CN202247947U - Soil retaining structure with anti-sliding cement soil piles - Google Patents

Soil retaining structure with anti-sliding cement soil piles Download PDF

Info

Publication number
CN202247947U
CN202247947U CN 201120378194 CN201120378194U CN202247947U CN 202247947 U CN202247947 U CN 202247947U CN 201120378194 CN201120378194 CN 201120378194 CN 201120378194 U CN201120378194 U CN 201120378194U CN 202247947 U CN202247947 U CN 202247947U
Authority
CN
China
Prior art keywords
soil
piles
pile
cement
sliding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201120378194
Other languages
Chinese (zh)
Inventor
刘全林
宋伟民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Qiangjin Foundation Engineering Co Ltd
Original Assignee
Shanghai Qiangjin Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Qiangjin Foundation Engineering Co Ltd filed Critical Shanghai Qiangjin Foundation Engineering Co Ltd
Priority to CN 201120378194 priority Critical patent/CN202247947U/en
Application granted granted Critical
Publication of CN202247947U publication Critical patent/CN202247947U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model relates to a soil retaining structure with anti-sliding cement soil piles, which comprises cement soil piles in the vertical direction, vertical bored concrete piles, SMW (soil mixing wall) construction piles steel sheet piles or diaphram walls as well as cement soil reinforcing piles connected obliquely with the soil retaining structure through top pressing beams or waist beams. The soil retaining structure is characterized in that the cement soil reinforcing piles are same in length and dip angle. The anti-sliding cement soil reinforcing piles are spiral spray and mixing pile bodies. Ribs which are steel strands or steel wire ropes are inserted into the pile bodies. The structure above is designed, so that the pile bodies are good in anti-sliding performance. An anti-sliding soil retaining wall is formed by constructing the anti-sliding cement soil piles which are same in dip angle and length in different positions of soft soil layers to be combined with vertical retaining piles, thereby greatly increasing the anti-sliding force of a reinforced soil slope.

Description

A kind of soil-baffling structure that has the antiskid cement earth pile
Technical field
The utility model relates to the geotechnical engineering technical field, and concrete reinforcing that relates to a kind of rock construction and supporting and protection structure through adding cement-soil antiskid pile body in soft soil, and through combination, form a kind of retaining wall, improve its reinforcing and support capacity greatly.
Background technology
In the engineering construction in China area such as coastal, riverine, ubiquity foundation soil weakness, poor stability, the characteristics that bearing capacity is on the low side especially in the developed area, are used for ground processing and the employed expense of bracing of foundation pit, and will have more than hundred billion yuan every year.At present; In China's ground processing and bracing of foundation pit engineering; The soil-baffling structure that adopts mainly contains diaphragm wall, bored pile, soil nailing wall, SMW worker's method and piled anchor structure; Often there are many defectives in the construction technology of these structures and receive the restriction of engineering geology and construction environment, is difficult to pore-forming when running into silt soil strata, powder soil horizon or flour sand layer like soil nailing or anchor pole, the deep-mixed pile processing degree of depth is limited.Deep-mixed pile body itself usually only uses as water-stop curtain, and can not singlely use as soil-baffling structure because intensity is lower.In order to reach the native purpose of retaining, need be in deep-mixed pile H shaped steel, in diaphragm wall, bored pile combine, support or anchor pole, form soil-baffling structure, often like this cause big difficulty for design and construction, construction cost is significantly improved.
Use the difficulty of construction and the more high deficiency of cost of existence respectively in view of above-mentioned soil-baffling structure; Through experimental study for many years; We have invented a kind of new soil-baffling structure---antiskid cement earth pile retaining wall; This retaining wall has not only overcome all deficiencies of soil-baffling structure at present commonly used, and is a kind of not only safety, environmental protection but also economical and the new structure fast of constructing.
The utility model content
The utility model technical problem to be solved is, overcomes the problem that exists in the prior art, and a kind of retaining wall that has the antiskid cement earth pile is provided.
For the technical scheme that addresses the above problem the utility model is such:
A kind of soil-baffling structure that has the antiskid cement earth pile; Comprise the cement earth pile of vertical direction, vertical castinplace pile, the stake of SMW worker's method, steel sheet pile or diaphragm wall; With with its through the stake of putting more energy into of capping beam or the oblique cement-soil that links to each other of waist rail; It is characterized in that the cement-soil pile length of putting more energy into is identical, the inclination angle is identical.
The antiskid cement-soil is put more energy into stake for churning, stirring, rotary jet stirring pile body, is inserted with the muscle body in the pile body, and the muscle body is steel strand or wire rope
The beneficial effect of the utility model is:
(1) pile body skid resistance height: do same inclination angle through on the diverse location of soft layer, executing, make up, form the antiskid retaining wall and increased the skid resistance that is reinforced slight slope greatly with the antiskid cement earth pile and the vertical retaining stake of length;
(2) effectively control slope displacement:, the initial displacement of side slope is eliminated when the stretch-draw through the muscle body in the oblique antiskid cement earth pile is applied pretension;
(3) the combination antislide pile becomes overall structure: set up horizontal waling the oblique antiskid pile body on the same level is all locked above that; Combine with vertical retaining wall, make the oblique antiskid pile body of different level all be combined into an overall structure through vertical retaining wall.
Description of drawings
Specify the utility model below in conjunction with the accompanying drawing and the specific embodiment;
Fig. 1 is the described cross-sectional view that has the retaining wall of antiskid cement earth pile of the utility model.
Fig. 2 is the described horizontal development structural representation that has the retaining wall of antiskid cement earth pile of the utility model.
The specific embodiment
For technological means, creation characteristic that the utility model is realized, reach purpose and be easy to understand understanding with effect, below in conjunction with concrete diagram, further set forth the utility model.
Referring to Fig. 1 and Fig. 2; A kind of retaining wall that has the antiskid cement earth pile; Comprise that vertical direction retaining stake in a row constitutes retaining wall 1, retaining wall is connected with the stake 2 (shown in A1, A2, A3, A4 among the figure) of putting more energy into of oblique a plurality of oblique antiskid cement-soil, and the stake of putting more energy into of a plurality of antiskid cement-soils is connected the top or the waist of retaining stake; A plurality of antiskid cement-soils pile length of putting more energy into is identical, and the inclination angle is identical.The inclination angle scope is 0~90 °.The antiskid cement-soil stake of putting more energy into specifically is 0~90 ° with the angle theta of vertical direction.When θ was 0 °, the stake of putting more energy into of antiskid cement-soil was the stake of vertical direction.When θ was 90 °, the stake of putting more energy into of antiskid cement-soil was the stake of horizontal direction.
The stake 2 of putting more energy into of a plurality of antiskid cement-soils is connected on the horizontal waling at retaining stake top.
The stake 2 of putting more energy into of a plurality of antiskid cement-soils is connected on the waist rail of retaining stake waist.Among the figure, A2, A3, A4 connect waist rail 3, and A1 connects on the top, horizontal waling 4.
The retaining stake is the vertical cement earth pile of interior slotting strength body, vertical bored pile, the stake of SMW worker's method or steel sheet pile.
The antiskid cement-soil is put more energy into stake for churning, stirring pile body, is inserted with pretensioned muscle body in the pile body, and the muscle body is steel strand or wire rope.
This job practices that has the retaining wall of antiskid cement earth pile is:
(1), at first use single shaft, two or three mixing pile machines, offices and men's body and cement grout mix form EFFECT OF CEMENT STABILIZED SOIL RETAINING WALL or water-stop curtain;
(2), vertical soil blocking pile body is composited to insert (or several) core (shaped steel, steel pipe, steel strand, prestressed concrete pipe pile, the stake of prestressed concrete pipe side, precast reinforced concrete structure etc.) through vibration or extruding then.Perhaps make bored pile, diaphragm wall, steel sheet pile etc. as vertical soil blocking pile body;
(3), the oblique antiskid cement earth pile construction technology of construction be mode through rotary jet stirring by design point of view, usage level jet drill rig, pass water-stop curtain, form a large diameter antiskid cement earth pile;
(4), add muscle body material in the antiskid cement earth pile: adopt steel strand, wire rope or non-metal rope body, the method by disposable dispensing or secondary dispensing joins muscle body material and anchor ingot plate on the center of antiskid cement soil pile together
(5), set up the horizontal waling of meter: be combined into an integral body in order to make antiskid cement soil pile and vertical retaining wall; The waling of a level is set up in requirement; The waling material adopts shaped steel or Reinforced Concrete Materials to make; Make all the antiskid cement soil piles on this horizontal level be combined into an integral body, like Fig. 1, shown in 2 through this waling structure and vertical retaining wall;
(6), construction pretension: the muscle body material in the antagonism water skiing earth pile body adopts the mode of prestressed stretch-draw; Eliminate the initial deformation of muscle body and check the quality of antiskid cement soil pile; Be locked on the horizontal waling by about 80% of design stretching force, the equal tensioning fixation of each root antiskid cement earth pile that requires this level is on the waling of this level.
More than show and described the advantage of basic principle, principal character and the utility model of the utility model.The technician of the industry should understand; The utility model is not restricted to the described embodiments; The principle of describing in the foregoing description and the manual that the utility model just is described; The utility model also has various changes and modifications under the prerequisite that does not break away from the utility model spirit and scope, and these variations and improvement all fall in the utility model scope that requires protection.The utility model requires protection domain to be defined by appending claims and equivalent thereof.

Claims (2)

1. soil-baffling structure that has the antiskid cement earth pile; Comprise the cement earth pile of vertical direction, vertical castinplace pile, the stake of SMW worker's method, steel sheet pile or diaphragm wall; With with its through the stake of putting more energy into of capping beam or the oblique cement-soil that links to each other of waist rail; It is characterized in that the cement-soil pile length of putting more energy into is identical, the inclination angle is identical.
2. a kind of soil-baffling structure that has the antiskid cement earth pile according to claim 1 is characterized in that, the antiskid cement-soil is put more energy into stake for churning, stirring, rotary jet stirring pile body, is inserted with the muscle body in the pile body, and the muscle body is steel strand or wire rope.
CN 201120378194 2011-09-28 2011-09-28 Soil retaining structure with anti-sliding cement soil piles Expired - Lifetime CN202247947U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120378194 CN202247947U (en) 2011-09-28 2011-09-28 Soil retaining structure with anti-sliding cement soil piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120378194 CN202247947U (en) 2011-09-28 2011-09-28 Soil retaining structure with anti-sliding cement soil piles

Publications (1)

Publication Number Publication Date
CN202247947U true CN202247947U (en) 2012-05-30

Family

ID=46109209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120378194 Expired - Lifetime CN202247947U (en) 2011-09-28 2011-09-28 Soil retaining structure with anti-sliding cement soil piles

Country Status (1)

Country Link
CN (1) CN202247947U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727340A (en) * 2015-03-11 2015-06-24 张江涛 High cutting slope anchor rope space framework supporting and retaining structure
CN103572775B (en) * 2012-07-30 2016-02-10 深圳市工勘岩土工程有限公司 The construction method of half Retaining Wall of welding with filler wire
CN105780778A (en) * 2014-12-22 2016-07-20 上海宝冶集团有限公司 Support method for old pipe inspection well in embedded excavation position of water inlet pipe of sewage pumping station
CN110593326A (en) * 2019-10-11 2019-12-20 西南交通大学 Basin hills abrupt slope area high-rise building synthesizes earthquake-resistant structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103572775B (en) * 2012-07-30 2016-02-10 深圳市工勘岩土工程有限公司 The construction method of half Retaining Wall of welding with filler wire
CN105780778A (en) * 2014-12-22 2016-07-20 上海宝冶集团有限公司 Support method for old pipe inspection well in embedded excavation position of water inlet pipe of sewage pumping station
CN104727340A (en) * 2015-03-11 2015-06-24 张江涛 High cutting slope anchor rope space framework supporting and retaining structure
CN110593326A (en) * 2019-10-11 2019-12-20 西南交通大学 Basin hills abrupt slope area high-rise building synthesizes earthquake-resistant structure

Similar Documents

Publication Publication Date Title
CN101775814B (en) Anti-slip cement soil pile soil blocking structure and construction method thereof
CN101798810A (en) Cement-soil composite pile inserted into reinforced concrete core materials
CN204370431U (en) A kind of occlusion long-short pile space enclosing structure
CN206941608U (en) A kind of diaphram wall foundation pit supporting construction
CN202247947U (en) Soil retaining structure with anti-sliding cement soil piles
CN202247910U (en) Soil retaining structure with different inclination angles of anti-skid cement soil pile
CN102535452A (en) Novel engineering pile
CN202247875U (en) Soil retaining structure of anti-skidding cement soil piles with different lengths
CN101514550A (en) Method using belled mixing piles for treating double-layer soft foundation
CN101514549B (en) Method using intermediate mixing piles for treating three-layer soft foundation
CN201190288Y (en) Pile foundation of building foundation length composite pile
CN205062809U (en) End support type screw thread core composite pile
CN102505698A (en) Soil mass supporting structure and construction method thereof
CN209162814U (en) A kind of novel anchor rod stake
CN102605775A (en) Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method
CN102235017A (en) Lateral force resisting method for soft soil foundation building
CN202530450U (en) Combination pile with flexible pile and rigid pile arranged up and down consubstantially
CN104831706A (en) Reinforcement method for red mud disposal sites
CN204662424U (en) Soil-cement bearing peg
CN208183780U (en) A kind of resistance to plucking structure
CN202448232U (en) Slurry preparation equipment
CN201137068Y (en) Impact force resistant pipe caisson filling pile for high-rise building
CN102061705B (en) Timbering wall of built-in prestressed reinforced concrete rectangular pile and construction method thereof
CN205999890U (en) Borehole thin-walled rubble fills out core grouting pile
CN201137085Y (en) Multi-stage pipe caisson pouring pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120530