CN109750691A - A kind of basement post-pouring zone underdrain method for constructing terrace - Google Patents
A kind of basement post-pouring zone underdrain method for constructing terrace Download PDFInfo
- Publication number
- CN109750691A CN109750691A CN201910069156.8A CN201910069156A CN109750691A CN 109750691 A CN109750691 A CN 109750691A CN 201910069156 A CN201910069156 A CN 201910069156A CN 109750691 A CN109750691 A CN 109750691A
- Authority
- CN
- China
- Prior art keywords
- underdrain
- drain bar
- terrace
- post
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The present invention discloses a kind of basement post-pouring zone underdrain method for constructing terrace, includes the following steps: (1) preparation of construction;(2) snap the line indicates that underdrain moves towards;(3) it is laid with drain bar;(4) fine-stone concrete is poured;(5) two side sealing of drain bar;(6) terrace is poured and is conserved.The present invention, using basement post-pouring zone coiled material drain bar underdrain method for constructing terrace, has good moisture-proof impervious effect, is further reduced basement bottom board hidden leakage defect on the basis of ne-leakage point before carrying out post empiricism, guaranteeing that terrace pours.
Description
Technical field
The invention belongs to the technical fields of basement drainage system, and in particular to a kind of basement post-pouring zone underdrain terrace is applied
Work method.
Background technique
Buildings waterproof plays a significant role guarantee building normal usage function and structure service life, concerning the common people people
Raw and social harmony.Construction waterproofing engineering technical quality steps up at present, has considerably reduced engineering leakage water rate, but ground
Lower room engineering leakage is still common quality defect common in engineering.
With the development and utilization of the underground space, more and more houses are designed using integral basement, integral basement control
The method of system sedimentation is setting post-cast strip, and the setting of a large amount of post-cast strips becomes the multiple position of basement bottom board leakage, and
Once occur leakage maintaining cost it is high, calculated according to engineering practice, every meter only maintenance cost up to 1000 yuan.For two, three, four
The underground engineering of grade waterproofing grade provides that body structure surface can according to " underground waterproof engineering inspection of quality specification " GB50208-2011
There is a small amount of wet stain, but a small amount of wet stain bring terrace yin tide seriously affects the use function of basement after engineering delivery, and because of ground
Face has been constructed completion, and bring maintenance cost is very big.
Summary of the invention
Goal of the invention: present invention aims at in view of the deficiencies of the prior art, providing a kind of basement post-pouring zone underdrain
Level ground construction method, the present invention is on the basis of ne-leakage point before carrying out post empiricism, guaranteeing that terrace pours, after basement
Band coiled material drain bar underdrain method for constructing terrace is poured, there is good moisture-proof impervious effect, is further reduced basement bottom board infiltration
Leak hidden danger.
Technical solution: a kind of basement post-pouring zone underdrain method for constructing terrace of the present invention includes the following steps:
(1) preparation of construction: firstly, the trend in gutter and the position of post-cast strip are determined according to construction drawing design requirement, in conjunction with
The layout drawing of post-cast strip underdrain is drawn in gutter and the position of sump, and underdrain must not intersect with gutter and be directly communicated to catchment
Well;Then, base cleaning carried out to ground as required, do ash cake floating screed, install gutter construction, and leakage scenarios arranged
Examination is received;Finally, selecting bump height for the coiled material drain bar of≤12mm, according to drain bar before the construction of post-cast strip underdrain
Specification is cut into width >=300mm lath by modulus;
(2) snap the line indicates that underdrain moves towards: according to the post-cast strip underdrain layout drawing of drafting, in the pop-up control of post empiricism seam two sides
Line, or unilateral control line determine different underdrain system trends according to catch pit position, and underdrain system must not move towards
It is connect with original design gutter;
(3) it is laid with drain bar: the drain bar salient point cut being laid with down along control line, drain bar connection uses the overlap joint of snapping
Mode, the lap width of drain bar are at least two rows of salient point snappings;
(4) it pours fine-stone concrete: pouring fine-stone concrete on the drain bar laid, struck off using floating rule, make to fill in drain bar salient point
Full fine-stone concrete, surface carry out hair pulling treatment;After the completion of pouring, shape under the concrete fulcrum and drain bar collective effect that are formed in salient point
At underdrain and guarantee the compression strength of terrace, while reducing destruction when pouring terrace to underdrain, is convenient for finished product protection;
(5) it two side sealing of drain bar: is laid with the gap of microlith concrete plug two sides, drain bar two sides respectively in drain bar underdrain two sides
Fine-stone concrete heap it is sloping and drain bar side is blocked it is closely knit, it is same with the concrete fulcrum that pours salient point in order to simplify working procedure
When construct;
(6) terrace is poured and is conserved: floor construction is carried out afterwards for 24 hours after the completion of construction, to thin on drain bar before floor construction
Stone concrete carries out watering or covering curing;It is many to the curing time of the fine-stone concrete on drain bar if not pouring terrace in time
In 7 days.
Preferably, in the step (4), pour fine-stone concrete with a thickness of 10mm.
Preferably, in the step (1), thickness >=0.7mm of drain bar.
The utility model has the advantages that (1) it is of the invention method it is simple, utilize the salient point and drain bar collective effect of anti-paving coiled material drain bar
It forming underdrain and guarantees the compression strength of terrace, the construction technology in the present invention is simple, and worker operation is convenient, and speed of application is fast,
And can construct simultaneously with base cleaning and gutter, on the duration of a project without influence, fast, the easy to operate, cost with speed of application
Low, the advantages that serious forgiveness is high;
(2) fine-stone concrete is perfused in the present invention in the salient point of drain bar in advance, guarantees terrace intensity, does not influence the construction matter of terrace
Amount, has the function of that anti-row combines using the underdrain of this method, effectively reduces basement bottom plate rear pouring tape hidden leakage defect, subtract
Few later period maintenance cost, improves owner's satisfaction, has preferable economic benefit and social benefit;
(3) material of the invention is environment friendly and pollution-free, on environment without influence;It reduces later period terrace to do over again, economize on resources.
Specific embodiment
Be described in detail below by technical solution of the present invention, but protection scope of the present invention be not limited to it is described
Embodiment.
Embodiment: a kind of basement post-pouring zone underdrain method for constructing terrace includes the following steps:
(1) preparation of construction: firstly, the trend in gutter and the position of post-cast strip are determined according to construction drawing design requirement, in conjunction with
The layout drawing of post-cast strip underdrain is drawn in gutter and the position of sump, and underdrain must not intersect with gutter and be directly communicated to catchment
Well;Then, base cleaning carried out to ground as required, do ash cake floating screed, install gutter construction, and leakage scenarios arranged
Examination is received;Finally, selecting bump height for the PVC roll material drain bar of≤12mm, the thickness of drain bar before the construction of post-cast strip underdrain
Degree >=0.7mm is cut into width >=300mm lath by modulus according to the specification of drain bar;
(2) snap the line indicates that underdrain moves towards: according to the post-cast strip underdrain layout drawing of drafting, in the pop-up control of post empiricism seam two sides
Line, or unilateral control line determine different underdrain system trends according to catch pit position, and underdrain system must not move towards
It is connect with original design gutter;
(3) it is laid with drain bar: the drain bar salient point cut being laid with down along control line, drain bar connection uses the overlap joint of snapping
Mode, the lap width of drain bar are at least two rows of salient point snappings;
(4) pour fine-stone concrete: pouring fine-stone concrete on the drain bar laid, pour fine-stone concrete with a thickness of 10mm, using scraping
Ruler strikes off, and makes to fill fine-stone concrete in drain bar salient point, and surface carries out hair pulling treatment;After the completion of pouring, the concrete that is formed in salient point
Underdrain is formed under fulcrum and drain bar collective effect and guarantees the compression strength of terrace, while being reduced when pouring terrace to underdrain
It destroys, is convenient for finished product protection;
(5) it two side sealing of drain bar: is laid with the gap of microlith concrete plug two sides, drain bar two sides respectively in drain bar underdrain two sides
Fine-stone concrete heap it is sloping and drain bar side is blocked it is closely knit, it is same with the concrete fulcrum that pours salient point in order to simplify working procedure
When construct;
(6) terrace is poured and is conserved: floor construction is carried out afterwards for 24 hours after the completion of construction, to thin on drain bar before floor construction
Stone concrete carries out watering or covering curing;It is many to the curing time of the fine-stone concrete on drain bar if not pouring terrace in time
In 7 days.
It is that need to carry out incoming inspection, and sampling inspection is carried out in accordance with regulations that PVC roll material drain bar, cement, sand, stone, which are marched into the arena, inspection
Surveying qualified rear can be used;Pea gravel concreten, which is marched into the arena, to check raw material quality, slump etc.;After the completion of terrace pours
It tests to strength grade of concrete.
Invention described in the present embodiment is applied to Wuhe County youth country fair west side work of renovating shantytowns project garden Village the second stage of the project
Ground library two, library three, library four, application effect is good, achieves good Social benefit and economic benefit.
Wuhe County youth's country fair west side work of renovating shantytowns project garden Village the second stage of the project: 35 Wan ㎡ of overall floorage, underground
One layer, 26/30 layer on the ground, frame-shear structure is located to the east of the west part of the ring road of Wuhe County, on the south Huaihe Road.Construction party of the present invention
Method for ground library two, library three, library four, 56000 ㎡ of the ground library gross area, basement bottom board waterproofing grade be second level, waterproof does
Method is polyurethane water-proof paint+concrete water-proof plate, and terrace way is 100mm thickness C20 pea gravel concreten.It is poured after this engineering is shared
Band 2690.5m, using basement post-pouring zone underdrain position terrace after construction method of the present invention without negative tidemark mark, water proof anti-seepage
Significant effect obtains local construction authorities and the favorable comment always of owner.
As described above, must not be explained although the present invention has been indicated and described referring to specific preferred embodiment
For the limitation to invention itself.It without prejudice to the spirit and scope of the invention as defined in the appended claims, can be right
Various changes can be made in the form and details for it.
Claims (3)
1. a kind of basement post-pouring zone underdrain method for constructing terrace, it is characterised in that include the following steps:
(1) preparation of construction: firstly, the trend in gutter and the position of post-cast strip are determined according to construction drawing design requirement, in conjunction with
The layout drawing of post-cast strip underdrain is drawn in gutter and the position of sump, and underdrain must not intersect with gutter and be directly communicated to catchment
Well;Then, base cleaning carried out to ground as required, do ash cake floating screed, install gutter construction, and leakage scenarios arranged
Examination is received;Finally, selecting bump height for the coiled material drain bar of≤12mm, according to drain bar before the construction of post-cast strip underdrain
Specification is cut into width >=300mm lath by modulus;
(2) snap the line indicates that underdrain moves towards: according to the post-cast strip underdrain layout drawing of drafting, in the pop-up control of post empiricism seam two sides
Line, or unilateral control line determine different underdrain system trends according to catch pit position, and underdrain system must not move towards
It is connect with original design gutter;
(3) it is laid with drain bar: the drain bar salient point cut being laid with down along control line, drain bar connection uses the overlap joint of snapping
Mode, the lap width of drain bar are at least two rows of salient point snappings;
(4) it pours fine-stone concrete: pouring fine-stone concrete on the drain bar laid, struck off using floating rule, make to fill in drain bar salient point
Full fine-stone concrete, surface carry out hair pulling treatment;After the completion of pouring, shape under the concrete fulcrum and drain bar collective effect that are formed in salient point
At underdrain and guarantee the compression strength of terrace, while reducing destruction when pouring terrace to underdrain, is convenient for finished product protection;
(5) it two side sealing of drain bar: is laid with the gap of microlith concrete plug two sides, drain bar two sides respectively in drain bar underdrain two sides
Fine-stone concrete heap it is sloping and drain bar side is blocked it is closely knit, it is same with the concrete fulcrum that pours salient point in order to simplify working procedure
When construct;
(6) terrace is poured and is conserved: floor construction is carried out afterwards for 24 hours after the completion of construction, to thin on drain bar before floor construction
Stone concrete carries out watering or covering curing;It is many to the curing time of the fine-stone concrete on drain bar if not pouring terrace in time
In 7 days.
2. a kind of basement post-pouring zone underdrain method for constructing terrace according to claim 1, it is characterised in that: the step
(4) in, pour fine-stone concrete with a thickness of 10mm.
3. a kind of basement post-pouring zone underdrain method for constructing terrace according to claim 1, it is characterised in that: the step
(1) in, thickness >=0.7mm of drain bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910069156.8A CN109750691A (en) | 2019-01-24 | 2019-01-24 | A kind of basement post-pouring zone underdrain method for constructing terrace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910069156.8A CN109750691A (en) | 2019-01-24 | 2019-01-24 | A kind of basement post-pouring zone underdrain method for constructing terrace |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109750691A true CN109750691A (en) | 2019-05-14 |
Family
ID=66404831
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910069156.8A Pending CN109750691A (en) | 2019-01-24 | 2019-01-24 | A kind of basement post-pouring zone underdrain method for constructing terrace |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109750691A (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059946A (en) * | 2017-06-20 | 2017-08-18 | 中国华西企业有限公司 | A kind of basement drain plate and its construction |
CN108360573A (en) * | 2018-01-19 | 2018-08-03 | 浙江大华建设集团有限公司 | Anti- basement bottom plate rear pouring tape leak device and its construction method |
-
2019
- 2019-01-24 CN CN201910069156.8A patent/CN109750691A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059946A (en) * | 2017-06-20 | 2017-08-18 | 中国华西企业有限公司 | A kind of basement drain plate and its construction |
CN108360573A (en) * | 2018-01-19 | 2018-08-03 | 浙江大华建设集团有限公司 | Anti- basement bottom plate rear pouring tape leak device and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105201025B (en) | Basement waterproofing construction and its construction method | |
CN104264717A (en) | Basement rigid material and flexible material combined waterproof construction method | |
CN205077752U (en) | Roofing flashing waterproofing membrane of department brick wall protection architecture | |
CN104988955B (en) | The anti-row's convolution waterproof system of ultra-deep basement and construction method | |
CN104153400B (en) | A kind of construction method of soft foundation pouring pile head waterproof | |
CN102776897B (en) | Wash apron anti-settling anti-cracking construction method and structure | |
CN101949207A (en) | Method for constructing subsided rest room | |
CN109184253A (en) | A kind of method for repairing and mending of exterior wall leakage | |
CN104234089B (en) | The construction method that a kind of basement guarded drainage combines | |
CN104514284A (en) | Waterproofing work technical process by spay-painting method | |
CN106555371B (en) | Garden large area pervious concrete road construction technique | |
CN205369737U (en) | Roof rainwater drainage breaking of contact structure | |
CN208762866U (en) | A kind of bridge greenbelt drainage structure | |
CN209194466U (en) | A kind of Reservoir Bank leakage preventing structure | |
CN109750691A (en) | A kind of basement post-pouring zone underdrain method for constructing terrace | |
CN207739293U (en) | A kind of basement roof waterproof construction | |
CN109881794A (en) | A kind of swimming pool waterproof construction | |
CN205046589U (en) | Waterproof structure of basement | |
CN205653877U (en) | Drainage device between building of adjacent underground | |
CN108571068A (en) | The insertion of steel fabric sheet cross section carries out high-strength concrete pouring construction engineering method | |
CN107989287A (en) | Inverted roof light and shade drainage system construction method | |
CN209907844U (en) | Bathroom falls board area and does wet subregion stagnant water steel sheet device futilely | |
CN208668644U (en) | A kind of outer wall impermeable leakage architecture | |
CN104775454A (en) | Construction method of underground engineering cement-based permeable crystallization type waterproof material | |
CN113006388A (en) | Inverted overhead facing brick roof concealed-buried exhaust pipeline invisible structure and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190514 |
|
RJ01 | Rejection of invention patent application after publication |