CN109784622A - Power grid project process monitoring method and system based on geographical wiring diagram - Google Patents

Power grid project process monitoring method and system based on geographical wiring diagram Download PDF

Info

Publication number
CN109784622A
CN109784622A CN201811500944.XA CN201811500944A CN109784622A CN 109784622 A CN109784622 A CN 109784622A CN 201811500944 A CN201811500944 A CN 201811500944A CN 109784622 A CN109784622 A CN 109784622A
Authority
CN
China
Prior art keywords
construction
wiring diagram
power grid
real
transformer substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811500944.XA
Other languages
Chinese (zh)
Other versions
CN109784622B (en
Inventor
周明
李安
武强
卢生炜
宋伶俐
刘行波
颜炯
李全
鲁锴
朱小波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd
State Grid Hubei Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Hubei Electric Power Co Ltd
Original Assignee
HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd
State Grid Hubei Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Hubei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd, State Grid Hubei Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Hubei Electric Power Co Ltd filed Critical HUBEI CENTRAL CHINA TECHNOLOGY DEVELOPMENT OF ELECTRIC POWER Co Ltd
Priority to CN201811500944.XA priority Critical patent/CN109784622B/en
Publication of CN109784622A publication Critical patent/CN109784622A/en
Application granted granted Critical
Publication of CN109784622B publication Critical patent/CN109784622B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a kind of power grid project process monitoring method and systems, belong to Power Project monitoring field, are specifically related to a kind of power grid project process monitoring method and system based on geographical wiring diagram.This method and system according to power grid project progress characteristic, in conjunction with map complex art, power grid project construction milestone node, monitoring power grid project actual field construction progress can be judged by geographical wiring diagram, and condition criterion and prediction are carried out to live construction progress abnormal conditions.

