CN109139053A - A kind of water conductive fault comprehensive treatment parallel construction system and construction method - Google Patents

A kind of water conductive fault comprehensive treatment parallel construction system and construction method Download PDF

Info

Publication number
CN109139053A
CN109139053A CN201811156915.6A CN201811156915A CN109139053A CN 109139053 A CN109139053 A CN 109139053A CN 201811156915 A CN201811156915 A CN 201811156915A CN 109139053 A CN109139053 A CN 109139053A
Authority
CN
China
Prior art keywords
group
ductule
grouting
tunnel
high pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811156915.6A
Other languages
Chinese (zh)
Inventor
刘结高
程爱民
翟恩发
孔皖军
郑根源
高银贵
尹宏昌
王宏伟
李全伦
史志国
国伟
常成林
赵少博
薛悟强
王印
吴寒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ordos Huaxing Energy Co Ltd
Huai Mine West Coal Mine Cci Capital Ltd
Original Assignee
Ordos Huaxing Energy Co Ltd
Huai Mine West Coal Mine Cci Capital Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ordos Huaxing Energy Co Ltd, Huai Mine West Coal Mine Cci Capital Ltd filed Critical Ordos Huaxing Energy Co Ltd
Priority to CN201811156915.6A priority Critical patent/CN109139053A/en
Publication of CN109139053A publication Critical patent/CN109139053A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

It includes: high pressure deep hole grouting system that the present invention, which provides a kind of water conductive fault comprehensive treatment parallel construction system and construction method, parallel construction system, and high pressure deep hole grouting system is located on the outside of tunnel in the rock mass of surrounding;High pressure deep hole grouting system includes high pressure deep hole grouting aperture apparatus, and high pressure deep hole grouting aperture apparatus includes first sleeve, and first sleeve is arranged in the rock stratum around tunnel, for providing positioning and support;Grouting with small pipe system, grouting with small pipe system are located at high pressure deep hole grouting system memory, and grouting with small pipe system is connected to the inner wall in tunnel;High pressure deep hole grouting system with grouting with small pipe system is parallel on the outside of tunnel constructs simultaneously;The method that the present invention uses high pressure deep hole grouting and grouting with small pipe parallel construction carries out so that grouting with small pipe is synchronous while high pressure deep hole grouting;The method that high pressure deep hole grouting uses three-wheel slip casting simultaneously, ductule uses the construction method of class interval, so that water conductive fault is effectively administered.

Description

A kind of water conductive fault comprehensive treatment parallel construction system and construction method
Technical field
The invention belongs to full section of tunnel slurry injection technique fields, and in particular to a kind of water conductive fault comprehensive treatment parallel construction System and construction method.
Background technique
Full section of tunnel slurry injection technique is that poor different of the soil properties such as weak water rich strata, crushed zone was directed in Tunnel Engineering Normal section frequently with construction method, by carrying out the work that slip casting plays soil mass consolidation and waterproof to tunnel surrounding ductule of constructing With, at present during on-site construction, these methods tool that lithology observation method of comparison, testization method etc. is usually taken, but uses in the past There is the features such as project amount is big, costly, accuracy rate is low.
It is mainly mining under safe waterpressure of aquifer coal seam that coal master, which mines, at present, and it is about 1MPa, coal seam that seat earth, which bears Ordovician karst water pressure, It is about 40~60m with Ordovician karst water distance, since coal seam floor grey watery difficult to understand is strong and mature fault, safe working is by bottom plate ash difficult to understand The threat of water, national mine water inrush data show that 70% water inrush accident all occurs during tunnelling in recent years, tunnel Water inrush accident is especially easily sent out when encountering tomography conducting Ordovician karst water in the process.It is controlled using the tomography design method based on previous bottom plate admittedly Manage the two tomographies administer it is long in time limit, effect is undesirable, although certain tomography drops are only 3m, the fault hydraulic conductivity is strong, Preceding prospecting bit hole water yield is high, and meet head on the position back water outlet 25m that drills3/ h, execution conditions are poor, and band is administered to it in grieshoch position difficult to understand Great difficulty is carried out.
Accordingly, it is desirable to provide it is a kind of for the insufficient water conductive fault comprehensive treatment parallel construction system of the above-mentioned prior art and Construction method.
Summary of the invention
The purpose of the present invention is to provide a kind of water conductive fault comprehensive treatment parallel construction systems and construction method at least Tomography is long in time limit, effect is undesirable, project amount is big, expense to administer for the tomography design method based on solid bottom plate at present for solution Problem high, accuracy rate is low.
To achieve the goals above, the invention provides the following technical scheme:
A kind of water conductive fault comprehensive treatment parallel construction system, the parallel construction system include:
High pressure deep hole grouting system, the high pressure deep hole grouting system are located on the outside of tunnel in the rock mass of surrounding;The height Pressing deep hole grouting system includes high pressure deep hole grouting aperture apparatus, and the high pressure deep hole grouting aperture apparatus includes first sleeve, described First sleeve is arranged in the rock stratum around tunnel, for providing positioning and support;
Grouting with small pipe system, the grouting with small pipe system is located at the high pressure deep hole grouting system memory, described small Conduit grouting system is connected to the inner wall in the tunnel;
The high pressure deep hole grouting system with grouting with small pipe system is parallel on the outside of tunnel constructs simultaneously.
A kind of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that high pressure deep hole grouting hole dress It sets further include:
Second casing, the outer diameter of second casing are less than the internal diameter of the first sleeve;Second casing is set with one heart It sets in the first sleeve, injected hole is equipped in second casing;
Short tube, the short tube are connected to the left side of second casing, and the short tube is equipped with pressure gauge;
Plug, the plug are connected on the left of the short tube, are equipped with spherical cavity in the plug, in the spherical cavity Equipped with the second gate valve.
A kind of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that the length of second casing is big In the length of the first sleeve, the first sleeve is concordant with the left end of second casing to be arranged;The first sleeve and The screed of same thickness is equipped between second casing, between second casing and the injected hole;Described first Casing and second casing are circumferentially distributed multiple through-holes, flow out out of casing for slurries, form the entirety of sealing.
A kind of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that the first sleeve left end connection There is first flange, second casing left end is connected with second flange, and the right end of the short tube is connected with third flange;Described One flange, the second flange and third flange abutting link together;The second flange is located at the first flange Between the third flange;
The short tube outer wall connection is equipped with pressure-measuring pipe, and the first gate valve is equipped in the pressure-measuring pipe, and the pressure-measuring pipe upper end connects It is connected to pressure gauge;First gate valve is for being connected to the pressure gauge and the short tube;
Preferably, the internal diameter of the short tube is identical as the internal diameter of second casing.
A kind of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that the injected hole has three groups, respectively For first group of injected hole, second group of injected hole and third group injected hole;Injected hole described in each group is along the circumferential direction of construction tunnel Be uniformly distributed, first group of injected hole is identical as the third group injected hole distribution mode, and with second group of the distribution Mode is different;
Preferably, first group of injected hole and third group injected hole and center line in roadway angle are 11~25 °, and hole depth is 43~56m;
More preferably, second group of injected hole and center line in roadway angle are 15~22 °, and hole depth is 57~62m.
A kind of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that the grouting with small pipe system packet Grouting with small pipe aperture apparatus is included, the grouting with small pipe aperture apparatus includes:
S group ductule, the s group ductule are arranged in the circumferential direction in tunnel, and one end of the s group ductule is from tunnel Inner wall radiates extend to the other end around;
Q group ductule, the q group ductule and the s group ductule are arranged at the circumferential direction interval in tunnel, the q The length of group ductule is greater than the length of the s group ductule;
Aqueduct, the aqueduct are located at the lower part of the left side in tunnel, the right side of the opening direction of the aqueduct towards tunnel Side.
