of described hanging basket drawstring is connected with hanging basket;
Described fixed mount of encorbelmenting includes vertical supporting rod, described vertical supporting rod is installed with two groups and is fixedly connected with described column Embrace stand column device, the top of described vertical supporting rod is installed with transverse supporting rod, and the upper surface of described column is resisted against described The lower section of transverse supporting rod, the free end of described transverse supporting rod is fixedly connected with described crossbeam.
2. hanging basket special hoisting fixing device as claimed in claim 1 it is characterised in that: described transverse supporting rod and described crossbeam The one end connecting is fixedly connected with and hangs thing ear, and described hanging is provided with least one and hangs thing hole on thing ear.
3. hanging basket special hoisting fixing device as claimed in claim 1 it is characterised in that: described transverse supporting rod is away from described horizontal stroke One end of beam is provided with a point weight via.
4. hanging basket special hoisting fixing device as claimed in claim 1 it is characterised in that: described armful of stand column device includes two The arm be arrangeding in parallel and being fixedly connected with described vertical supporting rod, two described arms extend to the opposite side and two of described column It is fixedly connected with reinforcing bolt between individual described arm, between two described arms, be welded with the reinforcing positioned at described column side Steel plate.
5. hanging basket special hoisting fixing device as claimed in claim 1 it is characterised in that: described hanging basket drawstring be steel wire rope.
6. the hanging basket special hoisting fixing device as described in claim 1 to 5 any claim it is characterised in that: described horizontal stroke U-shaped clip is provided with beam, the two free ends of described u-shaped clip are fixedly connected with described transverse supporting rod.
CN201620918289.XU 2016-08-22 2016-08-22 Special hoist and mount fixing device of hanging flower basket Expired - Lifetime CN205908004U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620918289.XU CN205908004U (en) 2016-08-22 2016-08-22 Special hoist and mount fixing device of hanging flower basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620918289.XU CN205908004U (en) 2016-08-22 2016-08-22 Special hoist and mount fixing device of hanging flower basket

Publications (1)

Publication Number Publication Date
CN205908004U true CN205908004U (en) 2017-01-25

Family

ID=57801464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620918289.XU Expired - Lifetime CN205908004U (en) 2016-08-22 2016-08-22 Special hoist and mount fixing device of hanging flower basket

Country Status (1)

Country Link
CN (1) CN205908004U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109809339A (en) * 2018-12-27 2019-05-28 大唐观音岩水电开发有限公司 Underwater movable hanging basket
CN111550062A (en) * 2020-06-01 2020-08-18 中建七局第二建筑有限公司 Hoisting steel frame design method applied to field of building curtain wall
CN115949225A (en) * 2023-03-14 2023-04-11 山东金城建设有限公司 Self-balancing installation and construction method for outer decoration hanging basket under inclined roof working condition

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109809339A (en) * 2018-12-27 2019-05-28 大唐观音岩水电开发有限公司 Underwater movable hanging basket
CN111550062A (en) * 2020-06-01 2020-08-18 中建七局第二建筑有限公司 Hoisting steel frame design method applied to field of building curtain wall
CN115949225A (en) * 2023-03-14 2023-04-11 山东金城建设有限公司 Self-balancing installation and construction method for outer decoration hanging basket under inclined roof working condition

Similar Documents

Publication Publication Date Title
CN100590277C (en) Overhead bridge type suspension scaffold
CN105401714B (en) Attached lifting scaffold and lifting method
CN202416829U (en) Turnover-free electric block inserted lift scaffold
CN101284628B (en) Hoisting method for framework of large tonnage pressing machine
CN209873592U (en) Lifting type movable auxiliary tool for installing variable-section cantilever on steel box girder
CN213572943U (en) A high-altitude working gondola with a high hanging bracket
CN104989111B (en) Steel construction high level construction method for hanging
CN204081437U (en) Climbing scaffold falling proof device
CN209975993U (en) Suspension cage
CN103991800A (en) Roof surface crane for building
CN210886924U (en) Maintenance platform in retractable double-cable-plane cable-stayed bridge tower stay cable area
CN106284961A (en) Small-sized attachment type raise scaffold
CN202865749U (en) Installation equipment of bridge guardrail framework
CN220014395U (en) Can have enough to meet need mounting bracket by intelligent integrated platform system bailey frame of equipping
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN212561213U (en) Railway pier top surrounding hanging basket safe operation platform
CN204038917U (en) Detachable external hanging type operating platform
CN212478505U (en) A detachable hanging basket truss support device
CN208934380U (en) A kind of Excitations for Long Span Suspension operating platform
CN207109614U (en) A kind of Hanging Basket for building
CN217479995U (en) Cantilever beam hanging basket construction assembled safety platform
CN218562984U (en) Reverse-pulling wall-riding type hanging basket protection system
CN216974136U (en) Novel portable hanging flower basket work platform of encorbelmenting
CN111979916B (en) Cable-stayed bridge tower part suspension construction method and suspension operation platform device
CN109779224A (en) Steel structure column overhead connection operating platform and construction method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 250100 No. 297 industrial North Road, Licheng District, Shandong, Ji'nan

Patentee after: POWERCHINA NUCLEAR ENGINEERING Co.,Ltd.

Address before: 250100 No. 297 industrial North Road, Licheng District, Shandong, Ji'nan

Patentee before: POWERCHINA NUCLEAR ENGINEERING Co.