CN109235481A - A kind of construction method preventing lifting by frost for transmission line of electricity column foundation - Google Patents

A kind of construction method preventing lifting by frost for transmission line of electricity column foundation Download PDF

Info

Publication number
CN109235481A
CN109235481A CN201811227519.8A CN201811227519A CN109235481A CN 109235481 A CN109235481 A CN 109235481A CN 201811227519 A CN201811227519 A CN 201811227519A CN 109235481 A CN109235481 A CN 109235481A
Authority
CN
China
Prior art keywords
transmission line
column foundation
foundation
steel cylinder
straight column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811227519.8A
Other languages
Chinese (zh)
Inventor
周保
李彬
陈静
马涛
张啟兴
张睿
张俊才
张永艳
隋嘉
孙莹
吕文斌
魏赛拉加
魏正发
严慧珺
辛倩男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinghai Geological Environment Monitoring Station
Qinghai Institute Of Hydrogeology And Engineering
Qinghai Nonferrous Third Geological Exploration Institute
Qinghai Normal University
Original Assignee
China Electric Power Construction Group Qinghai Electric Power Design Institute Co Ltd
QINGHAI GEOLOGICAL SURVEY INSTITUTE
Qinghai Institute Of Hydrogeology Engineering Geology And Environment Geology
Qinghai Geological Environmental Monitoring Main Station
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Construction Group Qinghai Electric Power Design Institute Co Ltd, QINGHAI GEOLOGICAL SURVEY INSTITUTE, Qinghai Institute Of Hydrogeology Engineering Geology And Environment Geology, Qinghai Geological Environmental Monitoring Main Station filed Critical China Electric Power Construction Group Qinghai Electric Power Design Institute Co Ltd
Priority to CN201811227519.8A priority Critical patent/CN109235481A/en
Publication of CN109235481A publication Critical patent/CN109235481A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种用于输电线路直柱基础防止冻拔的施工方法。包括:开挖基坑,输电线路直柱基础底座置于永冻土层,将直柱基础下部基础底座迅速回填;将按照直柱基础尺寸预先制作好的内侧焊接有万向轮的外侧钢筒套装在直柱基础上部;外侧钢筒套装完毕后,对外侧钢筒下部与直柱基础底座间的缝隙进行密封,密封后从上部向套装在直柱基础上的外侧钢筒及在其内侧焊接的万向轮形成的间隙内缓慢均匀的注入润滑剂;润滑剂注入完成后,迅速回填土方。本发明的施工方法,解决了在冻土的冻胀作用下,由于向上的冻拔力和多次冻融循环导致直柱基础上部被冻拔破坏的问题。实现了防止冻拔与施工一体化,具有效率高、施工速度快等优点,应用前景广泛。

The invention discloses a construction method for preventing freezing and pulling of a straight column foundation of a transmission line. Including: excavating the foundation pit, placing the base of the straight column foundation of the transmission line in the permafrost layer, and quickly backfilling the foundation base at the lower part of the straight column foundation; prefabricated according to the size of the straight column foundation and welding the inner side of the outer steel cylinder with the universal wheel Set on the upper part of the vertical column foundation; after the outer steel cylinder is set, seal the gap between the lower part of the outer steel cylinder and the base of the vertical column foundation, and then weld from the upper part to the outer steel cylinder set on the vertical column foundation and on the inside of it. Slowly and evenly inject lubricant into the gap formed by the universal wheel; after the lubricant injection is completed, quickly backfill the soil. The construction method of the present invention solves the problem that the upper part of the vertical column foundation is damaged by freezing and pulling due to the upward freezing pulling force and multiple freeze-thaw cycles under the action of frost heaving of the frozen soil. It realizes the integration of preventing freezing and pulling and construction, and has the advantages of high efficiency and fast construction speed, and has wide application prospects.

Description

A kind of construction method preventing lifting by frost for transmission line of electricity column foundation
Technical field
The present invention relates to electric system construction field more particularly to a kind of lifting by frost is prevented for transmission line of electricity column foundation Construction method.
Background technique
Electric system mainly includes generator, step-up substation, transmission line of electricity, the stepdown substation, power distribution system in power plant System and user's composition, wherein transmission line of electricity is the Chinese medicinal composition part of whole system.
Ever-frozen ground freezes throughout the year but summer topsoil melting layer.It is built in the building basis on ever-frozen ground, winter The volume increase due to the free moisture icing in foundation soil, warms up thaw collapse after becoming civilized and volume reduces, and multigelation can reduce ground The intensity of base soil generates differential settlement, and construction cracking is caused even to damage.The frost heave having due to frozen soil, melting property of sinking Etc. characteristics, transmission line of electricity column foundation is influenced very big, therefore must be taken in basic engineering.
Traditional conventional electrical power lines road column foundation pedestal in permafrost haorizon, just press on the upper layer of frozen soil layer by column foundation top In 2~3 years after dress, under the frost heave action of frozen soil, due to upward lifting by frost power, after thawing recycles, right cylinder base Plinth top is destroyed by lifting by frost, and column foundation is caused to fail, and then influences the normal work of entire transmission line of electricity, and 2~3 years of the later period Transmission line of electricity column foundation and ground permafrost haorizon, which combine together, afterwards would not occur lifting by frost.
Summary of the invention
Based on the above issues, a kind of construction method that lifting by frost is prevented for transmission line of electricity column foundation is needed, it is defeated to protect Electric line column foundation is not endured cold the destruction of pull out force.
The purpose of the invention is to provide a kind of construction methods that lifting by frost is prevented for transmission line of electricity column foundation, including Following steps:
Step S101: excavation pit, transmission line of electricity column foundation pedestal are placed among permafrost, are removed sole plate and are sealed mould Afterwards, transmission line of electricity column foundation infrastructure pedestal is backfilled rapidly, frozen soil is avoided to disturb;
Step S102: it after envelope mould is removed on transmission line of electricity column foundation top, will be made in advance according to transmission line of electricity column foundation size The outside steel cylinder that the inside performed is welded with universal wheel is sleeved on transmission line of electricity column foundation top, and adjusts to universal wheel Section, guarantees to touch transmission line of electricity column foundation surface;
Step S103: after the outside steel cylinder suit, to outside steel cylinder lower part and transmission line of electricity column foundation pedestal Between gap be sealed, welded to the outside steel cylinder being sleeved on transmission line of electricity column foundation and on the inside of it after sealing from top It is slowly uniformly injected into lubricant in the gap that the universal wheel connect is formed, guarantees that internal universal wheel keeps working condition;
Step S104: after the completion of lubricant injection, the earthwork is backfilled rapidly, carries out finishing operations.
Further, the outside steel cylinder can be square or columned.
Further, it can be connect between the universal wheel and transmission line of electricity column foundation welded on the inside of the outside steel cylinder Touching, moves up and down convenient for outside steel cylinder relative to transmission line of electricity column foundation.
Optimization, the lubricant can be butter.
Further, after the inside is welded with the outside steel cylinder installation of universal wheel, without taking out again.
The present invention provides a kind of construction method that lifting by frost is prevented for transmission line of electricity column foundation, solves the jelly in frozen soil Under swollen effect, since upward lifting by frost power and thawing recycle caused transmission line of electricity column foundation top and are destroyed by lifting by frost, The problem of causing column foundation to fail, and then influencing the normal work of entire transmission line of electricity.Realizing prevents lifting by frost and construction one Body, just by 2~3 years after dress especially in work transmission line, there are the upper layer summers of column foundation top frozen soil layer When thawing, have many advantages, such as that high-efficient, speed of application is fast, application prospect is extensive.
Detailed description of the invention
Fig. 1 is a kind of workflow of construction method that lifting by frost is prevented for transmission line of electricity column foundation of the present invention Figure;
Fig. 2 is a kind of construction section signal of construction method that lifting by frost is prevented for transmission line of electricity column foundation of the present invention Figure;
Fig. 3 is that a kind of middle column foundation of construction method that lifting by frost is prevented for transmission line of electricity column foundation of the present invention is Figure structure schematic representation is overlooked in the construction of square.
Fig. 4 is a kind of middle right cylinder base of construction method that lifting by frost is prevented for transmission line of electricity column foundation of the present invention Plinth is that figure structure schematic representation is overlooked in the construction of cylindrical body.
In figure: 1, transmission line of electricity column foundation, 2, outside steel cylinder, 3, universal wheel, 4, gap.
Specific embodiment
In view of preventing the construction method of lifting by frost using transmission line of electricity column foundation in frozen soil layer, to solve the jelly in frozen soil Under swollen effect, since upward lifting by frost power and thawing recycle caused transmission line of electricity column foundation top and are destroyed by lifting by frost, The invention for causing column foundation Problem of Failure two to be made.
The embodiment of the present invention is illustrated with reference to the accompanying drawing.It should be noted that in the absence of conflict, this The embodiment of invention and the technical characteristic in embodiment can be combined with each other, within the scope of the present invention.In addition, being Convenient for description, step number is used below, but this should not be construed limitation of the present invention, in addition, with lower section It, in some cases, can be to be different from although logical order is shown in flow charts for each step described in method Sequence herein executes shown or described step.
Embodiment of the method 1
According to an embodiment of the invention, providing a kind of construction method for preventing lifting by frost for transmission line of electricity column foundation.
Fig. 1 shows the flow chart of embodiment of the method for the invention, includes the following steps:
Step S101, excavation pit, transmission line of electricity column foundation pedestal are placed among permafrost, are removed sole plate and are sealed mould Afterwards, transmission line of electricity column foundation infrastructure pedestal is backfilled rapidly, frozen soil is avoided to disturb;
Step S102 will make in advance after envelope mould is removed on transmission line of electricity column foundation top according to transmission line of electricity column foundation size The outside steel cylinder that the inside performed is welded with universal wheel is sleeved on transmission line of electricity column foundation top, and adjusts to universal wheel Section, guarantees to touch transmission line of electricity column foundation surface;
Step S103, after the outside steel cylinder is set with, to outside steel cylinder lower part and transmission line of electricity column foundation pedestal Between gap be sealed, welded to the outside steel cylinder being sleeved on transmission line of electricity column foundation and on the inside of it after sealing from top It is slowly uniformly injected into lubricant in the gap that the universal wheel connect is formed, guarantees that internal universal wheel keeps working condition;
Step S104 backfills rapidly the earthwork, carries out finishing operations after the completion of lubricant injection.
The details of above-mentioned processing is described in detail below with reference to Fig. 2, includes transmission line of electricity column foundation (1), outside steel in Fig. 2 Cylinder (2), universal wheel (3), gap (4).
The outside steel cylinder is square.
It can be contacted between the universal wheel and transmission line of electricity column foundation welded on the inside of the outside steel cylinder, be convenient for outside Steel cylinder is moved up and down relative to transmission line of electricity column foundation.
Optimization, the lubricant is butter.
After the inside is welded with the outside steel cylinder installation of universal wheel, without taking out again.
Embodiment of the method 2
According to an embodiment of the invention, providing a kind of construction method for preventing lifting by frost for transmission line of electricity column foundation.
Fig. 1 shows the flow chart of embodiment of the method for the invention, includes the following steps:
Step S101, excavation pit, transmission line of electricity column foundation pedestal are placed among permafrost, are removed sole plate and are sealed mould Afterwards, transmission line of electricity column foundation infrastructure pedestal is backfilled rapidly, frozen soil is avoided to disturb;
Step S102 will make in advance after envelope mould is removed on transmission line of electricity column foundation top according to transmission line of electricity column foundation size The outside steel cylinder that the inside performed is welded with universal wheel is sleeved on transmission line of electricity column foundation top, and adjusts to universal wheel Section, guarantees to touch transmission line of electricity column foundation surface;
Step S103, after the outside steel cylinder is set with, to outside steel cylinder lower part and transmission line of electricity column foundation pedestal Between gap be sealed, welded to the outside steel cylinder being sleeved on transmission line of electricity column foundation and on the inside of it after sealing from top It is slowly uniformly injected into lubricant in the gap that the universal wheel connect is formed, guarantees that internal universal wheel keeps working condition;
Step S104 backfills rapidly the earthwork, carries out finishing operations after the completion of lubricant injection.
The details of above-mentioned processing is described in detail below with reference to Fig. 2, includes transmission line of electricity column foundation (1), outside steel in Fig. 2 Cylinder (2), universal wheel (3), gap (4).
The outside steel cylinder is columned.
It can be contacted between the universal wheel and transmission line of electricity column foundation welded on the inside of the outside steel cylinder, be convenient for outside Steel cylinder is moved up and down relative to transmission line of electricity column foundation.
Optimization, the lubricant is butter.
After the inside is welded with the outside steel cylinder installation of universal wheel, without taking out again.
The present invention provides a kind of construction method that lifting by frost is prevented for transmission line of electricity column foundation, solves the jelly in frozen soil Under swollen effect, since upward lifting by frost power and thawing recycle caused transmission line of electricity column foundation top and are destroyed by lifting by frost, The problem of causing column foundation to fail, and then influencing the normal work of entire transmission line of electricity.Realizing prevents lifting by frost and construction one Body, just by 2~3 years after dress especially in work transmission line, there are the upper layer summers of column foundation top frozen soil layer When thawing, have many advantages, such as that high-efficient, speed of application is fast, application prospect is extensive.

Claims (5)

1.一种用于输电线路直柱基础防止冻拔的施工方法,其特征在于:包括如下步骤:1. a construction method for the prevention of freezing and pulling of a straight column foundation of a transmission line, is characterized in that: comprise the steps: 步骤S101:开挖基坑,所述输电线路直柱基础底座置于永冻土层之中,拆除基础底座封模后,将所述输电线路直柱基础下部基础底座迅速回填,避免冻土扰动;Step S101 : excavating a foundation pit, placing the base of the straight column foundation of the transmission line in the permafrost layer, and removing the sealing mold of the foundation base, quickly backfilling the foundation base at the lower part of the straight column foundation of the transmission line to avoid permafrost disturbance ; 步骤S102:所述输电线路直柱基础上部拆除封模后,将按照所述输电线路直柱基础尺寸预先制作好的内侧焊接有所述万向轮的所述外侧钢筒套装在所述输电线路直柱基础上部,并对所述万向轮进行调节,保证能接触到所述输电线路直柱基础表面;Step S102: After removing the sealing mold from the upper part of the base of the straight column of the transmission line, set the outer steel cylinder with the universal wheel welded on the inner side, which is prefabricated according to the size of the base of the straight column of the transmission line, over the transmission line. The upper part of the straight column foundation, and the universal wheel is adjusted to ensure that it can contact the surface of the straight column foundation of the transmission line; 步骤S103:所述外侧钢筒套装完毕后,对所述外侧钢筒下部与所述输电线路直柱基础底座间的缝隙进行密封,密封后从上部向套装在所述输电线路直柱基础上的所述外侧钢筒及在其内侧焊接的所述万向轮形成的间隙内缓慢均匀的注入润滑剂,保证内部万向轮保持工作状态;Step S103: After the outer steel cylinder is assembled, the gap between the lower part of the outer steel cylinder and the base of the straight column of the transmission line is sealed, and after sealing, the gap between the upper part of the outer steel cylinder and the base of the straight column of the transmission line is sealed. Slowly and uniformly inject lubricant into the gap formed by the outer steel cylinder and the swivel wheel welded on the inner side to ensure that the inner swivel wheel maintains the working state; 步骤S104:所述润滑剂注入完成后,迅速回填土方,做好平整工作。Step S104: After the lubricant injection is completed, the earthwork is quickly backfilled, and the leveling work is done. 2.根据权利要求1所述的一种用于输电线路直柱基础防止冻拔的施工方法,其特征在于:所述的外侧钢筒可以为正方体或者圆柱状的。2 . The construction method for preventing frost pulling of a straight column foundation of a power transmission line according to claim 1 , wherein the outer steel cylinder can be a cube or a cylinder. 3 . 3.根据权利要求1所述的一种用于输电线路直柱基础防止冻拔的施工方法,其特征在于:所述的外侧钢筒内侧焊接的万向轮与输电线路直柱基础之间可以接触,便于外侧钢筒相对于输电线路直柱基础上下移动。3. A kind of construction method for preventing freeze-pulling of straight column foundation of transmission line according to claim 1, it is characterized in that: between the universal wheel welded on the inner side of the outer steel cylinder and the straight column foundation of the transmission line Contact, it is convenient for the outer steel cylinder to move up and down relative to the straight column foundation of the transmission line. 4.根据权利要求1所述的一种用于输电线路直柱基础防止冻拔的施工方法,其特征在于:所述的润滑剂为黄油。4 . A construction method for preventing freezing and pulling of a straight column foundation of a transmission line according to claim 1 , wherein the lubricant is butter. 5 . 5.根据权利要求1所述的一种用于输电线路直柱基础防止冻拔的施工方法,其特征在于:所述的内侧焊接有万向轮的外侧钢筒安装后,无需再次取出。5 . A construction method for preventing freezing pullout of a straight column foundation of a power transmission line according to claim 1 , wherein the outer steel cylinder with the universal wheel welded on the inner side does not need to be taken out again after being installed. 6 .
CN201811227519.8A 2018-10-22 2018-10-22 A kind of construction method preventing lifting by frost for transmission line of electricity column foundation Pending CN109235481A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811227519.8A CN109235481A (en) 2018-10-22 2018-10-22 A kind of construction method preventing lifting by frost for transmission line of electricity column foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811227519.8A CN109235481A (en) 2018-10-22 2018-10-22 A kind of construction method preventing lifting by frost for transmission line of electricity column foundation

Publications (1)

Publication Number Publication Date
CN109235481A true CN109235481A (en) 2019-01-18

Family

ID=65080853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811227519.8A Pending CN109235481A (en) 2018-10-22 2018-10-22 A kind of construction method preventing lifting by frost for transmission line of electricity column foundation

Country Status (1)

Country Link
CN (1) CN109235481A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111648413A (en) * 2020-06-10 2020-09-11 内蒙古大学 A device for anti-freezing and pulling out of pile foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080069335A (en) * 2007-01-23 2008-07-28 한국건설기술연구원 Fixation method of fixing force acting on foundation piles of permafrost
CN102877448A (en) * 2012-10-24 2013-01-16 中铁西北科学研究院有限公司 Deformation monitoring datum point device applicable to permafrost regions and method for mounting deformation monitoring datum point device
CN103306290A (en) * 2012-03-27 2013-09-18 中国电力科学研究院 Quick re-freezing and backfilling construction method for foundation ground of tower foundation in frozen ground area
CN105442626A (en) * 2015-12-23 2016-03-30 中国电力工程顾问集团西北电力设计院有限公司 Composite inclined column expansion foundation structure applied to power transmission line in permafrost region
CN108385673A (en) * 2018-03-14 2018-08-10 兰州有色冶金设计研究院有限公司 Miniature top filling ball sleeve pile pile and its construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080069335A (en) * 2007-01-23 2008-07-28 한국건설기술연구원 Fixation method of fixing force acting on foundation piles of permafrost
CN103306290A (en) * 2012-03-27 2013-09-18 中国电力科学研究院 Quick re-freezing and backfilling construction method for foundation ground of tower foundation in frozen ground area
CN102877448A (en) * 2012-10-24 2013-01-16 中铁西北科学研究院有限公司 Deformation monitoring datum point device applicable to permafrost regions and method for mounting deformation monitoring datum point device
CN105442626A (en) * 2015-12-23 2016-03-30 中国电力工程顾问集团西北电力设计院有限公司 Composite inclined column expansion foundation structure applied to power transmission line in permafrost region
CN108385673A (en) * 2018-03-14 2018-08-10 兰州有色冶金设计研究院有限公司 Miniature top filling ball sleeve pile pile and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111648413A (en) * 2020-06-10 2020-09-11 内蒙古大学 A device for anti-freezing and pulling out of pile foundation

Similar Documents

Publication Publication Date Title
CN104533434B (en) Construction method of rectangular ultra-shallow covered soil tunnel
WO2020248596A1 (en) Protection structure for preventing ground heave caused by tunnel grouting reinforcement and grouting method
CN110158649B (en) A construction method for adjacent underground pipelines during caisson subsidence construction
CN101250868B (en) Precipitation prepressing association motive power induration deep densification method
CN103696376A (en) Concrete foundation-free highway culvert for permafrost region
CN103527847B (en) Pipe burying structure capable of reducing pipe top vertical loads and construction method for pipe burying structure
CN102926378A (en) Conductive composite vacuum soft soil reinforcing prepressing method
CN105926636A (en) Freezing bottom-sealing construction method for deep foundation pit
CN110889163A (en) A method for controlling wide cracks in coal mining subsidence in loess hilly area
CN108239989B (en) Environment-friendly collapsible loess foundation structure and treatment method thereof
CN106869946A (en) Make bottom frozen construction method in a kind of sand-pebble layer tunneling subway station
CN110306595A (en) A co-construction structure and construction method of a power utility gallery and a flood wall
CN202577363U (en) H-shaped steel joint structure of underground diaphragm wall
CN109235481A (en) A kind of construction method preventing lifting by frost for transmission line of electricity column foundation
CN215858114U (en) Open caisson integrated configuration to existing pipeline transformation that dams
CN103046534B (en) Method for improving bearing capacity of foundation
CN205116201U (en) Open caisson construction equipment
CN210127498U (en) Permafrost region pile foundation anti-freezing-pulling structure
CN104947653B (en) For the decompression method of vibrator pipe sinking cast-in-place pile construction in saturation mud
CN102304913A (en) LCSG (Long-Concrete Short-Gravel) pile and vacuum prepressing combined processing method and device for soft soil foundation
CN109742715B (en) Arrangement structure of electric power pipe trench after transition and modification and electric power pipe trench transition and modification method
CN207891907U (en) A kind of environment-friendly type collapsible loess foundation structure
CN206467651U (en) Rectangular concrete pile for building piping lane side wall
CN209585134U (en) The light platform structure of frost damage prevention
CN204375987U (en) The little resistance ground network of main equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210622

Address after: 810000 77 Haiyan Road, Chengxi District, Xining City, Qinghai Province

Applicant after: QINGHAI GEOLOGICAL ENVIRONMENT MONITORING STATION

Applicant after: Qinghai nonferrous Third Geological Exploration Institute

Applicant after: QINGHAI NORMAL University

Applicant after: QINGHAI INSTITUTE OF HYDROGEOLOGY AND ENGINEERING

Address before: No.18, Wusi West Road, Chengxi District, Xining City, Qinghai Province 810000

Applicant before: QINGHAI GEOLOGICAL ENVIRONMENT MONITORING STATION

Applicant before: POWERCHINA QINGHAI ELECTRIC POWER DESIGN INSTITUTE Co.,Ltd.

Applicant before: QINGHAI GEOLOGICAL SURVEY INSTITUTE

Applicant before: QINGHAI INSTITUTE OF HYDROGEOLOGY AND ENGINEERING

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20190118

RJ01 Rejection of invention patent application after publication