CN100439600C - Treatment method of newly built high way railway engineering soft foundation - Google Patents
Treatment method of newly built high way railway engineering soft foundation Download PDFInfo
- Publication number
- CN100439600C CN100439600C CNB2006100485968A CN200610048596A CN100439600C CN 100439600 C CN100439600 C CN 100439600C CN B2006100485968 A CNB2006100485968 A CN B2006100485968A CN 200610048596 A CN200610048596 A CN 200610048596A CN 100439600 C CN100439600 C CN 100439600C
- Authority
- CN
- China
- Prior art keywords
- tamping
- soft foundation
- ram
- soft
- ramming
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
This invention relates to a new highway and railway projects soft ground process method. The method squeezes soft mud opening in the face of weak foundation through the following steps :a,equipments filling stone with the largest particle diameter of not more than 60cm; b,spreads 40-70cm thick layer stone in the soft ground surface-paved; c,adopts hammer ram, use hammer ram tamping force to tamping stone layer by point tamping or separate tamping and plus tamping, tamping out 2-3m tamping pit in selected tamping spots ; d,for every tamping pit ,follows filling -- tamping.,filling -- tamping until the tamping the settlement is in less than 2-7 after consecutive 2-3 tamping, and then stops tamping. This invention squeezes the soft and mud silting open in the soft surface of 2-6 meters, achieves the purpose of squeezing mud replacement, and finally forms hard shell replacement layer of 2-6 m thickness, enhances the bearing capacity of the ground, increases the stability of the ground.
Description
Technical field
The present invention relates to newly-built highway, railway engineering method for processing foundation, relate in particular to treatment of soft ground method in newly-built highway, the railway engineering.
Background technology
In the construction of highway, railway, require completion back settling amount little, for hard soil foundation, there are not much difficult problems in the surface evenness height, but for soft foundation, dealing with just has sizable difficulty.Soft foundation mainly is distributed in the intermountain valley floor in depression and mountain area between the hilllock of riverbed and valley floor thereof, hills area.The top layer mostly is the paddy field, the groundwater table height, and based on low liquid limit clay, folder thin layer high liquid limit clay, the part contains the decomposed rock fragment.The general soft shape of moulding of soil layer, mould firmly the part or stream is moulded shape, and engineering geological conditions is poor, allowable bearing 80-100KPa.General thickness is less than 10 meters.This geological conditions, in dry days, the surface of clay can form crust layer, adopt the 12-15T road roller to roll, also can only subdue 20cm-30cm, but one run into rainy season, rainwater soaks the back crust layer and promptly becomes ooze, will certainly cause the integral body of embankment to sink after the construction, as seen adopt road roller to roll processing and be not suitable for.Just the situation of many Highway Foundation processing of China is at present seen, no matter be to adopt deep-mixed pile or sand pile, and plastic draining board, the route operation situation after the processing all has depression in various degree, does not reach designing requirement.The first cofferdam of employing is also arranged, excavate soft foundation, change the way of filling out the design material, perhaps build bridge and pass through, but all have the cost height, the problem that progress is slow, the former also often causes the consequence of environmental disruption.
Summary of the invention
At the problems referred to above, task of the present invention provides a kind of newly-built highway, railway engineering soft foundation processing method, with under the prerequisite of not destroying environment, reduces construction cost, improves construction speed.
For finishing above-mentioned task, technical scheme of the present invention is; A kind of treatment method of newly built high way railway engineering soft foundation, this method squeeze ooze on the soft foundation surface as follows and open, and form the duricrust displacement layer:
A, outfit the largest particles diameter are no more than the filling building stones of 60cm;
B, completely spread the 40-80cm thick stone layer on the soft foundation surface;
C, adopt hammer ram, utilize hammer ram tamping force, ram out the tamping pit of 2-3m at selected tamping point with by ramming or separate tamping adds and mends the mode of ramming and arrange that tamping point rams stone layer;
D, for each tamping pit, by filler---ram, filler---ram until the settling amount of ramming for continuous 2-3 time less than 7cm, can stop to ram.
Described building stones adopt the building stones that cut into a mountain, and the unconfined compression strength of building stones is not less than 15Mpa.
Described tamping point is arranged in squares, and spacing is 2.2m, 2.4m, 2.8m.
The diameter of described hammer ram is between 1.0-1.5m, and hammer weighs 15-20T.
Ramming employing constructs from the middle mode of ramming to both sides of roadbed.
Described duricrust displacement layer is thick at 2-6m.
The present invention is by putting the building stones of regulatory specifications in shop, soft foundation surface, the filler while ramming, the ooze or the mud of weak roadbed top layer 2-6 rice thickness are squeezed out, reach the purpose of removing silt for replacement, the final thick duricrust displacement layer of 2-6 rice that forms, improve the bearing capacity of ground, increased the stability of ground.This mode is compared first cofferdam, excavates soft foundation again, changes to fill out design material or bridge formation and pass through, and it is low to have a cost, the advantage that construction speed is fast.In addition, this form of construction work is gathered materials on the spot, on the way the building stones that cut into a mountain of building the road are directly used in to ram fill out soft foundation, both solved that waste material takes up an area of and destroy problem of environment, reduced the consumption of cement, lime, sandstone again, and reduced operating expenses and produced the environmental disruption that building materials cause indirectly.Be exactly that rammer embankment formula row of the present invention is become silted up and replaced, and does not destroy geological structure on the way in addition, after construction is finished, the water resource of roadbed both sides and microorganism also possess certain permeability, do not destroy ecological environment on the way, and this point also has good economic benefits and social benefit.
The specific embodiment
Treatment method of newly built high way railway engineering soft foundation of the present invention, this method squeeze ooze on the soft foundation surface as follows and open, and form duricrust displacement layer: a, be equipped with the filling building stones that the largest particles diameter is no more than 60cm; B, completely spread the 40-80cm thick stone layer on the soft foundation surface; C, adopt hammer ram, utilize hammer ram tamping force, ram out the tamping pit of 2-3m at selected tamping point with by ramming or separate tamping adds and mends the mode of ramming and arrange that tamping point rams stone layer; D, for each tamping pit, by filler---ram, filler---ram until the settling amount of ramming for continuous 2-3 time less than 7cm, can stop to ram.Building stones adopt the building stones that cut into a mountain, and the unconfined compression strength of building stones is not less than 15Mpa.Tamping point is arranged in squares, and spacing can be set at as the case may be and be 2.2m, 2.4m, 2.8m.The diameter of hammer ram is between 1.0-1.5m, and hammer weighs 15-20T.Ramming employing constructs from the middle mode of ramming to both sides of roadbed, the ooze or the mud of weak roadbed top layer 2-6 rice thickness are squeezed out, reach the purpose of removing silt for replacement, finally form the thick duricrust displacement layer of 2-6 rice, improve the bearing capacity of ground, increased the stability of ground.
So-called by the some rammer, after being meant the square tamping point picture ash mark layout setting-out according to spacing 2.2m, 2.4m or 2.8m in advance, tamping point of the person of suffering is handled, each tamping point is rammed heavy amount continuously reach 2.5 meters, then, the limit is rammed to stopping ramming the limit and fill building stones in tamping pit, and the requirement that at every turn stops to ram is to ram deflection less than 5 centimetres.The building stones of at every turn dosing are between 70-100 centimetre, and last and ground line is caught up with flat.Mend rammer at last, smooth until ground.
So-called separate tamping, after being meant the square tamping point picture ash mark layout setting-out according to spacing 2.2m, 2.4m or 2.8m in advance, handle every a tamping point for one, each tamping point is rammed heavy amount continuously reach 2.5 meters, then, the limit is rammed to stopping ramming the limit and fill building stones in tamping pit, and the requirement that at every turn stops to ram is to ram deflection less than 5 centimetres.The building stones of at every turn dosing are between 70-100 centimetre, and last and ground line is caught up with flat.Then all tamping points of omitting are gone by above-mentioned requirements again and handle.Mend rammer at last, smooth until ground.
Claims (6)
1, a kind of treatment method of newly built high way railway engineering soft foundation is characterized in that, this method is squeezed ooze on the soft foundation surface as follows and opened, and forms the duricrust displacement layer:
A, outfit the largest particles diameter are no more than the filling building stones of 60cm;
B, completely spread the 40-80cm thick stone layer on the soft foundation surface;
C, adopt hammer ram, utilize hammer ram tamping force, ram out the tamping pit of 2-3m at selected tamping point with by ramming or separate tamping adds and mends the mode of ramming and arrange that tamping point rams stone layer;
D, for each tamping pit, by filler---ram, filler---ram until the settling amount of ramming for continuous 2-3 time less than 7cm, stop to ram.
2, soft foundation processing method according to claim 1 is characterized in that, described building stones adopt the building stones that cut into a mountain, and the unconfined compression strength of building stones is not less than 15Mpa.
3, soft foundation processing method according to claim 1 and 2 is characterized in that, sunrise is stated tamping point and is arranged in squares, and spacing is 2.2m, 2.4m or 2.8m.
4, soft foundation processing method according to claim 3 is characterized in that, the diameter of described hammer ram is between 1.0-1.5m, and hammer weighs 15-20T.
5, soft foundation processing method according to claim 4 is characterized in that, rams employing and constructs from the middle mode of ramming to both sides of roadbed.
6, soft foundation processing method according to claim 5 is characterized in that, described duricrust displacement layer is that 2-6m is thick.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100485968A CN100439600C (en) | 2006-08-11 | 2006-08-11 | Treatment method of newly built high way railway engineering soft foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100485968A CN100439600C (en) | 2006-08-11 | 2006-08-11 | Treatment method of newly built high way railway engineering soft foundation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1948626A CN1948626A (en) | 2007-04-18 |
CN100439600C true CN100439600C (en) | 2008-12-03 |
Family
ID=38018241
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2006100485968A Expired - Fee Related CN100439600C (en) | 2006-08-11 | 2006-08-11 | Treatment method of newly built high way railway engineering soft foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100439600C (en) |
Families Citing this family (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101368383B (en) * | 2008-09-11 | 2010-04-14 | 中国科学院武汉岩土力学研究所 | Method for treating soft soil roadbed by artificial composite crust layer |
CN101701442B (en) * | 2009-11-04 | 2011-04-27 | 天津大学 | Method for building road by pressing and silting large-scale silt sand in large powder and soil filled bag |
CN101787689B (en) * | 2010-03-26 | 2012-08-22 | 中国十九冶集团有限公司 | Forced ramming construction method for high slope filling with Xigeda soil |
CN101949122B (en) * | 2010-10-25 | 2012-07-04 | 河海大学 | Method for controlling settlement by horizontally drilling at embankment and injecting light weight replacing material under normal traffic circumstance |
CN102493304A (en) * | 2011-11-16 | 2012-06-13 | 天津市市政工程研究院 | Method for processing riverway sludge for filling subgrade by using construction wastes |
CN102561132B (en) * | 2012-01-11 | 2014-04-16 | 河海大学 | Plate supporting type embankment structure for post-construction settlement controlling of deep soft soil foundation on high-grade highway |
CN103031838B (en) * | 2012-12-07 | 2014-10-08 | 中铁四局集团第三建设有限公司 | Bridge site deep-layer displacement method |
CN103590409B (en) * | 2013-11-22 | 2015-07-15 | 天津住宅集团建设工程总承包有限公司 | Slurry replacing filling separate support construction method |
CN105544501A (en) * | 2015-12-11 | 2016-05-04 | 神翼航空器科技(天津)有限公司 | Reinforcing method for foundation by utilizing breaking hammer of excavator |
CN105525548A (en) * | 2015-12-15 | 2016-04-27 | 上海浦江桥隧高速公路管理有限公司 | Pavement structure aiming at locally high underground water level soft roadbed and full-depth digging maintenance method |
CN112359890B (en) * | 2020-11-11 | 2022-09-06 | 中国电建集团华东勘测设计研究院有限公司 | Earth-rock dam foundation geological defect silt squeezing and filling changing treatment method |
CN114541360A (en) * | 2022-03-30 | 2022-05-27 | 山西机械化建设集团有限公司 | Construction method for high-sensitivity and heavy-liquefaction soil layer foundation dynamic compaction replacement |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1667193A (en) * | 2004-03-08 | 2005-09-14 | 北京欣路特科技发展有限公司 | Construction method for positioning and compacting subgrade |
-
2006
- 2006-08-11 CN CNB2006100485968A patent/CN100439600C/en not_active Expired - Fee Related
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1667193A (en) * | 2004-03-08 | 2005-09-14 | 北京欣路特科技发展有限公司 | Construction method for positioning and compacting subgrade |
Non-Patent Citations (6)
Title |
---|
强夯加固填土的效果与机理分析. 周德泉,张可能,刘宏利,邓文清.中南大学学报(自然科学版),第35卷第2期. 2004 |
强夯加固填土的效果与机理分析. 周德泉,张可能,刘宏利,邓文清.中南大学学报(自然科学版),第35卷第2期. 2004 * |
强夯加固软土的新发展. 刘惠珊,陈克景.工业建筑,第1990卷第7期. 1990 |
强夯加固软土的新发展. 刘惠珊,陈克景.工业建筑,第1990卷第7期. 1990 * |
海口美兰国际机场场道工程强夯地基处理技术. 王永才,张晓东,王峰.山西建筑,第1999卷第3期. 1999 |
海口美兰国际机场场道工程强夯地基处理技术. 王永才,张晓东,王峰.山西建筑,第1999卷第3期. 1999 * |
Also Published As
Publication number | Publication date |
---|---|
CN1948626A (en) | 2007-04-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100439600C (en) | Treatment method of newly built high way railway engineering soft foundation | |
CN107059573B (en) | Construction method for solidifying soil body as road water stabilization layer | |
CN202031001U (en) | Compound water-permeable road structure | |
CN105152519B (en) | A kind of inorganic sludge curing agent, road-making material and preparation method thereof | |
CN104818707B (en) | Application cotton stalk consolidation and solidification dredging silt, the method for new barged-in fill | |
CN101545234A (en) | Method for constructing roadbed and base course by construction waste | |
WO2022077908A1 (en) | Isoenergetic deformation composite foundation utilizing microorganism to solidify aggregate, and construction method | |
CN106283944B (en) | The method for pressing washer stone and/or block stone to reinforce shallow layer soft ground | |
CN206902488U (en) | A kind of soft soil foundation high-filled embankment of effectively control settlement after construction | |
CN106116395A (en) | A kind of inorganic colloid methoder as road subbase course filler and compound method thereof | |
CN107881891A (en) | A kind of soft soil roadbed construction method of municipal administration | |
CN108677638A (en) | Express highway roadbed dam filling construction based on building waste | |
CN104711976A (en) | Construction waste recycled aggregate composite carrier pile and preparation method thereof | |
CN105951672B (en) | A kind of construction technology of novel embankment and bank protection | |
CN104763017B (en) | Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system | |
CN108505409B (en) | Solidified muddy soil and construction waste regenerated aggregate composite inorganic material and forming method thereof | |
CN205576857U (en) | Be suitable for hydraulic and hydroelectric engineering's super high enrockment dam structure | |
CN208009180U (en) | A kind of solidified slip soil and construction refuse regenerated grading are gathered materials the pavement structure of composition | |
CN214271530U (en) | Soft basic district road structure based on building rubbish is laid | |
CN210529400U (en) | Solidified building residue soil road structure | |
CN206359847U (en) | A kind of asphalt pavement structure of clinker silty filler | |
CN202492776U (en) | Compound ion soil curing agent and road structure paved by acetylene sludge | |
CN204803702U (en) | Building rubbish road bed course structure | |
CN112030643A (en) | Construction method of red mud-based assembled roadbed for expressway | |
CN215758302U (en) | High liquid limit soil roadbed structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20081203 Termination date: 20100811 |