Description

Power grid project process monitoring method and system based on geographical wiring diagram
Technical field
The present invention relates to a kind of power grid project process monitoring method and systems, belong to Power Project monitoring field, specifically It is related to a kind of power grid project process monitoring method and system based on geographical wiring diagram.
Background technique
Geographical wiring diagram is the basic data of Electric Power Network Planning and power grid construction, and operational management personnel can intuitively pass through very much Geographical wiring diagram auxiliary activities is managed power grid, mode is dispatched and a certain specific construction period work such as accident treatment carries out Decision and analysis.
Power grid project monitoring is related to the power grid project input and output overall process stage, includes project planning, project deposit, item Mesh plan, the project implementation and project completion, monitoring power grid project process are the real-time dynamic duties of each stage synchronization monitoring. This requires geographical wiring diagrams, and real-time monitoring, the pipe of the installation and deployment progress of situation and station equipment can be built to field engineering Reason.
But based on traditional multi-user's geographical wiring diagram, common drafting method is led to using general map as background Cross using AutoCAD Software on Drawing and show the geographical location in power plant, substation, the path of power circuit and they mutually Between connection relationship.Currently, traditional geographical wiring diagram, which does not have also, carries out " automatic monitoring " and " intelligence to power grid project process The function of prediction ", i.e., can not be accurate by existing geographical wiring diagram, efficient to predict power grid project process.Therefore, it is necessary to Seek a kind of method of automation assessment power grid project investment precision.
Summary of the invention
A brief summary of one or more aspects is given below to provide to the basic comprehension in terms of these.This general introduction is not The extensive overview of all aspects contemplated, and be both not intended to identify critical or decisive element in all aspects also non- Attempt to define the range in terms of any or all.Its unique purpose is to provide the one of one or more aspects in simplified form A little concepts are with the sequence for more detailed description given later.
Above-mentioned technical problem of the invention is mainly to be addressed by following technical proposals:
Map complex art is combined according to the investment feature (that is: planning, plan, implementation, clearing) of power grid project, realization is led to Power grid project construction milestone node, monitoring power grid project actual field construction progress situation can be judged by crossing geographical wiring diagram, and Condition criterion is carried out to live construction progress abnormal conditions and invests the process approach of accuracy prediction.
Automatic detection power grid project construction milestone technology
This technology need to be advised according to the Engineering Zone range and combination architectural engineering that project planning initial stage Bureau of Land and Resources allocates The boundary outer boundary that building is provided in redline figure, that is, limit the boundary using ownership range of construction-engineering project land used Line determines building red line coordinate points.It is substation's red line coordinate that this technology, which is mainly calculated,.With substation's surrounding enclosure wall quadrangle Point red line coordinate, is determined on traditional geographical wiring diagram by AutoCAD software and describes substation's workshop position.Substation applies Work scene is fixed in equipment for recording station equipment and provides a user factory trade mark identification, brand and device type differentiation, Product parameters, which are engraved on one's mind etc., assigns material object ID device coding number on the nameplate of information, the device intelligence terminal of utilization maturation on the market It all has pinhole cameras and has the characteristics of acquiring, emit and receive in real time nameplate material object ID, in conjunction with image recognition and intelligence Location technology completes the transmission of vision signal by video channel.
This technology, which passes through live practice of construction situation and detect to meet automatically, to be met power grid construction project and goes into operation mark and feature Engineering.Specific manifestation are as follows: the mark and feature of the default volunteer's commencement of works of power industry are to be opened at the construction field (site) using piling machine Begin the process formally driven piles, i.e. pile monkey moves up and down along pile frame (or guide rod), impacts stake top, so that stake is sunk, cause the fluting that breaks ground Start the mark of construction as permanent work.High-definition camera is installed to site and capital equipment before commencement of works simultaneously Head, once engineering meets the mark that goes into operation, Field Force can pass through camera screenshot and acquire on-stream time, and pass through video image Automatic remote transmission, is stored in geographical wiring diagram background data base.Realizing can be certainly by clicking substation on geographical wiring diagram It is dynamic to generate corresponding go into operation video image and on-stream time.It can be on map to the project of corresponding region to the engineering for the condition that meets Automatically generating for on-stream time (referring to that permanent work is formally broken ground and start the time of construction) is realized as trigger condition, together When, to the engineering of on-stream time is possessed as trigger flag, the trend and trend of route is presented on map by a dotted line;
Meet power grid construction project operation mark and feature by site operation condition detection satisfaction.Specific manifestation are as follows: (build If project is completely or partially built up by production capacity specified in design document or benefit) engineering as determine engineering go into operation Mark.It can be on map to realization production time (warp in the project of corresponding region as trigger condition to the engineering for the condition that meets The time checked and accepted qualified or reach inspection standards of completed project, meet operation standard, and formally transfer production or be delivered for use) It automatically generates.Meanwhile on map by the trend of route and trend are stabbed by production time on map be automatically performed dotted line to Solid line jumps.
Power grid project construction progress is precisely predicted
This technology estimation range based on above-mentioned automatic detection go into operation result engineering project.During build (after going into operation Report period is not yet constructed and put into operation) investment precision prediction, judgement.Using projects coordinate points as start trigger condition, in conjunction with Video Supervision Technique can check live video monitoring image by clicking corresponding engineering.Pass through the camera shooting of on-site monitoring equipment Head has zoom characteristic, can show the inside and outside equipment construction in station and installation situation.According to China's current statistical system, volume is counted The content and range of statistics include building, equipment, installation, other expenses of technological organization, new product development, labor and safety protection and acquiring minor items of fixed assets.According to electric power investment in fixed assets SS, Architectural engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract indirect rate) * (1+ profit Rate) * (the 1+ tax rate);Installing engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract overhead cost Rate) * (1+ profit margin) * (the 1+ tax rate) calculation.And the workload actually accomplished passes through video image carries out verifying it and build If unit (owner), construction party, management side inventory confirmed by the project amount of calling for tenders of project come match verifying its investment complete it is poor The opposite sex predicts that it invests accuracy.
Other explanations: because based on only substation, primary equipment and its station showed in geographical wiring diagram traditional at present External equipment (transmission line of electricity).Do not have also and technology is showed to the video image of secondary device, is combined according to the result of matching verifying Each ENGINEERING POINT setting investment completes vivid progress and calculates standard, it may be assumed that main transformer standard in place accounts for 30%, primary equipment (with Denso It sets installing engineering, gas insulated metal enclosed swit chgear installing engineering, stand with power distribution equipment installing engineering, reactive power compensator installing engineering) It is just standard 30%, (whole station cable construction engineering, whole station lightning protection and earthing or grounding means installing engineering, whole station electric appliance shine secondary device Bright device installing engineering, communication system equipment installing engineering) it is just standard 40%, it can only be used as and be tested by geographical wiring diagram part The budget method of result and auxiliary judgement practical business that card project is precisely invested.
Therefore, the present invention has the advantage that
1. by the Internet of Things skill such as the Map Generalization display technique of traditional geographical wiring diagram and Video Supervision Technique, image recognition Art combines, and is capable of the monitoring of quicklook and the realization power grid project process prepared;
2. change the feature for realizing that traditional geographical wiring diagram shows static data, it is precisely pre- by power grid project construction progress It surveys, the multidate informations such as project kickoff, operation setup state is intelligently showed with map, reduce the cost that reality is manually calculated Meanwhile improving power grid project investment quality.
Detailed description of the invention
It is incorporated herein and the attached drawing for forming part of specification instantiates the embodiment of the present invention, and attached drawing and explanation Book is further used for explaining the principle of the present invention together and one of ordinary skill in the art is enabled to make and use the disclosure.
Attached drawing 1 is the power grid project process monitoring method stream based on geographical wiring diagram at least one embodiment of the invention Cheng Tu;
Attached drawing 2 is to judge whether parameters accord in the construction of current transformer substation model at least one embodiment of the invention Close the method flow diagram of capital construction feature;
Attached drawing 3 is the flow chart of the power grid project construction schedule forecasting at least one embodiment of the invention;
Attached drawing 4 is the power grid project process monitoring system flow chart based on geographical wiring diagram at least one embodiment;
Attached drawing 5 is the verification project kickoff status diagram at least one embodiment of the invention.
Attached drawing 6 is the verification project operation status diagram at least one embodiment of the invention.
The embodiment of the present invention is described with reference to the accompanying drawings.
Specific embodiment
For the above objects, features and advantages of the present invention can be clearer and more comprehensible, below in conjunction with attached drawing to tool of the invention Body embodiment elaborates.
In the following description, numerous specific details are set forth in order to facilitate a full understanding of the present invention, but the present invention can be with It is different from other way described herein using other and implements, therefore the present invention is by the limit of following public specific embodiment System.
Embodiment 1
The embodiment of the present invention 1 describes a kind of power grid project process monitoring method based on geographical wiring diagram.
The power grid project process monitoring method in geographical wiring diagram of the present embodiment according to power grid project investment feature (that is: plan, plan, implementing, clearing) simultaneously combines map complex art, judges power grid project construction mileage by geographical wiring diagram Upright stone tablet node, monitoring power grid project actual field construction progress situation, and condition criterion is carried out to live construction progress abnormal conditions It is predicted with investment precision.
Fig. 1 is the flow chart of the power grid project process monitoring method the present invention is based on geographical wiring diagram.It mainly includes three A step, lower mask body, which is given, to be described in detail.
In step 10, the construction of transformer substation model based on geographical wiring diagram is established, and is determined in construction of transformer substation model All devices parameter.
In the present embodiment, the construction model of construction of transformer substation mainly includes workshop position, equipment and basis coordinates.
In the present embodiment, the determination of construction of transformer substation model and device parameter includes following as a preferred method, Sub-step:
Step 1002, construction of transformer substation model side is established in geographical wiring diagram according to construction-engineering project land used actual parameter Boundary's coordinate;
In the present embodiment, according to the Engineering Zone range that project planning initial stage Bureau of Land and Resources allocates and building can be combined The boundary outer boundary that building is provided in project planning red line figure, that is, limit the use ownership range of construction-engineering project land used Boundary line, determine building red line coordinate points, mainly calculating in the present embodiment is substation's red line coordinate.
It is soft by AutoCAD with substation's surrounding enclosure wall quadrangle point red line coordinate after determining substation's red line coordinate Part determines on traditional geographical wiring diagram and describes substation's workshop position.
Step 1004, according to setting, the GPS module of equipment positions pair in construction of transformer substation model in substation at the scene Answer device location;
At construction of transformer substation scene, there are many equipment, it can be by the GPS module in equipment in construction of transformer substation model Position corresponding device location.
Step 1006, according to setting, the video module of equipment matches pair in construction of transformer substation model in substation at the scene Device parameter is answered, and corresponding device parameter is matched with material object ID device coding number.
The nameplate of record information is typically provided in the equipment at construction of transformer substation scene.The information of nameplate record is usually wrapped It includes factory trade mark identification, brand and device type to distinguish, product parameters, ID device coding number in kind.Therefore, it can use city Mature device intelligence terminal acquires in real time, emits and receives nameplate material object ID on face, in conjunction with image recognition and intelligent positioning skill Art passes through the transmission of the achievable vision signal of video channel.After being collected into the parameter of acquisition, matched in construction of transformer substation model Corresponding device parameter, and corresponding device parameter is matched with material object ID device coding number.
By above step, the construction of transformer substation model based on geographical wiring diagram can establish, and determine construction of transformer substation All devices parameter in model.
In step 20, real-time collection site data judge every ginseng in the construction of current transformer substation model based on constraint condition Whether number meets capital construction feature, and by judging result real-time display in construction of transformer substation model.
Process described in Fig. 2 is a kind of specific embodiment of the present embodiment step 20.In the present embodiment, judgement is current Transformer station model construction in parameters whether meet capital construction feature include judge power grid capital construction whether meet go into operation feature and/or Judge whether power grid capital construction meets operation feature.
In the present embodiment, judge whether power grid capital construction meets the specific method for the feature that goes into operation as a preferred method, Include: to receive current device working condition image information, obtains current device after parsing current device working condition image information Current device all parts coordinate information is matched in constraint condition, meets constraint condition then by all parts coordinate information It is judged as and meets the feature that goes into operation, the constraint condition is to store the correspondence equipment work of character pair judgment criteria in the database Standard coordinate locating for state.
The mark and feature of the default volunteer's commencement of works of power industry are to start formally to drive piles using piling machine at the construction field (site) Process, i.e. pile monkey moves up and down along pile frame (or guide rod), impacts stake top, stake is made to sink, and the fluting that causes to break ground is as permanent Engineering starts the mark of construction.High-definition camera is installed to site and capital equipment before commencement of works simultaneously, once work Cheng Fuhe goes into operation mark, and Field Force can pass through camera screenshot and acquire on-stream time, and passes through video image automatic remote Transmission, is stored in geographical wiring diagram background data base.Realizing can be automatically generated pair on geographical wiring diagram by clicking substation That answers goes into operation video image and on-stream time.
In the present embodiment, judge whether power grid capital construction meets the specific method of operation feature as a preferred method, It is: receives current device working condition image information, it is each to obtain current device after parsing current device working condition image information Current device all parts quantity information is matched with constraint condition, meets constraint condition and then sentence by a number of components information Break to meet operation feature, the constraint condition is the number for storing the correspondence equipment of character pair judgment criteria in the database Amount.
In the present embodiment, it is completely or partially built up with construction project by production capacity specified in design document or benefit Engineering state as determine engineering go into operation mark.When engineering meets operation condition, meeting automatic trigger operation, the operation meeting It is automatically updated on map and realizes production time in the project of corresponding region.It is i.e. qualified by inspection or reach final acceptance of construction Standard meets operation standard, and the time formally transferring production or being delivered for use.Meanwhile the operation can also be on map by line The trend and trend on road are automatically performed dotted line jumping to solid line by production time stamp.
In step 30, real-time collection site data obtain scene features of construction schedule and normal pace feature in real time, will be real-time Construction progress feature is matched with standard working-out features of construction schedule, and by matching result real-time display in construction of transformer substation model In, power grid project construction progress can be carried out and precisely predicted, and real-time display is in construction of transformer substation model.
Fig. 3 is a kind of preferred flow of the power grid project construction schedule forecasting of step 30.The present embodiment it is signified in the phase of building Between refer to go into operation after be not yet constructed and put into operation in the report period.Power grid project construction schedule forecasting range is based on detecting automatically in step 20 The engineering project for the result that goes into operation.
As a preferred method, the present embodiment obtain scene in real time features of construction schedule and/or normal pace feature include with Lower sub-step:
Step 3002, using coordinate points locating for the starting working condition of current device as start trigger condition, acquisition is existing in real time Field video monitoring image information.
In the present embodiment, the camera of on-site monitoring equipment has zoom characteristic, can show the inside and outside equipment construction in station And installation situation.
Step 3004, it receives live video monitoring image information and figure identification is carried out according to the monitoring image received, with The construction and equipment installation progress of all items are counted, and investment performance is calculated based on statistical result.
In the present embodiment, statistical content and range are carried out according to following dimension: building, equipment, installation;According to electric power Investment in fixed assets SS obtains actual investment and completes volume.
In the present embodiment, architectural engineering finished value of investment is calculated based on following formula as a preferred method, installing engineering is thrown Provide completion volume:
Architectural engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract indirect rate) * (1 + profit margin) * (the 1+ tax rate);
Installing engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract indirect rate) * (1 + profit margin) * (the 1+ tax rate) calculation.
In this implementation column, the workload actually accomplished can be verified by video image.Pass through its construction unit's (industry It is main), construction party, management side for the project amount confirmation inventory of calling for tenders of project carry out matching image identification data to judge its practical work It measures.I.e. by image each equipment and its progress identify, be compared with project amount confirmation inventory, it is real to determine Border workload.
Step 3006, calculating standard investment completion volume based on following formula includes:
Modular building construction investment completion volume=
Standard installing engineering finished value of investment=
It, can also be by verification result real-time display in construction of transformer substation model in the present embodiment.
Only substation, primary equipment and its outside-the station equipment (transmission line of electricity) showed in geographical wiring diagram at present.According to The result of matching verifying completes vivid progress measuring and calculating standard in conjunction with the setting investment of each ENGINEERING POINT, it may be assumed that main transformer standard in place accounts for 30%, primary equipment (stand with power distribution equipment installing engineering, nothing by power distribution equipment installing engineering, gas insulated metal enclosed swit chgear installing engineering Reactive power compensation installations installing engineering) it is just standard 30%, secondary device (whole station cable construction engineering, whole station lightning protection and earthing or grounding means Installing engineering, the installing engineering of whole station electrical lighting device, communication system equipment installing engineering) it is just standard 40%, pass through geography The schedule that the result auxiliary display practical business that wiring diagram part Verification Project is precisely invested determines.
Embodiment 2
The embodiment of the present invention 2 describes a kind of power grid project process monitoring system based on geographical wiring diagram.
As shown in Fig. 2, the power grid project process monitoring system based on geographical wiring diagram includes below with device.
Model foundation device: for establishing the construction of transformer substation model based on geographical wiring diagram, and construction of transformer substation is determined All devices parameter in model;
Data acquisition device: being used for real-time live data, exports field data;
Capital construction characteristic condition judgment means: receiving the field data of data acquisition device output, is judged based on constraint condition Whether parameters meet capital construction feature in the construction of current transformer substation model, and by judging result real-time display in construction of transformer substation In model;
Features of construction schedule judgment means: the field data of data acquisition device output, the field data solution based on acquisition are received The real-time features of construction schedule in analysis scene and normal pace feature, by real-time construction progress feature and the progress of standard working-out features of construction schedule Match, and by matching result real-time display in construction of transformer substation model.
In the present embodiment, model foundation device is according to construction-engineering project land used actual parameter as a preferred method, Construction of transformer substation model boundary coordinate is established in geographical wiring diagram;Existed according to the GPS module of equipment in setting at the scene substation Corresponding device location is positioned in construction of transformer substation model;According to the video module of equipment in setting at the scene substation in substation Corresponding device parameter is matched in construction model, and corresponding device parameter is matched with material object ID device coding number.
Wherein, all devices parameter in construction model includes: that factory trade mark identification, brand and device type are distinguished, and is produced Product parameter is engraved on one's mind.
In the present embodiment, it is real to pass through the video module being arranged in equipment for data acquisition device as a preferred method, When acquire the working condition image information of current device, numbered based on the corresponding material object ID device coding of current device, by work State image information and corresponding material object ID device coding number transmit.Wherein, the acquisition step that data acquisition device executes Suddenly identical as the data acquisition flow of step 20 in 1 is implemented.
In the present embodiment, as a preferred method, when judgement, which meets, goes into operation feature, video module acquires currently in real time Equipment working state image information simultaneously acquires on-stream time, and real-time transmission data is stored in geographical wiring diagram background data base.
In the present embodiment, as a preferred method, features of construction schedule judgment means execute the step of with embodiment 1 in step Rapid 30 is identical.
Implementation result
Below with reference to practical power business demand, method of the invention is verified.
As shown in figure 4, by taking certain project of transmitting and converting electricity as an example;The unified view of coordinate pop-up is pinpointed by clicking the project of transmitting and converting electricity It can see that enclosure wall, road are completed in the image of frequency monitoring, scene has a machine constructing, it is possible thereby to infer substation's threeway One it is flat be completed, the component part of substation's building is formally driven piles.Meet stream state criterion, judges the transmission of electricity work Journey has gone into operation.
Project operation state can be verified by clicking geographical wiring diagram fixed point coordinate;With certain 500 kilovolts of project of transmitting and converting electricity For, the production time in program plan management platform is on March 30th, 2017;Pass through energy in the image of unified video monitoring Civil construction all finishes.Monitor that sleeping #1 becomes, sleeping #3 change installs.External cable and major project and corresponding mating The auxiliary equipment such as reactive power compensator all build up, then system generates corresponding production time.
By taking certain 110 kilovolts of project of transmitting and converting electricity as an example, project construction can be verified by clicking geographical wiring diagram fixed point coordinate Progress;According to project initial stage program plan, build second year for the project plan, estimate vivid investment progress be 70% (point Dial annual investment plan/total investment quota).It can see that civil construction finishes in image by unified video monitoring, outdoor is set Standby installation make good progress, and main transformer, reactive power compensator, whole station electrical lighting device install, whole station lightning protection and ground connection Device aerial part installs, and terminal tower unwrapping wire is as it can be seen that terminal tower to transformer substation framework isolates shelves unwrapping wire finishes.Also because of project It does not go into operation, at present the temporary no data in PMS, EMS.Construction of transformer substation is substantially completed from image information.
Statistical system standard based on the project:
Calculate the finished value of investment of the project according to:
Architectural engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract indirect rate) * (1 + profit margin) * (the 1+ tax rate);
Installing engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract indirect rate) * (1 + profit margin) * (the 1+ tax rate);
Volume is completed in the project investment are as follows: (50*500+200*600+500*1000) * (1+20%) * (1+5%)+10000* 3+200*50=852700 member.
As can be seen from the above description, the present invention passes through ground in conjunction with map complex art according to the progress characteristic of power grid project Reason wiring diagram can judge power grid project construction milestone node, monitoring power grid project actual field construction progress, and to scene Construction progress abnormal conditions carry out condition criterion and prediction.
In the present embodiment, although the above method to be illustrated to and is described as a series of actions to simplify to explain, answer It is appreciated and understood that, the order that these methods are not acted is limited, because according to one or more embodiments, some movements can be by not Occur with order and/or with from depicted and described herein or not shown herein and describe but those skilled in the art can be with Other movements understood concomitantly occur.
Those skilled in the art will further appreciate that, the various illustratives described in conjunction with the embodiments described herein Logic plate, module, circuit and algorithm steps can be realized as electronic hardware, computer software or combination of the two.It is clear Explain to Chu this interchangeability of hardware and software, various illustrative components, frame, module, circuit and step be above with Its functional form makees generalization description.Such functionality be implemented as hardware or software depend on concrete application and It is applied to the design constraint of total system.Technical staff can realize every kind of specific application described with different modes Functionality, but such realization decision should not be interpreted to cause departing from the scope of the present invention.
The step of method or algorithm for describing in conjunction with embodiment disclosed herein, can be embodied directly in hardware, in by processor It is embodied in the software module of execution or in combination of the two.Software module can reside in RAM memory, flash memory, ROM and deposit Reservoir, eprom memory, eeprom memory, register, hard disk, removable disk, CD-ROM or known in the art appoint In the storage medium of what other forms.Exemplary storage medium is coupled to processor so that the processor can be from/to the storage Medium reads and writees information.In alternative, storage medium can be integrated into processor.Pocessor and storage media can It resides in ASIC.ASIC can reside in user terminal.In alternative, pocessor and storage media can be used as discrete sets Part is resident in the user terminal.
In one or more exemplary embodiments, described function can be in hardware, software, firmware, or any combination thereof Middle realization.If being embodied as computer program product in software, each function can be used as one or more item instructions or generation Code may be stored on the computer-readable medium or be transmitted by it.Computer-readable medium includes computer storage medium and communication Both media comprising any medium for facilitating computer program to shift from one place to another.Storage medium can be can quilt Any usable medium of computer access.It is non-limiting as example, such computer-readable medium may include RAM, ROM, EEPROM, CD-ROM or other optical disc storages, disk storage or other magnetic storage apparatus can be used to carrying or store instruction Or data structure form desirable program code and any other medium that can be accessed by a computer.Any connection is also by by rights Referred to as computer-readable medium.For example, if software is using coaxial cable, fiber optic cables, twisted pair, digital subscriber line (DSL) or the wireless technology of such as infrared, radio and microwave etc is passed from web site, server or other remote sources It send, then the coaxial cable, fiber optic cables, twisted pair, DSL or such as infrared, radio and microwave etc is wireless Technology is just included among the definition of medium.Disk (disk) and dish (disc) as used herein include compression dish (CD), laser disc, optical disc, digital versatile disc (DVD), floppy disk and blu-ray disc, which disk (disk) are often reproduced in a manner of magnetic Data, and dish (disc) with laser reproduce data optically.Combinations of the above should also be included in computer-readable medium In the range of.
It is noted that " one embodiment ", " embodiment ", " example embodiment ", " some embodiments " etc. in specification Reference instruction described embodiment may include a particular feature, structure, or characteristic, but each embodiment may not necessarily include The a particular feature, structure, or characteristic.Moreover, such phrase is not necessarily referring to the same embodiment.In addition, ought retouch in conjunction with the embodiments When stating a particular feature, structure, or characteristic, regardless of whether being expressly recited, such feature, structure are realized in conjunction with other embodiments Or characteristic will be in the knowledge of those skilled in the art.
Offer is to make any person skilled in the art all and can make or use this public affairs to the previous description of the disclosure It opens.The various modifications of the disclosure all will be apparent for a person skilled in the art, and as defined herein general Suitable principle can be applied to other variants without departing from the spirit or scope of the disclosure.The disclosure is not intended to be limited as a result, Due to example described herein and design, but should be awarded and principle disclosed herein and novel features phase one The widest scope of cause.

Claims (10)

1. a kind of power grid project process monitoring method based on geographical wiring diagram characterized by comprising
The construction of transformer substation model based on geographical wiring diagram is established, determines the device parameter in construction of transformer substation model;
Real-time collection site data, the device parameter acquired based on preset constraint condition and in real time judge current transformer substation Whether the equipment in model meets capital construction feature, and by judging result real-time display in construction of transformer substation model;
After judging project onstream, the field data acquired in real time is confirmed with the project amount in advance confirmed inventory into Row is compared with the real-time features of construction schedule of determination, and the real-time features of construction schedule is shown in construction of transformer substation model.
2. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 1, which is characterized in that It further include matching real-time construction progress feature to determine construction speed with predetermined standard working-out features of construction schedule.
3. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 1, which is characterized in that Establishing construction of transformer substation model includes:
Construction of transformer substation model boundary coordinate is established in geographical wiring diagram according to construction-engineering project land used actual parameter;
Corresponding equipment is positioned in construction of transformer substation model according to the device location in collected live substation;
Corresponding device parameter is matched in construction of transformer substation model according to the video module of equipment in substation field, and will be corresponded to Device parameter is matched with material object ID device coding number.
4. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 1, which is characterized in that Real-time collection site data include: the working condition image for acquiring current device in real time by the video module being arranged in equipment Information is set working condition image information and corresponding material object ID based on the corresponding material object ID device coding number of current device Standby coding number transmits.
5. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 1, which is characterized in that Judge whether that meeting capital construction feature includes:
Current device working condition image information is received, it is each to obtain current device after parsing current device working condition image information A part coordinates information and/or quantity information, by current device all parts coordinate information and/or quantity information and constraint condition It is matched, the constraint condition is the locating mark of correspondence equipment working state for storing character pair judgment criteria in the database The quantity of quasi coordinates and/or equipment;
Wherein, meet the feature that goes into operation when coordinate information meets constraint condition and is judged as;Then sentence when quantity information meets constraint condition Break to meet operation feature.
6. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 5, which is characterized in that When judgement, which meets, goes into operation feature, video module acquires current device working condition image information in real time and acquires on-stream time, Real-time transmission data is stored in geographical wiring diagram background data base.
7. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 5, which is characterized in that Judgement also performs the following operation after meeting operation feature: testing when judging that corresponding number equipment is qualified by inspection or reaches completion After receipts standard meets operation standard, the formal time transferring production or being delivered for use is recorded, in construction of transformer substation model to correspondence Realization production time is automatically generated in the project in region.
8. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 1, which is characterized in that Obtaining the real-time features of construction schedule in scene and normal pace feature and carrying out matched specific method is:
Using coordinate points locating for the starting working condition of current device as start trigger condition, real-time collection site video monitoring image Information;
According to the monitoring image received, figure identification is carried out, to count the construction and equipment installation progress of all items, and is based on Statistical result calculates investment performance.
9. a kind of power grid project process monitoring method based on geographical wiring diagram according to claim 8, which is characterized in that
Architectural engineering finished value of investment, installing engineering finished value of investment are calculated based on following formula;
Architectural engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract indirect rate) * (1+ benefit Profit rate) * (the 1+ tax rate);
Installing engineering finished value of investment=Σ (the workload * budgetary unit price actually accomplished) * (1+ contract indirect rate) * (1+ benefit Profit rate) * (the 1+ tax rate) calculation.
10. a kind of power grid project process monitoring system based on geographical wiring diagram characterized by comprising
Model foundation device establishes the construction of transformer substation model based on geographical wiring diagram, determines setting in construction of transformer substation model Standby parameter;
Data acquisition device is used for real-time live data, exports field data;
Capital construction characteristic condition judgment means, obtain field data, the device parameter acquired based on preset constraint condition and in real time Judge whether the equipment in current transformer substation model meets capital construction feature, and by judging result real-time display in construction of transformer substation mould In type;
Features of construction schedule judgment means, after judging project onstream, by the field data acquired in real time and confirmation in advance Project amount confirmation inventory be compared with the real-time features of construction schedule of determination, the real-time features of construction schedule is shown in construction of transformer substation In model.
CN201811500944.XA 2018-12-10 2018-12-10 Power grid project progress monitoring method and system based on geographic wiring diagram Active CN109784622B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811500944.XA CN109784622B (en) 2018-12-10 2018-12-10 Power grid project progress monitoring method and system based on geographic wiring diagram

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811500944.XA CN109784622B (en) 2018-12-10 2018-12-10 Power grid project progress monitoring method and system based on geographic wiring diagram

Publications (2)

Publication Number Publication Date
CN109784622A true CN109784622A (en) 2019-05-21
CN109784622B CN109784622B (en) 2023-08-04

Family

ID=66496799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811500944.XA Active CN109784622B (en) 2018-12-10 2018-12-10 Power grid project progress monitoring method and system based on geographic wiring diagram

Country Status (1)

Country Link
CN (1) CN109784622B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110415110A (en) * 2019-07-31 2019-11-05 中国工商银行股份有限公司 Progress monitoring method, progress monitoring device and electronic equipment
CN112380982A (en) * 2020-11-13 2021-02-19 福建亿榕信息技术有限公司 Integrated monitoring method for progress and quality of infrastructure project in power industry
CN112633750A (en) * 2020-12-31 2021-04-09 华录智达科技有限公司 Bus acceptance management method and system based on CAN bus
CN113903099A (en) * 2021-08-30 2022-01-07 浙江文谷科技有限公司 Device monitoring method and system based on scada
CN115600716A (en) * 2022-12-13 2023-01-13 河北电力工程监理有限公司(Cn) Artificial intelligence supervision system and method for electric power engineering site

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2885962A1 (en) * 2009-06-25 2010-09-01 Certusview Technologies, Llc Methods and apparatus for assessing locate request tickets
CN105654398A (en) * 2015-11-05 2016-06-08 交通运输部公路科学研究所 Side slope construction assessment method based on centesimal system and multistage index system
CN108090610A (en) * 2017-12-14 2018-05-29 四川建筑职业技术学院 Orbit construction system based on BIM technology
WO2023029388A1 (en) * 2021-09-06 2023-03-09 广东电网有限责任公司湛江供电局 Cim model-based auxiliary power distribution network planning method and system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2885962A1 (en) * 2009-06-25 2010-09-01 Certusview Technologies, Llc Methods and apparatus for assessing locate request tickets
CN105654398A (en) * 2015-11-05 2016-06-08 交通运输部公路科学研究所 Side slope construction assessment method based on centesimal system and multistage index system
CN108090610A (en) * 2017-12-14 2018-05-29 四川建筑职业技术学院 Orbit construction system based on BIM technology
WO2023029388A1 (en) * 2021-09-06 2023-03-09 广东电网有限责任公司湛江供电局 Cim model-based auxiliary power distribution network planning method and system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周媛,冯林桥,张午阳,陈湘波: "图示化智能供配电网设计系统", 电力自动化设备 *
王凯: "面向绿色运维的建筑信息模型逆向设计法研究与实践", 《土木建筑工程信息技术》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110415110A (en) * 2019-07-31 2019-11-05 中国工商银行股份有限公司 Progress monitoring method, progress monitoring device and electronic equipment
CN110415110B (en) * 2019-07-31 2021-10-29 中国工商银行股份有限公司 Progress monitoring method, progress monitoring device and electronic equipment
CN112380982A (en) * 2020-11-13 2021-02-19 福建亿榕信息技术有限公司 Integrated monitoring method for progress and quality of infrastructure project in power industry
CN112633750A (en) * 2020-12-31 2021-04-09 华录智达科技有限公司 Bus acceptance management method and system based on CAN bus
CN113903099A (en) * 2021-08-30 2022-01-07 浙江文谷科技有限公司 Device monitoring method and system based on scada
CN113903099B (en) * 2021-08-30 2023-09-08 浙江文谷科技有限公司 Equipment monitoring method and system based on scada
CN115600716A (en) * 2022-12-13 2023-01-13 河北电力工程监理有限公司(Cn) Artificial intelligence supervision system and method for electric power engineering site
CN115600716B (en) * 2022-12-13 2023-04-07 河北电力工程监理有限公司 Artificial intelligence supervision system and method for electric power engineering site

Also Published As

Publication number Publication date
CN109784622B (en) 2023-08-04

Similar Documents

Publication Publication Date Title
CN109784622A (en) Power grid project process monitoring method and system based on geographical wiring diagram
CN107193375B (en) Electric power safety production scene interaction system based on virtual reality
CN109816161A (en) A kind of power distribution network operation computer-aided decision support System and its application method
CN111091609A (en) Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling
CN106845844A (en) Power transmission and transformation three-dimension visible sysem and application method
CN107194588A (en) A kind of bridge construction management system and method based on Quick Response Code and BIM technology
CN104101791A (en) Relay protection device fixed vale automatic test method and system
CN103778566A (en) Heat-engine plant monitoring and measuring method based on three-dimensional visualization demonstration
CN103034755A (en) Visual inspection method based on virtual reality technology for transformer substation
CN113096477A (en) Visual operation and maintenance work platform of virtual power station
CN109840701A (en) A kind of engineering construction quality control system
CN111384776B (en) VR-based transformer substation three-dimensional panoramic state monitoring method and system
CN110470379A (en) A kind of substation's movable-type intelligent noise continuous collecting system
CN105760429A (en) Power grid equipment data check method and system thereof
CN111062504A (en) AR technology-based intelligent power distribution station operation and maintenance system and method
CN106708984A (en) Method, apparatus and system for acquiring basic data of cable channel
CN103632198A (en) Visualized and full-life measurement asset management system based on intelligent mobile terminal
CN110930807A (en) Simulation training system of electric power system
CN107194566A (en) A kind of electric intelligent archive management method based on virtual reality
CN117077922A (en) BP neural network-based intelligent power grid power distribution method
CN108052561A (en) Routine test analysis method and device based on timeliness norm controlling
CN110322157A (en) A kind of distribution planning overall process assessment system
CN110112830A (en) A kind of supervisory control of substation information transmission platform
CN106940827B (en) AR (augmented reality) technology and VR (virtual reality) technology based modular power supply scheme automatic generation method
CN108428110A (en) A kind of acquisition methods of construction-engineering project management information

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant