CN102235017B - Lateral force resisting method for soft soil foundation building - Google Patents

Lateral force resisting method for soft soil foundation building Download PDF

Info

Publication number
CN102235017B
CN102235017B CN 201010166009 CN201010166009A CN102235017B CN 102235017 B CN102235017 B CN 102235017B CN 201010166009 CN201010166009 CN 201010166009 CN 201010166009 A CN201010166009 A CN 201010166009A CN 102235017 B CN102235017 B CN 102235017B
Authority
CN
China
Prior art keywords
building
foundation
lateral force
soft soil
taper pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201010166009
Other languages
Chinese (zh)
Other versions
CN102235017A (en
Inventor
王怀忠
秦夏强
魏宏超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoshan Iron and Steel Co Ltd
China MCC20 Group Corp Ltd
Original Assignee
Baoshan Iron and Steel Co Ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoshan Iron and Steel Co Ltd, China MCC20 Group Corp Ltd filed Critical Baoshan Iron and Steel Co Ltd
Priority to CN 201010166009 priority Critical patent/CN102235017B/en
Publication of CN102235017A publication Critical patent/CN102235017A/en
Application granted granted Critical
Publication of CN102235017B publication Critical patent/CN102235017B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

软土地基建筑物抵抗侧向力的方法,在直桩上施工完成建筑物及其基础,建筑物及其基础的竖向重力荷载由直桩承受,待建筑施工完成并且沉降稳定后,再从建筑物外侧向建筑物下的基础下方对称斜向打入斜桩,斜桩顶部设置在建筑物外轮廓一侧,其底部设置在建筑物外轮廓另一侧,并使斜桩顶部与基础连接。本发明软土地基建筑物抵抗侧向力的方法通过设置斜桩,可以有效提高建筑物承受侧向作用和荷载的能力;另外,本发明可用于新建建筑物,也可以用于加固已建建筑物。

The method for building on soft soil foundation to resist lateral force is to complete the construction of the building and its foundation on straight piles, and the vertical gravity load of the building and its foundation is borne by the straight piles. On the outside of the building, the inclined piles are symmetrically driven obliquely under the foundation under the building. The top of the inclined piles is set on one side of the outer contour of the building, and the bottom is set on the other side of the outer contour of the building, and the top of the inclined piles is connected to the foundation. . The method for resisting lateral force of a building on soft soil foundation of the present invention can effectively improve the ability of the building to withstand lateral action and load by setting inclined piles; in addition, the present invention can be used for newly-built buildings, and can also be used for reinforcing existing buildings thing.

Description

软土地基建筑物抵抗侧向力的方法Method of Resisting Lateral Force of Buildings on Soft Soil Foundation

技术领域 technical field

本发明涉及岩土工程、建筑工程,尤其涉及软土地基建筑物桩基工程中抵抗建筑物侧向力的方法。The invention relates to geotechnical engineering and construction engineering, in particular to a method for resisting building lateral force in soft soil foundation building pile foundation engineering.

背景技术 Background technique

软土地基一般设置强度低、压缩性高的软弱土层,在软土地基构筑建筑物,若对软土地基不加处理,往往会发生地基失稳或者过量沉陷,导致建筑物被破坏或不能正常使用。Soft soil foundations are generally set with weak soil layers with low strength and high compressibility. Buildings are constructed on soft soil foundations. If the soft soil foundation is not treated, foundation instability or excessive subsidence will often occur, resulting in buildings being damaged or unable to Normal use.

现有对软土地基处理的技术中如中国专利申请号CN200710068309.4所公开的“一种水泥搅拌土帷幕植入预制钢筋砼抗侧向力桩的方法”,其采用在施工现场先用水泥搅拌机沿桩体的植入深度,视土质及挤土情况,全程搅拌土或上部止水帷幕部分搅拌土形成帷幕,然后用压桩机植入桩体,使形成挡土止水围护墙,其中桩体采用钢筋砼预制T形/工字形桩,由于采用强力搅拌土或钻机引孔注浆,原则上适用于各类土质的围护工程。In the existing technology for soft soil foundation treatment, as disclosed in Chinese Patent Application No. CN200710068309.4, "A Method for Implanting Prefabricated Reinforced Concrete Anti-Lateral Force Pile with Cement Mixed Soil Curtain", it adopts the method of first using cement at the construction site. The mixer is placed along the depth of the pile body, depending on the soil quality and soil compaction, the whole process of mixing the soil or part of the upper water-stop curtain to form a curtain, and then the pile driver is used to implant the pile body to form a soil-retaining water-stop enclosure wall. Among them, the pile body adopts reinforced concrete prefabricated T-shaped / I-shaped piles, and because of the use of strong soil mixing or drilling rigs for grouting, it is suitable for various types of soil enclosure projects in principle.

还有如中国专利号CN99237125.2公开了“施打土层锚杆、斜桩、不开挖埋管的锤击装置”,该专利技术是在土建工程中工业与民用建筑的岩土工程中使用土层锚杆、斜桩、不开挖埋管的锤击装置,本装置由机座、塔架、卷扬机、冲击锤、导轨组成,其特征是:导轨固定在大滑轮的上轴上,导轨可以在0~90°之间任意倾角转动,冲击锤下面焊有4个轴承的车轮,冲击锤放在导轨上,被卷扬机拉动与放松,可以在导轨上下自由滚动冲击钢管,把粗细不等的钢管,按不同的角度打入土中,该装置的设备轻巧、可高低变化施工,可进入狭窄场地、山上、水下施工,无污染、无振动、可无噪声施工。Also as Chinese Patent No. CN99237125.2 discloses "a hammering device for driving soil anchors, inclined piles, and buried pipes without excavation", this patented technology is used in the geotechnical engineering of industry and civil buildings in civil engineering A hammering device for soil anchors, inclined piles, and buried pipes without excavation. This device is composed of a machine base, a tower, a hoist, an impact hammer, and a guide rail. It can be rotated at any inclination angle between 0 and 90°. There are four bearing wheels welded under the impact hammer. The impact hammer is placed on the guide rail, pulled and loosened by the hoist, and can freely roll up and down the guide rail to impact the steel pipe. The steel pipes are driven into the soil according to different angles. The equipment of this device is light and handy, and can be constructed with height changes. It can enter narrow sites, hills, and underwater constructions. It can be constructed without pollution, vibration, and noise.

另外,中国专利号CN97235911.7公开了“一种透空式防波堤桩基”,其包含结构单元和连接结构单元的横梁,至少两排结构单元呈前,后交错分布,结构单元由至少三根以下张上团、朝不同方向倾斜的、一端嵌固海底的单桩所组成的斜桩群以及位于单桩上部将所说的斜桩群上端固接成一体的桩帽组成。与现有技术相比,本实用新型具有在每延米堤长耗用桩基断面积相同的情况下,每延米堤长的水平承受力却提高四倍以上等优点。In addition, Chinese Patent No. CN97235911.7 discloses "a kind of permeable breakwater pile foundation", which includes structural units and beams connecting structural units. At least two rows of structural units are distributed in front and rear, and the structural units are composed of at least three or less The utility model is composed of an inclined pile group composed of single piles with one end embedded in the seabed, inclined in different directions, and a pile cap located on the upper part of the single pile to fix the upper ends of the said inclined pile group into one body. Compared with the prior art, the utility model has the advantages of increasing the horizontal bearing capacity by more than four times per linear meter of dike length under the condition that the sectional area of pile foundation is the same per linear meter of embankment length.

中国专利申请号CN92102906.3涉及建筑领域危险建筑物的处理方法,在基础出现沉陷或不均匀沉陷导致地基与基础边缘产生了剪切破坏,影响正常使用时,在基础各个部位加以斜桩,若是不均匀沉陷,则先在基础隆起多的一侧开沟槽使建筑物纠正到正常位置后,灌注桩体材料,并在隆起少(或下陷)的一侧加斜桩,隆起多的一侧少加斜桩,其沟槽位置、斜桩倾角、长度、多少,根据塑性理论求得,将基础各部位的沉降量与沉降差控制在一定的许可范围内,这样就使危险建筑物又能正常使用。Chinese patent application number CN92102906.3 relates to the treatment method of dangerous buildings in the construction field. When the foundation subsidence or uneven subsidence causes shear damage to the foundation and the edge of the foundation, which affects normal use, add inclined piles to various parts of the foundation. If If the subsidence is not uniform, first open a trench on the side with more uplift of the foundation to correct the building to the normal position, pour the pile material, and add inclined piles on the side with less uplift (or subsidence), and the side with more uplift Less inclined piles are added, and the groove position, inclined pile angle, length, and number are obtained according to the theory of plasticity, and the settlement and settlement difference of each part of the foundation are controlled within a certain allowable range, so that dangerous buildings can be built again. Normal use.

上述专利技术中虽然在基础各个部位加以斜桩处理危险建筑物的处理方法、另外桥梁和码头等建筑物也经常采取设置斜桩的方法抵抗侧向力,这些设置斜桩的方法由于以下原因不能广泛适用于工业和民用建筑中:Although in the above-mentioned patented technology, inclined piles are used to deal with dangerous buildings at various parts of the foundation, in addition bridges and docks and other buildings often adopt the method of setting inclined piles to resist lateral force, these methods of setting inclined piles cannot be used for the following reasons Widely used in industrial and civil buildings:

(1)因建筑物受正常的重力荷载作用向下沉降,斜桩顶部除受到压力和剪切之外,还产生弯曲变形,很容易因受力复杂且强度不足而破坏。(1) Due to the downward settlement of the building under the normal gravity load, in addition to being subjected to pressure and shear, the top of the inclined pile also undergoes bending deformation, which is easily damaged due to complex stress and insufficient strength.

(2)设置斜桩通常包括向建筑物外侧倾斜桩,斜桩可能超出建筑物许可的平面范围和深度范围。(2) Setting inclined piles usually includes inclined piles to the outside of the building, and the inclined piles may exceed the permitted plane range and depth range of the building.

(3)设置向建筑物内侧倾斜桩,建筑物在正常的重力荷载作用下,两侧向内倾斜桩斜桩之间的基础会产生较大的拉应力从而开裂破坏。(3) Install inclined piles to the inside of the building. Under the normal gravity load of the building, the foundation between the inclined piles on both sides will generate a large tensile stress and crack and fail.

发明内容 Contents of the invention

本发明的目的提供一种软土地基建筑物抵抗侧向力的方法,通过设置斜桩,可以有效提高建筑物承受侧向作用和荷载的能力;本方法可用于新建建筑物,也可以用于加固已建建筑物。The object of the present invention provides a kind of method that the building of soft soil foundation resists lateral force, by arranging inclined pile, can effectively improve the ability of building to bear lateral action and load; This method can be used for new building, also can be used for Fortify existing buildings.

为达到上述目的,本发明的技术方案是:For achieving the above object, technical scheme of the present invention is:

软土地基建筑物抵抗侧向力的方法,在直桩上施工完成建筑物及其基础,建筑物及其基础的竖向重力荷载由直桩承受,待建筑施工完成并且沉降稳定后,再从建筑物外侧向建筑物下的基础下方对称斜向打入斜桩,斜桩顶部设置在建筑物外轮廓一侧,其底部设置在建筑物外轮廓另一侧,并使斜桩顶部与基础连接。The method for building on soft soil foundation to resist lateral force is to complete the construction of the building and its foundation on straight piles, and the vertical gravity load of the building and its foundation is borne by the straight piles. On the outside of the building, the inclined piles are symmetrically driven obliquely under the foundation under the building. The top of the inclined piles is set on one side of the outer contour of the building, and the bottom is set on the other side of the outer contour of the building, and the top of the inclined piles is connected to the foundation. .

进一步,本发明软土地基建筑物抵抗侧向力的方法,其包括如下步骤:Further, the method for resisting lateral force of the soft ground building of the present invention comprises the following steps:

1)在新建建筑物位置先施工设置直桩和对称斜向打入斜桩;斜桩顶部设置在建筑物外轮廓一侧,其底部设置在建筑物外轮廓另一侧;1) At the location of the new building, construct straight piles and symmetrical obliquely driven inclined piles first; the top of the inclined piles is set on one side of the outer contour of the building, and the bottom is set on the other side of the outer contour of the building;

2)在直桩上施工建筑物基础,斜桩与建筑物基础断开,并且预留出沉降高度;2) Construct the building foundation on the straight pile, the inclined pile is disconnected from the building foundation, and the settlement height is reserved;

3)在建筑物基础上施工建筑物;3) Construction of buildings on building foundations;

4)建筑物施工完成并且沉降稳定后,再将斜桩的顶部与建筑物基础连接。4) After the construction of the building is completed and the settlement is stable, connect the top of the inclined pile to the foundation of the building.

又,本发明软土地基建筑物抵抗侧向力的方法,其特征是,包括如下步骤:Again, the method for resisting lateral force of the soft ground building of the present invention is characterized in that it comprises the following steps:

1.在已建建筑物下已经设置有建筑物基础及其下的直桩;1. The building foundation and the straight piles under it have been set up under the built building;

2.在建筑物基础上完成建筑物施工,并且沉降稳定后,再在建筑物基础之下对称斜向打入打入斜桩,斜桩顶部设置在建筑物外轮廓一侧,其底部设置在建筑物外轮廓另一侧。2. After the construction of the building is completed on the foundation of the building and the settlement is stable, the inclined piles are symmetrically driven obliquely under the foundation of the building. The top of the inclined pile is set on the side of the outer contour of the building, and the bottom is set The other side of the building outline.

另外,所述的建筑物基础的形式为条形、或筏板形,或箱形。In addition, the form of the building foundation is strip shape, or raft shape, or box shape.

所述的斜桩采用单位横截面积抗拉强度大于5MPa的桩。The inclined pile adopts a pile whose unit cross-sectional area tensile strength is greater than 5MPa.

软土地基建筑物基础增设向内倾斜桩,以抵抗侧向力。斜桩顶部既能够承受压力,也能够承受拉力。建筑物的竖向荷载作用下,建筑物两侧向内倾斜桩之间的基础拉应力可以被控制在强度允许范围内;斜桩主要受到因侧向荷载引起的轴向力,建筑物在竖向重力荷载作用下沉降引起斜桩顶部的剪切和弯曲内力可以被控制在强度允许范围内。Inwardly inclined piles are added to the foundation of buildings on soft soil foundation to resist lateral force. The top of the inclined pile can withstand both compression and tension. Under the vertical load of the building, the tensile stress of the foundation between the inwardly inclined piles on both sides of the building can be controlled within the allowable range of strength; the inclined piles are mainly subjected to the axial force caused by the lateral load, and the building is The shear and bending internal force at the top of the inclined pile caused by the settlement under the gravity load can be controlled within the allowable range of strength.

本发明的有益效果Beneficial effects of the present invention

1.本发明通过设置斜桩,可以有效提高建筑物承受侧向作用和荷载的能力,包括侧向地震作用、侧向土压力、风荷载、爆炸荷载、撞击作用等。1. The present invention can effectively improve the ability of buildings to withstand lateral actions and loads by setting inclined piles, including lateral seismic actions, lateral earth pressure, wind loads, blast loads, and impact effects.

2.斜桩能够对称布置,从而避免使建筑物承受局部偏心荷载。2. The inclined piles can be arranged symmetrically, so as to avoid the local eccentric load of the building.

3.本发明可用于新建建筑物,也可以用于加固已建建筑物。3. The present invention can be used for newly-built buildings, and can also be used for reinforcing existing buildings.

4.建筑物及基础的竖向重力荷载由直桩承受,沉降稳定后再将向内倾斜桩的顶部与基础连接,斜桩主要受到因侧向荷载引起的轴向力,因建筑物沉降引起的斜桩顶部剪切和弯曲内力可以被控制在强度允许范围内。4. The vertical gravity load of the building and the foundation is borne by the straight pile. After the settlement is stable, the top of the inwardly inclined pile is connected to the foundation. The inclined pile is mainly subjected to the axial force caused by the lateral load, which is caused by the settlement of the building. The shear and bending internal forces at the top of the inclined pile can be controlled within the allowable range of strength.

5.因竖向重力荷载作用,建筑物两侧向内倾斜桩之间的基础拉应力可以被控制在强度允许范围内,因而不会开裂。5. Due to the vertical gravity load, the foundation tensile stress between the inwardly inclined piles on both sides of the building can be controlled within the allowable range of strength, so it will not crack.

附图说明 Description of drawings

图1为本发明增设斜桩的建筑物的示意图;Fig. 1 sets up the schematic diagram of the building of inclined pile for the present invention;

图2a~图2c为本发明一实施例即新建建筑物增设斜桩的示意图;Fig. 2a~Fig. 2c are the schematic diagrams of an embodiment of the present invention namely newly-built buildings add inclined pile;

图3a~图3c为本发明另一实施例即已建建筑物增设斜桩的示意图。3a to 3c are schematic diagrams of another embodiment of the present invention, that is, adding inclined piles to existing buildings.

具体实施方式 Detailed ways

下面结合实施例对本发明做进一步说明。The present invention will be further described below in conjunction with embodiment.

参见图1,本发明软土地基建筑物抵抗侧向力的方法,在直桩1上施工完成建筑物2及其基础3,建筑物1及其基础3的竖向重力荷载由直桩1承受,待建筑施工完成并且沉降稳定后,再从建筑物2外侧向建筑物2下的基础3下方对称斜向打入斜桩4、5,斜桩4、5顶部设置在建筑物2外轮廓一侧,其底部设置在建筑物2外轮廓另一侧,并使斜桩顶部与基础3连接。Referring to Fig. 1, the method for the soft ground building of the present invention to resist lateral force, construction completes building 2 and foundation 3 thereof on straight pile 1, the vertical gravity load of building 1 and foundation 3 thereof is borne by straight pile 1 After the building construction is completed and the settlement is stable, the inclined piles 4 and 5 are symmetrically driven obliquely from the outside of the building 2 to the bottom of the foundation 3 under the building 2, and the tops of the inclined piles 4 and 5 are arranged on the outer contour of the building 2 side, the bottom of which is set on the other side of the outer contour of the building 2, and the top of the inclined pile is connected to the foundation 3.

待建筑施工完成并且沉降稳定之后再在建筑物下增设向内倾斜桩,使斜桩设置在建筑物许可的平面范围和深度范围内,在建筑物竖向重力荷载作用下建筑物基础和斜桩顶部产生的不利内力可以控制在允许范围内,建筑物的侧向力由斜桩抵抗。After the building construction is completed and the settlement is stable, add inward inclined piles under the building, so that the inclined piles are set within the permitted plane range and depth range of the building. Under the action of the vertical gravity load of the building, the building foundation and the inclined piles The unfavorable internal force generated at the top can be controlled within the allowable range, and the lateral force of the building is resisted by the inclined piles.

实施例1Example 1

参见图2a~图2c,本发明方法用于新建建筑物增设斜桩。Referring to Fig. 2a~Fig. 2c, the method of the present invention is used for adding inclined piles to new buildings.

1)在宽约10m的新建建筑物2位置先施工深约30m的直桩1和斜桩4、5;1) Construct the straight pile 1 and the inclined pile 4, 5 with a depth of about 30m at the position of the new building 2 with a width of about 10m;

2)斜桩4、5顶部设置在建筑物2外轮廓一侧,其底部设置在建筑物2外轮廓另一侧,这样斜桩4、5能够布置在许可的建筑物平面范围内;斜桩4、5采用灌入混凝土的钢管构件,其顶部既能够承受压力,也能够承受拉力,其单位横截面积抗拉强度大于5Mpa;2) The top of the inclined piles 4 and 5 is arranged on one side of the outer contour of the building 2, and the bottom thereof is arranged on the other side of the outer contour of the building 2, so that the inclined piles 4 and 5 can be arranged within the permitted building plane range; 4.5 Steel pipe members poured into concrete are used, the top of which can withstand both pressure and tension, and the tensile strength per unit cross-sectional area is greater than 5Mpa;

3)在直桩1上施工建筑物基础3,建筑物基础3的形式可以是条形、筏板形或箱形;斜桩4、5与建筑物基础3断开,并且预留出沉降高度;3) Build the building foundation 3 on the straight pile 1, the form of the building foundation 3 can be strip shape, raft shape or box shape; the inclined piles 4, 5 are disconnected from the building foundation 3, and the settlement height is reserved ;

4)在建筑物基础3上施工建筑物2;4) building a building 2 on the building foundation 3;

5)建筑物2施工完成并且沉降稳定后,再将斜桩4、5的顶部与基础3连接。5) After the construction of the building 2 is completed and the settlement is stable, the tops of the inclined piles 4 and 5 are connected to the foundation 3 .

实施例2Example 2

参见图3a~图3c,本发明方法用于已建建筑物增设斜桩。Referring to Fig. 3a to Fig. 3c, the method of the present invention is used for adding inclined piles to existing buildings.

1)在宽约10m的已建建筑物2下设置有建筑物基础3和深约30m的直桩1,基础3的形式可以是条形、筏板形或箱形;1) Under the built building 2 with a width of about 10m, a building foundation 3 and a straight pile 1 with a depth of about 30m are arranged, and the form of the foundation 3 can be strip-shaped, raft-shaped or box-shaped;

2)建筑物2施工完成并且沉降稳定后再在建筑物基础3之下沉入深约30m的斜桩4、5;2) After the construction of the building 2 is completed and the settlement is stable, the inclined piles 4 and 5 with a depth of about 30m are sunk under the building foundation 3;

3)斜桩4、5顶部设置在建筑物2外轮廓一侧,其底部设置在建筑物2外轮廓另一侧,这样斜桩4、5能够布置在许可的建筑物平面范围内;斜桩4、5采用灌入混凝土的钢管构件,其顶部既能够承受压力,也能够承受拉力;3) The top of the inclined piles 4 and 5 is arranged on one side of the outer contour of the building 2, and the bottom thereof is arranged on the other side of the outer contour of the building 2, so that the inclined piles 4 and 5 can be arranged within the permitted building plane range; 4.5 Steel pipe members poured into concrete are used, the top of which can withstand both pressure and tension;

4)斜桩4、5的顶部与建筑物基础3连接.;4) The tops of the inclined piles 4 and 5 are connected to the building foundation 3;

本发明可推广应用于软土地区的建筑工程和桩基工程中,有效提高建筑物承受侧向作用和荷载的能力。The invention can be popularized and applied in construction engineering and pile foundation engineering in soft soil areas, and can effectively improve the ability of buildings to bear lateral action and load.

Claims (7)

1. the method for soft soil foundation building lateral force resisting, building and basis thereof are completed in construction in straight stake, the vertical gravity load on building and basis thereof is subjected to by straight pile, until building construction complete and settlement stability after, below, basis symmetrical inclined under the building of building lateral is to squeezing into taper pile again, the taper pile top is arranged on building outline one side, and its bottom is arranged on building outline opposite side, and the taper pile top is connected with basic.
2. the method for soft soil foundation building lateral force resisting, is characterized in that, comprises the steps:
1) first construct at the new building object location and straight stake and symmetrical inclined are set to squeezing into taper pile; The taper pile top is arranged on building outline one side, and its bottom is arranged on building outline opposite side;
2) construction building thing basis in straight stake, taper pile and building foundation disconnect, and reserve settling height;
3) construction building thing on the building foundation;
4) architecture construction complete and settlement stability after, then the top of taper pile is connected with the building foundation.
3. the method for soft soil foundation building lateral force resisting as claimed in claim 2, is characterized in that,
Described taper pile adopts unit cross-sectional area tensile strength greater than the stake of 5MPa.
4. the method for soft soil foundation building lateral force resisting as claimed in claim 2, is characterized in that,
The form of described building foundation is bar shaped or raft plate shape or box-shaped.
5. the method for soft soil foundation building lateral force resisting, is characterized in that, comprises the steps:
1) be provided with under the built construction thing building foundation and under straight stake;
2) after settlement stability, then under the built construction beyond the region of objective existence side direction building foundation symmetrical inclined to squeezing into
Taper pile, taper pile top are arranged on building outline one side, and its bottom arranges outside the building
The profile opposite side, and the taper pile top is connected with the building foundation.
6. the method for soft soil foundation building lateral force resisting as claimed in claim 5, is characterized in that,
Described taper pile adopts unit cross-sectional area tensile strength greater than the stake of 5MPa.
7. the method for soft soil foundation building lateral force resisting as claimed in claim 5, is characterized in that,
The form of described building foundation is bar shaped or raft plate shape, or box-shaped.
CN 201010166009 2010-04-29 2010-04-29 Lateral force resisting method for soft soil foundation building Active CN102235017B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010166009 CN102235017B (en) 2010-04-29 2010-04-29 Lateral force resisting method for soft soil foundation building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010166009 CN102235017B (en) 2010-04-29 2010-04-29 Lateral force resisting method for soft soil foundation building

Publications (2)

Publication Number Publication Date
CN102235017A CN102235017A (en) 2011-11-09
CN102235017B true CN102235017B (en) 2013-06-19

Family

ID=44886087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010166009 Active CN102235017B (en) 2010-04-29 2010-04-29 Lateral force resisting method for soft soil foundation building

Country Status (1)

Country Link
CN (1) CN102235017B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318366A (en) * 2018-03-30 2019-10-11 天津大学 The Gravity Type Casisson Berth structure and its method of construction of friction pile are set in foundation
CN112709212B (en) * 2021-02-09 2022-05-17 胡小彦 Weak geological building foundation reinforcement construction method
CN114776229B (en) * 2022-04-25 2024-01-23 中铁大桥勘测设计院集团有限公司 Water area CPTU test system and test method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB263997A (en) * 1925-12-02 1927-01-13 Jorgen Saxild Improvements in and relating to the construction of quay walls, piers and other marine structures
CA2452136A1 (en) * 2002-07-08 2005-06-05 Richard M. Berry Pile array assembly system for reduced soil liquefaction
CN201144425Y (en) * 2007-12-27 2008-11-05 国网北京电力建设研究院 Micro pile tower foundation

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004044198A (en) * 2002-07-11 2004-02-12 Mitsubishi Heavy Ind Ltd Jacket type foundation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB263997A (en) * 1925-12-02 1927-01-13 Jorgen Saxild Improvements in and relating to the construction of quay walls, piers and other marine structures
CA2452136A1 (en) * 2002-07-08 2005-06-05 Richard M. Berry Pile array assembly system for reduced soil liquefaction
CN201144425Y (en) * 2007-12-27 2008-11-05 国网北京电力建设研究院 Micro pile tower foundation

Also Published As

Publication number Publication date
CN102235017A (en) 2011-11-09

Similar Documents

Publication Publication Date Title
CN103758134B (en) A kind of construction method combining Double-row Piles Support system
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN103774675B (en) Construction method of combined double-row pile combined with vertical prestressed bolt support system
CN205742213U (en) Foundation pit supporting construction
CN109183809B (en) Construction method for replacing support of composite support of muddy clay deep foundation pit engineering
CN203729308U (en) Double-row pile supporting system of reinforced concrete pile combined structural steel cement mixing pile wall
CN106759376A (en) Anchored Sheet Pile Wall for Excavation system and its construction method for closing on existing underground structure
CN104389315B (en) Consolidation grouting drilled pile wall and construction method thereof
CN207092107U (en) A kind of anti-subsidence structure using diaphram wall
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
CN107100179B (en) Light combined retaining structure and method for treating large-range high-fill slope engineering
CN206034454U (en) Supporting construction
CN102021901B (en) Method for putting up steel pipe pile platform of abrupt slope bare rock
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN106120791B (en) Nothing makees vertical supporting system underground structure covered back-digging construction method in advance
CN202730796U (en) Existing retaining wall rib plate type unloading reinforcing structure
CN205502063U (en) Combined type retaining structure
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN203891037U (en) Anchor bolt and tree pile combined retaining structure
CN205296177U (en) Dado bearing structure suitable for hole friction pile stake hole is dug in manual work
CN218622256U (en) Double-row pile and inclined pile combined type foundation pit support structure
CN106988337A (en) Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house
CN210002410U (en) ring frame support enclosure system capable of being used as retaining wall
CN106223344A (en) A kind of ground line piled anchor framework foundation pit supporting method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant