CN109292417A - Modularization assembly line and its construction method - Google Patents

Modularization assembly line and its construction method Download PDF

Info

Publication number
CN109292417A
CN109292417A CN201810873659.6A CN201810873659A CN109292417A CN 109292417 A CN109292417 A CN 109292417A CN 201810873659 A CN201810873659 A CN 201810873659A CN 109292417 A CN109292417 A CN 109292417A
Authority
CN
China
Prior art keywords
assembly
unit
modularization
guide rail
intelligent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810873659.6A
Other languages
Chinese (zh)
Inventor
隆正发
周浩君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Fengyun Zhi Chuang Technology Co Ltd
Original Assignee
Shenzhen Fengyun Zhi Chuang Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Fengyun Zhi Chuang Technology Co Ltd filed Critical Shenzhen Fengyun Zhi Chuang Technology Co Ltd
Priority to CN201810873659.6A priority Critical patent/CN109292417A/en
Publication of CN109292417A publication Critical patent/CN109292417A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G47/00Article or material-handling devices associated with conveyors; Methods employing such devices
    • B65G47/52Devices for transferring articles or materials between conveyors i.e. discharging or feeding devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G47/00Article or material-handling devices associated with conveyors; Methods employing such devices
    • B65G47/74Feeding, transfer, or discharging devices of particular kinds or types
    • B65G47/90Devices for picking-up and depositing articles or materials
    • B65G47/91Devices for picking-up and depositing articles or materials incorporating pneumatic, e.g. suction, grippers
    • B65G47/912Devices for picking-up and depositing articles or materials incorporating pneumatic, e.g. suction, grippers provided with drive systems with rectilinear movements only

Abstract

The present invention provides a kind of modularization assembly lines, including at least two Intelligent assembly robots that can mutually splice and for containing blank in at least jig to circulate in Intelligent assembly robot;Intelligent assembly robot includes control unit, delivery unit, supply unit and assembly unit;In addition, additionally providing a kind of modularization assembly line construction method.Present invention employs Intelligent assembly robots and jig to cooperate, full-automatic production line can be mutually spliced to form by least two Intelligent assembly robots to complete the production of product, or is mutually interted with demand by least two Intelligent assembly robots and several workers cooperatively form semi-automatic production line to complete the production of product according to the actual situation, and each Intelligent assembly robot only completes a process, it can be replaced and debug for different products easily, can not flexibly it switch to solve manual production in production line operation with automated production, the problem of single variety product can only be produced.

