- CN109763663B CN109763663B CN201811578393.9A CN201811578393A CN109763663B CN 109763663 B CN109763663 B CN 109763663B CN 201811578393 A CN201811578393 A CN 201811578393A CN 109763663 B CN109763663 B CN 109763663B
- Authority
- CN
- China
- Prior art keywords
- bar
- steel
- shaped connecting
- column
- protection device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种框架柱钢筋保护装置及其施工方法,包括可伸缩钢管、木模板、钢筋套管、条形连接钢板和连接螺帽,所述钢筋套管焊接在可伸缩钢管的顶端,所述可伸缩钢管沿长度方向上焊接有四道条形连接钢板,每两个条形连接钢板的焊接角度为90°,所述钢筋套管套在矩形柱四个角的竖向筋上,可伸缩钢管上的条形连接钢板两两相连,所述木模板插入条形连接钢板的缝隙中,并用连接螺帽连接固定,条形连接钢板上开设有螺纹孔,用于安装连接螺帽对木模板形成固定。本发明构造简单,操作方便,可大批量生产,对因混凝土内支撑拆撑时柱的预留柱插筋保护具有显著的效果,有效避免了基坑混凝土水平内支撑拆除及清运时对混凝土框架柱预留插筋的破坏。
Description
技术领域
本发明属于基坑支护施工技术领域,具体涉及一种框架柱钢筋保护装置及其施工方法。
背景技术
基坑支护的形式有多种,其中临时的水平内支撑结构应用较为广泛,随基坑深度的增加,混凝土水平内支撑结构可能有多道,基坑内临时水平内支撑结构要在地下室结构施工到达一定阶段,换撑施工达到一定强度后方可拆除,如不采取有效措施,内支撑的拆除对于结构的预留钢筋的破坏是十分严重的,对后续的钢筋调直工作甚至植筋工作具有较大影响,目前针对基坑内支撑拆除及清运时对柱钢筋的保护并无有效措施。。
发明内容
为了克服现有技术中基坑支护施工中的内支撑的拆除对于结构的预留钢筋破坏严重这一技术缺陷,本发明提供了一种框架柱钢筋保护装置及其施工方法,整体构造和用料简单、操作方便、可大批量生产,对拆撑时柱的预留钢筋保护具有显著的效果,可广泛应用于基坑内支撑拆除及清运时对柱钢筋的保护施工解决了上述技术问题。
本发明通过以下技术方案来实现上述目的,一种框架柱钢筋保护装置,包括可伸缩钢管、木模板、钢筋套管、条形连接钢板和连接螺帽,所述钢筋套管焊接在可伸缩钢管的顶端,所述可伸缩钢管沿长度方向上焊接有四道条形连接钢板,每两个条形连接钢板的焊接角度为90°,所述钢筋套管嵌套在矩形柱四个角的竖向筋上,可伸缩钢管上的条形连接钢板两两相连,所述木模板插入条形连接钢板的缝隙中,并用连接螺帽连接固定。
上述的一种框架柱钢筋保护装置,所述条形连接钢板上开设有螺纹孔,用于安装连接螺帽对木模板形成固定。
本发明在使用,主要通过以下步骤来完成框架柱钢筋保护装置的安装,以实现混凝土内支撑拆撑时对预留柱钢筋形成保护:
S1:将可伸缩钢管、钢筋套管以及条形连接钢板焊接在一起固定;
S2:将钢筋套管嵌套在矩形柱四个角的竖向筋上,可伸缩钢管上的条形连接钢板两两相连;
S3:木模板插入条形连接钢板的缝隙中;
S4:利用连接螺帽对条形连接钢板缝隙中的木模板进行固定,使得柱钢筋的四周被封闭,完成柱钢筋保护装置的安装。
总体而言,通过本发明所构思的以上技术方案与现有技术相比,可以达到以下有益效果:本发明所述的一种框架柱钢筋保护装置,构造简单,用料简单、操作方便、可大批量生产,对拆撑时柱的预留钢筋保护具有显著的效果,可广泛应用于基坑内支撑拆除及清运时对柱钢筋的保护施工。
附图说明
下面结合附图对本发明的具体实施方式做进一步详细的说明,其中:
图1为本发明一种框架柱钢筋保护装置的整体结构示意图;
图2为本发明一种框架柱钢筋保护装置拼装完成后的结构示意图;
图3为本发明一种框架柱钢筋保护装置拼装完成并插入木模板后的结构示意图;
图中:1-可伸缩钢管,2-木模板,3-钢筋套管,4-条形连接钢板,5-连接螺帽。
具体实施方式
如图1所示,为本发明一种框架柱钢筋保护装置的整体结构示意图,包括可伸缩钢管1、木模板2、钢筋套管3、条形连接钢板4和连接螺帽5,所述钢筋套管3焊接在可伸缩钢管1的顶端,所述可伸缩钢管1沿长度方向上焊接有四道条形连接钢板4,每两个条形连接钢板4的焊接角度为90°,所述钢筋套管3套在矩形柱四个角的竖向筋上,可伸缩钢管1上的条形连接钢板4两两相连,所述木模板2插入条形连接钢板4的缝隙中,并用连接螺帽5连接固定,条形连接钢板4上开设有螺纹孔,用于安装连接螺帽5对木模板形成固定。
本发明在使用,主要通过以下步骤来实现夹具的安装,方便牢固的将反顶构件和小型机械设备连接起来,在狭小空间内进行反顶作业:
步骤一:将可伸缩钢管1、钢筋套管3以及条形连接钢板4焊接在一起固定;
步骤二:将钢筋套管3嵌套在矩形柱四个角的竖向筋上,可伸缩钢管1上的条形连接钢板4两两相连,该步骤完成后的结构如图2所示;
步骤三:木模板2插入条形连接钢板4的缝隙中,该步骤完成后的整体结构如图3所示;
步骤四:利用连接螺帽5对条形连接钢板4缝隙中的木模板2进行固定,使得柱钢筋的四周被封闭,完成柱钢筋保护装置的安装。
本领域的技术人员容易理解,以上所述仅为本发明的较佳实施例而已,并不用于限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。
Claims (3)
1.一种框架柱钢筋保护装置,包括可伸缩钢管(1)、木模板(2)、钢筋套管(3)、条形连接钢板(4)和连接螺帽(5),其特征在于:所述钢筋套管(3)焊接在可伸缩钢管(1)的顶端,所述可伸缩钢管(1)沿长度方向上焊接有四道条形连接钢板(4),每道条形连接钢板包括两个条形连接钢板,每两个条形连接钢板(4)的焊接角度为90°,所述钢筋套管(3)套在矩形柱四个角的竖向筋上,相邻的可伸缩钢管(1)上的条形连接钢板(4)两两相连,所述木模板(2)插入条形连接钢板(4)的缝隙中,并用连接螺帽(5)连接固定。
2.根据权利要求1所述的一种框架柱钢筋保护装置,其特征在于:所述条形连接钢板(4)上开设有螺纹孔,用于安装连接螺帽(5)对木模板(2)形成固定。
3.一种如权利要求1所述的框架柱钢筋保护装置的施工方法,其特征在于:该施工方法主要包括以下步骤:
S1:将可伸缩钢管(1)、钢筋套管(3)以及条形连接钢板(4)焊接在一起固定;
S2:将钢筋套管(3)嵌套在矩形柱四个角的竖向筋上,可伸缩钢管(1)上的条形连接钢板(4)两两相连;
S3:木模板(2)插入条形连接钢板(4)的缝隙中;
S4:利用连接螺帽(5)对条形连接钢板(4)缝隙中的木模板(2)进行固定,使得柱钢筋的四周被封闭,完成柱钢筋保护装置的安装。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811578393.9A CN109763663B (zh) | 2018-12-24 | 2018-12-24 | 一种框架柱钢筋保护装置及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811578393.9A CN109763663B (zh) | 2018-12-24 | 2018-12-24 | 一种框架柱钢筋保护装置及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109763663A CN109763663A (zh) | 2019-05-17 |
CN109763663B true CN109763663B (zh) | 2021-05-14 |
Family
ID=66450837
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811578393.9A Active CN109763663B (zh) | 2018-12-24 | 2018-12-24 | 一种框架柱钢筋保护装置及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109763663B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114215270B (zh) * | 2021-12-21 | 2023-07-28 | 浙江恒鸿建设有限公司 | 外凸线条钢筋混凝土景观柱及施工方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10220021A (ja) * | 1997-02-05 | 1998-08-18 | Taisei Corp | 差筋等の間隔保持具 |
KR100986589B1 (ko) * | 2010-06-25 | 2010-10-08 | (주)해우엔지니어링건축사사무소 | 철근 콘크리트 공사의 여장 철근 보호 장치 |
CN104674821A (zh) * | 2014-12-29 | 2015-06-03 | 山西四建集团有限公司 | 小型基坑槽钢支护架体支护施工方法 |
CN205296879U (zh) * | 2015-12-22 | 2016-06-08 | 天津二建建筑工程有限公司第三分公司 | 一种建筑物框架柱用可调节、拆卸的护角装置 |
CN205348814U (zh) * | 2015-12-07 | 2016-06-29 | 中国建筑第八工程局有限公司 | 柱钢筋保护架结构 |
CN206143781U (zh) * | 2016-08-30 | 2017-05-03 | 辽宁省路桥建设集团有限公司 | 混凝土柱头钢筋防护罩 |
CN206591843U (zh) * | 2017-02-08 | 2017-10-27 | 中国一冶集团有限公司 | 一种可伸缩钢筋保护套管 |
CN207268090U (zh) * | 2017-08-31 | 2018-04-24 | 上海建工七建集团有限公司 | 预留插筋防护装置 |
-
2018
- 2018-12-24 CN CN201811578393.9A patent/CN109763663B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10220021A (ja) * | 1997-02-05 | 1998-08-18 | Taisei Corp | 差筋等の間隔保持具 |
KR100986589B1 (ko) * | 2010-06-25 | 2010-10-08 | (주)해우엔지니어링건축사사무소 | 철근 콘크리트 공사의 여장 철근 보호 장치 |
CN104674821A (zh) * | 2014-12-29 | 2015-06-03 | 山西四建集团有限公司 | 小型基坑槽钢支护架体支护施工方法 |
CN205348814U (zh) * | 2015-12-07 | 2016-06-29 | 中国建筑第八工程局有限公司 | 柱钢筋保护架结构 |
CN205296879U (zh) * | 2015-12-22 | 2016-06-08 | 天津二建建筑工程有限公司第三分公司 | 一种建筑物框架柱用可调节、拆卸的护角装置 |
CN206143781U (zh) * | 2016-08-30 | 2017-05-03 | 辽宁省路桥建设集团有限公司 | 混凝土柱头钢筋防护罩 |
CN206591843U (zh) * | 2017-02-08 | 2017-10-27 | 中国一冶集团有限公司 | 一种可伸缩钢筋保护套管 |
CN207268090U (zh) * | 2017-08-31 | 2018-04-24 | 上海建工七建集团有限公司 | 预留插筋防护装置 |
Also Published As
Publication number | Publication date |
---|---|
CN109763663A (zh) | 2019-05-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105888108A (zh) | 内置定位预制件钢筋混凝土剪力墙及施工方法 | |
CN105569331A (zh) | 一种混凝土圆柱模板的简易支撑方法 | |
CN210887275U (zh) | 一种混凝土桩承台模板结构 | |
CN109763663B (zh) | 一种框架柱钢筋保护装置及其施工方法 | |
CN203834926U (zh) | 清水混凝土地下室外墙模板支模结构 | |
CN113323189A (zh) | 一种基于槽钢连接件的装配式保温节能剪力墙及实施方法 | |
CN202157581U (zh) | 一种基坑临边定型化防护装置 | |
CN211228607U (zh) | 构筑物现浇混凝土结构外墙与底板整体成型施工结构 | |
CN204139622U (zh) | 可调节柱钢筋定位卡具 | |
CN210918296U (zh) | 一种方钢管套筒固定装置 | |
CN214116678U (zh) | 一种装配式胎膜 | |
CN202543907U (zh) | 用于灌注桩或钢管混凝土柱混凝土浇筑施工的操作平台 | |
CN105422140A (zh) | 井巷工程混凝土支护施工用支模装置 | |
CN205224593U (zh) | 一种用于钢筋混凝土立柱的支护结构 | |
CN115680116A (zh) | 一种装配式框架梁柱连接节点及其施工方法 | |
KR102370425B1 (ko) | 보거푸집의 안전난간대 | |
CN212406192U (zh) | 一种快拆式临边防护围挡 | |
CN209816670U (zh) | 一种设置在钢套箱内支撑钢管上的人行通道 | |
CN108755443B (zh) | 一种墩梁临时固结装置 | |
TW320667B (en) | A form plate fabric for prefabricated concrete | |
CN104032973A (zh) | 一种墙体托换技术及结构 | |
CN219138623U (zh) | 一种装配式简易围墙 | |
CN216076430U (zh) | 一种临边洞口防护装置 | |
CN107165478A (zh) | 一种可重复使用的装配式围挡单元 | |
CN104088580B (zh) | 一种可周转使用的组合式大门及其制作方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |