CN108052561A - Routine test analysis method and device based on timeliness norm controlling - Google Patents

Routine test analysis method and device based on timeliness norm controlling Download PDF

Info

Publication number
CN108052561A
CN108052561A CN201711260430.7A CN201711260430A CN108052561A CN 108052561 A CN108052561 A CN 108052561A CN 201711260430 A CN201711260430 A CN 201711260430A CN 108052561 A CN108052561 A CN 108052561A
Authority
CN
China
Prior art keywords
test
event
time
experiment
beginning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711260430.7A
Other languages
Chinese (zh)
Inventor
储炳南
郭明星
刘海峡
金生祥
李前宇
翟艳萍
刘炜
何奇善
陈振华
王清
周向涛
张秉权
孟浩
李恪
王潇
朱尘
徐义巍
白德龙
安振源
孟庆伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Inbasis Technology Co Ltd
INNER MONGOLIA DAIHAI ELECTRIC POWER GENERATION Co Ltd
Ningxia Jing Nengningdong Power Generation Corp Ltd
Beijing Energy Refco Group Ltd
Original Assignee
Beijing Inbasis Technology Co Ltd
INNER MONGOLIA DAIHAI ELECTRIC POWER GENERATION Co Ltd
Ningxia Jing Nengningdong Power Generation Corp Ltd
Beijing Energy Refco Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Inbasis Technology Co Ltd, INNER MONGOLIA DAIHAI ELECTRIC POWER GENERATION Co Ltd, Ningxia Jing Nengningdong Power Generation Corp Ltd, Beijing Energy Refco Group Ltd filed Critical Beijing Inbasis Technology Co Ltd
Priority to CN201711260430.7A priority Critical patent/CN108052561A/en
Publication of CN108052561A publication Critical patent/CN108052561A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/25Integrating or interfacing systems involving database management systems
    • G06F16/254Extract, transform and load [ETL] procedures, e.g. ETL data flows in data warehouses
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/24Querying
    • G06F16/245Query processing
    • G06F16/2458Special types of queries, e.g. statistical queries, fuzzy queries or distributed queries
    • G06F16/2477Temporal data queries
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Databases & Information Systems (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Computational Linguistics (AREA)
  • General Health & Medical Sciences (AREA)
  • Probability & Statistics with Applications (AREA)
  • Mathematical Physics (AREA)
  • Fuzzy Systems (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Software Systems (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Testing And Monitoring For Control Systems (AREA)

Abstract

The present invention provides a kind of routine test analysis method and device based on timeliness norm controlling, which includes:The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by photoelectricity transmission medium;According to event, experiment process event and the corresponding time point data of experiment End Event before field data extraction on-test, by time point data storage into database;It detects and whether there is experiment End Event in the first set period of time in the database;If so, on the basis of according to the time point data of the off-test event found, event and experiment process event before the on-test that there is satisfaction setting condition are searched whether successively forward;If there is event before the on-test for meeting setting condition and experiment process event, time on-test will be set at the beginning of experiment process event, the off-test time will be set at the beginning of off-test event, stores time on-test and off-test time.

Description

Routine test analysis method and device based on timeliness norm controlling
Technical field
The present invention relates to power plant equipment experimental technique, especially with regard to a kind of regular examination based on timeliness norm controlling Test analysis method and device.
Background technology
Power plant is needed to exercising supervision and monitoring whether the specification of personnel's operation in production process, and the prior art mainly collects In to some equipment of power plant carry out routine test analysis, its actual production process is estimated and instructed.These are Analysis and management to equipment, do not possess the administrative analysis to personnel, can not carry out management and control to personnel's operating process and result, and It is not real-time management and control, the processing of data is also more single, is carried out without complicated logical operation, and only for single equipment Analysis.
Such as entitled fire-fighting system routine test device, the patent application of Application No. 201320811816 are made For a kind of fire-fighting system routine test device, including water pipe, pressure gauge and flowmeter, water pipe includes and fire-fighting system The connection flexible pipe of host's pipeline spare interface connection under the overall leadership, pressure gauge and flowmeter are arranged on water pipe and in full flow item The pressure and flow of liquid in water pipe are detected under part.Fire-fighting system routine test device is by the way that connection flexible pipe is connected The routine test device interface reserved in fire-fighting system pipe network is connected to, simulates under fire condition several fire water spray nozzles simultaneously The full flow condition of startup recycles the flow and pressure for being arranged on pressure gauge and flow meter validation fire-fighting system on water pipe Whether power meets design requirement simultaneously, is the verification experimental verification carried out to equipment dependability, and experiment process can not be carried out after experiment Tracking can not realize comparison with previous experiment, and test effect can not embody.
It is for example entitled again:A kind of appraisal procedure for nuclear power plant's routine test period modulation, Application No. 201510323861.8 patent application, as a kind of appraisal procedure for routine test period modulation, comprise the following steps: (I) screening obtains the routine test week caused by nuclear power plant's fuel refulling cycle extends to the new refulling cycle by the former refulling cycle The inventory for the safety-related routine test project that phase need to adjust;(II) the routine test cycle in inventory need to be adjusted each regular Pilot project, assesses the influence degree of the adjustment to relevant device safety supervision level in its routine test cycle, and it is fixed to prove it The feasibility and the desired value in definite routine test cycle of test period phase adjustment.The standard of assessment result can be improved using this method True property reduces evaluation work amount, reduces the repeatability of demonstration, be conducive to promote, but this method is just for regular examination The optimization for periodically rationalizing and carrying out is tested, performance, experiment process to follow-up test are not concerned with, and are not one complete Routine test management system.
The content of the invention
An embodiment of the present invention provides a kind of routine test analysis method based on timeliness norm controlling, with by data Logic judgment or mathematical computations are carried out, realize that effect etc. is completed in timed reminding, automatic discrimination process of work, evaluation, and it is real Now the course of work is traced, foundation is checked to provide to test.
To achieve these goals, an embodiment of the present invention provides a kind of routine test analyses based on timeliness norm controlling Method, the routine test analysis method include:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by photoelectricity transmission medium;Live number According to operating status, time, electric current, voltage, the information such as temperature, pressure, vibration, depending on specific equipment and operating mode can be included.
According to the field data extract on-test before event, experiment process event and experiment End Event it is corresponding when Between point data, by the time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to deposit forward successively Event and experiment process event before the on-test to impose a condition is met;
If there is event before the on-test for meeting setting condition and experiment process event, opening for process event will be tested Time beginning is set to time on-test, will be set to the off-test time at the beginning of off-test event, stores the experiment Time started and off-test time.
In one embodiment, further include:It searches in the setting date corresponding in a few days database that floats and whether there is the setting Date corresponding test data sheet is reminded if it does not, being sent to experiment related personnel.
In one embodiment, the corresponding time point data of event is opening when meeting test requirements document condition before the on-test Begin time and end time;When the corresponding time point data of the experiment process event is time on-test and off-test Between;At the beginning of the corresponding time point data of the experiment End Event is off-test.
In one embodiment, on the basis of the time point data of the off-test event found, searching successively forward is No event and experiment process event before there is the on-test for meeting and imposing a condition, including:
On the basis of at the beginning of the corresponding off-test of off-test event, search in the second set period of time of setting With the presence or absence of experiment process event;
If it does, the off-test for judging the off-test time of the experiment process event found and finding Whether the time interval at the beginning of the off-test of event is in the first prefixed time interval;
If so, on the basis of time on-test of the experiment process event found, when searching the 3rd setting of setting Between in section with the presence or absence of event before on-test;
If set in the 3rd set period of time there are event before on-test, event is corresponding full before judging on-test The time interval of time on-test of end time and the experiment process event found during sufficient test requirements document condition Whether in the second prefixed time interval.
In one embodiment, if there is no event before the on-test for meeting setting condition and/or process event is tested, to It tests related personnel and sends prompting.
In one embodiment, which further includes:
The change rate of the value of feedback of corresponding device parameter was tested before the acquisition off-test time in 4th set period of time;
Judge the change rate whether in preset threshold range;
If the change rate, not in preset threshold range, to experiment, related personnel sends information, to remind experiment related Personnel are analyzed testing underproof reason.
In one embodiment, which further includes:
The tendency chart of different data is drawn according to the field data;
The tendency chart is sent to human-computer interaction module.
To achieve these goals, an embodiment of the present invention provides a kind of routine test analyses based on timeliness norm controlling Device, the routine test analytical equipment include:
Data receipt unit, for passing through the power plant equipment that photoelectricity transmission medium receives collection in worksite equipment and gathers in real time Field data;
Data record unit, for according to event, experiment process event and reality before field data extraction on-test The corresponding time point data of End Event is tested, by time point data storage into database;
Detection unit whether there is experiment End Event for detecting in the database in the first set period of time;
Searching unit on the basis of the time point data according to the off-test event found, is searched forward successively With the presence or absence of event before the on-test for meeting setting condition and experiment process event;
Setup unit, for process event will to be tested at the beginning of be set to time on-test, by off-test event At the beginning of be set to the off-test time, store time on-test and off-test time.
In one embodiment, whether the searching unit is additionally operable to search and be deposited in the setting date corresponding in a few days database that floats In the setting date corresponding test data sheet, reminded if it does not, being sent to experiment related personnel.
In one embodiment, the corresponding time point data of event is opening when meeting test requirements document condition before the on-test Begin time and end time;When the corresponding time point data of the experiment process event is time on-test and off-test Between;At the beginning of the corresponding time point data of the experiment End Event is off-test.
In one embodiment, the searching unit includes:
First searching module, on the basis of at the beginning of the corresponding off-test of off-test event, lookup to be set With the presence or absence of experiment process event in fixed second set period of time;
First judgment module, described in judging the off-test time of experiment process event found and finding Whether the time interval at the beginning of the off-test of off-test event is in the first prefixed time interval;
Second searching module, on the basis of time on-test of the experiment process event found, searching setting With the presence or absence of event before on-test in 3rd set period of time;
Second judgment unit, end time when meeting test requirements document condition for judging that event before on-test is corresponding With the time interval of time on-test of the experiment process event that finds whether in the second prefixed time interval.
In one embodiment, which further includes:First reminds transmitting element, for if there is no full Event and/or experiment process event, send to experiment related personnel and remind before the on-test to impose a condition enough.
In one embodiment, which further includes:
Acquiring unit tested the anti-of corresponding device parameter before the off-test time for obtaining in the 4th set period of time The change rate of feedback value;
Judging unit, for judging the change rate whether in preset threshold range;
Second reminds transmitting element, for sending information to experiment related personnel, to remind experiment related personnel to experiment Underproof reason is analyzed.
In one embodiment, further include:
Tendency chart drawing unit, for drawing the tendency chart of different data according to the field data;
Transmitting element, for the tendency chart to be sent to human-computer interaction module.
To achieve these goals, an embodiment of the present invention provides a kind of computer equipment, including memory, processor and The computer program that can be run on a memory and on a processor is stored, the processor performs real during the computer program Existing following steps:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by network;
According to the field data extract on-test before event, experiment process event and experiment End Event it is corresponding when Between point data, by the time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to deposit forward successively Event and experiment process event before the on-test to impose a condition is met;
If there is event before the on-test for meeting setting condition and experiment process event, opening for process event will be tested Time beginning is set to time on-test, will be set to the off-test time at the beginning of off-test event, stores the experiment Time started and off-test time.
To achieve these goals, an embodiment of the present invention provides a kind of computer readable storage medium, it is stored thereon with Computer program, the computer program realize following steps when being executed by processor:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by network;
According to the field data extract on-test before event, experiment process event and experiment End Event it is corresponding when Between point data, by the time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to deposit forward successively Event and experiment process event before the on-test to impose a condition is met;
If there is event before the on-test for meeting setting condition and experiment process event, opening for process event will be tested Time beginning is set to time on-test, will be set to the off-test time at the beginning of off-test event, stores the experiment Time started and off-test time.
The present invention can have by carrying out logic judgment or mathematical computations, the result after data compare by analysis to data More in time and be efficiently completed experiment work beneficial to subordinate electricity power enterprise, realize timed reminding, automatic discrimination process of work, The functions such as effect are completed in evaluation, and realize and the course of work is traced, and foundation is checked to provide to test.Solves existing hair Power plant is due to mostly building remote districts and dispersed placement, caused inspection timeliness, the practical significance and effect of supervision and check in The problem of all very low.
Description of the drawings
It in order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention, for those of ordinary skill in the art, without creative efforts, can be with Other attached drawings are obtained according to these attached drawings.
Fig. 1 is routine test analysis method one of the embodiment of the present invention based on timeliness norm controlling;
Fig. 2 is routine test analysis method two of the embodiment of the present invention based on timeliness norm controlling;
Fig. 3 is routine test analysis method three of the embodiment of the present invention based on timeliness norm controlling;
Fig. 4 is the logic function block diagram of the routine test analysis method of the embodiment of the present invention;
Fig. 5 is that the Tightness Property of Condenser Vacuum System of the embodiment of the present invention tests schematic diagram;
Fig. 6 opens class for the general examination of the embodiment of the present invention and tests schematic diagram;
Fig. 7 is the structure diagram one of the routine test analytical equipment of the embodiment of the present invention;
Fig. 8 is the structure diagram two of the routine test analytical equipment of the embodiment of the present invention.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment belongs to the scope of protection of the invention.
Fig. 1 is routine test analysis method of the embodiment of the present invention based on timeliness norm controlling, as shown in Figure 1, this is periodically Test analysis method includes:
S101:The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by photoelectricity transmission medium. Field data can include operating status, time, electric current, voltage, the information such as temperature, pressure, vibration, depending on specific equipment and operating mode Depending on.
S102:According to event, experiment process event and experiment End Event pair before field data extraction on-test The time point data answered, by time point data storage into database.
S103:It detects and whether there is experiment End Event in the first set period of time in the database.
First set period of time can be 5 minutes, and the present invention is not limited.
S104:If so, on the basis of according to the time point data of the off-test event found, searching successively forward is No event and experiment process event before there is the on-test for meeting and imposing a condition.
S105:If there is event before the on-test for meeting setting condition and experiment process event, process thing will be tested Time on-test is set at the beginning of part, the off-test time will be set at the beginning of off-test event, stores institute State time on-test and off-test time.
The executive agent of flow shown in FIG. 1 can be power plant's background server.Flow as shown in Figure 1 understands that this is fixed Phase test analysis method collection site data first therefrom extract time point data and store to database, then detection setting Whether there is experiment End Event in period in database, when there is experiment End Event, searching whether that there is satisfaction sets Event and experiment process event before the on-test of fixed condition, and will be at the beginning of the experiment process event that setting condition be met Time on-test is set to, the end time of off-test event is set to the off-test time.In this way, it can realize certainly It is dynamic to differentiate that process of work, evaluation complete the functions such as effect, and realize and the course of work is traced, to provide experiment inspection Look into foundation.
In order to ensure that electric power factory equipment can run well, the present invention can realize the regular prompting function of experiment, and lookup is set Corresponding floating fix the date in a few days in database with the presence or absence of the setting date corresponding test data sheet, if it does not, to It tests related personnel and sends prompting.It can be determined according to specific experiment the floating day, such as one day monthly is on-test Date if experiment does not carry out, may be set in front and rear 3 days of the Start Date and operations staff reminded to carry out correlation test. In one embodiment, which, that is, if experiment does not carry out, reminds operations staff on the day of test start date Carry out correlation test.
In one embodiment, the corresponding time point data of event is opening when meeting test requirements document condition before the on-test Begin time and end time;When the corresponding time point data of the experiment process event is time on-test and off-test Between;At the beginning of the corresponding time point data of the experiment End Event is off-test.
As one embodiment of the invention, as shown in Fig. 2, S104 includes the following steps:
S201:On the basis of at the beginning of the corresponding off-test of off-test event, when searching the second setting of setting Between in section with the presence or absence of experiment process event.
When second set period of time can be 26 small, the present invention is not limited.
S202:If it does, the examination for judging the off-test time of the experiment process event found and finding The time interval at the beginning of the off-test of End Event is tested whether in the first prefixed time interval.
First prefixed time interval can be for example 60 seconds, and the present invention is not limited.
S203:If so, on the basis of time on-test of the experiment process event found, search setting the 3rd and set With the presence or absence of event before on-test in section of fixing time.
When 3rd set period of time can be 26 small, the present invention is not limited.
S204:If set in the 3rd set period of time there are event before on-test, event pair before on-test is judged End time when meeting test requirements document condition answered and time on-test of the experiment process event found when Between be spaced whether in the second prefixed time interval.
Second prefixed time interval can be for example 60 seconds, and the present invention is not limited.
If there is no event before the on-test for meeting setting condition and/or experiment process event, short message can be passed through Etc. forms to experiment related personnel send remind.
For meeting the experiment of above-mentioned S204, can then the association of time of origin will be tested by interface with record storage Measuring point data takes, and carries out test evaluation.
In one embodiment, as shown in figure 3, Test model synthetic techniques include the following steps:
S301:The change of the value of feedback of corresponding device parameter was tested before the acquisition off-test time in 4th set period of time Rate;
S302:Judge the change rate whether in preset threshold range;
S303:If the change rate, not in preset threshold range, to experiment, related personnel sends information, to remind experiment Related personnel is analyzed testing underproof reason.
In addition, according to field data, the tendency chart of various different data can be drawn, the tendency chart can also be sent To human-computer interaction module, historical record is checked and compared for user.
Fig. 4 is the logic function block diagram of the routine test analysis method of the embodiment of the present invention, with reference to Fig. 4 to the present invention Routine test analysis method be briefly described.
As shown in figure 4, the field data for the power plant equipment that can be gathered in real time on the spot using collection in worksite equipment, scene The field data of collecting device acquisition, can be transmitted to power plant's background server, power plant's background service by photoelectricity transmission medium After device receives field data, it can store for data monitoring.Then, power plant's background server can be extracted from field data At the beginning of when meeting test requirements document condition and end time, the corresponding time point data of experiment process event are on-test Time and off-test time, at the beginning of the corresponding time point data of experiment End Event is off-test, and store to In database.Power plant's background server is also based on field data and operations staff is reminded to carry out test operation.
Afterwards, power plant's background server can search experiment completion event (off-test event), tested if finding Into event, on the basis of at the beginning of the corresponding off-test of off-test event, search in the second set period of time of setting With the presence or absence of experiment process event, if it does, judging the off-test time of the experiment process event found with finding The off-test event off-test at the beginning of time interval whether in the first prefixed time interval.If Time interval in the first prefixed time interval (such as 60 seconds), using time on-test of experiment process event for finding as Benchmark is searched with the presence or absence of event before on-test in the 3rd set period of time of setting, if in the 3rd set period of time of setting The end time for judging that event before on-test is corresponding when meeting test requirements document condition there are event before on-test and lookup The time interval of time on-test of the experiment process event arrived whether in the second prefixed time interval, if this when Between be spaced whether in the second prefixed time interval (such as 60 seconds), store test data sheet.
For the test data sheet of storage, front-end output, generation appraisal report, generation tendency chart can be carried out and be shown, And short message prompting etc. is carried out according to appraisal report.
Before the present invention has merged device data acquisition, data high-speed encrypted transmission and storage, computer logic computing, experiment Operating mode judges, the displaying of experiment process trend, evaluation, the comparison of all previous experiment process, user-friendly interface displaying and checks after experiment.
The present invention can periodically be required according to the experiment of setting, periodically be reminded, can be according to each experiment institute before prompting The parameter premise calls needed judge operating mode, remind operations staff that can carry out experiment work when meeting condition, if condition It is unsatisfactory for, then operations staff's current working is reminded not support to be tested.
The present invention carries out real time data analysis calculating, real-time recording unit routine test using computer programming language Logout in the process, and it is regular according to the timing variations of parameter during equipment test, in tens thousand of logouts certainly The data of the dynamic corresponding equipment of identification, form complete routine test by the event for the condition that meets according to specific rule and record, and It can be reminded according to setting to given client push note.
The human-computer interaction module of the present invention, is shown using advanced Html5 technologies, ensures the friend of the customer interaction page Good property.The present invention can utilize report tool to show the situation of change for testing a stage parameter in the process, and tendency chart instrument carries out The pattern situations of parameter during experiment, the comparison that user is facilitated to check and record in the past.It ensures equipment safety stable operation, carries The machine of liter set of long-period, stabilization, safe operation, and hidden danger, the monitoring stand-by equipment general level of the health existing for discovering device in time.
To sum up, compared with prior art, the present invention the present invention possesses following effect:
The real-time watch device operating condition in timeliness carries out logic judgment, using real-time to equipment working condition and parameter Data transmission, without the link of intermediate unloading, data reliability also has a distinct increment;
By logic sum number student movement point counting desorption device test situation, the effect of experiment can be checked by trend and report;
It realizes the transverse and longitudinal comparison of test of many times, the result of single test is appraised through comparison, provided to Field Force reliable Data foundation;
Timed reminding is provided, expire the experiment not carried out, judges experiment premise according to unit operating mode, reminds operation people in real time Member completes experiment, while provides the functions such as cellphone information push.
With reference to specific experiment, the present invention will be described:
1st, Tightness Property of Condenser Vacuum System is tested
Fig. 5 is that the Tightness Property of Condenser Vacuum System of the embodiment of the present invention tests schematic diagram, as shown in figure 5, testing each step such as Under:
Test each step explanation:
(1) periodically remind:According to test requirements document, monthly experiment work was carried out in 8th, designs timer, scanned daily, When scanning did not had the test data sheet by 8 days in simultaneity factor, send regular working and remind to corresponding operations staff, it is on the contrary then Prompting will not be generated.
(2) logout:The measuring point that experiment needs monitor includes:Unit load, vacuum pump operating status, vacuum pump electricity Stream, vacuum pump inlet pneumatic operated valve state;
A) unit load stabilization is detected in more than 480MW and has a vacuum pump operating status for " RUN ", vacuum pump Electric current is more than 100A, insertion event 1 (STEP1 in Fig. 1) in event base, at the beginning of being denoted as event 1 with the time this moment, terminates Time is sky;
B) monitor that vacuum pump operating status is become " stopping transport " from " RUN ", and vacuum pump inlet pneumatic operated valve state is pass It closes, and vacuum pump electric current is reduced to 0A from 100A, insertion event 2 (STEP2 in Fig. 1) in event base is recorded as thing with the time this moment At the beginning of part 2, the end time is sky, while the time this moment was written back in the end time of event 1;
C) monitor that vacuum pump operating status becomes " RUN " from " stoppage in transit ", and vacuum pump inlet pneumatic operated valve state is to beat It opens, insertion event 3 (STEP3 in Fig. 1) in event base, at the beginning of being recorded as event 3 with the time this moment, the end time is Sky, while the time this moment was written back in the end time of event 2.
3) complete test data sheet monitoring:Timer is set, the situation of change in 5 minutes in logout storehouse is monitored, searches Meet the event of condition and the complete test data sheet of composition, store in test data sheet storehouse, concrete mode is as follows:
A) data in every 5 minutes monitoring logout storehouses, searched events 3 record that (record generation has then proved experiment It completes);
B) after finding that event 3 records, be subject at the beginning of event 3, search 26 it is small when within the event 2 that occurs, and It is spaced at the beginning of the end time of event 2 and event 3 within 60 seconds;
C) it is subject at the beginning of the event 2 of the condition of satisfaction, searches time recent occurrence part 1, and the knot of event 1 It is spaced at the beginning of beam time and event 2 within 60 seconds;
If meeting conditions above, then it represents that the experiment is completed, at the beginning of experiment is denoted as at the beginning of event 2, The end time of experiment is denoted as at the beginning of event 3, stores in test data sheet storehouse, does not otherwise record, and can be according to system It is allocated to designated person and sends short message prompting.
(4) the failed analysis of causes is tested:If being unsatisfactory for conditions above, can carry out testing the failed analysis of causes, System is automatically reminded to operations staff and carries out routine test, is terminated when experiment is unexpected, system automatically analyzes experiment stop reason, and leads to Know operations staff.
(5) punctuality judges:Test requirements document monthly carries out experiment work on 8th, but can complete experiment at forward and backward 3 days and be considered as Complete routine test, when grabbing test data sheet, with experiment at the beginning of with seeking time is wanted to compare, judge whether subject to When.
(6) report self-evaluation, the record storage for the condition that meets is surveyed the association for testing time of origin by interface Point data takes, and carries out test evaluation, the vacuum mean decrease of 5 minutes before off-test is taken to judge, less than 270Pa/ Min is qualification;It is labeled as testing more than 270Pa/min unqualified, while provides and may cause underproof reason, be divided into:1、 Vacuum system imprecision;2nd, condenser water level is high;3rd, condenser copper tube fouling;4th, air ejector work is abnormal or efficiency reduces; 5th, quantity of circulating water deficiency;6th, circulating water temperature is high, is checked by professional to scene, and carries out field repair, treats next time Experiment is verified again.
(7) using tendency chart control, checked before certain time on-test 1 it is small when to after the end time 1 correlation when small Measuring point historical data, is shown, while previous record carry out trend comparison may be selected, provide it is artificial judge test effect according to According to.
The human-computer interaction module of the present invention, is shown using advanced Html5 technologies, ensures the friend of the customer interaction page Good property.Show the situation of change of a stage parameter during experiment using report tool, during tendency chart instrument is tested The pattern situations of parameter, the comparison that user is facilitated to check and record in the past.
2nd, class experiment is opened in general examination;
Fig. 6 opens class for the general examination of the embodiment of the present invention and tests schematic diagram, and the decision logic of Fig. 6 is:
The first step:Judge that currently whether meeting examination opens requirement;
Second step:Monitoring device starts;
3rd step:Equipment is stopped transport again.
After monitoring three events respectively, it is grouped also according to the judgment rule of Tightness Property of Condenser Vacuum System experiment, most Displaying eventually, repeats no more.
Conceived based on the application identical with above-mentioned routine test analysis method, the application provides a kind of routine test analysis dress It puts, as described in example below.Due to the principle that the routine test analytical equipment solves the problems, such as and routine test analysis method phase Seemingly, therefore the implementation of the routine test analytical equipment may refer to the implementation of routine test analysis method, and it is no longer superfluous to repeat part It states.
Fig. 7 is the structure diagram of the routine test analytical equipment of the embodiment of the present invention, as shown in fig. 7, the routine test point Analysis apparatus includes:
Data receipt unit 701, for passing through the power plant that photoelectricity transmission medium receives collection in worksite equipment and gathers in real time The field data of equipment;
Data record unit 702, for according to the field data extract on-test before event, experiment process event and The corresponding time point data of End Event is tested, by time point data storage into database;
Detection unit 703 whether there is experiment End Event for detecting in the database in the first set period of time;
Searching unit 704 on the basis of the time point data according to the off-test event found, is looked into forward successively It looks for the presence or absence of event before the on-test for meeting setting condition and experiment process event;
Setup unit 705, for process event will to be tested at the beginning of be set to time on-test, by off-test thing The off-test time is set at the beginning of part, stores time on-test and off-test time.
In one embodiment, the searching unit 704, which is additionally operable to search in the setting date corresponding in a few days database that floats, is It is no to set date corresponding test data sheet there are described, it is reminded if it does not, being sent to experiment related personnel.
In one embodiment, the corresponding time point data of event is opening when meeting test requirements document condition before the on-test Begin time and end time;When the corresponding time point data of the experiment process event is time on-test and off-test Between;At the beginning of the corresponding time point data of the experiment End Event is off-test.
In one embodiment, as shown in figure 8, the searching unit 704 includes:
First searching module 801, on the basis of at the beginning of the corresponding off-test of off-test event, searching It sets in the second set period of time with the presence or absence of experiment process event;
First judgment module 802, for judging off-test time of experiment process event for finding and finding Whether the time interval at the beginning of the off-test of the off-test event is in the first prefixed time interval;
Second searching module 803, on the basis of time on-test of the experiment process event found, lookup to be set With the presence or absence of event before on-test in fixed 3rd set period of time;
Second judgment unit 804, end when meeting test requirements document condition for judging that event before on-test is corresponding Whether the time interval of time and time on-test of the experiment process event found are in the second prefixed time interval It is interior.
In one embodiment, routine test analytical equipment further includes:First reminds transmitting element, for if there is no satisfaction Event and/or experiment process event, send to experiment related personnel and remind before the on-test of setting condition.
In one embodiment, routine test analytical equipment further includes:
Acquiring unit tested the anti-of corresponding device parameter before the off-test time for obtaining in the 4th set period of time The change rate of feedback value;
Judging unit, for judging the change rate whether in preset threshold range;
Second reminds transmitting element, for sending information to experiment related personnel, to remind experiment related personnel to experiment Underproof reason is analyzed.
In one embodiment, routine test analytical equipment further includes:Tendency chart drawing unit, for according to the field data Draw the tendency chart of different data;
Transmitting element, for the tendency chart to be sent to human-computer interaction module.
The present invention can have by carrying out logic judgment or mathematical computations, the result after data compare by analysis to data More in time and be efficiently completed experiment work beneficial to subordinate electricity power enterprise, realize timed reminding, automatic discrimination process of work, The functions such as effect are completed in evaluation, and realize and the course of work is traced, and foundation is checked to provide to test.Solves existing hair Power plant is due to mostly building remote districts and dispersed placement, caused inspection timeliness, the practical significance and effect of supervision and check in The problem of all very low.
The embodiment of the present invention additionally provides a kind of computer equipment, including memory, processor and storage on a memory And the computer program that can be run on a processor, the processor realize following steps when performing the computer program:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by network;
According to the field data extract on-test before event, experiment process event and experiment End Event it is corresponding when Between point data, by the time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to deposit forward successively Event and experiment process event before the on-test to impose a condition is met;
If there is event before the on-test for meeting setting condition and experiment process event, opening for process event will be tested Time beginning is set to time on-test, will be set to the off-test time at the beginning of off-test event, stores the experiment Time started and off-test time.
The embodiment of the present invention additionally provides a kind of computer readable storage medium, is stored thereon with computer program, described Following steps are realized when computer program is executed by processor:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by network;
According to the field data extract on-test before event, experiment process event and experiment End Event it is corresponding when Between point data, by the time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to deposit forward successively Event and experiment process event before the on-test to impose a condition is met;
If there is event before the on-test for meeting setting condition and experiment process event, opening for process event will be tested Time beginning is set to time on-test, will be set to the off-test time at the beginning of off-test event, stores the experiment Time started and off-test time.
It should be understood by those skilled in the art that, the embodiment of the present invention can be provided as method, system or computer program Product.Therefore, the reality in terms of complete hardware embodiment, complete software embodiment or combination software and hardware can be used in the present invention Apply the form of example.Moreover, the computer for wherein including computer usable program code in one or more can be used in the present invention The computer program production that usable storage medium is implemented on (including but not limited to magnetic disk storage, CD-ROM, optical memory etc.) The form of product.
The present invention be with reference to according to the method for the embodiment of the present invention, the flow of equipment (system) and computer program product Figure and/or block diagram describe.It should be understood that it can be realized by computer program instructions every first-class in flowchart and/or the block diagram The combination of flow and/or box in journey and/or box and flowchart and/or the block diagram.These computer programs can be provided The processor of all-purpose computer, special purpose computer, Embedded Processor or other programmable data processing devices is instructed to produce A raw machine so that the instruction performed by computer or the processor of other programmable data processing devices is generated for real The device for the function of being specified in present one flow of flow chart or one box of multiple flows and/or block diagram or multiple boxes.
These computer program instructions, which may also be stored in, can guide computer or other programmable data processing devices with spy Determine in the computer-readable memory that mode works so that the instruction generation being stored in the computer-readable memory includes referring to Make the manufacture of device, the command device realize in one flow of flow chart or multiple flows and/or one box of block diagram or The function of being specified in multiple boxes.
These computer program instructions can be also loaded into computer or other programmable data processing devices so that counted Series of operation steps is performed on calculation machine or other programmable devices to generate computer implemented processing, so as in computer or The instruction offer performed on other programmable devices is used to implement in one flow of flow chart or multiple flows and/or block diagram one The step of function of being specified in a box or multiple boxes.
It applies specific embodiment in the present invention to be set forth the principle of the present invention and embodiment, above example Explanation be only intended to help understand the present invention method and its core concept;Meanwhile for those of ordinary skill in the art, Thought according to the invention, there will be changes in specific embodiments and applications, in conclusion in this specification Appearance should not be construed as limiting the invention.

Claims (16)

1. a kind of routine test analysis method based on timeliness norm controlling, which is characterized in that including:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by photoelectricity transmission medium;
According to event, experiment process event and experiment End Event corresponding time point before field data extraction on-test Data, by time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to exist forward successively full Event and experiment process event before the on-test to impose a condition enough;
If there is event before the on-test for meeting setting condition and experiment process event, at the beginning of experiment process event Between be set to time on-test, the off-test time will be set at the beginning of off-test event, store the on-test Time and off-test time.
2. routine test analysis method according to claim 1, which is characterized in that further include:Search setting date correspondence Floating in a few days in database with the presence or absence of the setting date corresponding test data sheet, if it does not, to experiment relevant people Member, which sends, to be reminded.
3. routine test analysis method according to claim 1, which is characterized in that event is corresponding before the on-test Time point data is at the beginning of when meeting test requirements document condition and the end time;It is described to test the process event corresponding time Point data is time on-test and off-test time;The corresponding time point data of End Event of testing is off-test At the beginning of.
4. routine test analysis method according to claim 3, which is characterized in that according to the off-test event found Time point data on the basis of, search whether successively forward exist meet impose a condition on-test before event and experiment process Event, including:
On the basis of at the beginning of the corresponding off-test of off-test event, search setting the second set period of time in whether In the presence of experiment process event;
If it does, the off-test event for judging the off-test time of the experiment process event found and finding Off-test at the beginning of time interval whether in the first prefixed time interval;
If so, on the basis of time on-test of the experiment process event found, the 3rd set period of time of setting is searched Interior event before whether there is on-test;
If set in the 3rd set period of time there are event before on-test, the corresponding satisfaction examination of event before on-test is judged Whether the time interval of time on-test of end time and the experiment process event found when testing requirement condition In the second prefixed time interval.
5. routine test analysis method according to claim 1, which is characterized in that impose a condition if there is no satisfaction Event and/or experiment process event, send to experiment related personnel and remind before on-test.
6. routine test analysis method according to claim 3, which is characterized in that further include:
The change rate of the value of feedback of corresponding device parameter was tested before the acquisition off-test time in 4th set period of time;
Judge the change rate whether in preset threshold range;
If the change rate, not in preset threshold range, to experiment, related personnel sends information, to remind experiment related personnel It analyzes testing underproof reason.
7. routine test analysis method according to claim 1, which is characterized in that further include:
The tendency chart of different data is drawn according to the field data;
The tendency chart is sent to human-computer interaction module.
8. a kind of routine test analytical equipment based on timeliness norm controlling, which is characterized in that including:
Data receipt unit receives showing for the power plant equipment that gathers in real time of collection in worksite equipment for passing through photoelectricity transmission medium Field data;
Data record unit, for being tied according to event, experiment process event and experiment before field data extraction on-test The corresponding time point data of beam event, by time point data storage into database;
Detection unit whether there is experiment End Event for detecting in the database in the first set period of time;
Searching unit on the basis of the time point data according to the off-test event found, searches whether forward successively In the presence of event before the on-test for meeting setting condition and experiment process event;
Setup unit, for process event will to be tested at the beginning of be set to time on-test, by opening for off-test event Time beginning is set to the off-test time, stores time on-test and off-test time.
9. routine test analytical equipment according to claim 8, which is characterized in that the searching unit is additionally operable to search and set Corresponding floating fix the date in a few days in database with the presence or absence of the setting date corresponding test data sheet, if it does not, to It tests related personnel and sends prompting.
10. routine test analytical equipment according to claim 8, which is characterized in that event corresponds to before the on-test Time point data at the beginning of when meeting test requirements document condition and the end time;It is described experiment process event it is corresponding when Between point data be time on-test and off-test time;The corresponding time point data of End Event of testing is tied for experiment At the beginning of beam.
11. routine test analytical equipment according to claim 10, which is characterized in that the searching unit includes:
First searching module on the basis of at the beginning of the corresponding off-test of off-test event, searches setting the With the presence or absence of experiment process event in two set period of time;
First judgment module, for the experiment for judging the off-test time of the experiment process event found and finding Whether the time interval at the beginning of the off-test of End Event is in the first prefixed time interval;
Second searching module, on the basis of time on-test of the experiment process event found, searching setting the 3rd With the presence or absence of event before on-test in set period of time;
Second judgment unit, end time when meeting test requirements document condition for judging that event before on-test is corresponding is with looking into Whether the time interval of time on-test of the experiment process event found is in the second prefixed time interval.
12. routine test analytical equipment according to claim 8, which is characterized in that further include:First reminds transmission single Member, for event before the on-test if there is no satisfaction setting condition and/or experiment process event, to experiment related personnel It sends and reminds.
13. routine test analytical equipment according to claim 10, which is characterized in that further include:
Acquiring unit, for obtaining the value of feedback for testing corresponding device parameter before the off-test time in the 4th set period of time Change rate;
Judging unit, for judging the change rate whether in preset threshold range;
Second reminds transmitting element, for sending information to experiment related personnel, experiment related personnel to be reminded not conform to experiment The reason for lattice, is analyzed.
14. routine test analytical equipment according to claim 8, which is characterized in that further include:
Tendency chart drawing unit, for drawing the tendency chart of different data according to the field data;
Transmitting element, for the tendency chart to be sent to human-computer interaction module.
15. a kind of computer equipment including memory, processor and stores the meter that can be run on a memory and on a processor Calculation machine program, which is characterized in that the processor realizes following steps when performing the computer program:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by network;
According to event, experiment process event and experiment End Event corresponding time point before field data extraction on-test Data, by time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to exist forward successively full Event and experiment process event before the on-test to impose a condition enough;
If there is event before the on-test for meeting setting condition and experiment process event, at the beginning of experiment process event Between be set to time on-test, the off-test time will be set at the beginning of off-test event, store the on-test Time and off-test time.
16. a kind of computer readable storage medium, is stored thereon with computer program, which is characterized in that the computer program Following steps are realized when being executed by processor:
The field data for the power plant equipment that collection in worksite equipment gathers in real time is received by network;
According to event, experiment process event and experiment End Event corresponding time point before field data extraction on-test Data, by time point data storage into database;
It detects and whether there is experiment End Event in the first set period of time in the database;
If so, on the basis of according to the time point data of the off-test event found, search whether to exist forward successively full Event and experiment process event before the on-test to impose a condition enough;
If there is event before the on-test for meeting setting condition and experiment process event, at the beginning of experiment process event Between be set to time on-test, the off-test time will be set at the beginning of off-test event, store the on-test Time and off-test time.
CN201711260430.7A 2017-12-04 2017-12-04 Routine test analysis method and device based on timeliness norm controlling Pending CN108052561A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711260430.7A CN108052561A (en) 2017-12-04 2017-12-04 Routine test analysis method and device based on timeliness norm controlling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711260430.7A CN108052561A (en) 2017-12-04 2017-12-04 Routine test analysis method and device based on timeliness norm controlling

Publications (1)

Publication Number Publication Date
CN108052561A true CN108052561A (en) 2018-05-18

Family

ID=62122067

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711260430.7A Pending CN108052561A (en) 2017-12-04 2017-12-04 Routine test analysis method and device based on timeliness norm controlling

Country Status (1)

Country Link
CN (1) CN108052561A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109632205A (en) * 2018-12-05 2019-04-16 北京英贝思科技有限公司 The on-line calculation method of Tightness Property of Condenser Vacuum System
CN110175744A (en) * 2019-04-23 2019-08-27 中国核电工程有限公司 A kind of data processing method of nuclear power plant's accident treatment directive/guide confirmation
CN110262914A (en) * 2019-06-20 2019-09-20 北京北方华创微电子装备有限公司 A kind of semiconductor equipment process data processing method and system
CN111091255A (en) * 2018-10-23 2020-05-01 中核核电运行管理有限公司 Method for monitoring and applying periodic test data in real time

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104793075A (en) * 2015-03-30 2015-07-22 北京广利核系统工程有限公司 Periodic test system for protection systems for pressurized water reactor nuclear power plants
CN107169617A (en) * 2016-03-07 2017-09-15 中国电力科学研究院 A kind of controller switching equipment state evaluation system
CN207472305U (en) * 2017-09-25 2018-06-08 北京能源集团有限责任公司 Power plant experimental monitor

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104793075A (en) * 2015-03-30 2015-07-22 北京广利核系统工程有限公司 Periodic test system for protection systems for pressurized water reactor nuclear power plants
CN107169617A (en) * 2016-03-07 2017-09-15 中国电力科学研究院 A kind of controller switching equipment state evaluation system
CN207472305U (en) * 2017-09-25 2018-06-08 北京能源集团有限责任公司 Power plant experimental monitor

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111091255A (en) * 2018-10-23 2020-05-01 中核核电运行管理有限公司 Method for monitoring and applying periodic test data in real time
CN109632205A (en) * 2018-12-05 2019-04-16 北京英贝思科技有限公司 The on-line calculation method of Tightness Property of Condenser Vacuum System
CN110175744A (en) * 2019-04-23 2019-08-27 中国核电工程有限公司 A kind of data processing method of nuclear power plant's accident treatment directive/guide confirmation
CN110262914A (en) * 2019-06-20 2019-09-20 北京北方华创微电子装备有限公司 A kind of semiconductor equipment process data processing method and system

Similar Documents

Publication Publication Date Title
CN108375715B (en) Power distribution network line fault risk day prediction method and system
CN108052561A (en) Routine test analysis method and device based on timeliness norm controlling
CN103197138B (en) A kind of intelligent electric meter and monitoring method with power supply reliability and rate of qualified voltage monitoring function
CN109886475B (en) Information security situation perception system of measurement automation system based on AI
KR101916926B1 (en) Smart meter system and detection method applying abnormal information detection technology
CN106054104A (en) Intelligent ammeter fault real time prediction method based on decision-making tree
JP6298214B2 (en) System and method for maximizing the expected utility of signal injection test patterns within a utility grid
MX2013000577A (en) Machine learning for power grids.
CN109204389A (en) A kind of subway equipment fault diagnosis and self-healing method, system
CN103200051A (en) Intelligent substation message simulation testing and association message analysis system and method
CN110097275A (en) A kind of family change relational checking method and device based on platform area power failure data
CN104578411B (en) A kind of PMU data accesses the multi-source data safety check after AGC and failure locking method
CN109800995A (en) A kind of grid equipment fault recognition method and system
CN105445591B (en) Current transformer method for diagnosing faults and current transformer trouble-shooter
CN105373118A (en) Intelligent equipment data acquisition method
CN207472305U (en) Power plant experimental monitor
CN109903008A (en) A kind of subway work construction project progress visualization managing and control system and management-control method
Lu et al. The development of a smart distribution grid testbed for integrated information management systems
CN115936663A (en) Maintenance method and device for power system
Biswas et al. An Open-Source Library of Phasor Measurement Unit Data Capturing Real Bulk Power Systems Behavior
CN108320078A (en) A kind of power plant monitoring device timeliness index Test analysis method based on big data
CN113541126A (en) Power distribution network simulation system suitable for verifying advanced algorithm and algorithm verification method
Sivokobylenko et al. Detecting development scenarios of dynamic events in electric powernetworks smart-grid. Part 1 “Method”
CN114897196B (en) Operation management method, equipment and medium for office building water supply network
CN104239688A (en) Power switching method based on human reliability analysis

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180518

RJ01 Rejection of invention patent application after publication