Summary of the invention
The purpose of the present invention is to provide the building hoistway form frame systems with material distributing machine, are applied with solving hoistway in the prior art
Work needs to occupy tower crane and repeatedly hangs the problem of switch puts material distributing machine, realizes the release tower crane working time, improves the mesh of construction efficiency
's.
The present invention is achieved through the following technical solutions:
Building hoistway form frame system with material distributing machine, the lattice frame operation layer including distribution above and below hoistway and several layers,
Platform is set between adjacent two layers lattice frame operation layer, and the lattice frame operation layer includes template operation layer, on template operation layer
The lattice frame operation layer of side is reinforcing bar operation layer, and the lattice frame operation layer below template operation layer is climb operation layer;Top layer
Reinforcing bar operation layer platform on fix cloth machine base, material distributing machine is installed on cloth machine base;It is set in the template operation layer
Falsework is set, the template of face hoistway inner wall is fixedly connected with outside falsework, fixation is moved back on the platform of template operation layer bottom
Mould crossbeam, it is described to move back on mould crossbeam setting and move back mode-gear, further include with it is described move back that mode-gear is meshed move back mould rack gear, it is described to move back
The long axis of mould rack gear moves back mould rack gear and is fixedly connected with falsework perpendicular to hoistway inner wall;It is set in the climb operation layer of top layer
Support rod is set, the top of the support rod is fixedly connected with the platform of template operation layer bottom surface, and the bottom end of the support rod passes through
Wall-attached supporting seat is detachably connected with hoistway inner wall, and creeping formwork mechanism is also set up on the support rod.
Aiming at the problem that construction of hoistway in the prior art needs to occupy tower crane and repeatedly hangs switch and put material distributing machine, the present invention is proposed
Building hoistway form frame system with material distributing machine, this system include the lattice frame operation layer that several layers are distributed up and down, adjacent two layers lattice
Platform is set between framework operation layer, places to stand with operating personnel for equipment and construct.Lattice frame operation layer has been divided into template
Operation layer, reinforcing bar operation layer, climb operation layer.Wherein template operation layer is located at intermediate position, for building structure molding, moves back mould
Operation;All lattice frame operation layers above template operation layer are reinforcing bar operation layer, for reinforcing bar binding operation;Template operation
All lattice frame operation layers of layer lower section are climb operation layer, are torn open for wall-attached supporting seat peace, system climb operation.Top layer
Cloth machine base is fixed on the platform of reinforcing bar operation layer, therefore cloth machine base is located at the top of all lattice frame operation layers,
Material distributing machine is installed on cloth machine base.Specifically, material distributing machine selects different model according to actual demands of engineering, it is directly installed on cloth
Expect on machine base, material distributing machine is integrated in this form frame system, is climbed with form frame system, and traditional construction mode is avoided to need repeatedly to account for
Switch is hung with tower crane and puts material distributing machine, effectively improves construction site tower crane utilization rate, improves construction efficiency.Setting in template operation layer
Falsework, falsework are fixedly connected with the template of face hoistway inner wall outside, and mould is moved back in fixation on the platform of template operation layer bottom
Crossbeam, it is described to move back on mould crossbeam setting and move back mode-gear, further include with it is described move back that mode-gear is meshed move back mould rack gear, it is described to move back mould
The long axis of rack gear moves back mould rack gear and is fixedly connected with falsework perpendicular to hoistway inner wall.Therefore mode-gear rotation is moved back by driving,
It moves linearly to which mould rack gear is moved back in drive toward or away from the direction of hoistway inner wall, moves back mould rack gear towards close to hoistway
The direction of inner wall is mobile, then realizes die closing operation, otherwise the direction for moving back mould rack gear away from hoistway inner wall is mobile, then realizes and move back
Modulo operation.The climb operation layer of top layer is first climb operation layer below template operation layer, and branch is arranged inside
The top of strut, support rod is fixedly connected with the platform of template operation layer bottom surface, and the bottom end of support rod passes through wall-attached supporting seat and well
Road inner wall is detachably connected, and creeping formwork mechanism is also set up on the support rod.To realize under conventional operating condition, pass through wall-attached supporting seat
There is provided lower support and firm by support rod, when needing to climb entire form frame system, dismantle wall-attached supporting seat and hoistway inner wall it
Between connection, by creeping formwork mechanism drive support rod uplink, thus push top template operation layer, reinforcing bar operation layer it is common on
It moves, realizes whole creeping formwork operation.Wherein creeping formwork mechanism uses creeping formwork mechanism in the prior art, and this will not be repeated here.
The present invention solves the problems, such as that hoistway construction needs to occupy tower crane and repeatedly hangs switch in the prior art and puts material distributing machine, so that material distributing machine
It is integrated in this form frame system, climbs with form frame system, traditional construction mode is avoided to need repeatedly to occupy tower crane and hang switch and put cloth
Material machine effectively improves construction site tower crane utilization rate, improves construction efficiency.
Further, the upright bar for connecting upper lower platform is respectively provided in all lattice frame operation layers, the platform includes mutual
Vertical transverse horizontal beam, vertical equity beam and the steel springboard above transverse horizontal beam, vertical equity beam;It is described vertical
Bar, transverse horizontal beam are bolted between vertical equity beam.The upper layer and lower layer platform of lattice frame operation layer in this programme
Between connected by upright bar, every layer of platform all includes orthogonal transverse horizontal beam, vertical equity beam and is located at lateral water
Steel springboard above flat-topped ridge, vertical equity beam, platform can customize different sizes according to actual demands of engineering, meet various sizes
Hoistway construction needs, and provides adequately operation for operating personnel and puts space to good use.
Preferably, the creeping formwork mechanism includes guide rail, connects hydraulic climbing device, the hydraulic climbing device energy on guide rail
Enough to move along guide rail, hydraulic climbing device is connect with support rod.
Preferably, the mould rack gear that moves back is fixedly connected with falsework by connector along one end of long axis direction, is another
End is connect with telescopic supporting rod, and the telescopic supporting rod is connect far from the one end for moving back mould rack gear with falsework.Pass through connector
So that falsework is directly with moving and being moved for mould rack gear is moved back, wherein without any driving member, compared to the prior art
The middle mode being driven using great number of driving mechanism can significantly improve molding, the efficiency for moving back mould, reduce unnecessary mill
Damage reduces installation difficulty.The both ends of telescopic supporting rod respectively with move back mould rack gear, falsework is connect, provide skewed horizontal load, simultaneously
So that the pulling force or thrust to template are more uniform, the success rate for significantly improving molding, moving back mould.
Preferably, catching device is set between the bottom end and following platform of the support rod.The present invention is improved by catching device
Work safety, reduce security risk.
Preferably, anti-dumping idler wheel, the anti-dumping idler wheel are also set up on the outside of the bottom platform of the climb operation layer of top layer
It is contacted with hoistway inner wall.During entire form frame system climbs, anti-dumping idler wheel is rolled in hoistway inner wall always, to protect always
It holds tangent with hoistway inner wall, can ensure that entire form frame system keeps flat with hoistway inner wall by two opposite anti-dumping idler wheels
Row, that is, guarantee the vertical of this form frame system, avoids that skew influence top operation occurs during climbing.
Compared with prior art, the present invention having the following advantages and benefits:
Building hoistway form frame system of the present invention with material distributing machine, template operation layer are located at intermediate position, are used for building structure
It molds, move back modulo operation;All lattice frame operation layers above template operation layer are reinforcing bar operation layer, for reinforcing bar binding behaviour
Make;All lattice frame operation layers below template operation layer are climb operation layer, for wall-attached supporting seat peace to be torn open, system is climbed behaviour
Make.Cloth machine base is fixed on the platform of the reinforcing bar operation layer of top layer, therefore cloth machine base is located at the operation of all lattice frames
The top of layer installs material distributing machine on cloth machine base.The present invention solves hoistway construction in the prior art and needs to occupy tower crane
The problem of switch puts material distributing machine repeatedly is hung, so that material distributing machine is integrated in this form frame system, climbs with form frame system, avoids tradition
Form of construction work, which needs repeatedly to occupy tower crane, hangs switch and puts material distributing machine, effectively improves construction site tower crane utilization rate, improves construction work
Effect.
Detailed description of the invention
Attached drawing described herein is used to provide to further understand the embodiment of the present invention, constitutes one of the application
Point, do not constitute the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is the elevational schematic view of the specific embodiment of the invention;
Fig. 2 is the partial enlarged view in Fig. 1 at A;
Fig. 3 is the elevation of the climb operation layer of top layer in the specific embodiment of the invention.
Label and corresponding parts title in attached drawing:
1- template operation layer, 2- reinforcing bar operation layer, 3- climb operation layer, 4- hoistway, 5- falsework, 6- template, 7- are moved back
Mould crossbeam, 8- move back mode-gear, and 9- moves back mould rack gear, 10- cloth machine base, 11- material distributing machine, 12- support rod, 13- wall-attached supporting seat,
14- upright bar, 15- guide rail, 16- connector, 17- hydraulic climbing device, 18- telescopic supporting rod, 19- transverse horizontal beam, 20- are longitudinal
Horizontal beam, 21- steel springboard, 22- catching device, 23- anti-dumping idler wheel.