CN100564700C - The job practices of lattice type steel column tower crane pedestal - Google Patents

The job practices of lattice type steel column tower crane pedestal Download PDF

Info

Publication number
CN100564700C
CN100564700C CNB2007101646302A CN200710164630A CN100564700C CN 100564700 C CN100564700 C CN 100564700C CN B2007101646302 A CNB2007101646302 A CN B2007101646302A CN 200710164630 A CN200710164630 A CN 200710164630A CN 100564700 C CN100564700 C CN 100564700C
Authority
CN
China
Prior art keywords
laced
battened compression
tower crane
tower
battened
Prior art date
Application number
CNB2007101646302A
Other languages
Chinese (zh)
Other versions
CN101240550A (en
Inventor
李元武
李宏伟
韩葆和
Original Assignee
浙江省长城建设集团股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 浙江省长城建设集团股份有限公司 filed Critical 浙江省长城建设集团股份有限公司
Priority to CNB2007101646302A priority Critical patent/CN100564700C/en
Publication of CN101240550A publication Critical patent/CN101240550A/en
Application granted granted Critical
Publication of CN100564700C publication Critical patent/CN100564700C/en

Links

Abstract

The job practices of lattice type steel column tower crane pedestal: before underground excavation and construction, make a call to four bored piles in needs shoveling position, the pile cages that has welded the laced of battened compression member of being made up of angle steel and batten plate is cast in the bored pile, at the laced of battened compression member end face conversion load-bearing steel plate is installed, on conversion load-bearing steel plate, the body of the tower base section is installed, on the body of the tower base section, body of the tower is installed.Between four laced of battened compression member and around cut the earth, whenever dig 1-3 rice weld horizontal scissors bracing frame and vertical scissors bracing frame between laced of battened compression member down, dug foundation ditch after, under base plate of foundation pit, use four laced of battened compression member of connection cushion cap connection.This job practices applicability is stronger, must install and use the situation of tower crane before situation that is specially adapted to placed restrictions on by the foundation ditch place tower crane can not be installed in the foundation ditch that digs or the excavation of foundation pit in the foundation ditch position.The lattice tower crane pedestal Stability Analysis of Structures of building with this method, firmly, safety is higher.

Description

The job practices of lattice type steel column tower crane pedestal

Technical field

The present invention relates to a kind of construction techniques, particularly relate to the job practices of lattice type steel column tower crane pedestal.

Background technology

In the building trade, the vertical transport of the various constructional materialss on the building site is generally finished by tower crane, and whether steadily tower crane when the big object of hoisting weight operation safety, with tower crane pedestal is whether stable direct relation is arranged firmly.The job practices that tower crane pedestal is commonly used is to make a call to earlier four piles in the position of tower crane now, the body of the tower that on formed column foot, connects tower crane then by its pre-embedded bolt, stable inadequately, the safety of tower crane basis seat of building like this, along with rising progressively of building construction height, for keeping the stable of body of the tower, body of the tower is had to adopt and brace bar attachedly is connected with building.In addition, when large-scale basement or multi-storey basement construction, planar dimension is big because base pit engineering has, and cutting depth is dark, and vertical transport is particularly thorny, characteristics such as the construction plant is narrow and small, tower crane usually need be placed in the foundation ditch, during general way, digs the basement earthwork earlier, on the foundation ditch that digs, build tower crane pedestal again after having dug basement foundation ditch, tower crane is installed again.But, after running into foundation ditch and digging, be subjected to the foundation ditch place place restrictions on can not the foundation ditch that digs in tower crane is installed situation, perhaps must install and use the situation of tower crane during excavation of foundation pit in the foundation ditch position, just be not suitable for the method for above-mentioned construction tower crane pedestal.

Summary of the invention

The purpose of this invention is to provide that a kind of applicability is strong, the lattice type steel column tower crane pedestal job practices of easy construction, for realizing this goal of the invention, the technical solution used in the present invention is such:

The job practices of lattice type steel column tower crane pedestal is characterized in that comprising the steps:

1. make a call to the bored pile that matches with the tower crane body of the tower in four positions on the ground;

2. make laced of battened compression member: with four angle bar, two dual-purpose batten plates are welded into column;

3. laced of battened compression member is welded in the pile cages;

The pile cages that 4. will weld laced of battened compression member is cast in the bored pile;

5. at the laced of battened compression member end face conversion load-bearing steel plate is installed;

6. begin underground excavation and construction, between four laced of battened compression member and around cut the earth, dig certain distance under every, cut the bored pile pile concrete, weld horizontal scissors bracing frame between four laced of battened compression member, the vertical scissors bracing frame of welding between per two adjacent laced of battened compression member;

7. after the underground scholar of digging finishes, below the base plate of foundation pit that digs, construct steel concrete and connect cushion cap, four bored piles are linked together, further fix four laced of battened compression member.

Further, 5. above-mentioned steps can install the body of the tower base section afterwards on conversion load-bearing steel plate.

Mounting method between described laced of battened compression member, conversion load-bearing steel plate and the body of the tower base section is: pass conversion load-bearing steel plate and the welding of laced of battened compression member end face angle steel with one end of the anchor bolt on the body of the tower base section, again with laced of battened compression member end face angle steel and the welding of conversion load-bearing steel plate, and between laced of battened compression member side and conversion load-bearing steel plate bottom surface, weld the triangle stiffener, then the body of the tower base section is connected with the anchor bolt other end.

After described body of the tower base section installs, on the body of the tower base section, body of the tower can be installed.

Above-mentioned steps 7. after, aerated concrete building block or coarse sand separation layer can be set connecting between cushion cap and the base plate of foundation pit.

The described step 3. welding method of laced of battened compression member and pile cages is: laced of battened compression member and the bar welding of pile cages master muscle group, its lap length is no less than 3 meters.

Adopt the job practices of above-mentioned lattice type steel column tower crane pedestal, can before soil excavation, install tower crane earlier, the limit is dug the following cubic metre of earth limit of tower crane and is reinforced this tower crane pedestal with vertical support frame and horizontal shore, below base plate of foundation pit, construct steel concrete after foundation ditch digs again and connect cushion cap, further reinforce tower crane pedestal, can also be with already installed tower crane transportation cubic metre of earth when digging following cubic metre of earth of tower crane, this method easy construction, applicability is stronger, must install and use the situation of tower crane when particularly suitable is subjected to foundation ditch place restriction that the situation of tower crane or excavation of foundation pit can not be installed in the foundation ditch that digs in the foundation ditch position.The tower crane pedestal Stability Analysis of Structures of building with this method, firmly, safety is higher.

Description of drawings

Fig. 1 is for building the sectional drawing of the lattice type steel column tower crane pedestal that finishes.

Fig. 2 is the A-A sectional drawing of Fig. 1.

Fig. 3 is the B-B sectional drawing of Fig. 1.

Fig. 4 is the connection diagram of conversion load-bearing steel plate and laced of battened compression member.

Fig. 5 is the C-C sectional drawing of Fig. 4.

Fig. 6 is horizontal scissors bracing frame schematic diagram.

The specific embodiment

Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, present embodiment is the job practices of lattice type steel column tower crane pedestal, and concrete construction sequence is as follows:

1. make a call to the bored pile 1 that matches with the tower crane body of the tower in four positions on the ground;

2. make laced of battened compression member 3: four angle bar, 8, two dual-purpose batten plates 9 are welded into column;

3. laced of battened compression member 3 and pile cages 2 main muscle are helped the bar welding, its lap length is 3.5 meters;

The pile cages 2 that 4. will weld laced of battened compression member 3 is cast in the bored pile 1;

5. pass conversion load-bearing steel plate 4 and 8 welding of laced of battened compression member 3 end face angle steel with anchor bolt 11 1 ends, again laced of battened compression member end face angle steel 8 and conversion load-bearing steel plate 4 are welded, and between laced of battened compression member 3 sides and conversion load-bearing steel plate 4 bottom surfaces, weld triangle stiffener 10;

6. on conversion load-bearing steel plate 4, the body of the tower base section is installed;

7. the tower crane body of the tower is installed on the body of the tower base section;

8. begin underground excavation and construction, between four laced of battened compression member and around cut the earth, dig certain distance under every, cut the bored pile pile concrete, weld horizontal scissors bracing frame 5 between four laced of battened compression member 3, the vertical scissors bracing frame 6 of welding between per two adjacent laced of battened compression member 3;

9. after the underground scholar of digging finishes, below 12, construct steel concrete and connect cushion cap 7, four bored piles 1 are linked together, further fix four laced of battened compression member at the base plate of foundation pit that digs; 10. between described connection cushion cap 7 and base plate of foundation pit 12, be provided with and add coarse sand separation layer 13.

Claims (2)

1, the job practices of lattice type steel column tower crane pedestal is characterized in that comprising the steps:
1. make a call to the bored pile that matches with the tower crane body of the tower in four positions on the ground;
2. make laced of battened compression member: with four angle bar, two dual-purpose batten plates are welded into column;
3. laced of battened compression member is welded in the pile cages;
The pile cages that 4. will weld laced of battened compression member is cast in the bored pile;
5. at the laced of battened compression member end face conversion load-bearing steel plate is installed, on conversion load-bearing steel plate, the body of the tower base section is installed again; Mounting method between laced of battened compression member, conversion load-bearing steel plate and the body of the tower base section is: pass conversion load-bearing steel plate and the welding of laced of battened compression member end face angle steel with one end of the anchor bolt on the body of the tower base section, again with laced of battened compression member end face angle steel and the welding of conversion load-bearing steel plate, and between laced of battened compression member side and conversion load-bearing steel plate bottom surface, weld the triangle stiffener, then the body of the tower base section is connected with the anchor bolt other end;
6. begin underground excavation and construction, between four laced of battened compression member and around cut the earth, dig certain distance under every, cut the bored pile pile concrete, weld horizontal scissors bracing frame between four laced of battened compression member, the vertical scissors bracing frame of welding between per two adjacent laced of battened compression member;
7. after underground shoveling is finished, below the base plate of foundation pit that digs, construct steel concrete and connect cushion cap, four bored piles are linked together, further fix four laced of battened compression member; Between connection cushion cap and base plate of foundation pit, aerated concrete building block or coarse sand separation layer are set again.
2, the job practices of lattice type steel column tower crane pedestal according to claim 1, it is characterized in that described step 3. the welding method of laced of battened compression member and pile cages be: laced of battened compression member and the bar welding of pile cages master muscle group, its lap length is no less than 3 meters.
CNB2007101646302A 2007-12-26 2007-12-26 The job practices of lattice type steel column tower crane pedestal CN100564700C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007101646302A CN100564700C (en) 2007-12-26 2007-12-26 The job practices of lattice type steel column tower crane pedestal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007101646302A CN100564700C (en) 2007-12-26 2007-12-26 The job practices of lattice type steel column tower crane pedestal

Publications (2)

Publication Number Publication Date
CN101240550A CN101240550A (en) 2008-08-13
CN100564700C true CN100564700C (en) 2009-12-02

Family

ID=39932345

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007101646302A CN100564700C (en) 2007-12-26 2007-12-26 The job practices of lattice type steel column tower crane pedestal

Country Status (1)

Country Link
CN (1) CN100564700C (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094770A (en) * 2011-02-23 2011-06-15 河海大学 Design method for wind farm foundation
CN102134856B (en) * 2011-04-20 2012-05-30 天津市建工工程总承包有限公司 Tower crane foundation
CN102587406A (en) * 2012-03-13 2012-07-18 中天建设集团有限公司 Pouring construction method of concrete-filled tower crane foundation lattice column
CN102587407A (en) * 2012-03-23 2012-07-18 舜元建设(集团)有限公司 Construction method for tower crane foundation without bearing platform in deep foundation pit
CN103195076B (en) * 2013-03-28 2016-03-09 中国建筑第八工程局有限公司 Muddy Bottoms deep-excavation tower crane foundation construction method
CN103498482A (en) * 2013-09-30 2014-01-08 上海建工七建集团有限公司 Three-pile lattice type combined tower crane foundation structure
CN106495028A (en) * 2015-09-08 2017-03-15 上海宝冶集团有限公司 Tower crane conversion method for assembled architecture construction
CN105888265A (en) * 2016-03-01 2016-08-24 中国建筑第六工程局有限公司 Steel structure provisional measure latticed column butt junction location device and method
CN105951869B (en) * 2016-05-31 2017-12-15 中国一冶集团有限公司 A kind of construction method of the not reserved construction joint Tower Crane Foundation by Steel Lattice Column of underground garage
CN106480901B (en) * 2016-09-29 2020-02-07 舜元建设(集团)有限公司 Precise positioning method for lattice type steel stand column
CN107190764A (en) * 2017-04-29 2017-09-22 中国能源建设集团安徽电力建设第工程有限公司 A kind of booster stations building foundation construction method
CN107963545A (en) * 2017-11-24 2018-04-27 中国二冶集团有限公司 Installation method, method for dismounting and the mast-up of vertical storage tank
CN108086344A (en) * 2017-12-20 2018-05-29 中铁十局集团城市轨道交通工程有限公司 A kind of lattice tower-crane foundation structure and construction method

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
地下室中塔吊基座的施工. 陈川平,姚红.西部探矿工程,第86期. 2003
地下室中塔吊基座的施工. 陈川平,姚红.西部探矿工程,第86期. 2003 *
塔式起重机基础在深基坑中的设置. 李泰炯,王巧芬.建筑机械化,第7期. 2007
塔式起重机基础在深基坑中的设置. 李泰炯,王巧芬.建筑机械化,第7期. 2007 *
浅谈钢格构柱在塔机基础逆作法施工中的应用. 石宝娟,张德伟.四川建材,第6期. 2005
浅谈钢格构柱在塔机基础逆作法施工中的应用. 石宝娟,张德伟.四川建材,第6期. 2005 *
深基坑工程中大型塔吊支撑体系的设计与施工. 王志平.建筑施工,第28卷第7期. 2006
深基坑工程中大型塔吊支撑体系的设计与施工. 王志平.建筑施工,第28卷第7期. 2006 *

Also Published As

Publication number Publication date
CN101240550A (en) 2008-08-13

Similar Documents

Publication Publication Date Title
US10815633B2 (en) Apparatus and methods for underground structures and construction thereof
US20150354163A1 (en) Earth retaining system such as a sheet pile wall with integral soil anchors
CA2306130C (en) Reinforced retaining wall
CN106758831B (en) Across railway bridge swivel continuous beam construction method
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
AU2014237379B2 (en) Precast concrete retaining wall
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN101838968B (en) Double track bridge construction process crossing existing railway operational lines
CN100543239C (en) The method of three usages of one pile in a kind of underground construction
KR100633796B1 (en) Connecting structure of mid supporting beam for temporary soil sheathing work
CN101775814B (en) Anti-slip cement soil pile soil blocking structure and construction method thereof
CN101864773B (en) Deep foundation pit support process
CN101117805A (en) Underground engineering one-pile multi-use semi reverse construction method
CN103321241B (en) Deep water open type combination foundation harbour and construction method thereof
CN201137148Y (en) Double rows bamboo pile composite soil nail defending system
CN103437567B (en) Method for supporting existing building underground added storey through original pile foundations
CN101397852A (en) Construction method for increasing to build multi-storey basement to original building
CN102691300A (en) Construction method of foundation pit earthwork
KR20050082986A (en) Method of enlarging road width and preventing falling stone
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
CN102864946B (en) Process for supporting existing buildings through structural steel and horizontal rachel rod member and additionally adding multilayer basement
CN105133620B (en) Pit supporting construction and its construction method in local flow's modeling shape Muddy Bottoms soil body hole
KR101507924B1 (en) Structure and method of constructing concrete footing structure of top structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 310016 Great Wall Building, No. 60 Leiting Road, Shangcheng District, Hangzhou City, Zhejiang Province

Patentee after: Zhejiang three Construction Group Co., Ltd.

Address before: 310009 Building No. 8, Meihua Stele, Hangzhou City, Zhejiang Province

Patentee before: Zhejiang Changcheng Construction Group Co., Ltd.