CN109933863A - One kind being used for power plant's construct platform - Google Patents
One kind being used for power plant's construct platform Download PDFInfo
- Publication number
- CN109933863A CN109933863A CN201910142266.2A CN201910142266A CN109933863A CN 109933863 A CN109933863 A CN 109933863A CN 201910142266 A CN201910142266 A CN 201910142266A CN 109933863 A CN109933863 A CN 109933863A
- Authority
- CN
- China
- Prior art keywords
- module
- data
- building
- power plant
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 claims abstract description 37
- 238000012544 monitoring process Methods 0.000 claims abstract description 26
- 238000004088 simulation Methods 0.000 claims abstract description 21
- 238000004364 calculation method Methods 0.000 claims abstract description 16
- 230000010354 integration Effects 0.000 claims abstract description 12
- 238000012545 processing Methods 0.000 claims description 13
- 238000002372 labelling Methods 0.000 claims description 11
- 238000007781 pre-processing Methods 0.000 claims description 6
- 238000003672 processing method Methods 0.000 claims description 4
- 239000004035 construction material Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 6
- 238000005516 engineering process Methods 0.000 abstract description 3
- 238000013461 design Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 238000011161 development Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to construction systems technology fields, disclose a kind of for power plant's construct platform, including BIM model building module, simulation calculation module, update module, alert module, AR monitoring module and integration module;Constructing power plant's three-dimensional information model automatically by BIM information platform in the present invention can be improved efficiency, while build situation and whether data coincide for project information mark and functional promotion fining degree on threedimensional model and live-action map and real time contrast are practical.It can be found the problem early by constructing power plant's threedimensional model with BIM informatization platform, and it is handled, and it can reduce cost, by intelligent construct platform live-action map by project process, cost, quality Real-time Feedback in live-action map, it can be to entire project overall view monitoring, and manager is made to have telepresenc, whether the matching degree that can experience field data and actual conditions is true, can provide effective foundation for manager's decision.
Description
Technical field
The present invention relates to construction systems technology field, more particularly to a kind of is used for power plant's construct platform.
Background technique
BIM (Building Information Modeling) technology is that autodesk, inc. took the lead in proposing in 2002,
Being widely recognized as industry is obtained in the world at present, it can help to realize the integrated of architecture information, from building
Until building the termination of life cycle management, various information are integrated and a three-dimensional model information data always for design, construction, operation
In library, all parties such as design team, unit in charge of construction, installation fishery department and owner can be cooperated based on BIM, be had
Effect improves working efficiency, saves resource, reduces cost, to realize sustainable development.
The core of BIM is, using digitizing technique, to be mentioned by establishing virtual architectural engineering threedimensional model for this model
For the complete and consistent architectural engineering information bank of actual conditions.The information bank not only includes the geometry for describing building member
Information, professional attributes and status information further comprise the status information in non-component object (such as space, motor behavior).By this
A threedimensional model comprising architectural engineering information, substantially increases the Information Integration degree of architectural engineering, thus for building work
Journey item purpose relevant benefit side provides an engineering information exchange and shared platform.
Application number: CN201610752703.9, title are as follows: a kind of elevated structure BIM model modeling design method, the model
After foundation, not only whether the information such as spatial position, under-clearance, span, the construction size of bridge structure can be intuitively checked
Meet engine request.But monitoring and warning well can not be played the role of to the building site of hot work in progress.
Summary of the invention
The present invention provides a kind of for electricity for the disadvantage that control and monitoring are small, data feedback is inaccurate in the prior art
Factory's construct platform.
In order to solve the above-mentioned technical problem, the present invention is addressed by following technical proposals.
One kind being used for power plant's construct platform, including BIM model building module, simulation calculation module, update module, warning mould
Block, AR monitoring module and integration module;
BIM model building module, the construction data file for acquisition imported into BIM platform and generate simulation threedimensional model;
Data module is built in real time, for reading construction data deposit database in real time and being updated, will be counted in real time
Real-time three-dimensional model is generated according to BIM model building module is imported into;
Data constraint module generates restriction condition according to file destination, and lead for obtaining the file destination of construction power plant
Enter to simulation calculation module;
Simulation calculation module, for calculating the residual quantity number built in data module and data constraint module in the project in real time
According to differential data is then sent to alert module;
Alert module sends corresponding alert message for obtaining differential data, and according to differential data type;
AR outdoor scene generation module, including monitoring module and data labeling module, monitoring module by disposing on construction ground
Multiple monitoring cameras generate construction outdoor scene picture;Data labeling module obtains the building data built in data module in real time,
And it is labeled in the corresponding position of construction outdoor scene picture;
Integration module, for integrating and showing AR outdoor scene generation module and BIM model building module progress image.
Preferably, construction data file is CAD formatted file and PRO-E formatted file.
Preferably, architecture information include building type, building cost, construction material, building cost, building completeness,
Building size.
Preferably, further including processing module, processing module connects alert module, and processing module includes exception treatment module
And preprocessing module, the problem provides suggestion when exception treatment module is used for site operation;Preprocessing module is for giving
The estimated processing method prompt to go wrong out.
The present invention has significant technical effect: flat by BIM information in the present invention due to using above technical scheme
Platform constructs power plant's three-dimensional information model automatically can be improved efficiency, while project information being marked and threedimensional model and live-action map
Upper functional promotion fining degree and real time contrast is practical builds situation and whether data coincide.By with BIM informatization platform
Building power plant's threedimensional model can find the problem early, and be handled, and can reduce cost, and intelligent construct platform outdoor scene is passed through
Map by project process, cost, quality Real-time Feedback in live-action map, can be to entire project overall view monitoring, and make pipe
Reason person has telepresenc, and whether the matching degree that can experience field data and actual conditions is true, can mention for manager's decision
For effective foundation.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram for power plant's construct platform of the present invention;
Fig. 2 is a kind of flow diagram for power plant's construct platform of the present invention;
Fig. 3 is a kind of structural schematic diagram for processing module in power plant's construct platform of the present invention.
Specific embodiment
Present invention is further described in detail with embodiment with reference to the accompanying drawing.
Embodiment 1
As shown in Figure 1 to Figure 3, a kind of to be used for power plant's construct platform, including BIM model building module, simulation calculation module,
Update module, alert module, AR monitoring module and integration module;
BIM model building module, the construction data file for acquisition imported into BIM platform and generate simulation threedimensional model;
Data module is built in real time, for reading construction data deposit database in real time and being updated, will be counted in real time
Real-time three-dimensional model is generated according to BIM model building module is imported into;
Data constraint module generates restriction condition according to file destination, and lead for obtaining the file destination of construction power plant
Enter to simulation calculation module;
Simulation calculation module, for calculating the residual quantity number built in data module and data constraint module in the project in real time
According to differential data is then sent to alert module;
Alert module sends corresponding alert message for obtaining differential data, and according to differential data type;
AR outdoor scene generation module, including monitoring module and data labeling module, monitoring module by disposing on construction ground
Multiple monitoring cameras generate construction outdoor scene picture;Data labeling module obtains the building data built in data module in real time,
And it is labeled in the corresponding position of construction outdoor scene picture;
Integration module, for integrating and showing AR outdoor scene generation module and BIM model building module progress image.
Building data file is CAD formatted file and PRO-E formatted file.
Architecture information includes building type, building cost, construction material, building cost, building completeness, building size.
It further include processing module, processing module connects alert module, and processing module includes exception treatment module and pretreatment
Module, the problem provides suggestion when exception treatment module is used for site operation;Preprocessing module is predicted for providing
The processing method prompt of existing problem.
Constructing power plant's three-dimensional information model automatically by BIM information platform in the present invention can be improved efficiency, while by item
Functional promotion fining degree and real time contrast is practical builds situation sum number on mesh information labeling and threedimensional model and live-action map
According to whether coincideing.It can be found the problem, and be handled, and energy early by constructing power plant's threedimensional model with BIM informatization platform
Enough reduce cost, by intelligent construct platform live-action map by project process, cost, quality Real-time Feedback in live-action map,
Can be to entire project overall view monitoring, and manager is made to have telepresenc, of field data and actual conditions can be experienced
It is whether true with spending, effective foundation can be provided for manager's decision.
Embodiment 2
One kind being used for power plant's construct platform, including BIM model building module, simulation calculation module, update module, warning mould
Block, AR monitoring module and integration module;
BIM model building module, the construction data file for acquisition imported into BIM platform and generate simulation threedimensional model;
Data module is built in real time, for reading construction data deposit database in real time and being updated, will be counted in real time
Real-time three-dimensional model is generated according to BIM model building module is imported into;
Data constraint module generates restriction condition according to file destination, and lead for obtaining the file destination of construction power plant
Enter to simulation calculation module;
Simulation calculation module, for calculating the residual quantity number built in data module and data constraint module in the project in real time
According to differential data is then sent to alert module;
Alert module sends corresponding alert message for obtaining differential data, and according to differential data type;
AR outdoor scene generation module, including monitoring module and data labeling module, monitoring module by disposing on construction ground
Multiple monitoring cameras generate construction outdoor scene picture;Data labeling module obtains the building data built in data module in real time,
And it is labeled in the corresponding position of construction outdoor scene picture;
Integration module, for integrating and showing AR outdoor scene generation module and BIM model building module progress image.
It further include processing module, processing module connects alert module, and processing module includes exception treatment module and pretreatment
Module, the problem provides suggestion when exception treatment module is used for site operation;Preprocessing module is predicted for providing
The processing method prompt of existing problem.
Embodiment 3
One kind being used for power plant's construct platform, including BIM model building module, simulation calculation module, update module, warning mould
Block, AR monitoring module and integration module;
BIM model building module, the construction data file for acquisition imported into BIM platform and generate simulation threedimensional model;
Data module is built in real time, for reading construction data deposit database in real time and being updated, will be counted in real time
Real-time three-dimensional model is generated according to BIM model building module is imported into;
Data constraint module generates restriction condition according to file destination, and lead for obtaining the file destination of construction power plant
Enter to simulation calculation module;
Simulation calculation module, for calculating the residual quantity number built in data module and data constraint module in the project in real time
According to differential data is then sent to alert module;
Alert module sends corresponding alert message for obtaining differential data, and according to differential data type;
AR outdoor scene generation module, including monitoring module and data labeling module, monitoring module by disposing on construction ground
Multiple monitoring cameras generate construction outdoor scene picture;Data labeling module obtains the building data built in data module in real time,
And it is labeled in the corresponding position of construction outdoor scene picture;
Integration module, for integrating and showing AR outdoor scene generation module and BIM model building module progress image.
In short, the foregoing is merely presently preferred embodiments of the present invention, it is all according to equalization made by scope of the present invention patent
Variation and modification, shall all be covered by the patent of the invention.
Claims (4)
1. one kind is used for power plant's construct platform, it is characterised in that: including BIM model building module, simulation calculation module, update mould
Block, alert module, AR monitoring module and integration module;
BIM model building module, the construction data file for acquisition imported into BIM platform and generate simulation threedimensional model;
Data module is built in real time, and for reading construction data deposit database in real time and being updated, real time data is led
Enter to BIM model building module to generate real-time three-dimensional model;
Data constraint module generates restriction condition according to file destination, and imported into for obtaining the file destination of construction power plant
Simulation calculation module;
Simulation calculation module, for calculating the differential data built in data module and data constraint module in the project in real time,
Then differential data is sent to alert module;
Alert module sends corresponding alert message for obtaining differential data, and according to differential data type;
AR outdoor scene generation module, including monitoring module and data labeling module, monitoring module are multiple by disposing on construction ground
Monitoring camera generates construction outdoor scene picture;Data labeling module obtains the building data built in data module in real time, and marks
Note is in the corresponding position of construction outdoor scene picture;
Integration module, for integrating and showing AR outdoor scene generation module and BIM model building module progress image.
2. according to claim 1 a kind of for power plant's construct platform, it is characterised in that: construction data file is CAD lattice
Formula file and PRO-E formatted file.
3. according to claim 1 a kind of for power plant's construct platform, it is characterised in that: architecture information includes Building class
Type, building cost, construction material, building cost, building completeness, building size.
4. according to claim 1 a kind of for power plant's construct platform, it is characterised in that: it further include processing module, processing
Module connects alert module, and processing module includes exception treatment module and preprocessing module, and exception treatment module with applying on site
Working hour, the problem provided suggestion;Preprocessing module is used to provide the estimated processing method prompt to go wrong.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910142266.2A CN109933863A (en) | 2019-02-26 | 2019-02-26 | One kind being used for power plant's construct platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910142266.2A CN109933863A (en) | 2019-02-26 | 2019-02-26 | One kind being used for power plant's construct platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109933863A true CN109933863A (en) | 2019-06-25 |
Family
ID=66985897
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910142266.2A Pending CN109933863A (en) | 2019-02-26 | 2019-02-26 | One kind being used for power plant's construct platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109933863A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112287425A (en) * | 2020-09-17 | 2021-01-29 | 中国建筑股份有限公司 | Municipal engineering measurement positioning method and system |
CN115130998A (en) * | 2022-07-05 | 2022-09-30 | 广州高新工程顾问有限公司 | BIM-based decoration project construction quality process control system and method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105719200A (en) * | 2016-01-19 | 2016-06-29 | 上海杰图天下网络科技有限公司 | Method for carrying out engineering progress supervision by use of three-dimensional panoramic technology by combining BIM technology |
CN108764668A (en) * | 2018-05-15 | 2018-11-06 | 浙江大学 | A kind of facilities management system and method based on BIM technology |
CN108920750A (en) * | 2018-05-24 | 2018-11-30 | 武汉八维时空信息技术股份有限公司 | The fusion of engineering-built Dynamic and Multi dimensional information and cooperation interaction system |
CN109377066A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | A kind of live Schedule monitoring system and method based on threedimensional model |
-
2019
- 2019-02-26 CN CN201910142266.2A patent/CN109933863A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105719200A (en) * | 2016-01-19 | 2016-06-29 | 上海杰图天下网络科技有限公司 | Method for carrying out engineering progress supervision by use of three-dimensional panoramic technology by combining BIM technology |
CN108764668A (en) * | 2018-05-15 | 2018-11-06 | 浙江大学 | A kind of facilities management system and method based on BIM technology |
CN108920750A (en) * | 2018-05-24 | 2018-11-30 | 武汉八维时空信息技术股份有限公司 | The fusion of engineering-built Dynamic and Multi dimensional information and cooperation interaction system |
CN109377066A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | A kind of live Schedule monitoring system and method based on threedimensional model |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112287425A (en) * | 2020-09-17 | 2021-01-29 | 中国建筑股份有限公司 | Municipal engineering measurement positioning method and system |
CN115130998A (en) * | 2022-07-05 | 2022-09-30 | 广州高新工程顾问有限公司 | BIM-based decoration project construction quality process control system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Pan et al. | Integrating BIM and AI for smart construction management: Current status and future directions | |
Xue et al. | Semantic enrichment of building and city information models: A ten-year review | |
Zou et al. | CNN-based statistics and location estimation of missing components in routine inspection of historic buildings | |
Lv et al. | Impact of digital twins and metaverse on cities: History, current situation, and application perspectives | |
CN109460834A (en) | Build operation management system and its management method | |
CN109472483A (en) | A kind of building-site modeling method and system based on BIM model and technology of taking photo by plane | |
CN110083119A (en) | A kind of the visual power system machine room monitoring system and method twin based on number | |
CN109559069A (en) | Production management method, apparatus and terminal device based on assembled architecture platform | |
CN109557934A (en) | A kind of control method and device of the unmanned plane cruise based on assembled architecture platform | |
CN109558412A (en) | The data growing method and device of assembled architecture construct platform | |
CN110276555A (en) | Residential housing entity Life cycle analysis method based on internet and BIM | |
Yu et al. | RIOMS: An intelligent system for operation and maintenance of urban roads using spatio-temporal data in smart cities | |
CN103617329A (en) | Assembly time evaluating method based on artificial neural network and virtual assembly | |
CN109191577A (en) | A kind of distribution BIM collaborative platform | |
CN106203784A (en) | A kind of wisdom building system based on BIM and management method thereof | |
CN109933863A (en) | One kind being used for power plant's construct platform | |
CN113627768A (en) | Project construction management system based on digital twins | |
CN115936546A (en) | Assembly type building green construction management method and device based on digital twinning | |
CN114971437B (en) | Building engineering project risk assessment system and method | |
CN113392501A (en) | Mine digital twinning model and construction method thereof | |
CN110019435A (en) | Data processing method and system based on assembled architecture platform | |
CN109559070A (en) | The equipment production information management method and device of assembled architecture platform | |
Menegon et al. | The impact of industry 4.0 concepts and technologies on different phases of construction project lifecycle: a literature review | |
CN113807599B (en) | Intelligent construction informatization integrated management cloud platform | |
CN116167582A (en) | Intelligent construction progress monitoring system based on BIM technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190625 |
|
RJ01 | Rejection of invention patent application after publication |