CN202450774U CN 201120350212 CN201120350212U CN202450774U CN 202450774 U CN202450774 U CN 202450774U CN 201120350212 CN201120350212 CN 201120350212 CN 201120350212 U CN201120350212 U CN 201120350212U CN 202450774 U CN202450774 U CN 202450774U
Authority
CN
China
Prior art keywords
template
elevator shaft
climbing
support body
guide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120350212
Other languages
Chinese (zh)
Inventor
陈贻超
夏元云
颜斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
First Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Third Engineering Division filed Critical First Construction Co Ltd of China Construction Third Engineering Division
Priority to CN 201120350212 priority Critical patent/CN202450774U/en
Application granted granted Critical
Publication of CN202450774U publication Critical patent/CN202450774U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model discloses a shaft template of a small-step-pitch self-climbing elevator. The shaft template is characterized by comprising a stress-bearing frame body, a lifting system and a template system, wherein the stress-bearing frame body comprises a main steel platform (1), a frame body (3) and an upper platform (5); the lifting system comprises a lifting steel beam (2), a guide rail (6), a jack (7) and a climbing head (8); the template system comprises a calabash (9) and a sizing template (10); the frame body (3) and the guide rail (6) are fixed on the main steel platform (1); the lifting steel beam (2), the jack (7) and the climbing head (8) are respectively connected with the guide rail (6); the upper platform (5) is arranged at the upper part of the frame body (3); and the sizing template (10) is arranged on the upper platform (5) through the calabash (9) in a hoisting way. The template construction working efficiency in an elevator shaft can be effectively improved; after the shaft template is assembled, and the perpendicular transporting can be carried out without a tower crane and the like; and therefore, the assembling and disassembling working load of a scaffold in the elevator shaft and the using amount of transferring frame materials are reduced.

Description

Small step is apart from the elevator shaft template of climbing certainly
Technical field
The utility model relates to a kind of high level, super highrise building elevator shaft template, relates in particular to relate to a kind of small step apart from the elevator shaft template of climbing certainly.
Background technology
It is the main artery of whole building that the elevator shaft of highrise building cans be compared to; Single elevator shaft area is little; It is limited to hold the construction number of workers; How to improve speed of application and work efficiency, the operation of reduction elevator shaft of elevator shaft template security risk, guarantee the structure construction quality, how to shorten the rapid transport in job site vertical transportation machinery holding time and narrow place etc., be the several difficult of puzzlement structure construction all the time.If by conventional job practices, face several big problems such as work efficiency, cost, safety and vertical transport.
The utility model content
The utility model technical problem to be solved provides a kind of small step apart from from climbing the elevator shaft template, has solved the problems referred to above.
The utility model technical problem to be solved realizes through following technical scheme:
A kind of small step is characterized in that: comprise stressed support body, Hoisting System and template system apart from from climbing the elevator shaft template; Said stressed support body comprises main steel platform, support body and upper mounting plate;
Hoisting System comprises lifting girder steel, guide rail, jack and climbs head; Template system comprises cucurbit and typified form;
Said main steel platform upper holder body and guide rail; Promote girder steel, jack and climb head and all be connected with guide rail; Upper mounting plate is arranged on support body top, and typified form is lifted on the upper mounting plate through cucurbit.
Said main steel platform comprises girder, tumbler and bearing pin; Bearing pin is connected the girder two ends, and tumbler is connected with bearing pin.
Said lifting girder steel two ends are provided with tumbler, and tumbler is connected with the lifting girder steel through bearing pin.
Said guide rail has been provided with the constant spacing block.
Said jack is fixed on and promotes on the girder steel.
Said support body adopts section steel manufacture or scaffold building.
The directive wheel of support body verticality when said lifting girder steel top is provided with the control lifting.
The beneficial effect of the utility model:
The utility model does not need tower crane etc. to carry out vertical transport after can effectively improving elevator shaft inner formword construction efficiency, installation; Reduce scaffold building and dismounting workload and turnover rack material consumption in the elevator shaft; Owing to adopt above-mentioned technology, make the elevator shaft template construction become standard product, in factory process; On-site consolidation, the whole lifting.Compare with the routine construction; Significantly reduce transhipment of elevator shaft template and set-up time; Have characteristics such as few, the easy construction of lifting number of times, reliable in quality, safety be controlled; And effectively reduce scaffold building and dismounting workload and turnover rack material consumption in the elevator shaft, and accelerated construction speed, reduced cost.
Description of drawings
Fig. 1 elevator shaft template support body plan view
The main steel platform plane of Fig. 2-1 figure
The main steel platform of Fig. 2-2 elevation
Fig. 3 elevator shaft mould Hoisting System figure
Fig. 4 elevator shaft mould elevation
The form removable of Fig. 4-1 elevator shaft
Fig. 4-2 elevator shaft mould sketch map one that climbs
Fig. 4-3 elevator shaft mould sketch map two that climbs
Fig. 4-4 elevator shaft mould completion sketch map that climbs
Fig. 5 elevator shaft mould is reinforced sketch map
The specific embodiment
Shown in Fig. 1-5, a kind of small step is characterized in that: comprise stressed support body, Hoisting System and template system apart from from climbing the elevator shaft template; Said stressed support body comprises main steel platform 1, support body 3 and upper mounting plate 5; Hoisting System comprises and promotes girder steel 2, guide rail 6, jack 7 and climb 8; Template system comprises cucurbit 9 and typified form 10; Said main steel platform 1 upper holder body 3 and guide rail 6; Promote girder steel 2, jack 7 and climb 8 and all be connected with guide rail 6; Upper mounting plate 5 is arranged on support body 3 tops, and typified form 10 is lifted on the upper mounting plate 5 through cucurbit 9.
Said main steel platform 1 comprises girder 11, tumbler 12 and bearing pin 13; Bearing pin 13 is connected girder 11 two ends, and tumbler 12 is connected with bearing pin 13.
Wherein 11, tumbler 12 is main bearing member, need carry out checking computations according to service load; Tumbler 12 is in level under stationary state.Under the lifting state, under the effect of shear wall or other obstruction, outwards rotate around bearing pin 13.When running into hole to be provided, the stressed removal in tumbler 12 outsides, tumbler 12 becomes level under the deadweight effect, and counter-rotating jack back frame body moves down, and tumbler 12 is shelved in the hole to be provided; Said lifting girder steel 2 tops are provided with directive wheel 4, control support body 3 verticality when directive wheel 4 promotes at support body 3.
Said lifting girder steel 2 two ends are provided with tumbler 12, and tumbler 12 is connected with lifting girder steel 2 through bearing pin 13.Said guide rail 6 has been provided with the constant spacing block.
Said jack 7 is fixed on and promotes on the girder steel 2.Said support body 3 adopts section steel manufacture or scaffold building.
Set up in support body 3 integral body fix, typified form 10 liftings are accomplished and jack 7 debugging good after, organize small step can wholely promote main steel platform 1 and support body 3 after passing through apart from checking and accepting from the elevator shaft template of climbing, checking and accepting.During lifting, main steel platform 1 and support body 3 are in vacant state, girder steel 2 is stressed by promoting, when main steel platform 1 is promoted to lifting girder steel 2 positions; Tumbler 12 runs into the hole to be provided that is retained in shear wall or Lian Liangshang in advance, and tumbler 12 is progressively visited to advance in the hole to be provided under the deadweight effect, check that each tumbler state all puts in hole to be provided after; Jack 7 begins to move down, and tumbler 12 becomes level and is shelved on the hole to be provided, and support body 3 beginning is stressed by main steel platform 1; Jack 7, lifting girder steel 2 reverse again to last layer hole to be provided position; Support body promptly promotes and finishes, and can begin adjustment, reinforce typified form 10, stripping after the concreting; Adopt cucurbit 9 that typified form 10 is hung on the upper mounting plate 5, treat to begin next step circulation after the vertical reinforcement colligation finishes.
Said main steel platform 1, support body 3, typified form 10 are along being fixed on having small step at produce in factory in advance and promote apart from guide rail 6 guide rails of block are whole on the support body.

Claims (7)

1. a small step is characterized in that: comprise stressed support body, Hoisting System and template system apart from from climbing the elevator shaft template; Said stressed support body comprises main steel platform (1), support body (3) and upper mounting plate (5); Hoisting System comprises lifting girder steel (2), guide rail (6), jack (7) and climbs head (8); Template system comprises cucurbit (9) and typified form (10);
Said main steel platform (1) upper holder body (3) and guide rail (6); Promote girder steel (2), jack (7) and climb head (8) and all be connected with guide rail (6); Upper mounting plate (5) is arranged on support body (3) top, and typified form (10) is lifted on the upper mounting plate (5) through cucurbit (9).
2. small step as claimed in claim 1 is apart from the elevator shaft template of climbing certainly, and it is characterized in that: said main steel platform (1) comprises girder (11), tumbler (12) and bearing pin (13); Bearing pin (13) is connected girder (11) two ends, and tumbler (12) is connected with bearing pin (13).
3. small step as claimed in claim 1 is apart from the elevator shaft template of climbing certainly, and it is characterized in that: said lifting girder steel (2) two ends are provided with tumbler (12), and tumbler (12) is connected with lifting girder steel (2) through bearing pin.
4. small step as claimed in claim 1 is apart from the elevator shaft template of climbing certainly, and it is characterized in that: said guide rail (6) has been provided with the constant spacing block.
5. small step as claimed in claim 1 is characterized in that apart from the elevator shaft template of climbing certainly: said jack (7) is fixed on and promotes on the girder steel (2).
6. small step as claimed in claim 1 is characterized in that: said support body (3) employing section steel manufacture or scaffold building apart from from climbing the elevator shaft template.
7. small step as claimed in claim 6 is characterized in that: the directive wheel (4) of support body (3) verticality when said lifting girder steel (2) top is provided with the control lifting apart from from climbing the elevator shaft template.
CN 201120350212 2011-09-19 2011-09-19 Shaft template of small-step-pitch self-climbing elevator Expired - Fee Related CN202450774U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120350212 CN202450774U (en) 2011-09-19 2011-09-19 Shaft template of small-step-pitch self-climbing elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120350212 CN202450774U (en) 2011-09-19 2011-09-19 Shaft template of small-step-pitch self-climbing elevator

Publications (1)

Publication Number Publication Date
CN202450774U true CN202450774U (en) 2012-09-26

Family

ID=46866645

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120350212 Expired - Fee Related CN202450774U (en) 2011-09-19 2011-09-19 Shaft template of small-step-pitch self-climbing elevator

Country Status (1)

Country Link
CN (1) CN202450774U (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103806654A (en) * 2012-11-06 2014-05-21 中国五冶集团有限公司 Hydraulic support system for elevator shaft mold and operating method thereof
CN103821356A (en) * 2014-02-25 2014-05-28 上海鑫尔森模架工程有限公司 Construction equipment and system of elevator shaft shear wall
CN105113785A (en) * 2015-07-03 2015-12-02 中国十七冶集团有限公司 Super high-rise building core tube breaststroke creeping formwork device
CN105113777A (en) * 2015-09-11 2015-12-02 中国建筑第八工程局有限公司 Structural construction equipment with cooperative transmission by beams in multiple layers and climb method thereof
CN105317205A (en) * 2014-06-09 2016-02-10 中建四局第六建筑工程有限公司 Elevator shaft construction method and used device
CN107155336A (en) * 2014-01-31 2017-09-12 格雷戈里·约翰·内伯尔斯 Concrete towers and related mould bases and relative configurations method
CN107975233A (en) * 2018-01-11 2018-05-01 山东方圆建筑材料有限公司 A kind of elevator inner template revenue and expenditure system
CN108979114A (en) * 2017-05-31 2018-12-11 深圳市特辰科技股份有限公司 A kind of full-automatic scissor-type robot climbing frame
CN109235872A (en) * 2018-11-02 2019-01-18 四川省第六建筑有限公司 Building hoistway form frame system with material distributing machine
CN113738098A (en) * 2021-09-14 2021-12-03 广州达蒙安防科技有限公司 One-way self-locking lifting mechanism for elevator shaft die

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103806654A (en) * 2012-11-06 2014-05-21 中国五冶集团有限公司 Hydraulic support system for elevator shaft mold and operating method thereof
CN107155336A (en) * 2014-01-31 2017-09-12 格雷戈里·约翰·内伯尔斯 Concrete towers and related mould bases and relative configurations method
CN103821356A (en) * 2014-02-25 2014-05-28 上海鑫尔森模架工程有限公司 Construction equipment and system of elevator shaft shear wall
CN105317205A (en) * 2014-06-09 2016-02-10 中建四局第六建筑工程有限公司 Elevator shaft construction method and used device
CN105113785A (en) * 2015-07-03 2015-12-02 中国十七冶集团有限公司 Super high-rise building core tube breaststroke creeping formwork device
CN105113777A (en) * 2015-09-11 2015-12-02 中国建筑第八工程局有限公司 Structural construction equipment with cooperative transmission by beams in multiple layers and climb method thereof
CN105113777B (en) * 2015-09-11 2017-09-26 中国建筑第八工程局有限公司 The structure construction equipment and its method of climbing of power transmission are cooperateed with using multilayer beam
CN108979114A (en) * 2017-05-31 2018-12-11 深圳市特辰科技股份有限公司 A kind of full-automatic scissor-type robot climbing frame
CN107975233A (en) * 2018-01-11 2018-05-01 山东方圆建筑材料有限公司 A kind of elevator inner template revenue and expenditure system
CN109235872A (en) * 2018-11-02 2019-01-18 四川省第六建筑有限公司 Building hoistway form frame system with material distributing machine
CN113738098A (en) * 2021-09-14 2021-12-03 广州达蒙安防科技有限公司 One-way self-locking lifting mechanism for elevator shaft die

Similar Documents

Publication Publication Date Title
CN202450774U (en) Shaft template of small-step-pitch self-climbing elevator
CN103114681A (en) To-be-poured structure and construction method of high-altitude large-span reinforced concrete beam
CN105152032A (en) Installing method for bridge crane in enclosed environment workshop
CN205772984U (en) A kind of hanging apparatus of monolithic steel truss
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN102777030A (en) Method for building up formwork construction platform of lift shaft
CN202509754U (en) High-altitude steel structure node construction working platform
CN203113793U (en) Large formwork installation system of oblique structure
CN204455842U (en) Bridge precast beam plate girder erection frame
CN112360469A (en) Super-deep shaft sequential-lining single-side formwork-erecting lifting formwork and construction method
CN101818563B (en) Jack-up integral lifting mobile platform and using method
CN202689496U (en) Moving platform for steel pipe concrete post concrete casing
CN102398849A (en) Method for moving whole crawler crane down to dock
CN214573768U (en) Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot
CN201817201U (en) Trolley slippage construction device
CN204492173U (en) Elevator shaft integral lifting template operation platform
CN204850435U (en) Case roof beam of using top die body system promotes anti -falling device
CN204198306U (en) A kind of device for purlin lifting in building operation
CN203924652U (en) The operation platform of periphery shear wall between a kind of precast stair
CN203320922U (en) Supporting device for forming of elevator shaft template
CN202829498U (en) Hydraulic jacking device
CN201857225U (en) Hoisting device for bridge crane frame
CN205531262U (en) Steel construction construction platform can rise automatically
CN101664963A (en) Multifunctional operating platform for large-volume prestressed concrete box girder tensioning
CN213710309U (en) Lift shaft lifting type steel platform device for construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120926