CN202247910U - Soil retaining structure with different inclination angles of anti-skid cement soil pile - Google Patents
Soil retaining structure with different inclination angles of anti-skid cement soil pile Download PDFInfo
- Publication number
- CN202247910U CN202247910U CN 201120378191 CN201120378191U CN202247910U CN 202247910 U CN202247910 U CN 202247910U CN 201120378191 CN201120378191 CN 201120378191 CN 201120378191 U CN201120378191 U CN 201120378191U CN 202247910 U CN202247910 U CN 202247910U
- Authority
- CN
- China
- Prior art keywords
- soil
- pile
- cement
- different
- antiskid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Abstract
A soil retaining structure with different inclination angles of an anti-skid cement soil pile comprises a vertical cement soil pile, a vertical casting pile, an SMW (soil mixing wall) pile, a steel plate pile or an underground continuous wall and cement soil reinforcing piles, wherein the cement soil reinforcing piles are obliquely connected with the vertical cement soil pile, the vertical casting pile and the SMW pile through top press beams or waist beams. The sol retaining structure with different inclination angles is characterized in that the cement soil reinforcing piles are identical in length and different in inclination angle. According to the above structure, the piles are high in anti-skid performance, and anti-skid performance of a to-be-reinforced soil slope is improved greatly by the anti-skid soil retaining structure formed by combination of the vertical retaining piles and the anti-skid cement soil reinforcing piles which are constructed at different positions of a soft soil layer at the same inclination angle and in the same length.
Description
Technical field
The utility model relates to the geotechnical engineering technical field; Concrete reinforcing that relates to a kind of rock construction and supporting and protection structure, through adding cement-soil antiskid pile body in soft soil, and through combination; Form a kind of soil-baffling structure, improve its reinforcing and support capacity greatly.
Background technology
In the engineering construction in China area such as coastal, riverine, ubiquity foundation soil weakness, poor stability, the characteristics that bearing capacity is on the low side especially in the developed area, are used for ground processing and the employed expense of bracing of foundation pit, and will have more than hundred billion yuan every year.At present; In China's ground processing and bracing of foundation pit engineering; The soil-baffling structure that adopts mainly contains diaphragm wall, bored pile, soil nailing wall, SMW worker's method and piled anchor structure; Often there are many defectives in the construction technology of these structures and receive the restriction of engineering geology and construction environment, is difficult to pore-forming when running into silt soil strata, powder soil horizon or flour sand layer like soil nailing or anchor pole, the deep-mixed pile processing degree of depth is limited.Deep-mixed pile body itself usually only uses as water-stop curtain, and can not singlely use as soil-baffling structure because intensity is lower.In order to reach the native purpose of retaining, need be in deep-mixed pile H shaped steel, in diaphragm wall, bored pile combine, support or anchor pole, form soil-baffling structure, often like this cause big difficulty for design and construction, construction cost is significantly improved.
Use the difficulty of construction and the more high deficiency of cost of existence respectively in view of above-mentioned soil-baffling structure; Through experimental study for many years; We have invented a kind of new soil-baffling structure---anti-slip cement soil pile soil blocking structure; This soil-baffling structure has not only overcome all deficiencies of soil-baffling structure at present commonly used, and is a kind of not only safety, environmental protection but also economical and the new structure fast of constructing.
The utility model content
The utility model technical problem to be solved is, overcomes the problem that exists in the prior art, and a kind of soil-baffling structure that has different angle antiskid cement earth pile is provided.
For the technical scheme that addresses the above problem the utility model is such:
A kind of soil-baffling structure that has different angle antiskid cement earth pile; Comprise the cement earth pile of vertical direction, vertical castinplace pile, the stake of SMW worker's method, steel sheet pile or diaphragm wall; With with its through the stake of putting more energy into of capping beam or the oblique cement-soil that links to each other of waist rail; It is characterized in that the cement-soil pile length of putting more energy into is identical, the inclination angle is different.
A plurality of antiskid cement-soils put more energy into the stake different with the angle theta of vertical direction, θ is 0~90 °.
On the same horizontal plane a plurality of antiskid cement-soils put more energy into the stake different with the angle Φ of soil-baffling structure, Φ is 0~90 °.
The antiskid cement-soil is put more energy into stake for churning, stirring pile body, is inserted with pretensioned muscle body in the pile body, and the muscle body is steel strand or wire rope.
The beneficial effect of the utility model is:
(1) pile body skid resistance height: do same inclination angle through on the diverse location of soft layer, executing, make up, form the antiskid soil-baffling structure and increased the skid resistance that is reinforced slight slope greatly with the antiskid cement earth pile and the vertical retaining stake of length;
(2) effectively control slope displacement:, the initial displacement of side slope is eliminated when the stretch-draw through the muscle body in the oblique antiskid cement earth pile is applied pretension;
(3) the combination antislide pile becomes overall structure: set up horizontal waling the oblique antiskid pile body on the same level is all locked above that; Combine with vertical soil-baffling structure, make the oblique antiskid pile body of different level all be combined into an overall structure through vertical soil-baffling structure.
Description of drawings
Specify the utility model below in conjunction with the accompanying drawing and the specific embodiment;
Fig. 1 is the described cross-sectional view that has the soil-baffling structure of different angle antiskid cement earth pile of the utility model.
Fig. 2 is the described horizontal development structural representation that has the soil-baffling structure of different angle antiskid cement earth pile of the utility model.
The specific embodiment
For technological means, creation characteristic that the utility model is realized, reach purpose and be easy to understand understanding with effect, below in conjunction with concrete diagram, further set forth the utility model.
Referring to Fig. 1 and Fig. 2; A kind of soil-baffling structure that has different angle antiskid cement earth pile; Comprise that vertical direction retaining stake in a row constitutes soil-baffling structure 1, soil-baffling structure is connected with the stake 2 (shown in A1, A2, A3, A4 among the figure) of putting more energy into of oblique a plurality of oblique antiskid cement-soil, and the stake of putting more energy into of a plurality of antiskid cement-soils is connected the top or the waist of retaining stake; A plurality of antiskid cement-soils pile length of putting more energy into is identical, and the inclination angle is different.A kind of specifically be the antiskid cement-soil put more energy into the stake different with the angle theta of vertical direction, θ is 0~90 °.Another kind is, the stake of putting more energy into of the antiskid cement-soil on same horizontal plane is different with the angle Φ of soil-baffling structure, and Φ is 0~90 °.Designing this kind structure can better increase the skid resistance of soil-baffling structure.
The stake 2 of putting more energy into of a plurality of antiskid cement-soils is connected on the horizontal waling at retaining stake top.
The stake 2 of putting more energy into of a plurality of antiskid cement-soils is connected on the waist rail of retaining stake waist.Among the figure, A2, A3, A4 connect waist rail 3, and A1 connects on the top, horizontal waling 4.
The retaining stake is the vertical cement earth pile of interior slotting strength body, vertical bored pile, the stake of SMW worker's method or steel sheet pile.
The antiskid cement-soil is put more energy into stake for churning, stirring pile body, is inserted with pretensioned muscle body in the pile body, and the muscle body is steel strand or wire rope.
This job practices that has the soil-baffling structure of antiskid cement earth pile is:
(1), at first use single shaft, two or three mixing pile machines, offices and men's body and cement grout mix form EFFECT OF CEMENT STABILIZED SOIL RETAINING WALL or water-stop curtain;
(2), vertical soil blocking pile body is composited to insert (or several) core (shaped steel, steel pipe, steel strand, prestressed concrete pipe pile, the stake of prestressed concrete pipe side, precast reinforced concrete structure etc.) through vibration or extruding then.Perhaps make bored pile, diaphragm wall, steel sheet pile etc. as vertical soil blocking pile body;
(3), the oblique antiskid cement earth pile construction technology of construction be mode through rotary jet stirring by design point of view, usage level jet drill rig, pass water-stop curtain, form a large diameter antiskid cement earth pile;
(4), add muscle body material in the antiskid cement earth pile: adopt steel strand, wire rope or non-metal rope body, the method by disposable dispensing or secondary dispensing joins muscle body material and anchor ingot plate on the center of antiskid cement soil pile together
(5), set up the horizontal waling of meter: be combined into an integral body in order to make antiskid cement soil pile and vertical soil-baffling structure; The waling of a level is set up in requirement; The waling material adopts shaped steel or Reinforced Concrete Materials to make; Make all the antiskid cement soil piles on this horizontal level be combined into an integral body, like Fig. 1, shown in 2 through this waling structure and vertical soil-baffling structure;
(6), construction pretension: the muscle body material in the antagonism water skiing earth pile body adopts the mode of prestressed stretch-draw; Eliminate the initial deformation of muscle body and check the quality of antiskid cement soil pile; Be locked on the horizontal waling by about 80% of design stretching force, the equal tensioning fixation of each root antiskid cement earth pile that requires this level is on the waling of this level.
More than show and described the advantage of basic principle, principal character and the utility model of the utility model.The technician of the industry should understand; The utility model is not restricted to the described embodiments; The principle of describing in the foregoing description and the manual that the utility model just is described; The utility model also has various changes and modifications under the prerequisite that does not break away from the utility model spirit and scope, and these variations and improvement all fall in the utility model scope that requires protection.The utility model requires protection domain to be defined by appending claims and equivalent thereof.
Claims (4)
1. soil-baffling structure that has different angle antiskid cement earth pile; Comprise the cement earth pile of vertical direction, vertical castinplace pile, the stake of SMW worker's method, steel sheet pile or diaphragm wall; With with its through the stake of putting more energy into of capping beam or the oblique cement-soil that links to each other of waist rail; It is characterized in that the cement-soil pile length of putting more energy into is identical, the inclination angle is different.
2. a kind of soil-baffling structure that has different angle antiskid cement earth pile according to claim 1 is characterized in that, a plurality of antiskid cement-soils put more energy into the stake different with the angle theta of vertical direction, θ is 0~90 °.
3. a kind of soil-baffling structure that has different angle antiskid cement earth pile according to claim 1 is characterized in that, on the same horizontal plane a plurality of antiskid cement-soils put more energy into the stake different with the angle Φ of soil-baffling structure, Φ is 0~90 °.
4. a kind of soil-baffling structure that has different angle antiskid cement earth pile according to claim 1 is characterized in that, the antiskid cement-soil is put more energy into stake for churning, stirring, rotary jet stirring pile body, is inserted with the muscle body in the pile body, and the muscle body is steel strand or wire rope.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201120378191 CN202247910U (en) | 2011-09-28 | 2011-09-28 | Soil retaining structure with different inclination angles of anti-skid cement soil pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201120378191 CN202247910U (en) | 2011-09-28 | 2011-09-28 | Soil retaining structure with different inclination angles of anti-skid cement soil pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202247910U true CN202247910U (en) | 2012-05-30 |
Family
ID=46109172
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201120378191 Expired - Lifetime CN202247910U (en) | 2011-09-28 | 2011-09-28 | Soil retaining structure with different inclination angles of anti-skid cement soil pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202247910U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103074897A (en) * | 2013-01-18 | 2013-05-01 | 卫海 | Reinforced restraint earth compound supporting structure and construction method thereof |
CN103290861A (en) * | 2013-06-24 | 2013-09-11 | 天津住宅集团建设工程总承包有限公司 | Stiff cement and soil continuous wall pile pulling method capable of ensuring stable surrounding circumstances |
CN104912082A (en) * | 2014-03-14 | 2015-09-16 | 江苏东合南岩土工程技术研究有限公司 | Inclined assembled double-row steel sheet pile foundation pit supporting structure and construction method thereof |
-
2011
- 2011-09-28 CN CN 201120378191 patent/CN202247910U/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103074897A (en) * | 2013-01-18 | 2013-05-01 | 卫海 | Reinforced restraint earth compound supporting structure and construction method thereof |
CN103290861A (en) * | 2013-06-24 | 2013-09-11 | 天津住宅集团建设工程总承包有限公司 | Stiff cement and soil continuous wall pile pulling method capable of ensuring stable surrounding circumstances |
CN104912082A (en) * | 2014-03-14 | 2015-09-16 | 江苏东合南岩土工程技术研究有限公司 | Inclined assembled double-row steel sheet pile foundation pit supporting structure and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101775814B (en) | Anti-slip cement soil pile soil blocking structure and construction method thereof | |
CN101798810A (en) | Cement-soil composite pile inserted into reinforced concrete core materials | |
CN204370431U (en) | A kind of occlusion long-short pile space enclosing structure | |
CN206941608U (en) | A kind of diaphram wall foundation pit supporting construction | |
CN202247947U (en) | Soil retaining structure with anti-sliding cement soil piles | |
CN202247910U (en) | Soil retaining structure with different inclination angles of anti-skid cement soil pile | |
CN102535452A (en) | Novel engineering pile | |
CN202247875U (en) | Soil retaining structure of anti-skidding cement soil piles with different lengths | |
CN102493436A (en) | Novel manual tunneling construction method of rectangular anti-slide pile | |
CN201190288Y (en) | Pile foundation of building foundation length composite pile | |
CN102235017B (en) | Lateral force resisting method for soft soil foundation building | |
CN205062809U (en) | End support type screw thread core composite pile | |
CN107130617A (en) | A kind of flat pressure dispersing anchorage cable wall retaining structure of rock matter cut slope | |
CN204530685U (en) | A kind of cement-soil stiff composite pile | |
CN200996149Y (en) | Irrigation-engineering structural component | |
CN203846517U (en) | Vertical anchor bolt supporting structure | |
CN209603123U (en) | A kind of bottom-enlarging filling pile structure for cutting down negative friction | |
CN102828504A (en) | Precast reinforced concrete hollow lateral-force resisting pile and pile embedding method | |
CN102605775A (en) | Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method | |
CN102505698A (en) | Soil mass supporting structure and construction method thereof | |
CN207079600U (en) | A kind of flat pressure dispersing anchorage cable wall retaining structure of rock matter cut slope | |
CN202530450U (en) | Combination pile with flexible pile and rigid pile arranged up and down consubstantially | |
CN104831706A (en) | Reinforcement method for red mud disposal sites | |
CN209669864U (en) | A kind of combined type basis of spread foundation adding rock anchor pole and tower crane | |
CN107489143A (en) | A kind of concrete pouring of punched hole piles structure and its plain fill layer leakproof paste-making method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20120530 |
|
CX01 | Expiry of patent term |