Description

Modularization assembly line and its construction method
Technical field
The invention belongs to the technical fields of assembly line, are to be related to a kind of modularization assembly line and its building more specifically Method.
Background technique
Pipelining mode is widely applied a kind of production operation mode on present industrial, because it can allow each Production unit is only absorbed in a certain process of processing, greatly improves working efficiency and yield.But existing flow line production In technology, a certain product enters industrialized mass production, be not it is stranghtforward, usually product producing initial stage use Simple transmission assembly line carries out manual or semi-automatic production, and as each process scheduling and planning is completed, then is gradually introducing Automation equipment, it is final to realize full-automatic flow line production.It results in existing in existing pipelining in this way and ask as follows Topic: one, the connection problem of manual production and automated production, when a certain process not yet has automated production condition or a certain Process automation equipment breaks down, it is difficult to flexibly switch manual production, can only completely stop production, cause very big economic loss;Two, The product variety of flow line production is single, and existing full-automation assembly line is usually to carry out specific aim according to product produced Design, when product produced is replaced, needs to improve assembly line again, virtually improve production cost, reduce Production efficiency.
Summary of the invention
The purpose of the present invention is to provide a kind of modularization assembly line and its construction methods, to solve in the prior art, stream Manual production can not flexibly switch with automated production in waterline production operation, the technology that can only produce single variety product is asked Topic.
To achieve the goals above, the technical solution adopted by the present invention is that: provide a kind of modularization assembly line, including can It at least two Intelligent assembly robots that mutually splice and circulates at least for containing blank in the Intelligent assembly robot One jig;The Intelligent assembly robot includes for the control list according to preset computer program control process of producing product Member, the delivery unit for transporting the jig, the supply unit for storing and conveying accessory and for the blank into Row is processed and/or installs the accessory to the assembly unit in the blank, the delivery unit, the supply unit and institute Assembly unit is stated to be electrically connected with the control unit respectively.
Further, described control unit includes mainboard and human-computer interaction component, the human-computer interaction component, the transport Unit, the supply unit and the assembly unit are electrically connected with the mainboard respectively.
Further, the delivery unit includes conveyer belt and the first driving group for driving the conveyer belt to roll Part, adjacent two conveyer belt can dock from beginning to end, and first driving assembly is electrically connected with the mainboard.
Further, the delivery unit further includes set on the conveyer belt side for positioning the positioning of the jig Component, the positioning component are electrically connected with the mainboard.
Further, the supply unit include expect frame, be connected to for material position and with the material frame be used for will deposit in institute The accessory stated in material frame is delivered to second driving assembly for material position, and second driving assembly is electrically connected with the mainboard It connects.
Further, the assembly unit includes the first guide rail for being fixedly arranged on the conveyer belt top side, is vertically connected at institute State the second guide rail of the first guide rail top side, be movably connected on second guide rail for the blank carry out processing and/ Or by the accessory install in the blank mechanical hand, be used to second guide rail be driven to slide along first guide rail Third driving assembly and for drive the mechanical hand go up and down and along second guide rail sliding the 4th driving assembly, it is described Plane is parallel with plane where the conveyer belt where plane, second guide rail where first guide rail, the third driving group Part, the 4th driving assembly are electrically connected with the mainboard.
Further, multiple locating slots arranged at equal interval in length and breadth are offered on the jig.
Further, the Intelligent assembly robot further includes cabinet, the mainboard, the supply unit and the assembly Unit is installed in the cabinet, and the conveyer belt is through the cabinet and its opposite end stretches out in outside the cabinet, institute State the outside that human-computer interaction component is movably connected on the cabinet.
Further, the Intelligent assembly robot further includes at least three-wheel group for being movably connected on the cabinet bottom side.
The beneficial effect of modularization assembly line provided by the invention is: matching using Intelligent assembly robot with jig It closes, can mutually be spliced to form full-automatic production line by least two Intelligent assembly robots to complete the life of product It produces, or cooperatively forms half by the way that at least two Intelligent assembly robots and several workers are mutually interspersed with demand according to the actual situation Automation production flow line completes the production of product, and each Intelligent assembly robot only completes a process, can be easily Ground is replaced and is debugged for different product, to efficiently solve in production line operation manual production and automatic Metaplasia production can not flexibly switch, can only produce the technical issues of single variety product, greatly increase the spirit of flow line production Activity reduces the repacking cost of flow line production multiple product.
The present invention also provides a kind of modularization assembly line construction methods, include the following steps:
S01, the manufacturing process according to product are determined needed for the process for producing the product, and the corresponding process Blank and accessory;
S02, compatible jig therewith is processed according to the outer profile of the blank;
S03, compatible supply unit and assembly unit therewith are processed according to the outer profile of the process and the accessory;
S04, the Intelligent assembly robot for completing different processes is assembled using the supply unit and the assembly unit;
S05, according to the production process of the product, at least sequentially will be connected into modularization flowing water by two Intelligent assembly robots Line.
The beneficial effect of modularization assembly line construction method provided by the invention is: completing different works by least two The Intelligent assembly machine person series of sequence are formed, and each Intelligent assembly robot only completes a process, need to only adjust supply The structure of unit and assembly unit can be replaced and debug for different products easily, to efficiently solve Manual production can not flexibly switch with automated production in production line operation, the technology that can only produce single variety product is asked Topic, greatly increases the flexibility of flow line production, reduces the repacking cost of flow line production multiple product.
Detailed description of the invention
It to describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior art Needed in attached drawing be briefly described, it should be apparent that, the accompanying drawings in the following description is only of the invention some Embodiment for those of ordinary skill in the art without any creative labor, can also be according to these Attached drawing obtains other attached drawings.
Fig. 1 is the stereoscopic schematic diagram of modularization assembly line provided in an embodiment of the present invention;
Fig. 2 is the stereoscopic schematic diagram of Intelligent assembly robot provided in an embodiment of the present invention;
Fig. 3 is the stereoscopic schematic diagram of members in Intelligent assembly robot provided in an embodiment of the present invention;
Fig. 4 is the stereoscopic schematic diagram of jig in modularization assembly line provided in an embodiment of the present invention;
Fig. 5 is the flow chart of modularization assembly line construction method provided in an embodiment of the present invention;
Fig. 6 is the stereoscopic schematic diagram of isolator provided in an embodiment of the present invention;
Fig. 7 is the exploded perspective schematic diagram of isolator provided in an embodiment of the present invention.
Wherein, each appended drawing reference in figure:
1-modularization assembly line, 10-Intelligent assembly robots, 20-jigs, 12-delivery units, 13-supplies are single Member, 14-assembly units, 15-cabinets, 16-wheel groups, 17-indicator lights, 111-human-computer interaction components, 121-conveyer belts, 122-the first driving assembly, 123-positioning components, 131-material framves, 132-are for material position, the 133-the second driving assembly, 141- First guide rail, the 142-the second guide rail, 143-mechanical hands, 144-third driving assemblies, the 145-the four driving assembly, 146- 5th driving assembly, the 141-the first guide rail, 151-shields, 152-cabinet doors, 200-locating slots, 1231-position sensings Device, 1232-normal valves, 1430-suction nozzles, 2-isolators, 2a-pedestal, 2b-resistance, the first magnet of 2c-, 2d-first Magnetic conduction sheet, the first ferrite of 2e-, 2f-conductor, the second ferrite of 2g-, the second magnetic conduction sheet of 2h-, the second magnet of 2i-, 2j-compensating plate, 2k-lid.
Specific embodiment
In order to which technical problems, technical solutions and advantages to be solved are more clearly understood, tie below Accompanying drawings and embodiments are closed, the present invention will be described in further detail.It should be appreciated that specific embodiment described herein is only To explain the present invention, it is not intended to limit the present invention.
It should be noted that it can be directly another when element is referred to as " being fixed on " or " being set to " another element On one element or indirectly on another element.When an element is known as " being connected to " another element, it can To be directly to another element or be indirectly connected on another element.
It is to be appreciated that term " length ", " width ", "upper", "lower", "front", "rear", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "top", "bottom" "inner", "outside" is that orientation based on the figure or position are closed System, is merely for convenience of description of the present invention and simplification of the description, rather than the device or element of indication or suggestion meaning must have Specific orientation is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Implicitly include one or more of the features.In the description of the present invention, the meaning of " plurality " is two or more, Unless otherwise specifically defined.
Fig. 1 and Fig. 2 are please referred to, now modularization assembly line provided by the invention is illustrated.The modularization assembly line 1 packet Include at least two Intelligent assembly robots 10 and at least one jig 20, wherein at least two Intelligent assembly robots 10 can phase It is mutually spliced to form a full-automatic production line, can also mutually intert with several workers and cooperatively form a semi-automatic metaplasia Assembly line is produced, jig 20 circulates in Intelligent assembly robot 10 for containing blank, until blank adding by different processes Final product is formed after work and assembly;Herein, Intelligent assembly robot 10 includes control unit, delivery unit 12, supply list Member 13 and assembly unit 14, the control unit are used for the production process according to preset computer program control product, transport Unit 12 is used for transportation jig 20, and supply unit 13 is for storing and conveying accessory, and assembly unit 14 is for adding blank Work and/or accessory is installed to blank, delivery unit 12, supply unit 13 and assembly unit 14 are electrically connected with control unit respectively It connects.It is to be understood that job requirements of the Intelligent assembly robot 10 according to different processes, need the confession to different processes are completed The structure and shape for answering unit 13 and assembly unit 14 adjust accordingly, however since control unit only need to be to the program of loading It is adjusted, delivery unit 12 need to only cooperate with jig 20, therefore no matter all not need to control unit under any one process It is adjusted with the structure and shape of delivery unit 12;Assembly unit 14 can be individually to blank according to the job requirements of different processes It is processed, such as: gluing, spot welding or polishing, or individually complete for the accessory that supply unit 13 provides to be mounted in blank, or Person is completed at the same time the processing to blank and assembles accessory and blank.
Modularization assembly line 1 provided by the invention, compared with prior art, beneficial effect is: using Intelligent assembly Robot 10 and jig 20 cooperate, and full-automatic production stream can be mutually spliced to form by least two Intelligent assembly robots 10 Waterline is to complete the production of product, or passes through at least two Intelligent assembly robots 10 and several works with demand according to the actual situation People is mutually interspersed to cooperatively form semi-automatic production line to complete the production of product, and each Intelligent assembly robot 10 A process is only completed, can be replaced and debug for different products easily, so that it is raw to efficiently solve assembly line Producing manual production and automated production in operation can not flexibly switch, can only produce the technical issues of single variety product, significantly Ground improves the flexibility of flow line production, reduces the repacking cost of flow line production multiple product.
Further, referring to Fig. 2, a kind of specific embodiment as modularization assembly line provided by the invention, on Stating control unit includes mainboard (not shown) and human-computer interaction component 111, human-computer interaction component 111, above-mentioned delivery unit 12, on It states supply unit 13 and above-mentioned assembly unit 14 is electrically connected with mainboard respectively.Specifically, mainboard is to be integrated with central processing unit Main control board, human-computer interaction component 111 include display, control button etc. for for technical staff input computer program and Understand the operating condition of assembly line.
Further, referring to Fig. 3, a kind of specific embodiment as modularization assembly line provided by the invention, on Stating delivery unit 12 includes conveyer belt 121 and the first driving assembly 122, wherein and adjacent two conveyer belts 121 can dock from beginning to end, I.e. in modularization assembly line 1, adjacent Liang Ge Intelligent assembly robot 10 can be by respective 121 head and the tail of conveyer belt to fetching Mutually splicing is completed, the assembling of assembly line can be completed without in addition configuration conveyer belt in this way, to improve assembling modularization The efficiency of assembly line 1;First driving assembly 122 for drive conveyer belt 121 roll, and the first driving assembly 122 with it is above-mentioned Mainboard electrical connection.Specifically, the first driving assembly 122 includes the first driving motor, drive roll and driven roller etc., and first Driving motor is electrically connected with mainboard, and the first driving motor is sequentially connected by its drive shaft and drive roll, drive roll, Driven roller and conveyer belt 121 are sequentially connected;When work, central processing unit starts the first driving motor, and the first driving motor drives Rotate drive roll, drive roll causes the rolling of conveyer belt 121 and driven roller rotation, and conveyer belt 121 drives above-mentioned jig 20 move forward.Certainly, according to the actual situation and demand, in other embodiments of the invention, the first driving assembly 122 may be used also Including other components, do not limit uniquely herein.
Further, referring to Fig. 3, a kind of specific embodiment as modularization assembly line provided by the invention, on Stating delivery unit 12 further includes positioning component 123, and the side of said conveyer belt 121 is arranged in positioning component 123, for positioning Jig 20 is stated, and positioning component 123 is electrically connected with above-mentioned mainboard.Specifically, positioning component 123 includes position sensor 1231 With normal valve 1232, wherein position sensor 1231 includes towards the inductive head of conveyer belt 121, and normal valve 1232 includes valve body With the scalable positioning door bolt for being connected to valve body, positioning door bolt can be electromagnetic drive, hydraulic-driven or air pressure driving, in jig 20 The location hole with positioning door bolt cooperation is offered on side wall;When jig 20 is transported to assembly station by conveyer belt 121, inductive head inspection Measure jig 20, the location information of jig 20 is fed back to above-mentioned central processing unit by position sensor 1231, central processing unit to First driving assembly 122 issues instruction out of service, and starts normal valve 1232, and positioning door bolt is popped up and stretched by normal valve 1232 Enter the positioning hole of jig 20, so that jig 20 is located on the assembly station of conveyer belt 121, so, it is therefore prevented that jig 20 exists It is subjected to displacement in blank processing assembling process, ensure that going on smoothly for assembly process.Certainly, according to the actual situation and demand, In other embodiments of the invention, positioning component 123 may also include other components, not limit uniquely herein.
Further, referring to Fig. 3, a kind of specific embodiment as modularization assembly line provided by the invention, on Stating supply unit 13 includes material frame 131, for material position 132 and the second driving assembly 133, wherein the second driving assembly 133 and material Frame 131 is connected to, and the accessory for that will be stored in material frame 131 is delivered to for material position 132, and the second driving assembly 133 with Above-mentioned mainboard electrical connection.Specifically, material frame 131 includes pedestal, is offered on pedestal for material position 132, the second driving assembly 133 packet Cylinder and push rod are included, cylinder is fastenedly connected with pedestal, and push rod is connect with cylinder-driven, and push rod can will expect that stores in frame 131 matches Part is pushed to one by one in material position 132.Certainly, according to the actual situation and demand, in other embodiments of the invention, second drive Dynamic component 133 may also include other components, not limit uniquely herein.
Further, referring to Fig. 3, a kind of specific embodiment as modularization assembly line provided by the invention, on Stating assembly unit 14 includes the first guide rail 141, the second guide rail 142, mechanical hand 143, third driving assembly 144 and the 4th driving Component 145, wherein the first guide rail 141 is fixed at the top side of said conveyer belt 121, and the second guide rail 142 is vertically connected on The top side of one guide rail 141, mechanical hand 143 are movably connected on the second guide rail 142, for above-mentioned blank carry out processing and/or Above-mentioned accessory is installed to blank, third driving assembly 144 for driving the second guide rail 142 to slide along the first guide rail 141, the Four driving assemblies 145 are for driving mechanical hand 143 to go up and down and slide along the second guide rail 142;Herein, it is put down where the first guide rail 141 Face, 142 place plane of the second guide rail are parallel with 121 place plane of conveyer belt, third driving assembly 144, the 4th driving assembly 145 It is electrically connected with above-mentioned mainboard.Specifically, the first guide rail 141, the second guide rail 142 and conveyer belt 121 are horizontal positioned;Manipulator 143 Be detachably connected a variety of external members, by replace the different achievable crawl accessory of external member, discharge accessory, injecting glue, spot welding, polishing, The multiple functions such as dedusting or polishing;Third driving assembly 144 includes the second driving motor, the first drive screw and the first sliding block Deng, the second driving motor is electrically connected with mainboard, and the first drive screw is sequentially connected with the second driving motor and the first sliding block respectively, First sliding block connects the first guide rail 141 and the second guide rail 142;4th driving assembly 145 includes third driving motor, the 4th driving Motor, the second drive screw, third drive screw, the second sliding block and third sliding block etc., third driving motor, the 4th driving electricity Machine is electrically connected with mainboard, and the second drive screw is sequentially connected with third driving motor and the second sliding block respectively, third drive screw It is sequentially connected respectively with the 4th driving motor and third sliding block, the second sliding block connects the second guide rail 142 and third sliding block, and third is sliding Block is fastenedly connected with mechanical hand 143;When work, when central processing unit starts the second driving motor, the second driving motor passes through First drive screw drives the first sliding block to slide along the first guide rail 141, and the first sliding block drives the second guide rail 142 along the first guide rail 141 slidings, when central processing unit starts third driving motor, third driving motor drives second to slide by the second drive screw Block is slided along the second guide rail 142, and the second sliding block drives third sliding block and mechanical hand 143 to slide along the second guide rail 142, works as centre When managing device four driving motor of starting, the 4th driving motor drives third sliding block along the perpendicular of the second sliding block by third drive screw Histogram is to lifting, and third sliding block drives mechanical hand 143 to go up and down along the vertical direction of the second sliding block, in this way in third driving assembly 144 and 145 coordinated of the 4th driving assembly under mechanical hand 143 can realize the movement in three dimensions.Certainly, according to practical feelings Condition and demand, in other embodiments of the invention, third driving assembly 144 and the 4th driving assembly 145 may also include other Components do not limit uniquely herein.
Further, referring to Fig. 3, a kind of specific embodiment as modularization assembly line provided by the invention, Suction nozzle 1430 is removably connected on above-mentioned mechanical hand 143, suction nozzle 1430 is for being adapted to above-mentioned accessory, the i.e. end face of suction nozzle 1430 Profile is adapted with the outer profile of accessory, meanwhile, above-mentioned assembly unit 14 further includes vacuum pump (not shown) and the 5th driving group Part 146, wherein vacuum pump is connected to suction nozzle 1430, and the 5th driving assembly 146 is for driving suction nozzle 1430 to rotate, herein, vacuum Pump, the 5th driving assembly 146 are electrically connected with above-mentioned mainboard.Specifically, several suction holes, vacuum pump are offered on suction nozzle 1430 It is connected to by tracheae with suction hole, the 5th driving assembly 146 includes the 5th driving motor etc., and the 5th driving motor is electrically connected with mainboard It connects, and the 5th driving motor is sequentially connected by its drive shaft and suction nozzle 1430;When needs are matched from above-mentioned for the absorption of material position 132 When part, central processing unit starting vacuum pump is vacuumized, and the outside of suction hole forms the end that accessory is adsorbed on suction nozzle 1430 by negative pressure On face, when needing to discharge accessory, central processing unit closes vacuum pump, eliminates the negative pressure on the outside of suction hole, accessory is from recast It is fallen under in above-mentioned blank, when needing for accessory to be tightened in blank, central processing unit the 5th driving motor of starting, the 5th The accessory that driving motor drives suction nozzle 1430 and is adsorbed on suction nozzle 1430 rotates together, and then accessory is screwed in what accessory was specified In installation site.Certainly, according to the actual situation and demand, in other embodiments of the invention, the 5th driving assembly 146 may be used also Including other components, do not limit uniquely herein.
Further, referring to Fig. 4, a kind of specific embodiment as modularization assembly line provided by the invention, Multiple locating slots 200 are offered on above-mentioned jig 20, multiple locating slots 200 are equally spaced arranged along longitudinal and transverse two directions.Specifically Ground, the Internal periphery of locating slot 200 are adapted with the outer profile of above-mentioned blank, can contain multiple blank on each jig 20, and every A modularization assembly line 1 may include again multiple jigs 20, and such jig 20 circulates and can once produce multiple products, Duo Gezhi Tool 20 cooperates one by one with multiple Intelligent assembly robots 10, it is ensured that the production capacity of each Intelligent assembly robot 10 obtains abundant benefit With to greatly increase the production efficiency of modularization assembly line 1.
Further, referring to Fig. 2, a kind of specific embodiment as modularization assembly line provided by the invention, on Stating Intelligent assembly robot 10 further includes cabinet 15, and above-mentioned mainboard, above-mentioned supply unit 13 and above-mentioned assembly unit 14 are mounted on In cabinet 15, said conveyer belt 121 runs through cabinet 15, and the opposite end of conveyer belt 121 stretches out outside cabinet 15, above-mentioned man-machine Interactive component 111 is movably connected in the outside of cabinet 11.Specifically, mainboard, supply unit 13, assembly unit 14 and conveyer belt 121 middle parts are accommodated in cabinet 15, be ensure that the safety of Product Assembly process, are avoided extraneous factor to Product Assembly process Interference, meanwhile, human-computer interaction component 111 is hinged by the shell of display or connecting rod and cabinet 15, so that human-computer interaction circle Face is adjustable to suitable angle and manipulates for technical staff, improves the usage experience effect of technical staff.
Preferably, the top of cabinet 15 is provided with indicator light 17, for prompting the operation shape of Intelligent assembly robot 10 State improves the safety of production process.
Preferably, cabinet 15 includes shield 151, and shield 15 is located at supply unit 13, assembly unit 14 and conveying Outside with 121 middle parts, can be by the exposure of the middle part of supply unit 13, assembly unit 14 and conveyer belt 121 when shield 15 is opened Out, facilitate worker added into supply unit 13 accessory and technical staff to supply unit 13 and assembly unit 14 carry out dimension support And replacement.
Preferably, cabinet 15 further includes cabinet door 152, and mainboard and connection cables can be exposed when opening for cabinet door 152, side Just technical staff's wiring and to mainboard carry out dimension support and replacement.
Further, referring to Fig. 2, a kind of specific embodiment as modularization assembly line provided by the invention, on Stating Intelligent assembly robot 10 further includes at least three wheel groups 16, and wheel group 16 is movably connected in the bottom side of above-mentioned cabinet 15.Specifically Ground, at least three wheel groups 16 are evenly distributed in the outer side bottom surface of cabinet 15, are used to support cabinet 15 and facilitate Intelligent assembly machine Device people 10 is mobile, improves the flexibility and efficiency of the assembling of modularization assembly line 1.
Fig. 1 to Fig. 7 is please referred to, now modularization assembly line construction method provided by the invention is illustrated.The modularization Assembly line construction method includes the following steps:
S01, the manufacturing process according to product, blank needed for determining the process for producing the product, and the corresponding process And accessory;
S02, compatible jig 20 therewith is processed according to the outer profile of the blank;
S03, compatible supply unit 13 and assembly unit 14 therewith are processed according to the outer profile of the process and the accessory;
S04, the Intelligent assembly robot 10 for completing different processes is assembled using supply unit 13 and assembly unit 14;
At least two Intelligent assembly robots 10 are sequentially connected into modularization flowing water by S05, the production process according to product Line 1.
In order to facilitate a better understanding of modularization assembly line construction method provided by the invention, now by taking isolator 2 as an example into Row explanation: first passing through the analysis to 2 manufacturing process of isolator, determines that production isolator 2 needs successively by smearing soldering paste, putting Resistance, resistance burn-back put the first magnet, put the first magnetic conduction sheet, put the first ferrite, put conductor, put the second iron Oxysome puts the second magnetic conduction sheet, puts the second magnet, putting compensating plate and 12 procedure of spiral cover, corresponding 12 procedure Need pedestal 2a, resistance 2b, the first magnet 2c, the first magnetic conduction sheet 2d, the first ferrite 2e, conductor 2f, the second ferrite 2g, Two magnetic conduction sheet 2h, the second magnet 2i, compensating plate 2j and lid 2k;Then according to the outer profile processing jig 20 of pedestal 2a, that is, exist Multiple locating slots 200 compatible with the outer profile of pedestal 2a are opened up on jig 20, meanwhile, according to 12 procedure and resistance 2b, the first magnet 2c, the first magnetic conduction sheet 2d, the first ferrite 2e, conductor 2f, the second ferrite 2g, the second magnetic conduction sheet 2h, second The outer profile of magnet 2i, compensating plate 2j and lid 2k, adjustment expect frame 131 and/or for material position 132 and/or the second driving assemblies 133 Structure and mechanical hand 143 external member, adapt to 12 procedure and resistance 2b, the first magnet 2c, first to process Magnetic conduction sheet 2d, the first ferrite 2e, conductor 2f, the second ferrite 2g, the second magnetic conduction sheet 2h, the second magnet 2i, compensating plate 2j and 12 supply unit 13 and 12 assembly units 14 of the outer profile of lid 2k, then by 12 of identical planform 12 supply units 12 of control unit and identical planform are filled with 12 supply units 13 and this 12 respectively 12 Intelligent assembly robots 10 that 12 achievable 12 procedures are made are assembled with unit 14, then by 12 According to the precedence of 12 procedure, by conveyer belt 121, head and the tail are docked two-by-two for Intelligent assembly robot 10, are connected into life Produce the modularization assembly line 1 of isolator 2;When producing isolator 2,12 jigs 20 of pedestal 2a will be filled with seriatim from completion Smear soldering paste Intelligent assembly robot 10 conveyer belt 121 one end be sent into modularization assembly line 1 in, until last worker by The jig 20 for filling with isolator 2 is taken out from the other end of the conveyer belt 121 for the Intelligent assembly robot 10 for completing spiral cover in one ground.
Modularization assembly line construction method provided by the invention, compared with prior art, beneficial effect is: by least Two Intelligent assembly robots 10 for completing different processes connect and are formed, and each Intelligent assembly robot 10 only completes one Process need to only adjust the structure of supply unit 13 and assembly unit 14, can be replaced easily for different products and Debugging, thus efficiently solve manual production and automated production in production line operation can not flexibly switch, Zhi Nengsheng The technical issues of producing single variety product, greatly increases the flexibility of flow line production, it is a variety of to reduce flow line production The repacking cost of product.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (10)

1. modularization assembly line, which is characterized in that including at least two Intelligent assembly robots that can mutually splice and for containing Blank is in at least jig to circulate in the Intelligent assembly robot;The Intelligent assembly robot includes for according to default The computer program control control unit of process of producing product, the delivery unit for transporting the jig, for storing and Convey the supply unit of accessory and for carrying out processing to the blank and/or installing the accessory to the blank Assembly unit, the delivery unit, the supply unit and the assembly unit are electrically connected with the control unit respectively.
2. modularization assembly line as described in claim 1, which is characterized in that described control unit includes mainboard and human-computer interaction Component, the human-computer interaction component, the delivery unit, the supply unit and the assembly unit are electric with the mainboard respectively Connection.
3. modularization assembly line as claimed in claim 2, which is characterized in that the delivery unit includes conveyer belt and for driving The first driving assembly for rolling the conveyer belt, adjacent two conveyer belt can dock from beginning to end, first driving assembly with The mainboard electrical connection.
4. modularization assembly line as claimed in claim 3, which is characterized in that the delivery unit further includes being set to the conveying The positioning component for being used to position the jig with side, the positioning component are electrically connected with the mainboard.
5. modularization assembly line as claimed in claim 4, which is characterized in that the supply unit include material frame, for material position and What is be connected to the material frame is used to the accessory deposited in the material frame being delivered to second driving assembly for material position, institute The second driving assembly is stated to be electrically connected with the mainboard.
6. modularization assembly line as claimed in claim 4, which is characterized in that the assembly unit includes being fixedly arranged on the conveying The first guide rail with top side, is movably connected on second guide rail at the second guide rail for being vertically connected at first guide rail top side On for the blank carry out processing and/or by the accessory install in the blank mechanical hand, be used to drive institute State third driving assembly that the second guide rail is slided along first guide rail and for driving the mechanical hand to go up and down and along described the 4th driving assembly of two guide rails sliding, plane and the conveying where plane, second guide rail where first guide rail Band place plane is parallel, and the third driving assembly, the 4th driving assembly are electrically connected with the mainboard.
7. such as the described in any item modularization assembly lines of claim 3 to 6, which is characterized in that offered in length and breadth on the jig Multiple locating slots arranged at equal interval.
8. modularization assembly line as claimed in claim 7, which is characterized in that the Intelligent assembly robot further includes cabinet, The mainboard, the supply unit and the assembly unit are installed in the cabinet, and the conveyer belt is through the cabinet And its opposite end stretches out in outside the cabinet, the human-computer interaction component is movably connected on the outside of the cabinet.
9. modularization assembly line as claimed in claim 8, which is characterized in that the Intelligent assembly robot further includes that activity connects It is connected at least three-wheel group of the cabinet bottom side.
10. modularization assembly line construction method, which comprises the steps of:
S01, the manufacturing process according to product, blank needed for determining the process for producing the product, and the corresponding process And accessory;
S02, compatible jig therewith is processed according to the outer profile of the blank;
S03, compatible supply unit and assembly unit therewith are processed according to the outer profile of the process and the accessory;
S04, the Intelligent assembly robot for completing different processes is assembled using the supply unit and the assembly unit;
S05, according to the production process of the product, at least sequentially will be connected into modularization assembly line by two Intelligent assembly robots.
CN201810873659.6A 2018-08-02 2018-08-02 Modularization assembly line and its construction method Pending CN109292417A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810873659.6A CN109292417A (en) 2018-08-02 2018-08-02 Modularization assembly line and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810873659.6A CN109292417A (en) 2018-08-02 2018-08-02 Modularization assembly line and its construction method

Publications (1)

Publication Number Publication Date
CN109292417A true CN109292417A (en) 2019-02-01

Family

ID=65172453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810873659.6A Pending CN109292417A (en) 2018-08-02 2018-08-02 Modularization assembly line and its construction method

Country Status (1)

Country Link
CN (1) CN109292417A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113084513A (en) * 2021-03-29 2021-07-09 东莞湧德电子科技有限公司 Elastic production method capable of replacing oil bin

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002326127A (en) * 2001-04-26 2002-11-12 Fuji Photo Film Co Ltd Part carrying pallet
CN201882579U (en) * 2010-12-02 2011-06-29 惠州市数码特信息电子有限公司 Connection platform capable of storing material temporarily and double-layer automatic delivery line with connection platform
CN202010619U (en) * 2011-03-16 2011-10-19 深圳市恒力天科技有限公司 Automatic adhesive dispenser
CN102773199A (en) * 2012-07-20 2012-11-14 昆山迈致治具科技有限公司 Automatic dispensing machine
CN103803272A (en) * 2014-03-07 2014-05-21 苏州博众精工科技有限公司 Full-automatic assembly line mechanism
CN203938152U (en) * 2014-03-17 2014-11-12 厦门奥维丝精密机械有限公司 A kind of conveyor line precise mobile platform delivery system
CN204221349U (en) * 2014-09-03 2015-03-25 深圳通达电子有限公司 A kind of flexible production line for automatically assembling body
CN105173596A (en) * 2015-09-11 2015-12-23 深圳市宝尔威精密机械有限公司 Unit line body structure of modularized intelligent assembly line
CN205158095U (en) * 2015-10-20 2016-04-13 深圳市欧盛自动化有限公司 Carrier assembly line automatic system
CN205387346U (en) * 2016-02-22 2016-07-20 荣旗工业科技(苏州)有限公司 Assembly line module
CN207129604U (en) * 2017-09-12 2018-03-23 厦门攸信信息技术有限公司 A kind of station tool circulating conveyor of streamline
CN207297541U (en) * 2017-08-01 2018-05-01 东莞市大研自动化设备有限公司 A kind of assembling spot gluing equipment of VCM motor coil and shrapnel
CN207366650U (en) * 2017-08-18 2018-05-15 深圳市艾特讯科技有限公司 A kind of automatic test device
CN207536675U (en) * 2017-01-18 2018-06-26 东莞路点智能技术有限公司 A kind of swinging assembly line

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002326127A (en) * 2001-04-26 2002-11-12 Fuji Photo Film Co Ltd Part carrying pallet
CN201882579U (en) * 2010-12-02 2011-06-29 惠州市数码特信息电子有限公司 Connection platform capable of storing material temporarily and double-layer automatic delivery line with connection platform
CN202010619U (en) * 2011-03-16 2011-10-19 深圳市恒力天科技有限公司 Automatic adhesive dispenser
CN102773199A (en) * 2012-07-20 2012-11-14 昆山迈致治具科技有限公司 Automatic dispensing machine
CN103803272A (en) * 2014-03-07 2014-05-21 苏州博众精工科技有限公司 Full-automatic assembly line mechanism
CN203938152U (en) * 2014-03-17 2014-11-12 厦门奥维丝精密机械有限公司 A kind of conveyor line precise mobile platform delivery system
CN204221349U (en) * 2014-09-03 2015-03-25 深圳通达电子有限公司 A kind of flexible production line for automatically assembling body
CN105173596A (en) * 2015-09-11 2015-12-23 深圳市宝尔威精密机械有限公司 Unit line body structure of modularized intelligent assembly line
CN205158095U (en) * 2015-10-20 2016-04-13 深圳市欧盛自动化有限公司 Carrier assembly line automatic system
CN205387346U (en) * 2016-02-22 2016-07-20 荣旗工业科技(苏州)有限公司 Assembly line module
CN207536675U (en) * 2017-01-18 2018-06-26 东莞路点智能技术有限公司 A kind of swinging assembly line
CN207297541U (en) * 2017-08-01 2018-05-01 东莞市大研自动化设备有限公司 A kind of assembling spot gluing equipment of VCM motor coil and shrapnel
CN207366650U (en) * 2017-08-18 2018-05-15 深圳市艾特讯科技有限公司 A kind of automatic test device
CN207129604U (en) * 2017-09-12 2018-03-23 厦门攸信信息技术有限公司 A kind of station tool circulating conveyor of streamline

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113084513A (en) * 2021-03-29 2021-07-09 东莞湧德电子科技有限公司 Elastic production method capable of replacing oil bin

Similar Documents

Publication Publication Date Title
CN103337216B (en) A kind of machine photoelectricity gas-liquid integral flexible production comprehensive training system
CN104049198B (en) A kind of PCBA on-line Full unmanned testing system
CN103236219B (en) Linear multi-unit MPS automated logistics system
CN103056656B (en) Potentiometer mounting apparatus
CN204075438U (en) The automatic bonding equipment of a kind of piezo
CN209531308U (en) A kind of online automatic dispensing machine
CN109292417A (en) Modularization assembly line and its construction method
CN108500616A (en) A kind of full-automatic assembly system of acoustic control precision electric motor
CN210789992U (en) Novel workbench and flexible production line body
CN209267383U (en) A kind of small machine component automatic setup system
CN111725684A (en) Automatic equipment for flexible assembly of high-precision cylindrical electric connector
CN110270483A (en) Inductance glue spreader
CN113732723B (en) PC power supply automation line
CN205906707U (en) Module adsorption apparatus constructs and presss from both sides automatic plug -in components device of assembly line of getting mechanism
CN113305569B (en) Power supply fan assembling equipment
CN205437569U (en) Full -automatic electric welding machine people
CN109660080A (en) A kind of small machine component automatic setup system
CN109533961A (en) It is a kind of for testing the automatic feeding device of lithium battery protection board
CN205852226U (en) Module installed by screw, automatization's double track wire body produces module and production line
CN213255347U (en) Desktop spraying device for office equipment
CN209480728U (en) It is a kind of for testing the automatic feeding device of lithium battery protection board
CN209697337U (en) The online vision dispenser of SMT
CN207658620U (en) A kind of battery loading device
CN203205237U (en) Magnetic core assembling machine
CN208270831U (en) Automatic lock pays device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination