CN201202120Y - Mixing pile foundation pit supporting structure - Google Patents

Mixing pile foundation pit supporting structure Download PDF

Info

Publication number
CN201202120Y
CN201202120Y CNU2008200876805U CN200820087680U CN201202120Y CN 201202120 Y CN201202120 Y CN 201202120Y CN U2008200876805 U CNU2008200876805 U CN U2008200876805U CN 200820087680 U CN200820087680 U CN 200820087680U CN 201202120 Y CN201202120 Y CN 201202120Y
Authority
CN
China
Prior art keywords
pile
mixing pile
steel strand
anchorage
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008200876805U
Other languages
Chinese (zh)
Inventor
朱俊峰
阮张根
李斌
谢惠珍
严忠海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shunjiang Building Group
Original Assignee
Zhejiang Shunjiang Building Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Shunjiang Building Group filed Critical Zhejiang Shunjiang Building Group
Priority to CNU2008200876805U priority Critical patent/CN201202120Y/en
Application granted granted Critical
Publication of CN201202120Y publication Critical patent/CN201202120Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a mixing pile foundation pit supporting structure, which comprises a concrete mixing pile, an anchorage pile and a steel strand, wherein the anchorage pile is arranged on an axis which passes through the concrete mixing pile and is vertical to the edge of a foundation pit; and the steel strand is respectively connected with the concrete mixing pile and the anchorage pile. Above-mentioned scheme, the utility model discloses a mixing pile underground structure on concrete mixing pile basis, has increased the anchorage stake, and concrete mixing pile, anchorage stake pass through the steel strand cable and connect. The horizontal force of the top of the mixing pile on the soil body is offset by the pulling force of the steel cable, the stress form of the concrete mixing pile is improved, the anti-overturning capacity of the concrete mixing pile is improved, meanwhile, the cross section width of the mixing pile can be reduced compared with that of the engineering under the same condition, and the engineering cost is saved.

Description

A kind of stirring pile pit supporting construction
Technical field
The utility model relates to the deep foundation pit supporting structure in a kind of building operations, a kind of stirring pile pit supporting construction of more specifically saying so.
Background technology
In the method for pattern foundation pit supporting structure, soil nailing and composite soil nailing are used commonplace, and expense is also cheaper, if but can't adopt soil nailing or composite soil nailing because soil property reason and foundation depth are big the time, generally adopt deep-mixed pile supporting and protection structure.Existing agitation pile supporting and protection structure is the concrete pile on the foundation ditch limit of arranging, and can prevent to cheat subsiding of limit earth so on the one hand when digging pit, and can prevent to cheat wall infiltration in the hole on the other hand.Because above-mentioned agitation pile supporting and protection structure is the gravity by agitation pile self keeps the stable of side slope, the horizontal force action bottom offset that withstands on the soil body like this is excessive, causes piling wall integral body to topple easily.
The utility model content
At the problems referred to above, the problem that the utility model quasi-solution is determined provides a kind of agitation pile supporting and protection structure of agitation pile more stable and stronger, and it is excessive and cause piling wall integral body to topple to prevent that stake from withstanding on the horizontal force action bottom offset of the soil body.
For achieving the above object, the utility model by the following technical solutions: a kind of stirring pile pit supporting construction, it comprises concrete agitation pile, anchorage stake, steel strand cable, described anchorage stake is on concrete agitation pile and the axis vertical with the foundation ditch limit; Described steel strand cable is connected with concrete agitation pile, anchorage stake respectively.
Foundation ditch limit one side of described concrete agitation pile upper end is implanted with the band armored concrete slab, and the top of described concrete agitation pile and band armored concrete slab is provided with the contact beam that bears down on one, described steel strand cable with coagulate native agitation pile and get in touch beam by bearing down on one and be connected.Described steel strand cable preferably is provided with the PVC sleeve pipe outward.
Adopt such scheme, stirring pile pit supporting construction of the present utility model on concrete agitation pile basis, has increased the anchorage stake, and concrete agitation pile, anchorage stake connect by the steel strand cable.Agitation pile withstands on the horizontal force of the soil body like this, pulling force by the steel strand cable is offset, and has improved the stress form of concrete agitation pile, has improved concrete agitation pile resistance to capsizing, can reduce the breadth of section of agitation pile simultaneously than the engineering of equal conditions, save engineering cost.
Description of drawings
Fig. 1 is the schematic diagram of stirring pile pit supporting construction of the present utility model.
Among the figure, 1-concrete agitation pile, the stake of 2-anchorage, 3-steel strand cable, 4-foundation ditch limit, 5-is with armored concrete slab, the 6-contact beam that bears down on one, 7-PVC sleeve pipe.
The specific embodiment
As shown in Figure 1, stirring pile pit supporting construction of the present utility model, it is included in concrete agitation pile 1, anchorage stake 2, steel strand cable 3, and described anchorage stake 2 is on concrete agitation pile 1 and the axis vertical with foundation ditch limit 4.
Described steel strand cable 3 respectively with coagulate native agitation pile 1, anchorage stake 2 is connected.For guaranteeing the pulling force of steel strand cable 3, in practical operation, can tighten up steel strand cable 3 usefulness Chain blocks.
As improvement, foundation ditch limit 4 one sides of described concrete agitation pile 1 upper end are implanted with band armored concrete slab 5, the top of described concrete agitation pile 1 and band armored concrete slab 5 is provided with the contact beam 6 that bears down on one, and described steel strand cable 3 is got in touch beam 6 with concrete agitation pile 1 and is connected by bearing down on one.
Be the convenience in practical operation, will pass the temporary road of construction, can earlier PVC sleeve pipe 7 be embedded in the road, then as long as steel strand cable 3 is passed PVC sleeve pipe 7 as steel strand cable 3.

Claims (3)

1, a kind of stirring pile pit supporting construction, it comprises concrete agitation pile (1), it is characterized in that it also comprises anchorage stake (2), steel strand cable (3), described anchorage stake (2) is on concrete agitation pile (1) and the axis vertical with foundation ditch limit (4); Described steel strand cable (3) respectively with coagulate native agitation pile (1), anchorage stake (2) is connected.
2, stirring pile pit supporting construction according to claim 1, foundation ditch limit (4) one sides that it is characterized in that described concrete agitation pile (1) upper end are implanted with band armored concrete slab (5), the top of described concrete agitation pile (1) and band armored concrete slab (5) is provided with the contact beam (6) that bears down on one, described steel strand cable (3) with coagulate native agitation pile (1) and get in touch beam (6) by bearing down on one and be connected.
3, stirring pile pit supporting construction according to claim 1 and 2 is characterized in that the outer PVC sleeve pipe (7) that is provided with of described steel strand cable (3).
CNU2008200876805U 2008-05-28 2008-05-28 Mixing pile foundation pit supporting structure Expired - Lifetime CN201202120Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200876805U CN201202120Y (en) 2008-05-28 2008-05-28 Mixing pile foundation pit supporting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200876805U CN201202120Y (en) 2008-05-28 2008-05-28 Mixing pile foundation pit supporting structure

Publications (1)

Publication Number Publication Date
CN201202120Y true CN201202120Y (en) 2009-03-04

Family

ID=40424432

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200876805U Expired - Lifetime CN201202120Y (en) 2008-05-28 2008-05-28 Mixing pile foundation pit supporting structure

Country Status (1)

Country Link
CN (1) CN201202120Y (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100591861C (en) * 2008-05-28 2010-02-24 浙江舜江建设集团有限公司 Mixing pile foundation pit supporting structure
CN103806450A (en) * 2014-03-12 2014-05-21 中国建筑西南勘察设计研究院有限公司 Double-row pile foundation pit reinforcement structure
CN109056717A (en) * 2018-07-09 2018-12-21 广东工业大学 It is a kind of without support suspension device and its construction method
CN111560962A (en) * 2020-04-25 2020-08-21 北京市地质工程公司 Backfill area foundation pit supporting structure and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100591861C (en) * 2008-05-28 2010-02-24 浙江舜江建设集团有限公司 Mixing pile foundation pit supporting structure
CN103806450A (en) * 2014-03-12 2014-05-21 中国建筑西南勘察设计研究院有限公司 Double-row pile foundation pit reinforcement structure
CN109056717A (en) * 2018-07-09 2018-12-21 广东工业大学 It is a kind of without support suspension device and its construction method
CN109056717B (en) * 2018-07-09 2020-11-17 广东工业大学 Support-free supporting device and construction method thereof
CN111560962A (en) * 2020-04-25 2020-08-21 北京市地质工程公司 Backfill area foundation pit supporting structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN100564700C (en) The job practices of lattice type steel column tower crane pedestal
CN203034464U (en) Truss type foundation pit supporting structure
CN202559361U (en) Precast high strength concrete thin-wall steel pipe pile foundation pit supporting structure
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN106759442A (en) A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method
CN101446088A (en) Construction method for pole and tower foundation in Gobi Desert gravelly soil area
CN201202120Y (en) Mixing pile foundation pit supporting structure
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN106088115A (en) The method increasing Stability of Soil of High Side Slopes
CN201581394U (en) Large pile toe grout-injection precast pile
CN202323963U (en) Drainage and anchoring combined device for side slope
CN202401461U (en) Novel foundation pit shoring structure
CN202830994U (en) Protective structure for bedding slope bridge abutments
CN100591861C (en) Mixing pile foundation pit supporting structure
CN201874008U (en) Discontinuous concrete grouting pile and wall structure
CN204662246U (en) steep slope bridge pier structure
CN204023587U (en) A kind of novel environment friendly slope reinforcement structure
CN102493436A (en) Novel manual tunneling construction method of rectangular anti-slide pile
CN202543946U (en) Supporting structure for drainage type fender posts in soft soil area
CN202247929U (en) Plug-shaped bearing platform structure
CN202247910U (en) Soil retaining structure with different inclination angles of anti-skid cement soil pile
CN206110140U (en) A vertical solid that adds that is used for weak soil foundation ditch to put slope excavation greatly
CN214194751U (en) Intercepting drain structure suitable for steep rock slope
CN201874006U (en) Intubating grouting base of transmission line iron tower
CN102235017B (en) Lateral force resisting method for soft soil foundation building

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Effective date of abandoning: 20080528

AV01 Patent right actively abandoned

Effective date of abandoning: 20080528

C25 Abandonment of patent right or utility model to avoid double patenting