CN108360573A - Anti- basement bottom plate rear pouring tape leak device and its construction method - Google Patents

Anti- basement bottom plate rear pouring tape leak device and its construction method Download PDF

Info

Publication number
CN108360573A
CN108360573A CN201810054871.XA CN201810054871A CN108360573A CN 108360573 A CN108360573 A CN 108360573A CN 201810054871 A CN201810054871 A CN 201810054871A CN 108360573 A CN108360573 A CN 108360573A
Authority
CN
China
Prior art keywords
pressure release
aqueduct
layer
steel sleeve
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810054871.XA
Other languages
Chinese (zh)
Other versions
CN108360573B (en
Inventor
徐钢
马春雷
庄小平
叶黛
鲁寅
王翔
高峰
吴志余
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG DAHUA CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG DAHUA CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG DAHUA CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG DAHUA CONSTRUCTION GROUP CO Ltd
Priority to CN201810054871.XA priority Critical patent/CN108360573B/en
Publication of CN108360573A publication Critical patent/CN108360573A/en
Application granted granted Critical
Publication of CN108360573B publication Critical patent/CN108360573B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention discloses anti-basement bottom plate rear pouring tape leak device and its construction methods.Described device includes the stone layer and drain bar being laid on from bottom to up on basement bottom board, irrigating gate is provided on drain bar, pressure release steel bushing bottom of the tube is installed in irrigating gate, aqueduct is equipped in pressure release steel sleeve, diversion bottom of the tube is installed in stone layer, and drain bar upper surface is equipped with pea gravel concreten layer, and pea gravel concreten layer is equipped with base concrete layer and post-cast strip concrete layer, pea gravel concreten is filled between aqueduct and pressure release steel sleeve, aqueduct upper port is equipped with end cap.The configuration of the present invention is simple, construction are flexible, securely and reliably, effectively reduce the probability that basement bottom board percolating water happens, and substantially reduce the probability and workload of later stage closure and repair, it is suitable for popularization and application, especially suitable for Industrial and Civil Engineering basement bottom plate rear pouring tape, for the higher engineering of level of ground water, economic benefit is especially pronounced.

Description

Anti- basement bottom plate rear pouring tape leak device and its construction method
Technical field
The invention belongs to technical field of building construction, and in particular to a kind of anti-basement bottom plate rear pouring tape leak device and its Construction method.
Background technology
As urban underground space construction scope is constantly to big and Shenzhen Development Bank, in order to ensure the globality and basement of structure The impermeability of structure, the form of generally use post-cast strip, the provisional deformation joint as indwelling in monolithic reinforced concrete structure. After reaching sealing condition, then with slightly expanded concrete post-cast strip is closed, structure is made to form continuous entirety.In basement bottom board In the closed construction in post-cast strip, the impervious key technical problem as bottom plate rear pouring tape closure construction of anti-floating, while also with the later stage Leak stopping is closely related with the problems such as repair.
The traditional way of basement bottom plate rear pouring tape is that post-cast strip one-piece casting or segmentation pour, such construction party Method, can because under bottom plate hydraulic pressure it is excessive can not pressure release, and post-cast strip concrete is caused to not fully achieved setting strength and bear too early Water pressure has buried hidden danger for post-cast strip leakage problem, this undoubtedly adds a series of cumbersome works such as later stage leak stopping and repair Make.Such conventional method causes the later stage to block and is expended with repair because failing to solve the problems, such as the hydraulic pressure under basement bottom board early period A large amount of manpower and materials, and on environment and owner using all causing inevitable influence.
Invention content
For the above-mentioned problems in the prior art, the purpose of the present invention is to provide poured after a kind of anti-basement bottom board Band leak device and its construction method.
The anti-basement bottom plate rear pouring tape leak device, including the stone that is laid on from bottom to up on basement bottom board Layer and drain bar, it is characterised in that irrigating gate is provided on drain bar, pressure release steel bushing bottom of the tube is installed close with it in irrigating gate Cooperation, pressure release steel sleeve is interior to be equipped with aqueduct, and diversion bottom of the tube is installed in stone layer, and drain bar upper surface is equipped with microlith coagulation Soil layer, pea gravel concreten layer are equipped with base concrete layer and post-cast strip concrete layer, are filled out between aqueduct and pressure release steel sleeve Filled with pea gravel concreten, aqueduct upper port is equipped with end cap.
The anti-basement bottom plate rear pouring tape leak device, it is characterised in that the thickness of stone layer is 35mm-50mm, stone Seed diameter is 10-25mm.
The anti-basement bottom plate rear pouring tape leak device, it is characterised in that covering pours 10mm in the aperture of drain bar Thick pea gravel concreten.
The anti-basement bottom plate rear pouring tape leak device, it is characterised in that the bottom equalization of pressure release steel sleeve opens up six A notch, and setting steel wire is bound in pressure release steel bushing bottom of the tube by notch.
The anti-basement bottom plate rear pouring tape leak device, it is characterised in that drain bar uses FSH25 cross drain bars, Height 25mm, unit mass 1050g/m2, elongation at break >=25%.
The anti-basement bottom plate rear pouring tape leak device, it is characterised in that aqueduct uses DN40 galvanized pipes, diversion Manage stretching post-cast strip suitable for reading concrete layer upper surface 45-55mm;Setting is respectively welded in diversion pipe outer wall and pressure release steel bushing inside pipe wall There is sealing piece;The welding of pressure release steel bushing pipe outer wall is provided with steel plate for sealing water.
The anti-basement bottom plate rear pouring tape leak device, it is characterised in that sealing piece and steel plate for sealing water welding position are equal Between surfacing steel bar and bottom layer of the reinforcing steel in post-cast strip.
The anti-basement bottom plate rear pouring tape leaks construction method, it is characterised in that be laid with including stone and drain bar, The positioning of pressure release steel sleeve, the binding of microlith concrete placings, sole plate reinforcing bar, sole plate concreting, post-cast strip concrete pour It builds, aqueduct is embedded and gap closing, aqueduct closure and floor construction.
The anti-basement bottom plate rear pouring tape leaks construction method, it is characterised in that is as follows:
1)Before stone and drain bar are laid with drain bar laying, it is first laid with stone on basement bottom board as filter layer, ensures water It circulates in drain bar lower part, hole is cut in the middle part of drain bar, as the irrigating gate of pressure release steel sleeve, covered in the aperture of drain bar Pour 10mm pea gravel concretens;
2)The bottom of pressure release steel sleeve positioning pressure release steel sleeve is first impartial to be opened up six notches and binds upper steel wire, then will be let out Compressed steel sleeve bottom stretches into the irrigating gate of drain bar, and pressure release steel sleeve is located under draining plate face;
3)Fine-stone concrete, which is cast on drain bar, pours pea gravel concreten, and the intensity of the pea gravel concreten is higher than basement bottom board coagulation One grade of native intensity;
4)It includes surfacing steel bar and bottom layer of the reinforcing steel that sole plate reinforcing bar, which binds sole plate reinforcing bar, first binds bottom layer of the reinforcing steel, simultaneously Rectangular steel reinforcement cage is bound on the outside of pressure release steel sleeve, then binds surfacing steel bar, then is banded with square bar on the outside of pressure release steel sleeve Muscle cage;
5)Sole plate concreting
6)It is suitable for reading with adhesive plaster temporary enclosed pressure release steel sleeve before the concreting post-cast strip concreting of post-cast strip, then into Row concreting, post-cast strip side carry out dabbing and clear up reinforcing bar, and post-cast strip concrete is used than sole plate concrete rank The microdilatancy pea gravel concreten of a high grade in casting process, under vibrating head oblique cutting to steel plate for sealing water, and carries out two before initial set It is secondary to shake again;
7)The embedded and gap closing of aqueduct will be higher by the pressure release steel bushing of sole plate concrete(1)It is cut to neat with bottom plate Aqueduct is buried after flat, diversion bottom of the tube extends to stone layer bottom, the gap microdilatancy between aqueduct and pressure release steel bushing Pea gravel concreten is filled and closely knit;
8)Aqueduct blocks and floor construction is after post-cast strip concrete reaches intensity, is sealed aqueduct using screw pipe cap It is stifled, then carry out floor construction.
By using above-mentioned technology, compared with prior art, beneficial effects of the present invention are as follows:The present invention is in industry Under basement bottom board because caused by hydraulic pressure is excessive the multiple sex chromosome mosaicism such as basement floating-up, large area percolating water, by using elder generation Pre-buried relief tube, re-closed post-cast strip block relief tube after after post-cast strip, concrete reaches intensity, and this method, which has reached, lets out The effect of water decompression, can effectively reduce the floating of basement bottom plate rear pouring tape, the probability of percolating water, hence it is evident that improve basement bottom The quality of board concrete and terrace, to solve the construction difficult problem of basement bottom plate rear pouring tape percolating water, after substantially reducing Phase blocks the probability and workload with repair, and this method is easy to operate, and construction is flexible, securely and reliably, the base in original post-cast strip Suitably increase process on plinth, effectively reduces the probability that basement bottom board percolating water happens, and substantially reduce the later stage The probability and workload with repair are blocked, is suitable for popularization and application, especially suitable for Industrial and Civil Engineering basement bottom board Post-cast strip, for the higher engineering of level of ground water, economic benefit is especially pronounced.
Description of the drawings
Fig. 1 is the device of the invention structural schematic diagram.
In figure:1- pressure release steel sleeves, 2- sealing pieces, 3- steel plate for sealing water, 4- pea gravel concreten layers, 5- drain bars, 501- draw The mouth of a river, 6- stone layers, 7- notches, 8- aqueducts, the post-cast strips 9- concrete layer, 901- surfacing steel bars, 902- bottom layer of the reinforcing steel, 10- Pea gravel concreten.
Specific implementation mode
Below in conjunction with Figure of description, the invention will be further described, but protection scope of the present invention is not limited in This:
As shown in Figure 1, the anti-basement bottom plate rear pouring tape leak device of the present invention, including it is laid on basement bottom board from bottom to up On stone layer 6 and drain bar 5, the thickness of stone layer 6 be 35mm-50mm, cobble-stone diameter 10-25mm is provided on drain bar 5 Irrigating gate 501, the interior covering of aperture of drain bar 5 pour the pea gravel concreten of 10mm thickness, and 1 bottom of pressure release steel sleeve is installed into diversion It is fitted close with it in mouth 501, aqueduct 8 is equipped in pressure release steel sleeve 1,8 bottom of aqueduct is installed in stone layer 6, is drained 5 upper surface of plate is equipped with pea gravel concreten layer 4, and pea gravel concreten layer 4 is equipped with base concrete layer and post-cast strip concrete layer 9, Pea gravel concreten 10 is filled between aqueduct 8 and pressure release steel sleeve 1,8 upper port of aqueduct is equipped with end cap.
The bottom equalization of the pressure release steel sleeve 1 of the present invention opens up six notches 7, and by notch 7 at 1 bottom of pressure release steel sleeve Portion's binding setting steel wire, avoids the stone of stone layer 6 from entering in pressure release steel sleeve 1.
The drain bar 5 of the present invention uses FSH25 cross drain bars, height 25mm, unit mass 1050g/m2, extension at break Rate >=25%;Aqueduct 8 uses DN40 galvanized pipes, 8 stretching post-cast strip suitable for reading concrete layer of aqueduct, 9 upper surface 45-55mm;Draw 8 outer wall of water pipe and 1 inner wall of pressure release steel sleeve are respectively welded and are provided with sealing piece 2;The welding of 1 outer wall of pressure release steel sleeve is provided with sealing Steel plate 3;Sealing piece 2 and 3 welding position of steel plate for sealing water are between the surfacing steel bar 901 of post-cast strip and bottom layer of the reinforcing steel 902.
As shown in Figure 1, the service sleeve pilot method of the present invention, which solves basement bottom plate rear pouring tape, leaks construction method, including Stone and drain bar laying, the positioning of pressure release steel sleeve, microlith concrete placings, sole plate reinforcing bar are bound, sole plate concrete pours Build, post-cast strip concreting, aqueduct are embedded and gap closing, aqueduct blocks and floor construction, be as follows:
1)Before stone and drain bar are laid with the laying of drain bar 5, stone is first laid on basement bottom board as filter layer, stone Grain size 10mm-25mm, thickness 35mm-50mm are advisable, and must not contain silt in stone, ensure that water circulates in 5 lower part of drain bar, 5 middle part of drain bar cuts hole, is covered as the irrigating gate 501 of pressure release steel sleeve, in the aperture of drain bar 5 and pours 10mm microliths Concrete in 5 process of deployment of drain bar, must not have soil, yellow ground etc. to enter 5 lower section of drain bar, it is ensured that the space of drain bar 5 is smooth It is logical;
2)Pressure release steel sleeve positions 1 outer wall of pressure release steel sleeve and is equipped with steel plate for sealing water 3, and the bottom of pressure release steel sleeve 1 is first impartial to open If six notches 7 simultaneously bind upper steel wire, then 1 bottom of pressure release steel sleeve is stretched into the irrigating gate 501 of drain bar 5, and pressure release Steel sleeve 1 is located under 5 face of drain bar, avoids the blocking that pressure release steel sleeve 1 is caused when later stage casting and compacting of concrete, to ensure pressure release steel It is unimpeded to cover in-pipe flow, pressure release steel sleeve 1 is one reserved every 15m or so at post-cast strip, and range deviation controls within 1m, 3 height difference tolerance of steel plate for sealing water on pressure release steel sleeve 1 is less than 10mm, and when the present invention is implemented, the positioning of pressure release steel sleeve 1 is adopted It is welded and is positioned with spacer bar, it should be ensured that 1 time mouth of pressure release steel sleeve stretches into drain bar 5 to being laid at stone, and pressure release steel sleeve 1 is worn It is blocked using pea gravel concreten at the hole of drain bar 5, spillage when avoiding concreting, outside sealing piece welding position is in Between pressure release steel sleeve and the middle and lower part of sole plate, inside sealing piece welding position is in pressure release steel sleeve and sole plate Between middle part, welding form is full weld, answers timely scarfing cinder in welding process, and face of weld is answered smooth, and welding pit should fill up, and ensure It is completely enclosed between zinc-plated aqueduct and sealing piece;
3)Fine-stone concrete is cast on drain bar 5 and pours pea gravel concreten, and the intensity of the pea gravel concreten is mixed higher than basement bottom board Solidifying soil one grade of intensity;
4)It includes surfacing steel bar 901 and bottom layer of the reinforcing steel 902 that sole plate reinforcing bar, which binds sole plate reinforcing bar, first binds bottom layer of the reinforcing steel 902, while rectangular steel reinforcement cage is bound in 1 outside of pressure release steel sleeve, then surfacing steel bar 901 is bound, then in 1 outside of pressure release steel sleeve It is banded with rectangular steel reinforcement cage, steel plate for sealing water 3 is between bottom layer of the reinforcing steel 902 and surfacing steel bar 901;
5)Sole plate concreting
6)It is suitable for reading with adhesive plaster temporary enclosed pressure release steel sleeve 1 before the concreting post-cast strip concreting of post-cast strip, then into Row concreting, post-cast strip side carry out dabbing and clear up reinforcing bar, and post-cast strip concrete is used than sole plate concrete rank The microdilatancy pea gravel concreten of a high grade, is checked oneself before the concreting of post-cast strip inside teams and groups, and then supervising engineer checks and accepts Qualification can pour;In casting process, under vibrating head oblique cutting to steel plate for sealing water 3, the duration of vibrating should be such that concrete surface produces Capture is starched, bubble-free, and until not sinking, the distance of shift position should be not more than 400mm, ensure not leakage, not cross to shake, and first Progress is secondary before solidifying shakes again;
7)The pressure release steel bushing 1 for being higher by sole plate concrete is cut to by the embedded and gap closing of aqueduct to be flushed with bottom plate Afterwards bury aqueduct 8, diversion pipe outer wall be equipped with sealing piece 2, sealing piece 2 between bottom layer of the reinforcing steel 902 and surfacing steel bar 901, 8 bottom of aqueduct extends to 6 bottom of stone layer, 8 stretching post-cast strip concrete surface 50mm suitable for reading of aqueduct or so, aqueduct 8 with let out Gap between compressed steel sleeve 1 is filled and closely knit with microdilatancy pea gravel concreten;
8)Aqueduct blocks and floor construction is after post-cast strip concrete reaches intensity, is carried out aqueduct 8 using screw pipe cap It blocks, then carries out floor construction.
The present invention obtains following advantageous effect by using above-mentioned technology:
1. social benefit
1)Basement bottom plate rear pouring tape leakage construction method construction is solved using service sleeve pilot method, efficiently solves basement The key technical problem of base plate leakage water, it is disposable to solve post-cast strip percolating water problem, largely reduce later stage terrace The difficulty of construction, while guaranteeing role is played to the construction quality of terrace;
2)The basement space that percolating water probability substantially reduces so that the underground space function of owner is not affected, and effectively reduces Owner is to the complaint probability of Water Seepage in Basement, to generate extensive social benefit;
3)Basement bottom plate rear pouring tape leakage construction method construction basement bottom plate rear pouring tape is solved using service sleeve pilot method Closing reaches:Good, the high-quality resultant effect of low cost, perception.
2. economic benefit
For integral construction and later period maintenance, the present invention is even compensated because reducing many grouting for water plugging and later period maintenance Expense, more traditional post-cast strip closure construction has greater advantage from cost.This engineering method post empiricism is in original traditional cost About 29.9 yuan/m of upper increase, needed cost summary sheet refers to the following table 1 at a pressure release diversion, and common post-cast strip maintenance cost is about 207 yuan/m, by taking 90 linear meter post-cast strips as an example, conventional construction method post-cast strip percolating water ratio is about 39%(Investigation knot in industry Fruit), specific cost is relatively shown in Table 2.
Needed cost summary sheet at the pressure release diversion of the invention of table 1
The cost of 2 two kinds of construction methods of table compares
To sum up compare, this engineering method can saving construction cost about 63%(Large-area backplane leak, terrace cracking expense are not counted).
3. environmental benefit
Service sleeve pilot method solves basement bottom plate rear pouring tape and leaks construction method, and large scale saves later stage leak stopping on material And the material of repair, and leak stopping and service material can largely generate environment different degrees of pollution, avoid tieing up because of percolating water Repair and caused by basement space secondary pollution.Therefore this engineering method is also significant to environmental protection.
Application Example 1
A engineerings went into operation in 2 months 2014, were located at Yuhang District, overall floorage 127366.17m2, frame-shear-wall structure, engineering For basement one, ground 18-24 layers of residential building, basement bottom plate rear pouring tape about 2645m.Basement bottom plate rear pouring tape closing application " service sleeve pilot method solves basement bottom plate rear pouring tape and leaks construction method ", when basement floor construction is completed 6 months, Basement bottom board is without apparent percolating water phenomenon.
Application Example 2
B engineerings go into operation in September, 2015, are located at Yuhang District, overall floorage 78580.39m2, and basement construction area is 41018.12 m2, frame-shear-wall structure, engineering F3/B3, ground 1-12 layers, basement bottom plate rear pouring tape length is about 752m.Basement bottom plate rear pouring tape closing applies " service sleeve pilot method solution basement bottom plate rear pouring tape leakage construction party Method ", when basement floor construction is completed 6 months, basement bottom board is without apparent percolating water phenomenon.

Claims (9)

1. anti-basement bottom plate rear pouring tape leak device, including the stone layer that is laid on from bottom to up on basement bottom board(6)With Drain bar(5), it is characterised in that drain bar(5)On be provided with irrigating gate(501), pressure release steel sleeve(1)It installs into irrigating gate bottom (501)In be fitted close with it, pressure release steel sleeve(1)It is interior to be equipped with aqueduct(8), aqueduct(8)It installs into stone layer bottom(6) In, drain bar(5)Upper surface is equipped with pea gravel concreten layer(4), pea gravel concreten layer(4)Base concrete layer is equipped with to pour with after Band concrete layer(9), aqueduct(8)With pressure release steel sleeve(1)Between be filled with pea gravel concreten(10), aqueduct(8)Upper end Mouth is equipped with end cap.
2. anti-basement bottom plate rear pouring tape leak device according to claim 1, it is characterised in that stone layer(6)Thickness For 35mm-50mm, cobble-stone diameter 10-25mm.
3. anti-basement bottom plate rear pouring tape leak device according to claim 1, it is characterised in that drain bar(5)Aperture It is interior to cover the pea gravel concreten for pouring 10mm thickness.
4. anti-basement bottom plate rear pouring tape leak device according to claim 1, it is characterised in that pressure release steel sleeve(1)'s Bottom equalization opens up six notches(7), and pass through notch(7)In pressure release steel sleeve(1)Bottom binding setting steel wire.
5. anti-basement bottom plate rear pouring tape leak device according to claim 1, it is characterised in that drain bar(5)Using FSH25 cross drain bars, height 25mm, unit mass 1050g/m2, elongation at break >=25%.
6. anti-basement bottom plate rear pouring tape leak device according to claim 1, it is characterised in that aqueduct(8)Using DN40 galvanized pipes, aqueduct(8)Stretching post-cast strip suitable for reading concrete layer(9)Upper surface 45-55mm;Aqueduct(8)It outer wall and lets out Compressed steel casing(1)Inner wall, which is respectively welded, is provided with sealing piece(2);Pressure release steel sleeve(1)Outer wall welding is provided with steel plate for sealing water (3).
7. anti-basement bottom plate rear pouring tape leak device according to claim 1, it is characterised in that sealing piece(2)And sealing Steel plate(3)Welding position is in the surfacing steel bar of post-cast strip(901)With bottom layer of the reinforcing steel(902)Between.
8. a kind of anti-basement bottom plate rear pouring tape based on claim 1 described device leaks construction method, it is characterised in that packet Include stone and drain bar laying, the positioning of pressure release steel sleeve, the binding of microlith concrete placings, sole plate reinforcing bar, sole plate concrete It pours, post-cast strip concreting, aqueduct is embedded and gap is closed, aqueduct blocks and floor construction.
9. anti-basement bottom plate rear pouring tape according to claim 8 leaks construction method, it is characterised in that specific steps are such as Under:
1)Stone and drain bar are laid with drain bar(5)Before laying, it is first laid with stone on basement bottom board as filter layer, protects Water is demonstrate,proved in drain bar(5)Lower part is circulated, drain bar(5)Middle part cuts hole, the irrigating gate as pressure release steel sleeve(501), row Water plate(5)Aperture in covering pour 10mm pea gravel concretens;
2)Pressure release steel sleeve positions pressure release steel sleeve(1)Bottom it is first impartial open up six notches(7)And bind upper steel wire Net, then by pressure release steel sleeve(1)Drain bar is stretched into bottom(5)Irrigating gate(501)In, and pressure release steel sleeve(1)Positioned at draining Plate(5)Under face;
3)Fine-stone concrete is cast in drain bar(5)On pour pea gravel concreten, the intensity of the pea gravel concreten is higher than basement bottom board One grade of concrete strength;
4)It includes surfacing steel bar that sole plate reinforcing bar, which binds sole plate reinforcing bar,(901)With bottom layer of the reinforcing steel(902), first bind bottom Layer reinforcing bar(902), while in pressure release steel sleeve(1)Outside binds rectangular steel reinforcement cage, then binds surfacing steel bar(901), then letting out Compressed steel casing(1)Outside is banded with rectangular steel reinforcement cage;
5)Sole plate concreting
6)Before the concreting post-cast strip concreting of post-cast strip, with adhesive plaster temporary enclosed pressure release steel sleeve(1)It is suitable for reading, Concreting is carried out again, and post-cast strip side carries out dabbing and clears up reinforcing bar, and post-cast strip concrete is used than sole plate concrete The microdilatancy pea gravel concreten of the high grade of rank in casting process, under vibrating head oblique cutting to steel plate for sealing water, and advances in initial set Row is secondary to shake again;
7)The embedded and gap closing of aqueduct will be higher by the pressure release steel bushing of sole plate concrete(1)It is cut to and bottom plate Aqueduct is buried after flushing(8), aqueduct(8)Bottom extends to stone layer(6)Bottom, aqueduct(8)With pressure release steel bushing(1)It Between gap be filled with microdilatancy pea gravel concreten and closely knit;
8)Aqueduct blocks and floor construction is after post-cast strip concrete reaches intensity, using screw pipe cap by aqueduct(8)Into Row blocks, then carries out floor construction.
CN201810054871.XA 2018-01-19 2018-01-19 Device for preventing post-cast strip of basement floor from leaking and construction method thereof Active CN108360573B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810054871.XA CN108360573B (en) 2018-01-19 2018-01-19 Device for preventing post-cast strip of basement floor from leaking and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810054871.XA CN108360573B (en) 2018-01-19 2018-01-19 Device for preventing post-cast strip of basement floor from leaking and construction method thereof

Publications (2)

Publication Number Publication Date
CN108360573A true CN108360573A (en) 2018-08-03
CN108360573B CN108360573B (en) 2020-07-07

Family

ID=63006415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810054871.XA Active CN108360573B (en) 2018-01-19 2018-01-19 Device for preventing post-cast strip of basement floor from leaking and construction method thereof

Country Status (1)

Country Link
CN (1) CN108360573B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750691A (en) * 2019-01-24 2019-05-14 中建八局第三建设有限公司 A kind of basement post-pouring zone underdrain method for constructing terrace
CN111764397A (en) * 2020-05-28 2020-10-13 浙江土工岩土科技有限公司 Underground diaphragm wall plugging device and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050080022A (en) * 2005-07-04 2005-08-11 (주)도화구조 기술사무소 Plumbing for draining underground water and controlled de-watering system with target water level using the plumbing
CN201212156Y (en) * 2008-06-17 2009-03-25 朱邃科 Interception and drainage system of basement engineering
CN101748753A (en) * 2008-12-06 2010-06-23 广西建工集团第五建筑工程有限责任公司 Plugging construction method of reserved opening of basement soleplate and tower crane foundation and post-pouring zone reserved opening
CN204343342U (en) * 2014-12-10 2015-05-20 奥意建筑工程设计有限公司 A kind of basement floor constructions with spilled water hole

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050080022A (en) * 2005-07-04 2005-08-11 (주)도화구조 기술사무소 Plumbing for draining underground water and controlled de-watering system with target water level using the plumbing
CN201212156Y (en) * 2008-06-17 2009-03-25 朱邃科 Interception and drainage system of basement engineering
CN101748753A (en) * 2008-12-06 2010-06-23 广西建工集团第五建筑工程有限责任公司 Plugging construction method of reserved opening of basement soleplate and tower crane foundation and post-pouring zone reserved opening
CN204343342U (en) * 2014-12-10 2015-05-20 奥意建筑工程设计有限公司 A kind of basement floor constructions with spilled water hole

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109750691A (en) * 2019-01-24 2019-05-14 中建八局第三建设有限公司 A kind of basement post-pouring zone underdrain method for constructing terrace
CN111764397A (en) * 2020-05-28 2020-10-13 浙江土工岩土科技有限公司 Underground diaphragm wall plugging device and method

Also Published As

Publication number Publication date
CN108360573B (en) 2020-07-07

Similar Documents

Publication Publication Date Title
CN204000956U (en) A kind of basement bottom plate rear pouring tape structure
CN207193996U (en) A kind of precipitation pipe well well-sealing device
CN206706792U (en) Deep foundation pit precipitation well construction
CN206706791U (en) Base pit dewatering well plugging structure
CN103572808A (en) Building toilet caisson waterproof device and construction method
CN112459116A (en) Construction method for rebuilding basement bottom plate of existing building
CN110761307B (en) Earth-rock cofferdam water seepage treatment structure and construction method
CN108360573A (en) Anti- basement bottom plate rear pouring tape leak device and its construction method
CN108166532A (en) A kind of groutable underground continuous wall connector and its construction method
CN105756100B (en) Basement post-pouring zone system and preparation method thereof
CN104652495A (en) Waterproof construction process for joint of inner support upright post of foundation pit and bottom plate
CN105178342B (en) Precipitation well casing and method for blocking reserved hole of foundation pit through precipitation well casing
CN109138116A (en) Concrete expires packet drainage pipeline tubine construction method
CN111636483A (en) Waterproof device for reverse construction concrete structure gap and construction method
CN108149701A (en) It is a kind of for the shut-in well end pipe of plugging dewatering well and plugging dewatering well method
CN105970882B (en) Solve the structure and its building method of face dam construction time dam body reverse osmosis water problems
CN209040133U (en) Well-covering device for dewatering well suitable for rich groundwater region
CN206829163U (en) A kind of high artesian section construction Yield rainfall relation device
CN110359495A (en) Comprehensive pipe gallery structure seam construction and its construction method
CN207003440U (en) A kind of foundation ditch spring water treatment system
CN210621879U (en) Steel construction vestibule drainage structures system
CN112227395A (en) Well sealing device and method for large-water-pressure-drop well in building raft
CN111719504A (en) Ecological landscape ditch and construction process thereof
CN115233718B (en) Anti-seepage plugging structure of foundation pit dewatering well and plugging method of foundation pit dewatering well
CN218970182U (en) Combined lining repairing structure for seepage of well and pool

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant