CN102535452A - Novel engineering pile - Google Patents

Novel engineering pile Download PDF

Info

Publication number
CN102535452A
CN102535452A CN2010105891606A CN201010589160A CN102535452A CN 102535452 A CN102535452 A CN 102535452A CN 2010105891606 A CN2010105891606 A CN 2010105891606A CN 201010589160 A CN201010589160 A CN 201010589160A CN 102535452 A CN102535452 A CN 102535452A
Authority
CN
China
Prior art keywords
stake
pile
hole
pipe
bearing capacity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105891606A
Other languages
Chinese (zh)
Inventor
王云艇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2010105891606A priority Critical patent/CN102535452A/en
Publication of CN102535452A publication Critical patent/CN102535452A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a novel engineering pile, which belongs to the technical field of buildings and pile foundations of structures. As a result, a new pile type, a new structure and an innovative construction method are adopted for improving single-pile bearing capacity, ensuring pile quality, avoiding pile scrappage during construction, accelerating construction progress and the like against the pile foundation being in line with the result. The technical scheme of the result comprises the following steps of: mechanical equipment is used for punching and drilling a pile hole till a supporting course, pumping slurry out of the hole without pouring concrete, hoisting a preformed pile into the hole till the lower end part of the pile reaches the supporting course, and sinking the preformed pile through a vibration method or a hammering method or other methods so as to insert the end of the pile into the supporting course by a certain scale; and filling up a gap between the preformed pile and the pile hole by pressure grouting so as to improve friction force in the lateral direction of the pile. When the preformed pile which is driven into the pile hole comprises multiple joints, the pile needs to be connected; and due to the particularity produced by implementation of the result, when the pile is connected, a fixer is required, and the structure and a using method of the fixer are of one part of contents of the result.

Description

A kind of new type of engineering stake
Affiliated technical field, background technology
Affiliated technical field: building, structure pile foundation technology field
Background technology: the existing technology that improves bearing capacity of single pile has stake end enlarged footing technology, two road enlarged footing technology (on pile body, doing enlarged footing).
Precast reinforced concrete piles buries behind the pile sinking, and bearing capacity of pile tip and pile body frictional resistance are all big, by the stake type of extensive employing, when ground has hard soil layer to penetrate, then should adopt other type.Long spiral shell is exerted pressure and irritated castinplace pile is new science and technology stake type, advantage many (short etc.) like the duration, and if its drill bit is the sharp subdrilling head of employing and on cutting edge, weld carbide bit; Then can bore hardpan; The length of this stake can reach 30m, when surpassing situation such as this length, also should adopt other types.The stake type of existing engineering piles has multiple, and various stake types are applicable to the situation that it is suitable for, and wants plasma discharge when multiple stake type is constructed, and can not the mud in the stake hole be drained entirely, and sediment can reduce the bearing capacity of stake at the bottom of the hole.
Many engineering piles might produce the situation that broken pile etc. is scrapped stake in construction.The books that reflect this achievement figure viewed from behind technology: " ground foundation engineering " (second edition), Chinese Water Conservancy water power publishing house 2010.3 second editions; " Foundation Design " China Electric Power Publishing House 2009.2 publishes; " ground and basis " BJ University Press 2010.10 publishes
Summary of the invention
The present invention adopts the job practices of new stake type, new construction and innovation, makes to be fit to use the pile foundation of this achievement to improve bearing capacity of single pile, to ensure quality of pile, to avoid constructing that king-pile is scrapped and accelerating construction progress etc., and this achievement technical scheme is:
1, dash, bore the stake hole to bearing stratum with plant equipment, after mud is extracted out in the hole, placing of concrete not; But will give in system stake lifting goes into, the through bearing stratum of stake end, a dimensioning bassets on the stake top; Then make and give the system stake and sink to some extent, make the stake end insert bearing stratum one dimensioning, thereby improve bearing capacity of pile tip with vibratory drilling method or hammering method or additive method; The space of giving between system stake and the stake hole is filled up with pressure grouting, thereby improves the frictional resistance of stake side direction.
2, for pressure grouting, the system of the giving stake of going into the post hole has two kinds of special constructions, and the first is equipped with grout pipe in the inboard of stake outer surface; It two is equipped with grout pipe in stake inside; The grout pipe of both of these case has many pulp holes on the side of stake external surface; This hole small pipeline outer with passing to stake is connected, and during pressure grouting, the pressure slurry gets into grout pipe and flows into the space between stake and the stake hole through the slurry outlet on its side, small pipeline; If also will be in the milk to the stake bottom, then grout pipe should extend the absolute altitude of stake bottom.
3, for a certain reason, the grouting that can take in addition has two kinds, and the first is by existing technology grouting, and it also is conventional giving the system pilework; It two is to make a grouting pipeline with giving system stake hollow part, and the horizontal small pipeline of hollow part and its side UNICOM is to an outer wall.
When 4, going into the giving system stake more piece is arranged an of hole, carry out will using a kind of fixator in the stake connection, its base plate is processed by steel plate; The centre is great circle hole Q, and Q is slightly little for the stake boring ratio, and fixator is placed on the aperture in a hole when using; The Q center overlaps with stake center, hole, and when two joint stakes were connected, joint stake A up grasped its position by lifting machine; Another joint below stake B insert among the Q and the certain size that bassets, pass the horizontal hole G of B stake upper end section with a pipe P, the P two ends are by two bearing supports on the fixator; This two bearing is positioned on the base plate at Q diameter line two ends, after connection A, the B two joint stakes; Mobile P pipe makes its disengaging B stake and operates lifting machine and lets two of A, B having connected move down, and the operating process of connection more piece stake by that analogy.
5, P pipe can a pipe; But also 2-section pipe, if adopt 2-section pipe, this 2-section pipe inserts the two ends of G hole respectively during use.
6, insert bearing stratum one dimensioning in the end of below pile cutoff in order to yield system stake, this pile cutoff lower end should be pointed metalwork.
7, to the stake hole and give the space between the system stake; Adopt the used material of slip casing by pressure; The additive etc. that research is used cement, clay, swell soil, flyash, fine sand and can be produced certain effect; Its blend proportion according to project situation experimentize select excellent, thereby ensure the quality of products and practice thrift engineering cost.
8, give employed innovation utensil in innovation structure and the construction of system stake; All to calculate, confirm size, grasp the principle of not only safety but also joint money with principles such as structural mechanics; Size is neither less than normal not bigger than normal yet, according to the engineering actual conditions confirm the calculated data that will use.
Description of drawings
Fig. 1 is the preformed pile constructional drawing that is equipped with grout pipe, and a. component is an elevation; B, c component are section legends.Each symbolic representation: 1-preformed pile; 2-pulp hole; The pointed metalwork in 3-stake bottom; The 4-grout pipe; 5-pulp small pipeline; 6-hollow preformed pile hollow part.
Fig. 2 is the fixator constructional drawing, comprises plan view and lateral view, each symbolic representation:
The 1-base plate; Da Yuan hole, 2-centre; The 3-bearing; The 4-bolt hole; 5-timber hole.
The specific embodiment
Be fit to use the pile foundation engineering of this achievement, its Construction unit and this achievement patentee implement this patent achievement in signatory back.

Claims (8)

1. the present invention adopts the job practices of new stake type, new construction and innovation, makes to be fit to use the pile foundation of this achievement to improve bearing capacity of single pile, to ensure quality of pile, to avoid constructing that king-pile is scrapped and accelerating construction progress etc., and this achievement characteristic is:
Dash, bore the stake hole to bearing stratum with plant equipment, after mud is extracted out in the hole, placing of concrete not; But will give in system stake lifting goes into, the through bearing stratum of stake end, a dimensioning bassets on the stake top; Then make and give the system stake and sink to some extent, make the stake end insert bearing stratum one dimensioning, thereby improve bearing capacity of pile tip with vibratory drilling method or hammering method or additive method; The space of giving between system stake and the stake hole is filled up with pressure grouting, thereby improves the frictional resistance of stake side direction.
2. the new technology of raising bearing capacity of single pile according to claim 1 is characterized in that: for pressure grouting, the system of the giving stake of going into the post hole has two kinds of special constructions, and the first is equipped with grout pipe in the inboard of stake outer surface; It two is equipped with grout pipe in stake inside; The grout pipe of both of these case has many pulp holes on the side of stake external surface; This hole small pipeline outer with passing to stake is connected, and during pressure grouting, the pressure slurry gets into grout pipe and flows into the space between stake and the stake hole through the slurry outlet on its side, small pipeline; If also will be in the milk to the stake bottom, then grout pipe should extend the absolute altitude of stake bottom.
3. the new technology of raising bearing capacity of single pile according to claim 1 is characterized in that: for a certain reason, the grouting that can take in addition has two kinds, and the first is by existing technology grouting, and it also is conventional giving the system pilework; It two is to make a grouting pipeline with giving system stake hollow part, and the horizontal small pipeline of hollow part and its side UNICOM is to an outer wall.
4. the new technology of raising bearing capacity of single pile according to claim 1 is characterized in that: when going into the giving system stake more piece is arranged an of hole, carry out will using a kind of fixator in the stake connection; Its base plate is processed by steel plate, and the centre is great circle hole Q, and Q is slightly little for the stake boring ratio; Fixator is placed on the aperture in a hole when using, and the Q center overlaps with stake center, hole, when two joint stakes are connected; One joint stake A up grasps its position by lifting machine, another joint below stake B insert among the Q and the certain size that bassets, pass the horizontal hole G of B stake upper end section with a pipe P; The P two ends are by two bearing supports on the fixator, and this two bearing is positioned on the base plate at Q diameter line two ends, after connection A, the B two joint stakes;, mobile P pipe makes its disengaging B stake and operates lifting machine and lets two of A, B having connected move down, and the operating process of connection more piece stake is by that analogy.
5. fixator according to claim 4 is characterized in that: P pipe can a pipe; But also 2-section pipe, if adopt 2-section pipe, this 2-section pipe inserts the two ends of G hole respectively during use.
6. the new technology of raising bearing capacity of single pile according to claim 1 is characterized in that: insert bearing stratum one dimensioning in the end of below pile cutoff in order to yield system stake, this pile cutoff lower end should be pointed metalwork.
7. the new technology of raising bearing capacity of single pile according to claim 1; It is characterized in that: to the stake hole and give the space between the system stake; Adopt the used material of slip casing by pressure; The additive etc. that research is used cement, clay, swell soil, flyash, fine sand and can be produced certain effect, its blend proportion according to project situation experimentize select excellent, thereby ensure the quality of products and practice thrift engineering cost.
8. the new technology of raising bearing capacity of single pile according to claim 1; It is characterized in that: give employed innovation utensil in innovation structure and the construction of system stake; All to calculate, confirm size, grasp the principle of not only safety but also joint money with the structural mechanics principle; Size is neither less than normal not bigger than normal yet, according to the engineering actual conditions confirm the calculated data that will use.
CN2010105891606A 2010-12-15 2010-12-15 Novel engineering pile Pending CN102535452A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105891606A CN102535452A (en) 2010-12-15 2010-12-15 Novel engineering pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105891606A CN102535452A (en) 2010-12-15 2010-12-15 Novel engineering pile

Publications (1)

Publication Number Publication Date
CN102535452A true CN102535452A (en) 2012-07-04

Family

ID=46343357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105891606A Pending CN102535452A (en) 2010-12-15 2010-12-15 Novel engineering pile

Country Status (1)

Country Link
CN (1) CN102535452A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015414A (en) * 2012-12-31 2013-04-03 建华建材(中国)投资有限公司 Precast concrete post grouting pile and grouting process
CN103498467A (en) * 2013-10-14 2014-01-08 成军 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation
CN104110031A (en) * 2013-04-22 2014-10-22 南通市常青建筑安装工程有限公司 High-bearing-capacity foundation pile and method for processing same and foundation
CN104894936A (en) * 2015-04-07 2015-09-09 陈运辉 Lateral-piling soil-squeezing grouting method for repairing settling roadbeds, and precast pile
CN106223341A (en) * 2016-07-25 2016-12-14 东南大学 Marine large diameter steel pipe pile slip casting around pile device and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2158493A (en) * 1984-03-16 1985-11-13 Earl & Wright Ltd Method of installing a pile
FR2634804A1 (en) * 1988-07-28 1990-02-02 Soletanche Method of inserting a prefabricated post in a very deep bore and post for the use of this method.
JPH02125016A (en) * 1988-11-02 1990-05-14 Ishizue Kensetsu:Kk Hollow drilling grouting method
KR0136958B1 (en) * 1994-10-28 1998-05-15 임성철 Piles comprising both precast concrete portions and concrete portions cast in situ
CN1912253A (en) * 2006-06-21 2007-02-14 闫雪晖 Construction method of prestressed tubular pile
CN101148874A (en) * 2007-10-11 2008-03-26 李树源 Construction method for increasing dry auger boring pouring pile bearing capacity
CN101182716A (en) * 2007-12-05 2008-05-21 中北大学 Pile sinking method of Synchronization grouting static pressure precast pile
CN101333812A (en) * 2008-08-04 2008-12-31 上海市基础工程公司 Grouter for back side grouting and its construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2158493A (en) * 1984-03-16 1985-11-13 Earl & Wright Ltd Method of installing a pile
FR2634804A1 (en) * 1988-07-28 1990-02-02 Soletanche Method of inserting a prefabricated post in a very deep bore and post for the use of this method.
JPH02125016A (en) * 1988-11-02 1990-05-14 Ishizue Kensetsu:Kk Hollow drilling grouting method
KR0136958B1 (en) * 1994-10-28 1998-05-15 임성철 Piles comprising both precast concrete portions and concrete portions cast in situ
CN1912253A (en) * 2006-06-21 2007-02-14 闫雪晖 Construction method of prestressed tubular pile
CN101148874A (en) * 2007-10-11 2008-03-26 李树源 Construction method for increasing dry auger boring pouring pile bearing capacity
CN101182716A (en) * 2007-12-05 2008-05-21 中北大学 Pile sinking method of Synchronization grouting static pressure precast pile
CN101333812A (en) * 2008-08-04 2008-12-31 上海市基础工程公司 Grouter for back side grouting and its construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015414A (en) * 2012-12-31 2013-04-03 建华建材(中国)投资有限公司 Precast concrete post grouting pile and grouting process
CN103015414B (en) * 2012-12-31 2016-04-13 建华建材投资有限公司 A kind of precast concrete post grouting pile and grouting process
CN104110031A (en) * 2013-04-22 2014-10-22 南通市常青建筑安装工程有限公司 High-bearing-capacity foundation pile and method for processing same and foundation
CN104110031B (en) * 2013-04-22 2017-12-26 南通市常青建筑安装工程有限公司 High-bearing capacity foundation pile and its processing method with basis
CN103498467A (en) * 2013-10-14 2014-01-08 成军 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation
CN103498467B (en) * 2013-10-14 2015-07-22 江苏溧阳城建集团有限公司 High-bearing-capacity foundation pile and processing method for high-bearing-capacity foundation pile and foundation
CN104894936A (en) * 2015-04-07 2015-09-09 陈运辉 Lateral-piling soil-squeezing grouting method for repairing settling roadbeds, and precast pile
CN106223341A (en) * 2016-07-25 2016-12-14 东南大学 Marine large diameter steel pipe pile slip casting around pile device and construction method thereof
CN106223341B (en) * 2016-07-25 2018-03-20 东南大学 Marine large diameter steel pipe pile slip casting around pile device and its construction method

Similar Documents

Publication Publication Date Title
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
CN203808822U (en) Full-hydraulic double power head device of rotary drilling rig
CN105780763B (en) Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN102011399B (en) PHC pile-based multiple high jet pedestal pile construction method
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN104863131A (en) Polygonal cement-soil stirring pile and formation method thereof
CN102535452A (en) Novel engineering pile
CN104863132A (en) Bougainvillea spectabilis willd-shaped cement-soil mixing pile and shaping method thereof
CN108824471A (en) A kind of deep water drift net multi-column pier foundation and its construction method
CN105297710A (en) High-pressure-jetting cement soil twist drill and reamed reinforced concrete grouting combined pile and manufacturing method
CN1206419C (en) Combined rock-embedding pile and its construction method
CN206752454U (en) One kind perfusion embedded pile
CN102493439A (en) Building fundamental pile constructional element
CN102587372A (en) Construction method for burying pile by under reaming and grouting
CN209339143U (en) A kind of concrete pipe pile construction equipment
CN102619223A (en) Binding-enhanced type rigid and soft combined pile and construction method
CN203129143U (en) Static pressure jet flow piling wall forming equipment
CN102767337A (en) Sleeve type screw pile machine drill and construction method for eliminating barriers
CN212670554U (en) Full-casing hydraulic hammering soil-squeezing cast-in-place pile device
CN202247910U (en) Soil retaining structure with different inclination angles of anti-skid cement soil pile
CN109339044A (en) A kind of concrete pipe pile construction equipment
CN101761348B (en) Multi-directional anchor pile one-step formed drilling tool
CN202187335U (en) Novel engineering pile
CN208251078U (en) A kind of bottom-expanding sinking-pipe pilework

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
DD01 Delivery of document by public notice

Addressee: Wang Yunting

Document name: the First Notification of an Office Action

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120704