CN109594448A - The temporary road construction method of linear engineering - Google Patents

The temporary road construction method of linear engineering Download PDF

Info

Publication number
CN109594448A
CN109594448A CN201811448658.3A CN201811448658A CN109594448A CN 109594448 A CN109594448 A CN 109594448A CN 201811448658 A CN201811448658 A CN 201811448658A CN 109594448 A CN109594448 A CN 109594448A
Authority
CN
China
Prior art keywords
road
temporary
temporary road
construction
linear engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811448658.3A
Other languages
Chinese (zh)
Inventor
张春新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Original Assignee
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd, North China Metallurgical Construction Engineering Construction Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201811448658.3A priority Critical patent/CN109594448A/en
Publication of CN109594448A publication Critical patent/CN109594448A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • E01C9/08Temporary pavings
    • E01C9/086Temporary pavings made of concrete, wood, bitumen, rubber or synthetic material or a combination thereof
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/48Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention provides a kind of temporary road construction method of linear engineering, include the following steps: to release the construction sideline of temporary road further according to center line of road, temporary road is one-way road according to releasing temporary road middle line is required;Make the construction sideline in multiple road widening areas far from the side of linear engineering in temporary road along temporary road length direction;The roadbed of the temporary road made and road widening area is bulldozed steel slag on simultaneously grinding compacting, then place Min layers, and is layered carry out grinding compacting;The installation template at the construction sideline in temporary road and road widening area, and the casting concrete in template, are carried out continuously later and pave, vibrate, flattening, plastering, so that concrete road surface surfacing;Timely road pavement cover simultaneously sprinkling maintenance after concrete pavement construction.The present invention reduces temporary road width, only in local setting road widening area, can both save material, save cost, reduce waste, and can reduce later period temporary road and abolish influence to environment.

Description

The temporary road construction method of linear engineering
Technical field
The present invention relates to Construction Technology fields, more specifically, are related to a kind of temporary road construction of linear engineering Method.
Background technique
For convenience of constructing in construction process, material is to carry out handling using truck crane, and automotive pump is used when concrete It is pumped, when truck crane, automotive pump operation is both needed to road occupying operation, it is therefore necessary to build the temporary road system to make rational planning for System just can guarantee that material supply and engineering are gone on smoothly.When at present for constructing in linear process such as underground pipe gallery, Conveying the general practice in order to facilitate material is completely to build the temporary road that main road width is 6m or more (two-way traffic), which accounts for Ground area is big, investment is more, and has greater environmental impacts.
Summary of the invention
In view of the above problems, the object of the present invention is to provide a kind of temporary road construction methods of linear engineering, to solve Traditional method takes up a large area, puts into more problems.
To achieve the goals above, the present invention is realized by technical solution below:
A kind of temporary road construction method of linear engineering, includes the following steps:
S1: according to releasing temporary road middle line is required, the construction sideline of the temporary road is released further according to center line of road, The temporary road is one-way road;
S2: multiple roads are made far from the side of linear engineering in the temporary road along the temporary road length direction Widen the construction sideline in area;
S3: the roadbed of the temporary road made and the road widening area is bulldozed simultaneously grinding compacting, then place Min layers Upper steel slag, and it is layered carry out grinding compacting;
S4: the installation template at the construction sideline in the temporary road and the road widening area, and poured in template Concrete is carried out continuously later and paves, vibrates, flattening, plastering, so that concrete road surface surfacing;
S5: timely road pavement cover simultaneously sprinkling maintenance after concrete pavement construction.
Further, one road widening area is set every 50-80m on the temporary road.
Further, the width of the temporary road is 4-5m, the width of the temporary road and the road widening area The sum of be 7.5-8.5m.
Further, on the road surface hardened, road surface is sawn into small translot with the trench saw along width of roadway direction.
Further, the consistency of thickness of mounted form height and temporary road.
Further, the road widening area is trapezoidal, and the top margin length that trapeziform road widens area is 30m
Compared with prior art, the present invention at least has the advantages that the present invention reduces temporary road width, temporarily The local setting road widening area of road, the setting in road widening area can provide multiple function, such as vehicle meeting, truck crane, The functions such as automotive pump branch vehicle operation can both save material in this way, save cost, reduce waste, and can reduce later period temporary road The influence to environment is abolished, civilized construction is conducive to.
To the accomplishment of the foregoing and related purposes, one or more aspects of the present invention includes being particularly described below especially The feature pointed out.Certain illustrative aspects of the invention is described in detail in the following description and the annexed drawings.However, these aspects refer to What is shown is only that some of the various ways in the principles of the present invention can be used.In addition, the present invention is intended to include it is all this A little aspects and their equivalent.
Detailed description of the invention
It is of the invention by reference to the description below in conjunction with attached drawing, and with a more complete understanding of the present invention Other purposes and result will be more clearly understood and understood.In the accompanying drawings:
Fig. 1 is the temporary road structural schematic diagram of the embodiment of invention.
Identical label indicates similar or corresponding feature or function in all the appended drawings.
Specific embodiment
Hereinafter, specific embodiments of the present invention will be described in detail with reference to the accompanying drawings.
See Fig. 1, the present invention provides a kind of temporary road construction methods of linear engineering, in the present embodiment, linear work It is illustrated for the underground pipe gallery engineering in the city Cheng Yimou, which is always about 5.43km, comprehensive in the underground Temporary road is built in the foundation pit upper sideline side of piping lane engineering, includes the following steps:
S1: according to design drawing and requisition use total station the one of the foundation pit upper sideline 2 of underground pipe gallery in 1 range Side carries out setting-out to temporary road midline position, makes the construction side of temporary road 3 with steel ruler further according to temporary road middle line Line 30, temporary road 3 are one-way road, and width 4-5m, wherein the width of temporary road 3 is that 4.5m is best, is convenient for vapour in this way Vehicle and automobile pump operation;
S2: for guarantee vehicle two-way traffic, along 3 length direction of temporary road every 50-80m temporary road 3 remotely The construction sideline 40 in multiple trapezoidal road widening areas 4 is made in the side of lower pipe gallery engineering, and trapeziform road widens the top in area 4 Edge lengths are 30m, which can not only be used for can be automobile-used, also prop up automobile-used, temporary road 3 and road for crane, pump truck Widening the sum of the width in area 4 is 7.5-8.5m, wherein the sum of the width in temporary road 3 and road widening area 4 be 8m be most preferably, this Sample not only saves occupied area, but also does not influence meeting;
S3: first bull-dozer is used to flatten on the roadbed of the temporary road 3 and multiple road widening areas 4 made, then is pressed with 18t Road machine grinding compacting;It rolls with vibrated roller rolling layer 5-6 times, first pass static pressure, remaining is vibration pressure, wheelmark overlapping 30-40cm;It is layered making steel slag, then layered rolling later, is compacted, is rolled to surfacing with 12-15t road roller, it is close Until reality is without obvious wheelmark;
S4: the installation template at the construction sideline in temporary road 3 and road widening area 4, template use steel form, and template is answered Not damaged and have enough intensity, form height should be no more than ± 2mm with 3 consistency of thickness of temporary road, error;Again in template Casting concrete is carried out continuously later and paves, vibrates, flattening, plastering, so that concrete roadway surface is smooth, adopts wherein vibrating With internal vibration stick;On the road surface hardened, road surface is sawn into small translot with the trench saw along its width direction, with road pavement Carry out anti-skidding processing;
S5: timely road pavement cover simultaneously sprinkling maintenance, curing time 14d after construction.
The temporary road construction method of linear engineering according to the present invention is described in an illustrative manner above with reference to attached drawing.But It is, it will be appreciated by those skilled in the art that the temporary road construction method of the linear engineering proposed for aforementioned present invention, also Various improvement can be made on the basis of not departing from the content of present invention.Therefore, protection scope of the present invention should be by appended The content of claims determines.

Claims (6)

1. a kind of temporary road construction method of linear engineering, which comprises the steps of:
S1: according to releasing temporary road middle line is required, the construction sideline of the temporary road is released further according to center line of road, described Temporary road is one-way road;
S2: multiple road widenings are made far from the side of linear engineering in the temporary road along the temporary road length direction The construction sideline in area;
S3: the roadbed of the temporary road made and the road widening area is bulldozed steel on simultaneously grinding compacting, then place Min layers Slag, and it is layered carry out grinding compacting;
S4: the installation template at the construction sideline in the temporary road and the road widening area, and coagulation is poured in template Soil is carried out continuously later and paves, vibrates, flattening, plastering, so that concrete road surface surfacing;
S5: timely road pavement cover simultaneously sprinkling maintenance after concrete pavement construction.
2. the temporary road construction method of linear engineering as described in claim 1, which is characterized in that on the temporary road Every 50-80m, one road widening area is set.
3. the temporary road construction method of linear engineering as described in claim 1, which is characterized in that the width of the temporary road Degree is 4-5m, and the sum of the temporary road and the width in the road widening area are 7.5-8.5m.
4. the temporary road construction method of linear engineering as described in claim 1, which is characterized in that on the road surface hardened On, road surface is sawn into small translot with the trench saw along width of roadway direction.
5. the temporary road construction method of linear engineering as described in claim 1, which is characterized in that mounted form height With the consistency of thickness of temporary road.
6. the temporary road construction method of linear engineering as described in claim 1, which is characterized in that the road widening area is Trapezoidal, the top margin length that trapeziform road widens area is 30m.
CN201811448658.3A 2018-11-28 2018-11-28 The temporary road construction method of linear engineering Pending CN109594448A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811448658.3A CN109594448A (en) 2018-11-28 2018-11-28 The temporary road construction method of linear engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811448658.3A CN109594448A (en) 2018-11-28 2018-11-28 The temporary road construction method of linear engineering

Publications (1)

Publication Number Publication Date
CN109594448A true CN109594448A (en) 2019-04-09

Family

ID=65960516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811448658.3A Pending CN109594448A (en) 2018-11-28 2018-11-28 The temporary road construction method of linear engineering

Country Status (1)

Country Link
CN (1) CN109594448A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111877068A (en) * 2020-05-26 2020-11-03 中建八局天津建设工程有限公司 Arrangement and construction method of temporary road for assembly type construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1321320A (en) * 1970-12-28 1973-06-27 Minnesota Mining & Mfg Vehicle guidance system
CN102352589A (en) * 2011-07-21 2012-02-15 济南城建集团有限公司 Construction method for road base concrete side mold
CN204511451U (en) * 2015-02-13 2015-07-29 中铁第一勘察设计院集团有限公司 A kind of inclined shaft structure improving conevying efficiency
CN204676387U (en) * 2015-01-16 2015-09-30 大陆交通建设集团有限公司 A kind of cement concrete pavement becomes base layer structure
CN106320123A (en) * 2016-08-16 2017-01-11 桐城市永锦建筑工程有限公司 Construction method of soft soil roadbed
CN106758640A (en) * 2016-11-09 2017-05-31 中铁局集团天津建设工程有限公司 A kind of town road and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1321320A (en) * 1970-12-28 1973-06-27 Minnesota Mining & Mfg Vehicle guidance system
CN102352589A (en) * 2011-07-21 2012-02-15 济南城建集团有限公司 Construction method for road base concrete side mold
CN204676387U (en) * 2015-01-16 2015-09-30 大陆交通建设集团有限公司 A kind of cement concrete pavement becomes base layer structure
CN204511451U (en) * 2015-02-13 2015-07-29 中铁第一勘察设计院集团有限公司 A kind of inclined shaft structure improving conevying efficiency
CN106320123A (en) * 2016-08-16 2017-01-11 桐城市永锦建筑工程有限公司 Construction method of soft soil roadbed
CN106758640A (en) * 2016-11-09 2017-05-31 中铁局集团天津建设工程有限公司 A kind of town road and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111877068A (en) * 2020-05-26 2020-11-03 中建八局天津建设工程有限公司 Arrangement and construction method of temporary road for assembly type construction

Similar Documents

Publication Publication Date Title
CN104005313B (en) Asphalt concrete pavement dividing strip road kerb construction method
CN103866670B (en) Fabricated vehicle bearing pavement and construction method thereof
CN107542017A (en) A kind of assembled road construction method
CN100439600C (en) Treatment method of newly built high way railway engineering soft foundation
CN103321111B (en) Streetcar track connects the construction method of paving
CN104060631B (en) A kind of manhole mouth elevation Dynamic controlling structure
CN106592368A (en) Asphalt pavement paving no-cutting construction method
CN108130837A (en) A kind of prefabricated road plate and its construction method
CN107805989A (en) Temporary road rolling compacted concrete pavement reconstruction structure and its construction method
CN110438914A (en) Water tank culvert and its construction method are crossed on soft soil foundation
CN103343503B (en) Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method
CN108612049B (en) Construction method for shore protection engineering construction by adopting integral steel slip form structure
CN109594448A (en) The temporary road construction method of linear engineering
CN107142839A (en) A kind of attachment means of pile slab structure floorings and roadbed
CN203795460U (en) Basic structure of ballasting tower crane
CN105672172B (en) A kind of construction method of Dacroment steel highway barrier
CN209443368U (en) The overhead anti-ponding structure in bridge floor edge
CN104988839B (en) Subgrade and pavement pave edge no formwork erection construction paving help plant equipment
CN203429528U (en) Bridge-type precast-reinforced-concrete-trough-plate wear-resistant pavement structure system
CN203096758U (en) Hard concrete smooth foundation pit for installing drainage pipeline
CN203700899U (en) Steel tool-type temporary construction road
JP2018080484A (en) Gas station pavement structure and pavement structure construction method
CN207347861U (en) Prefabricated reinforced concrete roadbed
CN204570436U (en) Subgrade and pavement pave edge without formwork erection construction paving help plant equipment
CN204551166U (en) A kind of precast concrete block for down-hole repairing road

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190409

RJ01 Rejection of invention patent application after publication