CN109577456A - The construction method of environmental prefabricated assembling type reinforced concrete chute drainage system - Google Patents

The construction method of environmental prefabricated assembling type reinforced concrete chute drainage system Download PDF

Info

Publication number
CN109577456A
CN109577456A CN201811491221.8A CN201811491221A CN109577456A CN 109577456 A CN109577456 A CN 109577456A CN 201811491221 A CN201811491221 A CN 201811491221A CN 109577456 A CN109577456 A CN 109577456A
Authority
CN
China
Prior art keywords
chute
precast section
prefabricated
mold
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811491221.8A
Other languages
Chinese (zh)
Other versions
CN109577456B (en
Inventor
陈小林
朱凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Ang Chuang Technology Co Ltd
Original Assignee
Hangzhou Ang Chuang Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Ang Chuang Technology Co Ltd filed Critical Hangzhou Ang Chuang Technology Co Ltd
Priority to CN201811491221.8A priority Critical patent/CN109577456B/en
Publication of CN109577456A publication Critical patent/CN109577456A/en
Application granted granted Critical
Publication of CN109577456B publication Critical patent/CN109577456B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/227Gutters; Channels ; Roof drainage discharge ducts set in sidewalks
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers

Landscapes

  • Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Sewage (AREA)

Abstract

The present invention relates to a kind of construction method of environmental prefabricated assembling type reinforced concrete chute drainage system, main construction procedure includes: that chute is prefabricated, grass planting diaphragm capsule is prefabricated, the installation of groove construction, the power that disappears step, the installation of torrent slot standard precast section, the installation of prefabricated catch pit, the installation of grass planting diaphragm capsule, spherical detachable filter screen installation.Between chute precast section together using " stacked tile type " concave-convex hasp, and together using wirerope whole strand pricking, then by wirerope both ends drawknot on the pre-buried pull ring of prefabricated catch pit, grass planting diaphragm capsule finally is embedded at the top of chute precast section.Chute drainage system of the present invention uses prefabricated assembled design concept, have the characteristics that install convenient, speed of application be fast and ecological, environmental protective, it is drained caused by solving because of the problems such as the infiltration of masonry class chute, leak, sedimentation and deformation and the Moisture Damages such as empties, washes away to roadbed, there is preferable economic technology benefit.

Description

The construction method of environmental prefabricated assembling type reinforced concrete chute drainage system
Technical field
The present invention relates to a kind of construction methods of environmental prefabricated assembling type reinforced concrete chute drainage system, belong to Highway engineering field, suitable for the vertical drainage construction at the abrupt slope of embankment and cutting.
Background technique
In highway engineering, chute is mainly used to drain and achievees the purpose that slow down water velocity, for highway subgrade Play very big protective effect, torrent slot structure it is reasonable whether be directly related to the safety of roadbed, in previous construction often Using the draining chute of side slope of embankment mortar flag stone structure, since its raw material slabstone is difficult to uniform specification, while stone-laying team 5 skilled workers lack, and cause construction technology quality and are difficult to control and guarantee, this draining chute is caused sand easily occur Starch not full, jointing falls off, seeps water, leak, and chute sedimentation and deformation, cracking wash away roadbed, forms roadbed and washes in a pan sky, serious person Subgrade settlement is even caused to deform and collapse.
Therefore, in order to which the percolating water for effectivelying prevent mortar flag stone chute easily to occur causes roadbed side slope Moisture Damage problem, It is necessary to research and develop a kind of convenient, reliable in quality chute of constructing, made of the present invention exactly develops in this context, Applied to practical chute construction in will generate significant economic benefit and social benefit.
Summary of the invention
It is an object of the invention to not full for mortar existing for traditional side slope of embankment mortar flag stone chute, jointing is de- It falls, seep water, leak, it is easily-deformable, crack and cause subgrade settlement to deform and the problems such as collapse, propose a kind of prefabricated dress of the ecotype Construction method with formula armored concrete chute drainage system, this method Piecemeal erection chute precast section from bottom to top, and By the concave-convex hasp of adjacent chute precast section " stacked tile type ", while wirerope both ends being passed through to the wirerope hole of resistance sliding tooth from bottom to top, And water flow dynamic energy is reduced using its anti-sliding stop of bottom resistance sliding tooth, using upper surface buffle sill, then by wirerope both ends drawknot pre- It, then will be in the good grass planting diaphragm capsule insertion precast section side wall tongue and groove of pre-production on the pre-buried pull ring of catch pit processed.
In order to achieve the above technical purposes, the invention adopts the following technical scheme:
Environmental prefabricated assembling type reinforced concrete chute drainage system, it is characterised in that: it includes that torrent slot standard is prefabricated Section, the non-standard precast section of chute, wirerope, prefabricated catch pit, the power that disappears step, grass planting diaphragm capsule, spherical detachable filter screen, rubble Bed course, waterproof geotextiles;Described torrent slot standard precast section one end inner surface bottom is equipped with protrusion, and other end outer surface bottom is set Fluted, outer surface bottom is uniformly equipped with resistance sliding tooth;Described non-standard precast section one end of chute is equipped with hook, the other end Outer surface bottom is equipped with groove, and outer surface bottom is uniformly equipped with resistance sliding tooth;The reserved wirerope hole in the resistance sliding tooth two sides;Institute The top for stating torrent slot standard precast section and the non-standard precast section of chute is designed for tongue and groove, and top is embedded in grass planting diaphragm capsule;Institute Stating grass planting diaphragm capsule is inner hollow, and bottom face has angle with horizontal plane, and upper surface is parallel to the horizontal plane;The torrent slot standard Between precast section and the non-standard precast section of chute together using " stacked tile type " concave-convex hasp, and existed using wirerope whole strand pricking Together, wirerope both ends drawknot is on the pull ring of prefabricated catch pit.
The staggered setting buffle sill of the torrent slot standard precast section and chute non-standard precast section inner surface bottom.
The prefabricated catch pit is set to chute water inlet locations, and the non-standard precast section of chute is fixed by hook In the side wall of prefabricated catch pit.
The non-standard precast section of chute installs spherical detachable filter screen, chute water outlet position in water inlet locations Install the power step that disappears.
The spherical detachable filter screen is fixed in grass planting on fixing clamp, and through fixing clamp using steel wire lashing Lateral wall of molding flask and the non-standard precast section side wall of chute.
The fixing clamp connects middle splint and two sides clamping plate by fixing bolt, and two sides clamping plate is movable, by tightening Fixing bolt can fix two sides clamping plate, and two sides clamping plate inner wall end is respectively provided with rubber pad.
The construction method of environmental prefabricated assembling type reinforced concrete chute drainage system, it is characterised in that including following Step:
Step 1: chute is prefabricated: according to the special construction of chute precast section, designing and producing more set torrent slot standard precast sections With the mold of the non-standard precast section of chute, mold is divided into inner side template and outboard template two parts, and is assemblied in using bolt Together, mold is made of steel plate and there are perfusing hole, the uniform setting back cords in outside in mold, to guarantee the entirety of mold Stability;The brush release agent in the mold of torrent slot standard precast section and the non-standard precast section of chute, and according to design configurations Concrete protective layer pad is arranged when entering mould in reinforcing bar;After the completion of arrangement of reinforcement enters mould, by the inner side template of mold and outboard template two Divide and be bolted on together, and concrete perfusion and vibrating forming into fill orifice;
Step 2: grass planting diaphragm capsule is prefabricated: according to the mold of design size production grass planting diaphragm capsule, mold is divided into inner side template and outside Template two parts, and be assembled together using bolt, mold is made of steel plate and there are perfusing holes, and outside is uniform in mold Setting back cord, to guarantee the overall stability of mold;The brush release agent in the mold of grass planting diaphragm capsule, by the inner side template of mold It is bolted on together with outboard template two parts, and concrete perfusion and vibrating forming into fill orifice;
Step 3: groove construction: measuring unwrapping wire to torrent groove location before installation, carry out groove layering according to unwrapping wire result and open It digs and is compacted in place, guarantee that channel bottom is smooth solid;It is laid with waterproof geotextiles in the trench, guarantees that waterproof geotextile laying is flat Whole, seam crossing welds closely knit;Uniformly layering is laid with blotter and is compacted in place, directly on being laid with the waterproof geotextiles completed To designed elevation;
Step 4: the power step installation that disappears: chute water outlet of first constructing disappears power step concrete foundation, and the power step peace that will disappear Dress is fixed on the water outlet position of design;
Step 5: torrent slot standard precast section is installed: Piecemeal erection chute precast section from bottom to top, first segment torrent slot standard Before precast section installation, first wirerope is penetrated from top to bottom from the wirerope hole of resistance sliding tooth side, then the wirerope from the resistance sliding tooth other side Hole is pierced by from bottom to top, is banketed after then fixing the positioning of first segment torrent slot standard precast section, then around back-filling in layers compacting; When second section torrent slot standard precast section is installed, first it is taken with first segment torrent slot standard precast section using " stacked tile type " bumps It is buckled together and fixes, wirerope both ends are passed through from bottom to top then and are filled out around the wirerope hole of resistance sliding tooth, then back-filling in layers compacting Soil;And so on until whole torrent slot standard precast sections are installed;
Step 6: prefabricated catch pit installation: after torrent slot standard precast section is installed, prefabricated catch pit being mounted on design Water inlet locations, back-filling in layers compacting surrounding are banketed;After prefabricated catch pit is installed, by the anti-of the non-standard precast section of chute The side wall of prefabricated catch pit is fixed on to hook, and with final section torrent slot standard precast section using " stacked tile type " concave-convex hasp Together, then wirerope both ends are passed through to the wirerope hole of resistance sliding tooth from bottom to top, then by wirerope both ends drawknot in prefabricated catch pit Side wall two pre-buried pull rings on, banket around last back-filling in layers compacting;
Step 7: grass planting diaphragm capsule is installed: grass planting diaphragm capsule being mounted in torrent slot standard precast section and chute one by one from bottom to top In the tongue and groove of non-standard precast section, after grass planting diaphragm capsule is installed, it is packed into planting soil in grass planting diaphragm capsule and is afforested;
Step 8: spherical detachable filter screen installation: spherical detachable filter screen is passed through to the two sides clamping plate of steel wire and fixing clamp Connection, it is further by the fixed two sides clamping plate of fixing bolt, two sides Boards wall is non-in grass planting lateral wall of molding flask and chute Standard precast section side wall.
The invention has the characteristics that and the utility model has the advantages that
(1) torrent slot standard precast section and the non-standard precast section of chute can batch production, standardization, Virtual production, overcome biography In system side slope of embankment mortar flag stone chute the problems such as mortar flag stone specification disunity, the easily settled deformation of chute, cracking, resistance Shape, antiscour, anti-leakage ability are stronger, and it is more convenient to safeguard and replace in later period use;Simultaneously torrent slot standard precast section with Protrusion and groove between the non-standard precast section of chute by setting realize " stacked tile type " concave-convex hasp, and pass through wirerope entirety Lashing, the bonding strength between component are stronger;
(2) torrent slot standard precast section is set with chute non-standard precast section inner surface bottom equipped with buffle sill, water outlet position The power step that disappears has been set, can effectively reduce water flow dynamic energy, has reduced water flow for the erosion damage of chute;Torrent slot standard precast section It is equipped with resistance sliding tooth with chute non-standard precast section outer surface bottom, precast section is can effectively avoid and is slided with the gradient, increase and apply The safety of work and the stability of chute;
(3) the non-standard precast section of torrent slot standard precast section, chute and grass planting diaphragm capsule are that prefabrication generates, comparison tradition The construction of side slope of embankment mortar flag stone chute effectively reduces the workload at scene, and the cost of chute precast section is far below slurry Build slabstone;
(4) it is embedded in grass planting diaphragm capsule at the top of torrent slot standard precast section and the non-standard precast section of chute, by grass planting diaphragm capsule It bankets plantation, it is more ecological and environmentally friendly to compare traditional side slope of embankment mortar flag stone chute, while increasing the beauty of chute Property;
(5) chute water inlet locations install spherical detachable filter screen, and then effectively filter water body impurity, avoid chute stifled Plug, while filter screen is detachable, facilitates the maintenance cleaning in later period.
Detailed description of the invention
Fig. 1 is environmental prefabricated assembling type reinforced concrete chute drainage system sectional view;
Fig. 2 is environmental prefabricated assembling type reinforced concrete chute drainage system plan view;
Fig. 3 is torrent slot standard precast section plane;
Fig. 4 is torrent slot standard precast section A-A sectional view;
Fig. 5 is torrent slot standard precast section B-B cross-section diagram;
Fig. 6 is torrent slot standard precast section C-C cross-section diagram;
Fig. 7 is torrent slot standard precast section D-D cross-section diagram;
Fig. 8 is the fixed schematic diagram of spherical detachable filter screen;
Fig. 9 is that fixing clamp opens schematic diagram;
Figure 10 is fixing clamp closure schematic diagram.
In figure: 1. torrent slot standard precast sections, 2. resistance sliding tooths, 3. buffle sills, 4. hooks, 5. tongue and grooves, 6. protrusions, 7. is recessed Slot, 8. wireropes, 9. pull rings, 10. grass planting diaphragm capsules, 11. prefabricated catch pits, 12. disappear power step, 13. spherical detachable filter screens, 14. blotter, 15. waterproof geotextiles, 16. wirerope holes, the non-standard precast section of 17. chutes, 18. road shoulders, 19. fixing clamps, 20. steel wire, 21. middle splints, 22. two sides clamping plates, 23. fixing bolts, 24. rubber pads.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawing and by embodiment, and following embodiment is to the present invention Explanation be not limited to following embodiment.The construction of certain highway subgrade slope chute drainage system, the roadbed side slope gradient are β, Using the construction method of environmental prefabricated assembling type reinforced concrete chute drainage system.
In conjunction with shown in attached drawing 1 and Fig. 2, ecotype prefabricated assembling type reinforced concrete chute draining system of the present invention System includes torrent slot standard precast section 1, the non-standard precast section 17 of chute, wirerope 8, prefabricated catch pit 11, the power that disappears step 12, plants Careless diaphragm capsule 10, spherical detachable filter screen 13, blotter 14, waterproof geotextiles 15;Table in 1 one end of torrent slot standard precast section Face bottom is equipped with protrusion 6, and other end outer surface bottom is equipped with groove 7, and outer surface bottom is uniformly equipped with resistance sliding tooth 2;Torrent Non-standard 1 one end of precast section of slot is equipped with hook 4, and other end outer surface bottom is equipped with groove 7, and outer surface bottom is uniformly equipped with Resistance sliding tooth 2;The reserved wirerope hole 16 in 2 two sides of resistance sliding tooth;The top of torrent slot standard precast section 1 and the non-standard precast section 17 of chute Portion is the design of tongue and groove 5, and top is embedded in grass planting diaphragm capsule 10;In torrent slot standard precast section 1 and the non-standard precast section 17 of chute The staggered setting buffle sill 3 of surface bottom portion;Grass planting diaphragm capsule 10 is inner hollow, and bottom face and horizontal plane have angle β, upper surface It is parallel to the horizontal plane;Using " stacked tile type " concave-convex hasp between torrent slot standard precast section 1 and the non-standard precast section 17 of chute Together, and using 8 whole strand pricking of wirerope together, 8 both ends drawknot of wirerope is on the pull ring 9 of prefabricated catch pit 11;Prefabricated collection Puddle 11 is set to chute water inlet locations, and the non-standard precast section 17 of chute is fixed on prefabricated catch pit 11 by hook 4 Side wall;The non-standard precast section 17 of chute installs spherical detachable filter screen 13, chute water outlet position in water inlet locations Install the power step 12 that disappears.
As shown in Fig. 3, Fig. 4, Fig. 5, Fig. 6 and Fig. 7,1 one end inner surface bottom of torrent slot standard precast section is equipped with protrusion 6, other end outer surface bottom is equipped with groove 7, and outer surface bottom is uniformly equipped with resistance sliding tooth 2, the reserved steel in 2 two sides of resistance sliding tooth Cable hole 16;It is designed at the top of torrent slot standard precast section 1 for tongue and groove 5, the embeddable grass planting diaphragm capsule 10 in top;Torrent slot standard is prefabricated The staggered setting buffle sill 3 in 1 inner surface bottom of section.
As shown in Fig. 8, Fig. 9 and Figure 10, prefabricated catch pit 11 is set to chute water inlet locations, and chute is non-standard Precast section 17 is fixed on the side wall of prefabricated catch pit 11 by hook 4;Spherical detachable filter screen 13 is using steel wire lashing solid In clamp 19, and 10 side wall of grass planting diaphragm capsule and non-standard 17 side wall of precast section of chute are fixed in by fixing clamp 19;Gu Clamp 19 connects middle splint 21 and two sides clamping plate 22 by fixing bolt 23, and two sides clamping plate 22 is movable, by tightening fixation Bolt 23 can fix two sides clamping plate 22, and clamping plate 22 inner wall end in two sides is respectively provided with rubber pad 24.
Above-mentioned ecotype prefabricated assembling type reinforced concrete chute drainage system main construction course is as follows:
Step 1: chute is prefabricated: according to the special construction of chute precast section, designing and producing more set torrent slot standard precast sections 1 and the non-standard precast section 17 of chute mold, mold is divided into inner side template and outboard template two parts, and is assembled using bolt Together, mold is made of steel plate and there are perfusing hole, the uniform setting back cords in outside in mold, to guarantee the whole of mold Body stability;The brush release agent in the mold of torrent slot standard precast section 1 and the non-standard precast section 17 of chute, and according to design Concrete protective layer pad is arranged when entering mould in configuration reinforcement;After the completion of arrangement of reinforcement enters mould, by the inner side template and outboard template of mold Two parts are bolted on together, and concrete perfusion and vibrating forming into fill orifice;
Step 2: grass planting diaphragm capsule is prefabricated: according to the mold of design size production grass planting diaphragm capsule 10, mold is divided into inner side template and outer Side template two parts, and be assembled together using bolt, mold is made of steel plate and there are perfusing holes, and outside is equal in mold Even setting back cord, to guarantee the overall stability of mold;The brush release agent in the mold of grass planting diaphragm capsule 10, by the inside of mold Template and outboard template two parts are bolted on together, and concrete perfusion and vibrating forming into fill orifice;
Step 3: groove construction: measuring unwrapping wire to torrent groove location before installation, carry out groove layering according to unwrapping wire result and open It digs and is compacted in place, guarantee that channel bottom is smooth solid;It is laid with waterproof geotextiles 15 in the trench, guarantees that waterproof geotextiles 15 are spread If smooth, seam crossing welds closely knit;Uniformly layering is laid with blotter 14 and presses on being laid with the waterproof geotextiles 15 completed Actual arrival position, until designed elevation;
Step 4: the power step installation that disappears: chute water outlet of first constructing disappears 12 concrete foundation of power step, and the power step that will disappear 12 are fixed on the water outlet position of design;
Step 5: torrent slot standard precast section is installed: Piecemeal erection chute precast section from bottom to top, first segment torrent slot standard Before precast section 1 is installed, first wirerope 8 is penetrated from top to bottom from the wirerope hole 16 of 2 side of resistance sliding tooth, then from 2 other side of resistance sliding tooth Wirerope hole 16 be pierced by from bottom to top, then by the positioning of first segment torrent slot standard precast section 1 it is fixed after, then back-filling in layers compacting Surrounding is banketed;When second section torrent slot standard precast section 1 is installed, first it is used with first segment torrent slot standard precast section 1 " folded Tile style " bumps hasp is together and fixed, then 8 both ends of wirerope is passed through to the wirerope hole 16 of resistance sliding tooth 2 from bottom to top, then be layered It bankets around being backfilling and compacted;And so on until whole torrent slot standard precast sections 1 are installed;
Step 6: prefabricated catch pit installation: after torrent slot standard precast section 1 is installed, prefabricated catch pit 11 being mounted on and is set The water inlet locations of meter, back-filling in layers compacting surrounding are banketed;It is after prefabricated catch pit 11 is installed, chute is non-standard prefabricated The hook 4 of section 17 is fixed on the side wall of prefabricated catch pit 11, and uses " stacked tile type " with final section torrent slot standard precast section 1 8 both ends of wirerope together, are then passed through the wirerope hole 16 of resistance sliding tooth 2 by concave-convex hasp from bottom to top, then by 8 both ends drawknot of wirerope On two pre-buried pull rings 9 of the side wall of prefabricated catch pit 11, banket around last back-filling in layers compacting;
Step 7: grass planting diaphragm capsule is installed: grass planting diaphragm capsule 10 being mounted in torrent slot standard precast section 1 and torrent one by one from bottom to top In the tongue and groove 5 of the non-standard precast section 17 of slot, after grass planting diaphragm capsule 10 is installed, it is packed into planting soil in grass planting diaphragm capsule 10 and carries out Greening;
Step 8: spherical detachable filter screen installation: spherical detachable filter screen 13 is passed through to the two sides of steel wire and fixing clamp 19 Clamping plate 22 connects, and further by the fixed two sides clamping plate 22 of fixing bolt 23, two sides clamping plate 22 is fixed on 10 side of grass planting diaphragm capsule Wall and non-standard 17 side wall of precast section of chute.
It describes the invention in detail in conjunction with the embodiments above, but the content is only preferable implementation of the invention Example, should not be considered as limiting the scope of the invention.It is all according to all the changes and improvements made by the present patent application range Deng should all still fall within patent covering scope of the invention.

Claims (1)

1. the construction method of environmental prefabricated assembling type reinforced concrete chute drainage system, it is characterised in that including following step It is rapid:
Step 1: chute is prefabricated: according to the special construction of chute precast section, designing and producing more set torrent slot standard precast sections (1) and the mold of the non-standard precast section of chute (17), mold are divided into inner side template and outboard template two parts, and using bolt It is assembled together, mold is made of steel plate and there are perfusing hole, the uniform setting back cords in outside in mold, to guarantee mold Overall stability;The brush release agent in the mold of torrent slot standard precast section (1) and the non-standard precast section of chute (17), and According to design configurations reinforcing bar, concrete protective layer pad is set when entering mould;After the completion of arrangement of reinforcement enters mould, by the inner side template of mold and Outboard template two parts are bolted on together, and concrete perfusion and vibrating forming into fill orifice;
Step 2: grass planting diaphragm capsule is prefabricated: according to design size production grass planting diaphragm capsule (10) mold, mold be divided into inner side template and Outboard template two parts, and be assembled together using bolt, mold is made of steel plate and there are perfusing hole, the outside in mold Uniform setting back cord, to guarantee the overall stability of mold;The brush release agent in the mold of grass planting diaphragm capsule (10), by mold Inner side template and outboard template two parts are bolted on together, and concrete perfusion and vibrating forming into fill orifice;
Step 3: groove construction: measuring unwrapping wire to torrent groove location before installation, carry out groove layering according to unwrapping wire result and open It digs and is compacted in place, guarantee that channel bottom is smooth solid;Waterproof geotextiles (15) are laid in the trench, guarantee waterproof geotextiles (15) laying is smooth, seam crossing welding is closely knit;Uniformly layering is laid with rubble pad on being laid with the waterproof geotextiles (15) completed Layer (14) is simultaneously compacted in place, until designed elevation;
Step 4: the power step installation that disappears: chute water outlet of first constructing disappears power step (12) concrete foundation, and the power platform that will disappear Rank (12) is fixed on the water outlet position of design;
Step 5: torrent slot standard precast section is installed: Piecemeal erection chute precast section from bottom to top, first segment torrent slot standard Before precast section (1) installation, first wirerope (8) is penetrated from top to bottom from the wirerope hole (16) of resistance sliding tooth (2) side, then from resistance sliding tooth (2) the wirerope hole (16) of the other side is pierced by from bottom to top, after then first segment torrent slot standard precast section (1) positioning is fixed, It bankets around back-filling in layers compacting again;When second section torrent slot standard precast section (1) is installed, first by itself and first segment chute mark Quasi- precast section (1) is together and fixed using " stacked tile type " concave-convex hasp, then passes through at wirerope (8) both ends from bottom to top anti-skid It bankets around the wirerope hole (16) of tooth (2), then back-filling in layers compacting;And so on until whole torrent slot standard precast sections (1) It is installed;
Step 6: prefabricated catch pit installation: after torrent slot standard precast section (1) is installed, prefabricated catch pit (11) being installed It bankets around the water inlet locations of design, back-filling in layers compacting;It is after prefabricated catch pit (11) is installed, chute is nonstandard The hook (4) of quasi- precast section (17) is fixed on the side wall of prefabricated catch pit (11), and with final section torrent slot standard precast section (1) wirerope (8) both ends together, are then passed through using " stacked tile type " concave-convex hasp by the wirerope hole of resistance sliding tooth (2) from bottom to top (16), it then by wirerope (8) both ends drawknot on two pre-buried pull rings (9) of the side wall of prefabricated catch pit (11), is finally layered back It tamps and bankets around real;
Step 7: grass planting diaphragm capsule install: from bottom to top by grass planting diaphragm capsule (10) be mounted in one by one torrent slot standard precast section (1) and In the tongue and groove (5) of the non-standard precast section of chute (17), after grass planting diaphragm capsule (10) is installed, it is packed into grass planting diaphragm capsule (10) Planting soil is simultaneously afforested;
Step 8: spherical detachable filter screen installation: spherical detachable filter screen (13) is passed through steel wire and fixing clamp (19) Two sides clamping plate (22) connection, it is further fixed two sides clamping plate (22) by fixing bolt (23), two sides clamping plate (22) is fixed on Grass planting diaphragm capsule (10) side wall and the non-standard precast section of chute (17) side wall.
CN201811491221.8A 2018-12-07 2018-12-07 Construction method of ecological prefabricated assembly type reinforced concrete rapid trough drainage system Active CN109577456B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811491221.8A CN109577456B (en) 2018-12-07 2018-12-07 Construction method of ecological prefabricated assembly type reinforced concrete rapid trough drainage system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811491221.8A CN109577456B (en) 2018-12-07 2018-12-07 Construction method of ecological prefabricated assembly type reinforced concrete rapid trough drainage system

Publications (2)

Publication Number Publication Date
CN109577456A true CN109577456A (en) 2019-04-05
CN109577456B CN109577456B (en) 2020-11-20

Family

ID=65926619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811491221.8A Active CN109577456B (en) 2018-12-07 2018-12-07 Construction method of ecological prefabricated assembly type reinforced concrete rapid trough drainage system

Country Status (1)

Country Link
CN (1) CN109577456B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114808858A (en) * 2022-05-31 2022-07-29 山西路桥第七工程有限公司 Construction process of laminated-tile type reinforced concrete rapid trough

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001123577A (en) * 1999-10-27 2001-05-08 Showa Concrete Ind Co Ltd Woody-cement composite block and woody product
CN2701911Y (en) * 2004-04-23 2005-05-25 陈瑞文 Combined construction of environmental protection pervious grass planting case
KR100537175B1 (en) * 2005-09-16 2005-12-16 (주)삼원기술단 Drain apparatus of roda
CN201620330U (en) * 2009-11-03 2010-11-03 中交第一公路勘察设计研究院有限公司 Tile-type chute
CN106013191A (en) * 2016-07-11 2016-10-12 杭州江润科技有限公司 Environmental-friendly grass concrete highway slope protection structure and construction method thereof
CN205653880U (en) * 2016-04-26 2016-10-19 何立东 Prevent blockking up afforestation gutter
CN207176432U (en) * 2017-06-16 2018-04-03 中交第二公路工程局有限公司 A kind of precast assembly chute
CN108677871A (en) * 2018-05-28 2018-10-19 南昌工程学院 A kind of construction method of assembled grass planting concrete precast block and its ecological revetment
CN108708383A (en) * 2018-08-30 2018-10-26 河北建筑工程学院 A kind of plant-growing type eco-concrete bank protection and its construction method
CN108755708A (en) * 2018-05-07 2018-11-06 安徽省公路桥梁工程有限公司 A kind of Soft Rock Slope ecological protection construction method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001123577A (en) * 1999-10-27 2001-05-08 Showa Concrete Ind Co Ltd Woody-cement composite block and woody product
CN2701911Y (en) * 2004-04-23 2005-05-25 陈瑞文 Combined construction of environmental protection pervious grass planting case
KR100537175B1 (en) * 2005-09-16 2005-12-16 (주)삼원기술단 Drain apparatus of roda
CN201620330U (en) * 2009-11-03 2010-11-03 中交第一公路勘察设计研究院有限公司 Tile-type chute
CN205653880U (en) * 2016-04-26 2016-10-19 何立东 Prevent blockking up afforestation gutter
CN106013191A (en) * 2016-07-11 2016-10-12 杭州江润科技有限公司 Environmental-friendly grass concrete highway slope protection structure and construction method thereof
CN207176432U (en) * 2017-06-16 2018-04-03 中交第二公路工程局有限公司 A kind of precast assembly chute
CN108755708A (en) * 2018-05-07 2018-11-06 安徽省公路桥梁工程有限公司 A kind of Soft Rock Slope ecological protection construction method
CN108677871A (en) * 2018-05-28 2018-10-19 南昌工程学院 A kind of construction method of assembled grass planting concrete precast block and its ecological revetment
CN108708383A (en) * 2018-08-30 2018-10-26 河北建筑工程学院 A kind of plant-growing type eco-concrete bank protection and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114808858A (en) * 2022-05-31 2022-07-29 山西路桥第七工程有限公司 Construction process of laminated-tile type reinforced concrete rapid trough

Also Published As

Publication number Publication date
CN109577456B (en) 2020-11-20

Similar Documents

Publication Publication Date Title
CN106759496B (en) Anti-settling inspection shaft changes the outfit technique
CN207846349U (en) A kind of water blocking earth dam
CN110158389A (en) A kind of light soil road structure and its construction method
CN108755319A (en) A kind of road construction method and the road built using the engineering method
CN108560586A (en) Half prefabricated assembled pipe gallery and its construction method
CN110820720A (en) Water-blocking and drainage-resisting anti-floating construction structure and method
KR101065555B1 (en) System preventing non-woven from mortar particles filled up the back space of PCL Precasting Concrete Lining and method constructing the non-woven to PCL
CN109487641A (en) A kind of high-speed railway monoblock type cable slot structure and surface layer of subgrade bed construction method
CN210262555U (en) Light soil road structure
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN105756100B (en) Basement post-pouring zone system and preparation method thereof
CN205296209U (en) Prestressed anchorage cable assembled stake siding wall protective structure
CN109371910A (en) Pad ground raising protection and construction method
CN109577456A (en) The construction method of environmental prefabricated assembling type reinforced concrete chute drainage system
CN106012971A (en) Vegetation concrete protection slope and construction method thereof
CN108589747A (en) EPS light road banks are widened in conjunction with plant biological bag protective slope structure and construction method
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN112900482A (en) Assembled internal-pulling anchor type gravity retaining wall and construction method thereof
CN106567365B (en) Earth and rockfill dam longitudinal reinforcement construction method
CN108797842A (en) Seismic shear wall and its construction method
CN211228180U (en) Culvert structure capable of protecting embankment
KR20020022446A (en) Repairing method of earth-fill dam
CN208293589U (en) A kind of EPS light road bank is widened in conjunction with plant biological bag protective slope structure
KR101111655B1 (en) method for reinforced of soft ground by using top pile
CN110004938A (en) A kind of foundation pit side-wall structural strengthening suspension device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant