CN105781101A - Truss type hydraulic entire steel platform climbing formwork - Google Patents

Truss type hydraulic entire steel platform climbing formwork Download PDF

Info

Publication number
CN105781101A
CN105781101A CN201610285775.7A CN201610285775A CN105781101A CN 105781101 A CN105781101 A CN 105781101A CN 201610285775 A CN201610285775 A CN 201610285775A CN 105781101 A CN105781101 A CN 105781101A
Authority
CN
China
Prior art keywords
vertical main
wall
formwork
main framework
truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610285775.7A
Other languages
Chinese (zh)
Inventor
刘建国
张永前
石丛林
刘太峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XINGHEREN CONSTRUCTION TECHNOLOGY Co Ltd BEIJING
Original Assignee
XINGHEREN CONSTRUCTION TECHNOLOGY Co Ltd BEIJING
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XINGHEREN CONSTRUCTION TECHNOLOGY Co Ltd BEIJING filed Critical XINGHEREN CONSTRUCTION TECHNOLOGY Co Ltd BEIJING
Priority to CN201610285775.7A priority Critical patent/CN105781101A/en
Publication of CN105781101A publication Critical patent/CN105781101A/en
Pending legal-status Critical Current

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28—Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention relates to the technical field of building equipment, and discloses a truss type hydraulic entire steel platform climbing formwork, which comprises a vertical main frame, a wall-attaching device, a track, anti-dropping climbers, a horizontal formwork-pushing mechanism and a formwork; the wall-attaching device is connected with a preburied wall part, and the vertical main frame is hung on the wall-attaching device, and is detachably connected with the wall-attaching device through an unloading pin and a safety pin; the track is connected with the vertical main frame, and is detachably connected with the wall-attaching device, and the vertical main frame can slide up and down along the track; the anti-dropping climbers are fixed on the vertical main frame, and the anti-dropping climbers are driven by a climbing hydraulic cylinder to drive the entire vertical main frame to climb; the direction of an operating handle can be changed to drive the vertical main frame and the track to climb alternately; the horizontal formwork-pushing mechanism is fixed on a cross beam of the vertical main frame, and the formwork is fixed at the front end of the horizontal formwork-pushing mechanism. The invention adopts an integrated design, all the components can be produced in the factory, the equipment degree is high, climbing and all formwork dismounting and mounting operations adopt hydraulic power, the truss type hydraulic entire steel platform climbing formwork is easy to operate, and action is visual.

Description

A kind of truss-like hydraulic pressure integral steel platform jumping formwork
Technical field
The present invention relates to Architectural Equipment technical field, particularly to a kind of truss-like hydraulic pressure integral steel platform jumping formwork.
Background technology
In the Core Walls Structure work progress of Steel-concrete Composite system high-rise building, traditional construction method is usually Core Walls Structure one-piece casting, but for the high-rise building that some monolayer area are bigger, Core Walls Structure monolayer area is also relatively large, core-tube partial construction still adopts the construction method of this traditional one-piece casting, require that the labour force of each work post of input is just very big, labour force and resource distribution are uneven, and construction period is also long, the control of duration and cost is all unfavorable.
For solving the problem that Core Walls Structure one-piece casting brings, some construction of super highrise building sides attempt Core Walls Structure bigger for monolayer area is divided construction section, change cross construction into, so can save construction cost, balance resource distribution, shortens construction period simultaneously, but the division of construction section also brings a series of problem, after dividing such as construction section, in the construction of jumping formwork, the setting of operation at top integral steel platform, concreting process, the placement location etc. of material distributing machine all becomes comparatively difficulty.
Summary of the invention
The purpose of the present invention overcomes the deficiencies in the prior art exactly, it is provided that a kind of truss-like hydraulic pressure integral steel platform jumping formwork, including vertical main framework, wall-attaching equipment, guide rail, anti-fall climbing device, horizontal former pushing mechanism, template;
Described wall-attaching equipment is fixing with wall body built-in fitting to be connected, and described vertical main framework is suspended in described wall-attaching equipment by hook, and is removably connected by off-load bearing pin and safety plug and described wall-attaching equipment;
Described guide rail is connected with described vertical main framework, and removably connects with described wall-attaching equipment, and described vertical main framework can slide up and down along described guide rail;
Described anti-fall climbing device is fixed on described vertical main framework, including the hydraulic cylinder that climbs, hydraulic oil pump, operation handle, described in the anti-fall climbing device that climbs described in Driven by Hydraulic Cylinder drive described vertical main framework entirety to climb;Change described operation handle orientations to realize described vertical main framework and described guide rail and alternately climb;
Described horizontal former pushing mechanism is fixed on described vertical main framework crossbeam, and described template is fixed on described horizontal former pushing mechanism front end, and described horizontal former pushing mechanism realizes matched moulds or form removal by pushing away mould hydraulic cylinder.
Further, described vertical main framework includes crossbeam, column, diagonal brace, outer vertical rod, upper frame, lower suspension bracket, hook, crown wall assembly, connects each through bearing pin or bolt;Several described vertical main frameworks are connected as entirety by connecting cross beam.
Further, described wall-attaching equipment includes attached wall plate, guide holder, installs bolt, off-load bearing pin, safety plug;By installing, bolt and body of wall are fixing to be connected described attached wall plate, and described guide holder mounts in described attached wall plate, and described guide holder is fixed spacing by described safety plug.
Further, described horizontal former pushing mechanism includes pushing away mould track, pushes away mould coaster, model sheetinstallat vertical beam, regulates pole, push away mould hydraulic cylinder mounting seat;Described push away mould hydraulic cylinder be installed on described in push away mould hydraulic cylinder mounting seat.
Further, described vertical main framework alien invasion is provided with shoulder guard net.
The invention have the benefit that
(1) structural system adopts the arrangement of vertically and horizontally truss, and monolithic truss assembling is convenient and swift, solves large span and requires that component specification is big, processing and the big problem of site operation difficulty;
(2) the vertically and horizontally interlaced layout of truss, arranging upper, middle and lower three layers altogether along support body short transverse, arrange different cross section and the truss of height according to the loading characteristic of every layer, all connection nodes all adopt gusset plate and bolt to connect, forming integral steel platform area big, intensity is high;
(3) construction flowing water fragment position support body does not carry out burst according to the division of structure construction section, not only solves owing to flowing water section divides the difficulty problem that the inner core jumping formwork brought is arranged, solves the problem that two construction section differing heights climb with template simultaneously;
(4) owing to integral steel platform bearing capacity is higher, stability is better, the small-sized material distributing machine that original design each flowing water section is separately provided can be optimized for the large-scale material distributing machine placed in the middle part of a structure, while saving equipment cost, also provide conveniently for concreting;
(5) integral steel platform adopts the mode that two-shipper position, four corners is arranged, four eight, corner seat in the plane jacking integral steel platforms, act on owing to two adjacent seats in the plane promote power simultaneously, the probability broken down in two seats in the plane simultaneously is greatly lowered, the problem solving the asynchronous lifting of conventional construction method jumping formwork;
(6) promoted asynchronous factor by jumping formwork to affect, conventional construction method is generally adopted the mode that single pit shaft platform support body individually promotes, and this kind of mode entirety lifting synchronicity is better, achieve 28 seats in the plane of three pit shaft steel platforms to climb simultaneously, the jumping formwork activity duration can shorten more than half, thus improve efficiency of construction;
(7) this system adopts modularized design, assembles main frame and adopts split-type design, and single component weight is light, it is simple to Assembling, and between assembly, many employing bearing pins connect, quick for installation;
(8) horizontal former pushing mechanism equipment hydraulic power, matched moulds and form removal are easy and simple to handle, decrease that template is artificial and the time, thus accelerate construction speed;
(9) protection adopts expanded metal lath outward, and intensity is high, long service life, profile neat appearance;
(10) wall-attaching equipment adopts split-type design, and attached wall plate and guide holder are separate, uses bearing pin to connect, can first be installed on body of wall by the attached wall plate of lighter in weight, be then directed to seat and mount on attached wall plate during installation, and flexible operation is light.
The embodiment of the present invention adopts Integration Design, and all component all completes in factory process, and equipment degree is high, and climbing and tearing die closing operation open all adopts hydraulic power to complete, and processing ease, action is directly perceived.
Accompanying drawing explanation
Fig. 1 show structure construction flowing water section and divides and elevator numbering figure.
Fig. 2 show shown in Fig. 12,5,8# cylinder jumping formwork profile.
Fig. 3 show 5# elevator shaft integral truss-type steel platform plane layout drawing.
Fig. 4 show 5# elevator shaft integral truss-type steel platform profile.
Fig. 5 show embodiment of the present invention one truss-like hydraulic pressure integral steel platform jumping formwork elevational schematic view.
Fig. 6 show vertical main framework structural representation.
Fig. 7 show vertical main framework perspective view.
Fig. 8 show wall-attaching equipment structural representation.
Fig. 9 show horizontal former pushing mechanism structural representation.
nullIn figure: 1-vertical main framework、2-guide rail、3-wall-attaching equipment、4-shoulder guard net、5-hydraulic oil pump、6-climbs hydraulic pump、7-pushes away mould hydraulic cylinder、The horizontal former pushing mechanism of 8-、9-crossbeam、The anti-fall climbing device of 10-、11-template、12-longitudiual truss、13-lateral connection truss、14-longitudiual truss、15-lateral connection truss、16-steel wire rope、17-chain block、18-steel platform support body、19-body of wall、101-upper frame、The outer vertical rod of 103-、104-links up with、105-column、106-diagonal brace、107-crown wall assembly、Suspension bracket under 108-、301-attached wall plate、302-installs bolt、303-safety plug、304-off-load bearing pin、305-guide holder、801-model sheetinstallat vertical beam、802-regulates pole、803-pushes away mould hydraulic cylinder mounting seat、804-pushes away mould track、805-pushes away mould coaster.
Detailed description of the invention
The specific embodiment of the invention is described in detail below in conjunction with concrete accompanying drawing.It should be noted that, what the combination of technical characteristic described in following embodiment or technical characteristic was not construed as isolating, they can be mutually combined thus reaching superior technique effect.In the accompanying drawing of following embodiment, the identical label that each accompanying drawing occurs represents identical feature or parts, can be applicable in different embodiment.
As shown in figs 1-9, embodiment of the present invention one truss-like hydraulic pressure integral steel platform jumping formwork, including vertical main framework 1, wall-attaching equipment 3, guide rail 2, anti-fall climbing device 10, horizontal former pushing mechanism 8, template 11;
Described wall-attaching equipment 3 is fixing with wall body built-in fitting to be connected, and described vertical main framework 1 is suspended in described wall-attaching equipment 3 by linking up with 104, and is removably connected with described wall-attaching equipment 3 by off-load bearing pin 304 and safety plug 303;
Described guide rail 2 is connected with described vertical main framework 1, and removably connects with described wall-attaching equipment 3, and described vertical main framework 1 can slide up and down along described guide rail 2;
Described anti-fall climbing device 10 is fixed on described vertical main framework 1, including the hydraulic cylinder 6 that climbs, hydraulic oil pump 5, operation handle, described in the hydraulic cylinder 6 that climbs drive described anti-fall climbing device 10 to drive described vertical main framework 1 entirety to climb;Change described operation handle orientations and realize described vertical main framework 1 and described guide rail 2 alternately climbs;
Described horizontal former pushing mechanism 8 is fixed on described vertical main framework 1 crossbeam 9, and described template 11 is fixed on described horizontal former pushing mechanism 8 front end, and described horizontal former pushing mechanism 8 realizes matched moulds or form removal by pushing away mould hydraulic cylinder 7.
Preferably, described vertical main framework 1 includes crossbeam 9, column 105, diagonal brace 106, outer vertical rod 103, upper frame 101, lower suspension bracket 108, hook 104, crown wall assembly 107, connects each through bearing pin or bolt;Several described vertical main frameworks 1 are connected as entirety by connecting cross beam.
Preferably, described wall-attaching equipment 3 includes attached wall plate 301, guide holder 305, installs bolt 302, off-load bearing pin 304, safety plug 303;By installing, bolt 302 is fixing with body of wall 19 to be connected described attached wall plate 301, and described guide holder 305 mounts in described attached wall plate 301, and described guide holder 305 is fixed spacing by described safety plug 303.
Preferably, described horizontal former pushing mechanism 8 includes pushing away mould track 804, pushes away mould coaster 805, model sheetinstallat vertical beam 801, regulates pole 802, push away mould hydraulic cylinder mounting seat 803;Described push away mould hydraulic cylinder 7 be installed on described in push away mould hydraulic cylinder mounting seat 803.
Preferably, described vertical main framework 1 alien invasion is provided with shoulder guard net 4.
Illustrate for structure shown in Fig. 1, Fig. 1 show a Super-high-rising building Core Walls Structure site plan, whole Core Walls Structure Area comparison is big, it is divided into nine elevator shafts (numbering 1#-9# cylinder), it is divided into two construction sections (respectively construction section I and construction section II) in left and right, wherein 4#-6# pit shaft therefrom portion separates, and structure on two sides lays respectively at two different construction flowing water sections.Construct according to truss-like integral steel platform hydraulic climbing shuttering system construction method of the present invention.Wherein 2,5,8# cylinder hydraulic climbing shuttering profile such as Fig. 2, wherein 5# cylinder site plan such as Fig. 3,5# elevator shaft integral truss-type steel platform profile, such as Fig. 4.
Embodiment of the present invention truss-like hydraulic pressure integral steel platform jumping formwork is before use, first special safe practice arrangement and method for construction is worked out by professional, adjust this system load and each assembly stressing conditions, separately design each assembly and truss member cross section according to the load in construction and stressing conditions;The safe practice that special construction team and relevant speciality technical staff carry out arrangement and method for construction should be first organized to tell somebody what one's real intentions are before implementing at the scene.
Complete part in building structure to set up fence operation scaffold and set up platform as assembling, building reserved wall-attaching equipment 3 installation built-in fitting on construction wall 19, wall-attaching equipment in Fig. 53 is arranged on structure set aside pre-embedded part position by bolt, assemble vertical main framework 1 and be arranged in wall-attaching equipment 3 by carrying hook 104, guide rail 2 being installed in wall-attaching equipment 3.
As shown in Figure 8, wall-attaching equipment is by attached wall plate 301, guide holder 305, installing bolt 302, off-load bearing pin 304, safety plug 303 forms, its concrete installation method is, with installing bolt 302, the attached wall plate 301 of lighter in weight is fixed on building structure exterior wall 19, is then directed to seat 305 and mounts on attached wall plate 301, use safety plug 303 to be fixed spacing.
As shown in Figure 6, vertical main framework 1, including crossbeam 9, column 105, diagonal brace 106, outer vertical rod 103, upper frame 101, lower suspension bracket 108, hook 104, crown wall assembly 107, it is assembled into an entirety each through pin bolt.
As shown in Figure 9; horizontal former pushing mechanism 8 is by pushing away mould track 804; push away mould coaster 805; model sheetinstallat vertical beam 801; regulate pole 802, push away mould hydraulic cylinder mounting seat 803 and form, in advance and push away mould hydraulic cylinder 7 and be completed; lifting, to crossbeam 9 top of the vertical main framework 1 assembled, is installed by bolt and is put in place.
As it is shown in figure 5, by guide rail 2, climb hydraulic cylinder 6, anti-fall climbing device 10 and hydraulic oil pump 5 are installed and are put in place, so far integrated form truss-like hydraulic pressure integral steel platform creeping formwork vertical structure installation.
As shown in Figure 4, use longitudiual truss 12 that independent vertical main framework 1#-4# is connected into longitudinal entirety, in like manner use longitudiual truss 12 that independent vertical main framework 5#-8# is connected into longitudinal entirety, then use lateral connection truss 13 that two groups of longitudiual truss are connected into entirety, scaffold board is laid at truss top, install the cat ladder that the lower scope of operation uses, protection expanded metal lath 4 is installed outside support body, is formed and close protection.
Installing upper frame uses longitudiual truss 14 that independent vertical main framework 1#-4# upper frame is connected into longitudinal entirety, in like manner use longitudiual truss 14 that independent vertical main framework 5#-8# upper frame portion is connected into longitudinal entirety, then use lateral connection truss 15 that two groups of longitudiual truss are connected into entirety, shown in Fig. 4, complete the installment work of top twice vertically and horizontally truss.
Successively assemble in this way and set up, template 11 uses chain block 17 and steel wire rope 16 are hung on steel platform support body 18, completes truss-like integral steel platform template system as shown in Figure 4.
After installing, treat that superstructure has been constructed, after installing wall-attaching equipment 3 shown in Fig. 5, power is provided by hydraulic oil pump 5, driving is climbed hydraulic cylinder 6, promote the guide rail 2 of climbing template device, guide rail 2 is fixed in upper strata wall-attaching equipment 3 after putting in place by lifting, then the operation handle of anti-fall climbing device 10 is adjusted, the driving hydraulic cylinder 6 that climbs promotes whole truss platform support body, after rising to design height, off-load bearing pin 304 is used to be fixed in wall-attaching equipment 3 by the assembling vertical main framework 1 of integral steel platform support body, so far complete truss-like hydraulic pressure integral steel platform creeping formwork one to climb the cycle.
Superstructure reinforcing bar binding completes; being transferred to by the valve of hydraulic oil pump 5 shown in Fig. 5 pushes away on mould hydraulic cylinder 7; pushing away mould hydraulic cylinder 7 by driving makes horizontal former pushing mechanism 8 drive full wafer template 11 to travel forward; or use the formwork hoisting device being made up of chain block 17, steel platform support body 18, steel wire rope 16, complete matched moulds work;Treat that concreting completes, again drive push away mould hydraulic cylinder 7 drive horizontal former pushing mechanism 8 template 11 is slided backward or uses hang die device complete form removal work;So far integrated form truss-like hydraulic pressure integral steel platform creeping formwork one conjunction, form removal cycle are completed.
After completing work above, truss-like hydraulic pressure integral steel platform creeping formwork enters the next one and climbs the cycle, repeat above step complete to climb and close, the form removal cycle, aforesaid operations is until building structure completes repeatedly.
The invention have the benefit that
(1) structural system adopts the arrangement of vertically and horizontally truss, and monolithic truss assembling is convenient and swift, solves large span and requires that component specification is big, processing and the big problem of site operation difficulty;
(2) the vertically and horizontally interlaced layout of truss, arranging upper, middle and lower three layers altogether along support body short transverse, arrange different cross section and the truss of height according to the loading characteristic of every layer, all connection nodes all adopt gusset plate and bolt to connect, forming integral steel platform area big, intensity is high;
(3) construction flowing water fragment position support body does not carry out burst according to the division of structure construction section, not only solves owing to flowing water section divides the difficulty problem that the inner core jumping formwork brought is arranged, solves the problem that two construction section differing heights climb with template simultaneously;
(4) owing to integral steel platform bearing capacity is higher, stability is better, the small-sized material distributing machine that original design each flowing water section is separately provided can be optimized for the large-scale material distributing machine placed in the middle part of a structure, while saving equipment cost, also provide conveniently for concreting;
(5) integral steel platform adopts the mode that two-shipper position, four corners is arranged, four eight, corner seat in the plane jacking integral steel platforms, act on owing to two adjacent seats in the plane promote power simultaneously, the probability broken down in two seats in the plane simultaneously is greatly lowered, the problem solving the asynchronous lifting of conventional construction method jumping formwork;
(6) promoted asynchronous factor by jumping formwork to affect, conventional construction method is generally adopted the mode that single pit shaft platform support body individually promotes, and this kind of mode entirety lifting synchronicity is better, achieve 28 seats in the plane of three pit shaft steel platforms to climb simultaneously, the jumping formwork activity duration can shorten more than half, thus improve efficiency of construction;
(7) this system adopts modularized design, assembles main frame and adopts split-type design, and single component weight is light, it is simple to Assembling, and between assembly, many employing bearing pins connect, quick for installation;
(8) horizontal former pushing mechanism equipment hydraulic power, matched moulds and form removal are easy and simple to handle, decrease that template is artificial and the time, thus accelerate construction speed;
(9) protection adopts expanded metal lath outward, and intensity is high, long service life, profile neat appearance;
(10) wall-attaching equipment adopts split-type design, and attached wall plate and guide holder are separate, uses bearing pin to connect, can first be installed on body of wall by the attached wall plate of lighter in weight, be then directed to seat and mount on attached wall plate during installation, and flexible operation is light.
The present invention adopts Integration Design, and all component all completes in factory process, and equipment degree is high, and climbing and tearing die closing operation open all adopts hydraulic power to complete, and processing ease, action is directly perceived.
Although have been presented for several embodiments of the present invention herein, it will be appreciated by those of skill in the art that without departing from the spirit of the invention, it is possible to the embodiments herein is changed.Above-described embodiment is illustrative of, should restriction using the embodiments herein as interest field of the present invention.

Claims (5)

1. a truss-like hydraulic pressure integral steel platform jumping formwork, it is characterised in that include vertical main framework, wall-attaching equipment, guide rail, anti-fall climbing device, horizontal former pushing mechanism, template;
Described wall-attaching equipment is fixing with wall body built-in fitting to be connected, and described vertical main framework is suspended in described wall-attaching equipment by hook, and is removably connected by off-load bearing pin and safety plug and described wall-attaching equipment;
Described guide rail is connected with described vertical main framework, and removably connects with described wall-attaching equipment, and described vertical main framework can slide up and down along described guide rail;
Described anti-fall climbing device is fixed on described vertical main framework, including the hydraulic cylinder that climbs, hydraulic oil pump, operation handle, described in the anti-fall climbing device that climbs described in Driven by Hydraulic Cylinder drive described vertical main framework entirety to climb;Change described operation handle orientations to realize described vertical main framework and described guide rail and alternately climb;
Described horizontal former pushing mechanism is fixed on described vertical main framework crossbeam, and described template is fixed on described horizontal former pushing mechanism front end, and described horizontal former pushing mechanism realizes matched moulds or form removal by pushing away mould hydraulic cylinder.
2. truss-like hydraulic pressure integral steel platform jumping formwork as claimed in claim 1, it is characterised in that described vertical main framework includes crossbeam, column, diagonal brace, outer vertical rod, upper frame, lower suspension bracket, hook, crown wall assembly, connects each through bearing pin or bolt;Several described vertical main frameworks are connected as entirety by connecting cross beam.
3. truss-like hydraulic pressure integral steel platform jumping formwork as claimed in claim 1, it is characterised in that described wall-attaching equipment includes attached wall plate, guide holder, installs bolt, off-load bearing pin, safety plug;By installing, bolt and body of wall are fixing to be connected described attached wall plate, and described guide holder mounts in described attached wall plate, and described guide holder is fixed spacing by described safety plug.
4. truss-like hydraulic pressure integral steel platform jumping formwork as claimed in claim 1, it is characterised in that described horizontal former pushing mechanism includes pushing away mould track, pushes away mould coaster, model sheetinstallat vertical beam, regulates pole, push away mould hydraulic cylinder mounting seat;Described push away mould hydraulic cylinder be installed on described in push away mould hydraulic cylinder mounting seat.
5. the truss-like hydraulic pressure integral steel platform jumping formwork as described in any one of claim 1-4, it is characterised in that described vertical main framework alien invasion is provided with shoulder guard net.
CN201610285775.7A 2016-05-02 2016-05-02 Truss type hydraulic entire steel platform climbing formwork Pending CN105781101A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610285775.7A CN105781101A (en) 2016-05-02 2016-05-02 Truss type hydraulic entire steel platform climbing formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610285775.7A CN105781101A (en) 2016-05-02 2016-05-02 Truss type hydraulic entire steel platform climbing formwork

Publications (1)

Publication Number Publication Date
CN105781101A true CN105781101A (en) 2016-07-20

Family

ID=56401464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610285775.7A Pending CN105781101A (en) 2016-05-02 2016-05-02 Truss type hydraulic entire steel platform climbing formwork

Country Status (1)

Country Link
CN (1) CN105781101A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401210A (en) * 2016-11-21 2017-02-15 成都建筑工程集团总公司 Tool type vertical traffic stair for assembled building elevator shaft
CN107190650A (en) * 2017-07-26 2017-09-22 中交路桥华东工程有限公司 Truss-like is without pull bar hydraulic climbing die block system and its construction technology
CN107299754A (en) * 2017-07-13 2017-10-27 北京市建筑工程研究院有限责任公司 A kind of horizontal self-interacting type hydraulic climbing material platform
CN109235872A (en) * 2018-11-02 2019-01-18 四川省第六建筑有限公司 Building hoistway form frame system with material distributing machine
CN110984565A (en) * 2019-12-30 2020-04-10 吴权辉 Creeping formwork device for building construction
CN111119469A (en) * 2019-12-30 2020-05-08 吴权辉 Cast-in-place concrete construction method
CN112049400A (en) * 2020-09-08 2020-12-08 西北工业大学 A double guide groove type attachment device and method for a self-elevating high-altitude sliding mode operating platform
CN112482738A (en) * 2020-12-04 2021-03-12 西北工业大学 Attached self-lifting high-altitude sliding mode operation platform and method
CN112727074A (en) * 2020-12-28 2021-04-30 乾日安全科技(北京)有限公司 Building machine and building construction method
CN116950378A (en) * 2023-07-27 2023-10-27 高达建设管理发展有限责任公司 A lightweight and turnable integrated platform for housing construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130341813A1 (en) * 2012-06-13 2013-12-26 Norton Baum Self-Lifting Concrete Form Adapted To Accommodate Horizontal Reinforcing Steel
CN203559582U (en) * 2013-08-11 2014-04-23 北京星河人施工技术有限责任公司 Integrated hydraulic creeping formwork
US20140175259A1 (en) * 2012-10-12 2014-06-26 Norton Baum Modular Panel Concrete Form For Self-Lifting Concrete Form System
CN204876579U (en) * 2015-08-07 2015-12-16 俊川建筑科技有限公司 Building construction system
CN205742991U (en) * 2016-05-02 2016-11-30 北京星河人施工技术有限责任公司 A kind of truss-like hydraulic pressure integral steel platform jumping formwork

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130341813A1 (en) * 2012-06-13 2013-12-26 Norton Baum Self-Lifting Concrete Form Adapted To Accommodate Horizontal Reinforcing Steel
US20140175259A1 (en) * 2012-10-12 2014-06-26 Norton Baum Modular Panel Concrete Form For Self-Lifting Concrete Form System
CN203559582U (en) * 2013-08-11 2014-04-23 北京星河人施工技术有限责任公司 Integrated hydraulic creeping formwork
CN204876579U (en) * 2015-08-07 2015-12-16 俊川建筑科技有限公司 Building construction system
CN205742991U (en) * 2016-05-02 2016-11-30 北京星河人施工技术有限责任公司 A kind of truss-like hydraulic pressure integral steel platform jumping formwork

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401210A (en) * 2016-11-21 2017-02-15 成都建筑工程集团总公司 Tool type vertical traffic stair for assembled building elevator shaft
CN107299754A (en) * 2017-07-13 2017-10-27 北京市建筑工程研究院有限责任公司 A kind of horizontal self-interacting type hydraulic climbing material platform
CN107190650A (en) * 2017-07-26 2017-09-22 中交路桥华东工程有限公司 Truss-like is without pull bar hydraulic climbing die block system and its construction technology
CN107190650B (en) * 2017-07-26 2023-12-15 中交路桥华东工程有限公司 Truss type pull-rod-free hydraulic climbing formwork system and construction process thereof
CN109235872A (en) * 2018-11-02 2019-01-18 四川省第六建筑有限公司 Building hoistway form frame system with material distributing machine
CN110984565B (en) * 2019-12-30 2021-08-17 广东中泸建设集团有限公司 Creeping formwork device for building construction
CN111119469A (en) * 2019-12-30 2020-05-08 吴权辉 Cast-in-place concrete construction method
CN110984565A (en) * 2019-12-30 2020-04-10 吴权辉 Creeping formwork device for building construction
CN112049400A (en) * 2020-09-08 2020-12-08 西北工业大学 A double guide groove type attachment device and method for a self-elevating high-altitude sliding mode operating platform
CN112482738A (en) * 2020-12-04 2021-03-12 西北工业大学 Attached self-lifting high-altitude sliding mode operation platform and method
CN112482738B (en) * 2020-12-04 2022-01-28 西北工业大学 Attached self-lifting high-altitude sliding mode operation platform and method
CN112727074A (en) * 2020-12-28 2021-04-30 乾日安全科技(北京)有限公司 Building machine and building construction method
CN112727074B (en) * 2020-12-28 2021-08-27 乾日安全科技(北京)有限公司 Building machine and building construction method
CN116950378A (en) * 2023-07-27 2023-10-27 高达建设管理发展有限责任公司 A lightweight and turnable integrated platform for housing construction

Similar Documents

Publication Publication Date Title
CN205742991U (en) A kind of truss-like hydraulic pressure integral steel platform jumping formwork
CN203559582U (en) Integrated hydraulic creeping formwork
CN101845883B (en) Climbing scaffold system and construction method
CN108532769B (en) Jacking construction method of assembled additional elevator shaft structure
CN102230313B (en) Bridge thin-wall hollow-pier chain block hoisting operation platform and construction method thereof
CN103741947B (en) Tube-frame-supporting type hydraulic climbing integral steel platform formwork truss layer construction method
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN106400951B (en) A method for simultaneous construction of horizontal and vertical structures of super high-rise buildings
CN209482679U (en) Tub brace type integral steel platform suitable for sloping core construction
CN201250038Y (en) Wall-attached elevator hoistway
CN109457931A (en) Tub brace type integral steel platform and its construction method suitable for sloping core construction
CN103758341A (en) Steel column drum rack support type hydraulic lifting overall steel platform cross truss layer construction method
CN106592826A (en) Construction method for cylindrical frame supporting type hydraulic-climbing integral steel platform formwork shear steel plate layer
CN109184190A (en) It climbs and carries integrated beam type hydraulic climbing platform and its installation method
CN107476561A (en) A kind of attachment type raise scaffold and its construction
CN108286332A (en) A kind of concrete of crossing soars aloft beam from climbing monoblock type bylinder system and construction method
CN108331336A (en) The integrated lifting steel plateform system and its construction method of floor synchronous construction
CN109162437A (en) Integral steel platform and its construction method for more steel plate shear force walls
CN107100361B (en) Inner support aluminum dipping form device and its installation method are climbed outside a kind of
CN114541740A (en) Integral steel platform formwork equipment for inclined wall construction and construction method thereof
CN106639328A (en) Concrete beam steel reinforcement framework construction device and method
CN113896124A (en) Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform, installation process and climbing method thereof
AU2008227238B2 (en) Scaffold with handrail frames provided with post sections
CN108005373B (en) Integrated lifting platform system and assembling method thereof
CN107268971B (en) A double self-elevating external climbing frame of a super high-rise building and its application method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160720

RJ01 Rejection of invention patent application after publication