CN106088115A - The method increasing Stability of Soil of High Side Slopes - Google Patents
The method increasing Stability of Soil of High Side Slopes Download PDFInfo
- Publication number
- CN106088115A CN106088115A CN201610608763.3A CN201610608763A CN106088115A CN 106088115 A CN106088115 A CN 106088115A CN 201610608763 A CN201610608763 A CN 201610608763A CN 106088115 A CN106088115 A CN 106088115A
- Authority
- CN
- China
- Prior art keywords
- soil
- slope
- high side
- guard wall
- side slopes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/20—Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
Abstract
The present invention relates to a kind of method increasing Stability of Soil of High Side Slopes, a kind of method that soil being applied to the realm of building construction increases Stability of Soil of High Side Slopes.The present invention provides can greatly reduce excavated volume, it is easy to construction, safety is high, simple to operate, can effectively protect the method increasing Stability of Soil of High Side Slopes preventing soil quality dam from slope instability easily occurring under heavy rain, earthquake operating mode, comprise the following steps: a, the soil body is cut slope process, set up porous draining steel pipe, steel pipe Nei Neisai scupper hose;B, set up concrete guard wall at toe, pour into neat slurry at gabion or rock ballast top, to orrhorrhea top so that it is form entirety.Side slope top is suitably cut slope and is processed by the present invention, sets up concrete guard wall and reinforced gabion, and backfills space with rock ballast, and its excavated volume is few, easy construction, safety is high, simple to operate, process cost is low, it is possible to increase the drag at toe, dramatically increases the stability of soil-slope.
Description
Technical field
The present invention relates to a kind of method increasing Stability of Soil of High Side Slopes, particularly one is applied to the realm of building construction
Soil increase Stability of Soil of High Side Slopes method.
Background technology
Soil quality dam structure refers to the soil body thickness edge slope structure more than 25 meters, when soil body thickness is more than 25 meters, its
Highly big, there is batholith in soil body bottom, under heavy rain, earthquake operating mode, slope instability easily occurs, and building and engineering cause weight
When affecting greatly.In the prior art to the biggest soil-slope, in order to ensure its stable type, typically take to cut side slope slow
(typically can delay in 1:2.5) or a large amount of excavation slope, the method increasing slope retaining measure.But it is of the prior art several
In solution, unfavorable to construction investment, the duration is had an impact simultaneously, be also unfavorable for construction.Therefore prior art does not also have
One can greatly reduce excavated volume, it is simple to construction, and safety is high, simple to operate, it is possible to effectively protects preventing soil quality dam from existing
The method increasing Stability of Soil of High Side Slopes of slope instability is easily there is under heavy rain, earthquake operating mode.
Summary of the invention
The technical problem to be solved is to provide one can greatly reduce excavated volume, it is simple to construction, safety
Height, simple to operate, it is possible to effectively to protect the increase soil property preventing soil quality dam from slope instability easily occurring under heavy rain, earthquake operating mode
The method of Stability for High Slope.
For solving above-mentioned technical problem, the method increasing Stability of Soil of High Side Slopes that the present invention uses, including following step
Rapid:
A, the soil body is cut slope process, 3.9 meters to 4.1 meters scopes bottom side slope, excavate into 1:0.749 to 1 temporarily:
The abrupt slope of 0.51, and set up porous draining steel pipe in this range, steel pipe Nei Neisai scupper hose;
B, in the range of 2 meters to 3 meters from toe, set up concrete guard wall, between concrete guard wall and slope body, first place steel
Muscle gabion, then backfill in space with rock ballast, concrete guard wall height flushes with reinforced gabion.When concrete guard wall reaches age
After, pour into neat slurry at gabion or rock ballast top, to orrhorrhea top so that it is form entirety.
Further, concrete guard wall basis dowel is connected with basement rock.
Further, at concrete guard wall, PVC drain pipe is buried underground.
Further, pouring into the ratio of mud of neat slurry at gabion or rock ballast top is 0.7:1.
Further, described concrete guard wall uses the concrete of label C15.
Further, at side slope, geotextiles is laid.
The invention has the beneficial effects as follows: the present invention side slope top is suitably cut slope process, set up concrete guard wall with
And reinforced gabion, and backfill space with rock ballast, its excavated volume is few, easy construction, and safety is high, simple to operate, processes cost low,
The drag at toe can be increased, dramatically increase the stability of soil-slope.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention;
Parts, position and numbering in figure: side slope 1, gradual sloped portion 2, reinforced gabion 3, concrete guard wall 4, rock ballast backfill
Layer 5, draining steel pipe 6, geotextiles 7, dowel 8, PVC drain pipe 9, abrupt slope part 10.
Detailed description of the invention
The invention will be further described below in conjunction with the accompanying drawings.
For solving above-mentioned technical problem, the method increasing soil quality dam 1 stability that the present invention uses, including following step
Rapid:
A, the soil body is cut slope process, bottom side slope 1,3.9 meters to 4.1 meters scopes, excavate into 1:0.749 extremely temporarily
The abrupt slope of 1:0.51, and set up porous draining steel pipe 6 in this range, steel pipe Nei Neisai scupper hose;
B, in the range of 2 meters to 3 meters from toe, set up concrete guard wall 4, first place between concrete guard wall 4 and slope body
Reinforced gabion 3, then backfill in space with rock ballast, form the rock ballast backfill layer 5 in figure, concrete guard wall 4 height and reinforced gabion 3
Flush.After concrete guard wall 4 reaches age, pour into neat slurry at gabion or rock ballast top, to orrhorrhea top so that it is
Form entirety.The method increasing soil quality dam 1 stability using the application only suitably carries out part side slope and cuts slope process, shape
Become gradual sloped portion 2 in Fig. 1, retain a part of abrupt slope part 10 and make slope ratio be maintained at the scope of 1:0.749 to 1:0.51, and entering
Row is cut the place of slope process and is arranged porous draining steel pipe 6, steel pipe Nei Neisai scupper hose, can be greatly saved compared to existing technology
Excavation workload, and get rid of the hydrops that heavy rain causes in time, improve side slope 1 stability.Coagulation is set up in toe certain limit
Soil barricade 4, and backfill with reinforced gabion 3 and rock ballast so that it is side slope 1 is formed effectively protection.
Concrete guard wall 4 basis dowel 8 is connected with basement rock.Concrete guard wall 4 is connected by dowel 8 with batholith,
Newly-increased structure can be made to form entirety with batholith, thus improve structural stability.
PVC drain pipe 9 is buried underground at concrete guard wall 4.PVC drain pipe 9 is set in concrete guard wall 4, can be timely
Get rid of the rainwater assembled inside concrete guard wall 4.
Gabion or rock ballast for ensureing backfill can be effectively formed an entirety and pour into striaght cement at gabion or rock ballast top
The ratio of mud of slurry is 0.7:1.
For ensureing concrete guard wall 4 mass, described concrete guard wall 4 uses the concrete of label C15.
At side slope, lay geotextiles 7 can play waterproof effect.
Side slope 1 top is suitably cut slope and is processed by the present invention, sets up concrete guard wall 4 and reinforced gabion 3, and uses stone
Slag backfill space, its excavated volume is few, easy construction, and safety is high, simple to operate, processes cost low, it is possible to increase resisting at toe
Power, significantly increases the stability of soil-slope 1.
Claims (6)
1. the method increasing Stability of Soil of High Side Slopes, it is characterised in that: comprise the following steps:
A, the soil body cut slope process, in 3.9 meters to the 4.1 meters scopes in side slope (1) bottom, excavate into 1:0.749 to 1 temporarily:
The abrupt slope of 0.51, and set up porous draining steel pipe (6) in this range, steel pipe Nei Neisai scupper hose;
B, in the range of 2 meters to 3 meters from toe, set up concrete guard wall (4), first place between concrete guard wall (4) and slope body
Reinforced gabion (3), then backfill in space with rock ballast, concrete guard wall (4) height flushes with reinforced gabion (3), when concrete keeps off
After wall (4) reaches age, pour into neat slurry at gabion or rock ballast top, to orrhorrhea top so that it is form entirety.
2. the method increasing Stability of Soil of High Side Slopes as claimed in claim 1, it is characterised in that: by concrete guard wall (4) base
Plinth dowel (8) is connected with basement rock.
3. the method increasing Stability of Soil of High Side Slopes as claimed in claim 1, it is characterised in that: at concrete guard wall (4) place
Bury PVC drain pipe (9) underground.
4. the method increasing Stability of Soil of High Side Slopes as claimed in claim 1, it is characterised in that: fill at gabion or rock ballast top
The ratio of mud entering neat slurry is 0.7:1.
5. the method increasing Stability of Soil of High Side Slopes as claimed in claim 1, it is characterised in that: described concrete guard wall (4)
Use the concrete of label C15.
6. the method increasing Stability of Soil of High Side Slopes as claimed in claim 1, it is characterised in that: at side slope, lay geotextiles
(7)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610608763.3A CN106088115A (en) | 2016-07-28 | 2016-07-28 | The method increasing Stability of Soil of High Side Slopes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610608763.3A CN106088115A (en) | 2016-07-28 | 2016-07-28 | The method increasing Stability of Soil of High Side Slopes |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106088115A true CN106088115A (en) | 2016-11-09 |
Family
ID=57478476
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610608763.3A Pending CN106088115A (en) | 2016-07-28 | 2016-07-28 | The method increasing Stability of Soil of High Side Slopes |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106088115A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106498977A (en) * | 2016-11-23 | 2017-03-15 | 中国电建集团成都勘测设计研究院有限公司 | Outrigger formula retaining wall structure |
CN108316237A (en) * | 2018-01-26 | 2018-07-24 | 南京珍珠泉园林建设有限公司 | Revetment barricade |
CN108842781A (en) * | 2018-08-06 | 2018-11-20 | 中国电建集团华东勘测设计研究院有限公司 | A kind of Excavation of High And Steep Slopes tap cinder construction method |
CN109098191A (en) * | 2018-09-19 | 2018-12-28 | 河北工业大学 | A kind of depth cheats method for reinforcing side slope of paddling suddenly |
CN113684910A (en) * | 2021-07-22 | 2021-11-23 | 中国市政工程西北设计研究院有限公司 | Construction method for jacking pipe to exit from inclined slope |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201581404U (en) * | 2009-09-28 | 2010-09-15 | 西京学院 | Isolated retaining wall |
KR101045314B1 (en) * | 2010-05-10 | 2011-06-29 | 주식회사 우빈기술개발 | Retaining wall and construnction method of retaining wall |
CN203498847U (en) * | 2013-10-22 | 2014-03-26 | 敬启培 | Landslide prevention system |
CN104863176A (en) * | 2015-06-10 | 2015-08-26 | 上海煤气第二管线工程有限公司 | Natural gas pipeline engineering retaining wall and construction method thereof |
KR20150138771A (en) * | 2014-06-02 | 2015-12-10 | 정창현 | Water storage type retaining wall with double wall structure and the construction method therefor |
-
2016
- 2016-07-28 CN CN201610608763.3A patent/CN106088115A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201581404U (en) * | 2009-09-28 | 2010-09-15 | 西京学院 | Isolated retaining wall |
KR101045314B1 (en) * | 2010-05-10 | 2011-06-29 | 주식회사 우빈기술개발 | Retaining wall and construnction method of retaining wall |
CN203498847U (en) * | 2013-10-22 | 2014-03-26 | 敬启培 | Landslide prevention system |
KR20150138771A (en) * | 2014-06-02 | 2015-12-10 | 정창현 | Water storage type retaining wall with double wall structure and the construction method therefor |
CN104863176A (en) * | 2015-06-10 | 2015-08-26 | 上海煤气第二管线工程有限公司 | Natural gas pipeline engineering retaining wall and construction method thereof |
Non-Patent Citations (1)
Title |
---|
邱云: "某水电站进水口上方堆积体边坡变形及工程治理措施", 《水电站设计》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106498977A (en) * | 2016-11-23 | 2017-03-15 | 中国电建集团成都勘测设计研究院有限公司 | Outrigger formula retaining wall structure |
CN108316237A (en) * | 2018-01-26 | 2018-07-24 | 南京珍珠泉园林建设有限公司 | Revetment barricade |
CN108316237B (en) * | 2018-01-26 | 2020-02-14 | 南京珍珠泉园林建设有限公司 | Revetment retaining wall |
CN108842781A (en) * | 2018-08-06 | 2018-11-20 | 中国电建集团华东勘测设计研究院有限公司 | A kind of Excavation of High And Steep Slopes tap cinder construction method |
CN109098191A (en) * | 2018-09-19 | 2018-12-28 | 河北工业大学 | A kind of depth cheats method for reinforcing side slope of paddling suddenly |
CN113684910A (en) * | 2021-07-22 | 2021-11-23 | 中国市政工程西北设计研究院有限公司 | Construction method for jacking pipe to exit from inclined slope |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106088115A (en) | The method increasing Stability of Soil of High Side Slopes | |
CN106703044B (en) | One kind stream modeling shape rinse fill soft stratum slope combination supporting method | |
CN204343339U (en) | A kind of temporary support columns waterproof base plate | |
CN202689031U (en) | Deep foundation pit retaining and protecting retaining wall | |
CN107762535A (en) | Cut-and-cover tunnel secretly does construction technology under complicated geological environment | |
CN203393530U (en) | Anti-floating lightweight high-fill embankment structure | |
CN103290850A (en) | Arch combination foundation pit retaining and protection system and construction method thereof | |
CN110158649A (en) | The construction method of Adjacent Underground Pipeline when a kind of caisson sinking construction | |
CN203808088U (en) | Gabion gully detention structure for top of hydropower station slag yard | |
CN104131571B (en) | A kind of deep foundation pit supporting construction method | |
CN104775438B (en) | The method of tower position foundation pit construction in karst landform basis rainy season | |
CN203654301U (en) | Expanding soil slope protection system | |
CN101793027A (en) | Core-grouted static pressure anchor rod pile | |
CN204703189U (en) | A kind of cutting barricade being applicable to crevice water, diving growth | |
CN208167783U (en) | Gear mud wall composite structure | |
CN108487301B (en) | In-situ gravity type retaining wall structure for fractured rock mass side slope | |
CN102787608A (en) | Gravity type foundation pit supporting system under vacuum effect and construction method | |
CN102926403B (en) | Roof construction method by cover-excavation method | |
CN206956731U (en) | One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer | |
CN205917706U (en) | Soil property high slope structure | |
CN201635072U (en) | Centrally grouted static-pressured anchor pile former | |
CN213088018U (en) | Shield constructs down and wears building to prevent supporting construction of settlement control | |
CN204919578U (en) | Vacuum tubular well precipitation system under special geological conditions | |
CN103774698B (en) | Soil engineering drainage-free construction method | |
CN103306293A (en) | Reinforcement structure and construction method for water-rich landslide |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161109 |