A kind of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that the s group ductule includes s1 group Ductule, s2 group ductule, s3 group ductule, s4 group ductule, s5 group ductule, s6 group ductule, s7 group ductule, s8 group Ductule and s9 group ductule;One end of the s1 group ductule is connected at the left side in the tunnel, the s2 group ductule One end be connected to the left side in the tunnel and the crown junction in tunnel;One end of the s5 group ductule is connected to the lane The crown junction of road right side and tunnel;The s3 group ductule and the s4 group ductule are evenly distributed on that the s2 group is small to be led Between pipe and the s5 group ductule;One end of the s6 group ductule is connected at the right side in the tunnel;The s7 group is small Conduit to s9 group ductule is uniformly arranged on the tunnel bottom;
The q group ductule includes q1 group ductule, q2 group ductule, q3 group ductule, q4 group ductule, q5 group is small leads Pipe, q6 group ductule, q7 group ductule, q8 group ductule and q9 group ductule;One end of the q1 group ductule is connected to institute State the left side in tunnel and the bottom junction in tunnel;One end of the q7 group ductule is connected to right side and the tunnel in the tunnel Bottom junction;The q8 group ductule and q9 group ductule are arranged perpendicular to the bottom in the tunnel;The q4 group is small to be led Pipe is connected to the highest point of the arch in the tunnel;The q2 group ductule be located at the s1 group ductule and s2 group ductule it Between;The q3 group ductule is between the s2 group ductule and s3 group ductule;The q5 group ductule is located at the s4 Between group ductule and s5 group ductule;The q6 group ductule is between the s5 group ductule and s6 group ductule;
The aqueduct is connected on the U-shaped canopy leg, is connected with one section of exposed pipe on the right side of the aqueduct, described exposed Pipe is identical as the internal diameter of the aqueduct, is connected with ring flange on the right side of the exposed pipe;
The s group ductule and q group ductule are extended towards tunnelling direction in country rock with 60~90 ° of inclination angles It is interior;
The s group ductule and q group ductule are the steel floral tube of one end sealing, and the other end of the steel floral tube is equipped with spiral shell Line, the sealed end of the steel floral tube is in coniform, for creeping into rock mass;The surrounding of the steel floral tube offers through-hole, for going out Slurry;
It is also connected with water guide gate valve on the right side of the aqueduct, for controlling the opening and closing of water flow;
Preferably, the liftoff spacing of the aqueduct is not less than 300mm.
A kind of construction method of water conductive fault comprehensive treatment parallel construction system, the construction method include the following steps:
Step 1, high pressure deep hole grouting:
Step 11, drill construction technique program is determined:
Under suggesting that progress is upper herein, specific value is placed on specification, or be placed on power 9, power 9 and 10 originally merges It is one.
After drilling tool aperture drilling and tripping in first sleeve → note dual slurry sealing → pressure-bearing pass the test → drilling tool super hole cutter Into and the second casing of tripping in → note dual slurry sealing → pressure-bearing pass the test after → drilling tool super hole cutter proceeds to projected depth → observation Water, hydraulic pressure and the water temperature in the whole hole of water outlet drilling;
Step 12, it tripping in first sleeve and the second casing and is fixed:
It is first crept into forward using drill bit A, then tripping in first sleeve, then infuses rapid hardening expansion hole sealing agent and carry out sealing;
It is first crept into forward using drill bit B, then the second casing of tripping in, note dual slurry carries out sealing;
Step 13, sealing inspection:
After first sleeve and the second casing sealing in step 12, using high pressure slurry pump respectively to first sleeve and second Casing carries out sealing quality examination, then is crept into drill bit C;
Step 2, grouting with small pipe:
Step 21, ductule is chosen:
Ductule synchronous construction when roadway construction deep hole grouting drills, ductule are not less than 1.5m, and material is 1 cun of Φ Steel floral tube, steel pipe exposed junction is threaded, surrounding should open up uniform through-hole;
Step 22, ductule is installed:
Two groups of ductules of s group ductule and q group ductule are constructed in channel spacing, every group of spacing 4m, can be according to live real Border situation arrangement group number, general arrangement group number should cover entire construction area;A, two groups of b each 9 holes, with 60~90 ° of inclination angle courts Driving front is squeezed into country rock;It squeezes into after country rock, slip casting can be carried out to ductule;
Step 23, aqueduct is installed:
Aqueduct is securely taken root on U-shaped canopy leg, so that the exposed 200mm of aqueduct, revealed section need welding flange, from Ground spacing is not less than 300mm, to install control Water gate valve;Installing for aqueduct is not limited to design position, according to practical water outlet It installs position;
Step 3, high pressure deep hole grouting and grouting with small pipe parallel construction:
While high pressure deep hole grouting, grouting with small pipe is constructed while being carried out.
A kind of construction method of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that the step 12 Described in drill bit A use Φ 168mm drill bit, the distance crept into forward be 6m;
The drill bit B uses the drill bit of Φ 127mm, and the distance crept into forward is 12m;
Cement slurry ratio of mud 1:1 in double slurries, cement slurry and waterglass volume ratio 1:0.6.
A kind of construction method of water conductive fault comprehensive treatment parallel construction system as described above, it is preferable that the step 11 In, cement slurry and waterglass volume ratio are 1:1~1:0.6 in the dual slurry;
In the step 12, the slip casting strengthening material of sealing is P.O42.5 portland cement, water and 35~40 Baume degrees Waterglass;
In the step 12, final grouting pressure 9MPa;
In the step 22, in grouting with small pipe, grouting pressure is not less than 6MPa;
There are two aqueducts in the step 23, and distance is 800mm between two pipes.
Compared with the immediate prior art, technical solution provided by the invention has following excellent effect:
The method that the present invention uses high pressure deep hole grouting and grouting with small pipe parallel construction, so that in high pressure deep hole grouting Grouting with small pipe is synchronous simultaneously carries out;The method that high pressure deep hole grouting uses three-wheel slip casting simultaneously, ductule use class interval Construction method so that water conductive fault is effectively administered.The invention enables water conductive fault administer the tomography duration shorten, work Journey amount is less, expense is low, accuracy rate is high.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide further understanding of the present invention, and of the invention shows Examples and descriptions thereof are used to explain the present invention for meaning property, does not constitute improper limitations of the present invention.Wherein:
Fig. 1 is the high-pressure slip-casting hole aperture layout drawing of the embodiment of the present invention;
Fig. 2 is the high-pressure slip-casting hole floor map of the embodiment of the present invention;
Fig. 3 is the high-pressure slip-casting hole diagrammatic cross-section of the embodiment of the present invention;
Fig. 4 is the first and third wheel slip casting section effect diagram of the embodiment of the present invention;
Fig. 5 is the second wheel slip casting section effect diagram of the embodiment of the present invention;
Fig. 6 is the section deep hole grouting cloth hole overall effect schematic diagram of the embodiment of the present invention;
Fig. 7 is that the ductule s group of the embodiment of the present invention arranges sectional schematic diagram;
Fig. 8 is that the conduit q group of the embodiment of the present invention arranges sectional schematic diagram;
Fig. 9 is the ductule plan view of the embodiment of the present invention;
Figure 10 is the ductule section arrangement schematic diagram of the embodiment of the present invention;
Figure 11 is the ductule structural schematic diagram of the embodiment of the present invention.
In figure: 11, first sleeve;12, the second casing;13, injected hole;14, first flange;15, second flange;16, Three flanges;17, pressure gauge;18, the first gate valve;19, short tube;110, the second gate valve;111, the 4th flange;112, plug;21, One wheel Grouting Pipe;22, the second wheel Grouting Pipe;23, third round Grouting Pipe;31, tunnel;41, left side;42, right side;43, third lock Valve;44, reinforcing bar;51 screw threads;52, steel floral tube;53, tip;54, slurry outlet;S1, first group of conduit;S2, second group of conduit;s3, Third group conduit;S4, the 4th group of conduit;Q1, the 5th group of conduit;Q2, the 6th group of conduit;Q3, the 7th group of conduit;Q4, the 8th group Conduit.
Specific embodiment
The present invention will be described in detail below with reference to the accompanying drawings and embodiments.It should be noted that in the feelings not conflicted Under condition, the features in the embodiments and the embodiments of the present application be can be combined with each other.
In the description of the present invention, term " longitudinal direction ", " transverse direction ", "upper", "lower", "front", "rear", "left", "right", " perpendicular Directly ", the orientation or positional relationship of the instructions such as "horizontal", "top", "bottom" is to be based on the orientation or positional relationship shown in the drawings, and is only For ease of description the present invention rather than require the present invention that must be constructed and operated in a specific orientation, therefore should not be understood as pair Limitation of the invention.Term used in the present invention " connected ", " connection " shall be understood in a broad sense, for example, it may be fixedly connected, It may be a detachable connection;It can be directly connected, can also be indirectly connected by intermediate member, for the common of this field For technical staff, the concrete meaning of above-mentioned term can be understood as the case may be.
According to a particular embodiment of the invention, as shown in Figure 1, being 13 aperture layout drawing of high-pressure slip-casting hole of the invention, the Sleeve 11 internal diameter 146mm, length 5.5m, 12 internal diameter 108mm of first sleeve.Length 11m, center are injected hole 13;Pressure gauge The outflow of the water in pipeline can be can control on 17 with the pressure in display pipes, the second gate valve 110;112 left end of plug is connected with 4th flange 111 is convenient for other external pipelines.It is high-pressure slip-casting end view of the invention, high pressure injection as shown in Fig. 2 to 6 Slurry 13 mouthfuls of hole arrangement is divided into three-wheel, respectively, first round Grouting Pipe 21, the second wheel Grouting Pipe 22, third round Grouting Pipe 23, first Grouting Pipe 21 is taken turns as the arrangement of third round Grouting Pipe 23, the arrangement of the second wheel Grouting Pipe 22 and first round slip casting Pipe 21 and third round Grouting Pipe 23 are different.It is arranged in this way so that intensity of the tunnel 31 in tunneling process is guaranteed.It prevents The harm of water conductive fault bring.It is grouting with small pipe end view of the invention, ductule in the present invention as described in Fig. 7-11 Slip casting is divided into s and two big groups of q, and each big group is divided into 9 groups, i.e. first group of conduit s1 again;Second group of conduit s2;Third group conduit s3;4th group of conduit s4;5th group of conduit q1;6th group of conduit q2;7th group of conduit q3;8th group of conduit q4;9th group is led Pipe q5, s and q two organizes greatly spaced apart arrangement, so that its area coverage becomes wider, and bring effect is more obvious.Together When tunnel bottom be equipped with reinforcing bar 44, for providing support, ductule front end is equipped with tip 53, convenient for being more easily inserted into rock mass In, ductule is surrounded by slurry outlet 54.
According to a particular embodiment of the invention, a kind of water conductive fault comprehensive treatment parallel construction system, parallel construction system Including high pressure deep hole grouting system, high pressure deep hole grouting system is located in the rock mass of 31 outside surrounding of tunnel.High pressure deep hole grouting System includes 13 device of high pressure deep hole grouting hole, and 13 device of high pressure deep hole grouting hole includes first sleeve 11, and first sleeve 11 is set It sets in the rock stratum around tunnel 31.For providing positioning and support.
Grouting with small pipe system, grouting with small pipe system are located at high pressure deep hole grouting system memory, grouting with small pipe system It is connected to the inner wall in tunnel 31.
According to a particular embodiment of the invention, 13 device of high pressure deep hole grouting hole further includes first sleeve 12, first sleeve 12 outer diameter is less than the internal diameter of first sleeve 11.First sleeve 12 is arranged concentrically in first sleeve 11, is set in first sleeve 12 There is injected hole 13.Short tube 19, short tube 19 are connected to the left side of first sleeve 12, and short tube 19 is equipped with pressure gauge 17.Plug 112, Plug 112 is connected to 19 left side of short tube, and spherical cavity is equipped in plug 112, is equipped with the second gate valve 110 in spherical cavity.
According to a particular embodiment of the invention, the length of first sleeve 12 is greater than the length of first sleeve 11, first sleeve 11 concordant with the left end of first sleeve 12 are arranged.Between first sleeve 11 and first sleeve 12, first sleeve 12 and injected hole 13 Between be equipped with the screed of same thickness.First sleeve 11 and first sleeve 12 are circumferentially distributed multiple through-holes, for starching Liquid is flowed out out of casing, forms the entirety of sealing.
According to a particular embodiment of the invention, 11 left end of first sleeve is connected with first flange 14,12 left end of first sleeve It is connected with second flange 15, the right end of short tube 19 is connected with third flange 16.First flange 14, second flange 15 and third flange 16 are close to link together.Second flange 15 is between first flange 14 and third flange 16.The connection of 19 outer wall of short tube is equipped with Pressure-measuring pipe, pressure-measuring pipe is interior to be equipped with the first gate valve 18, and pressure-measuring pipe upper end is connected with pressure gauge 17.First gate valve 18 is for being connected to pressure Table 17 and short tube 19.
Preferably, the internal diameter of short tube 19 is identical as the internal diameter of first sleeve 12.
According to a particular embodiment of the invention, injected hole 13 has three groups, respectively first group of injected hole, second group of injected hole With third group injected hole.Surrounding of each group of injected hole 13 along construction tunnel 31 is uniformly distributed, first group of injected hole and third Group injected hole distribution mode is identical and different from the distribution mode of second group of injected hole.
Preferably, first group of injected hole and third group injected hole and 31 centerlines of tunnel be 11~25 ° (such as 11 °, 12 °, 13 °, 14 °, 15 °, 18 °, 20 °, 22 °, 25 °), hole depth be 43~56m (such as 43m, 45m, 46m, 48m, 49m, 52m, 53m、55m、56m)。
More preferably, second group of injected hole 13 and 31 centerlines of tunnel be 15~22 ° (such as 15 °, 16 °, 17 °, 18 °, 19 °, 20 °, 21 °, 22 °), hole depth is 57~62m (such as 57m, 58m, 59m, 60m, 61m, 62m).
According to a particular embodiment of the invention, grouting with small pipe system includes grouting with small pipe aperture apparatus, grouting with small pipe Aperture apparatus includes,
S group ductule, s group ductule are arranged in the surrounding in tunnel 31, and one end of s group ductule is from 31 inner wall of tunnel to four Week extends to the other end.
Q group ductule, q group ductule and s group ductule interval are arranged, and the length of q group ductule is greater than s group ductule Length.
Aqueduct, aqueduct are located at the lower part of the left side 41 in tunnel 31, the right side of the opening direction of aqueduct towards tunnel 31 42。
According to a particular embodiment of the invention, s group ductule include s1 group ductule, s2 group ductule, s3 group ductule, S4 group ductule, s5 group ductule, s6 group ductule, s7 group ductule, s8 group ductule and s9 group ductule.S1 group ductule One end be connected at the left side 41 in tunnel 31, one end of s2 group ductule is connected to the left side 41 in tunnel 31 and the top in tunnel 31 Encircle junction.One end of s5 group ductule is connected to the crown junction of tunnel 31 right side 42 and tunnel 31.S3 group ductule and S4 group ductule is evenly distributed between s2 group ductule and s5 group ductule.One end of s6 group ductule is connected to tunnel 31 At right side 42.S7 group ductule to s9 group ductule is uniformly arranged on 31 bottom of tunnel.
Q group ductule include q1 group ductule, q2 group ductule, q3 group ductule, q4 group ductule, q5 group ductule, Q6 group ductule, q7 group ductule, q8 group ductule and q9 group ductule.One end of q1 group ductule is connected to the left side in tunnel 31 The bottom junction of side 41 and tunnel 31.One end of q7 group ductule is connected to the right side 42 in tunnel 31 and the bottom in tunnel 31 is handed over Meet place.Q8 group ductule and q9 group ductule are arranged perpendicular to the bottom in tunnel 31.Q4 group ductule is connected to the arch in tunnel 31 The highest point in portion.Q2 group ductule is located between s1 group ductule and s2 group ductule.Q3 group ductule is located at s2 group ductule Between s3 group ductule.Q5 group ductule is located between s4 group ductule and s5 group ductule.Q6 group ductule is located at s5 group Between ductule and s6 group ductule.
Aqueduct is connected on U-shaped canopy leg, is connected with one section of exposed pipe, the internal diameter of exposed pipe and aqueduct on the right side of aqueduct It is identical, ring flange is connected on the right side of exposed pipe.
S group ductule and q group ductule are extended towards 31 tunneling direction of tunnel in country rock with 60~90 ° of inclination angles.
S group ductule and q group ductule are the steel floral tube 52 of one end sealing, and the other end of steel floral tube 52 is equipped with screw thread 51, the sealed end of steel floral tube 52 is in coniform, for creeping into rock mass.The surrounding of steel floral tube 52 offers through-hole, is used for pulp.
It is also connected with water guide gate valve on the right side of aqueduct, for controlling the opening and closing of water flow.
Preferably, the liftoff spacing of aqueduct is not less than 300mm.
A kind of construction method of water conductive fault comprehensive treatment parallel construction system, construction method include the following steps:
Step 1, high pressure deep hole grouting:
Step 11, drill construction technique program is determined:
After drilling tool aperture drilling, tripping in first sleeve 11 → note dual slurry sealing → pressure-bearing pass the test → drilling tool super hole cutter After into, tripping in first sleeve 12 → note dual slurry sealing → pressure-bearing pass the test → drilling tool super hole cutter proceeds to projected depth → observation Water, hydraulic pressure and the water temperature in the whole hole of water outlet drilling.
Step 12, it tripping in first sleeve 11 and first sleeve 12 and is fixed:
6m, tripping in first sleeve 11 are crept into using Φ 168mm drill bit, note rapid hardening expansion hole sealing agent carries out sealing, cement slurry Ratio of mud 1:1, cement slurry and waterglass volume ratio 1:0.6.
12m, tripping in first sleeve 12 are crept into using Φ 127mm drill bit, note dual slurry carries out sealing, the cement slurry ratio of mud 1: 1, cement slurry and waterglass volume ratio 1:0.6.
Step 13, sealing inspection:
By the first sleeve 11 in step 12 and after 12 sealing of first sleeve 8 hours, first sleeve is done with high pressure slurry pump 11 and second set of pressure-bearing sealing quality examination, into first sleeve 11, water filling, aperture pressure are stablized 30 minutes up to 3Mpa, with aperture And the not permeable leak in periphery is qualification, otherwise again slip casting sealing until qualified.Into first sleeve 12, water filling, aperture pressure reach 5Mpa stablizes 30 minutes, is qualification with the not permeable leak in aperture and periphery, otherwise again slip casting sealing until qualified.First sleeve 12 After sealing passed examination, the voltage-controlled Water gate valve of 108mm high is installed with the drill bit C of Φ 75mm and is drilled into design hole depth.
Step 2, grouting with small pipe:
Step 21, ductule is chosen:
Ductule synchronous construction when deep hole grouting drilling is constructed in tunnel 31, ductule are not less than 1.5m, and material is 1 cun of Φ Steel floral tube 52, steel pipe exposed junction is threaded 51, surrounding should open up uniform through-hole.
Step 22, ductule is installed:
Two groups of ductules of s group ductule and q group ductule are staggeredly constructed in tunnel 31, and every group of spacing 4m can be according to scene Actual conditions arrangement group number, general arrangement group number should cover entire construction area.A, two groups of b each 9 holes, with 60~90 ° of inclination angles It is squeezed into country rock towards driving front.It squeezes into after country rock, slip casting can be carried out to ductule.
Step 23, aqueduct is installed:
Aqueduct is securely taken root on U-shaped canopy leg, so that the exposed 200mm of aqueduct, revealed section need welding flange, from Ground spacing is not less than 300mm, to install control Water gate valve.Installing for aqueduct is not limited to design position, according to practical water outlet It installs position.
Step 3, high pressure deep hole grouting and grouting with small pipe parallel construction:
While high pressure deep hole grouting, grouting with small pipe is constructed while being carried out.
According to a particular embodiment of the invention, in step 11, cement slurry and waterglass volume ratio are 1:1~1 in dual slurry: 0.6。
In step 12, the slip casting strengthening material of sealing is the water of P.O42.5 portland cement, water and 35~40 Baume degrees Glass.
In step 12, final grouting pressure 9MPa.
According to a particular embodiment of the invention, in step 22, in grouting with small pipe, grouting pressure is not less than 6MPa.
There are two aqueducts in step 23, and distance is 800mm between two pipes.
According to a particular embodiment of the invention, the present invention is controlled according to the geology and hydrogeological parameter of Tang Jia meeting mine The checking computations of range are managed, safe impermeable layer thickness calculation formula and 31 water-resisting floor of digging laneway are pacified as follows for the checking computations for the treatment of range Full water pressure calculation formula is as follows for the geology and hydrogeological parameter and 31 design parameter of tunnel, exploitation of Tang Jia meeting mine:
Safe impermeable layer thickness calculation formula:
The safe impermeable layer thickness of t-, m in formula;
31 baseplate width of the tunnel L-, L=5.5m;
The average severe of γ-water-resisting floor, γ=0.025MN/m3
KpThe average tensile strength of water-resisting floor, Kp=1.0MPa;
The head pressure that p- water-resisting floor is born, p=1.1MPa.
Calculate to obtain t=4.05m.
The safe hydraulic pressure of 31 water-resisting floor of digging laneway
In formula, the safe hydraulic pressure that p- water-resisting floor is able to bear, MPa;
T- impermeable layer thickness, t=12m;
31 width of the tunnel L-, L=5.5m;
The average severe of γ-water-resisting floor, 0.025MN/m3
KpThe average tensile strength of water-resisting floor, Kp=1.0MPa
Calculate to obtain p=9.82MPa.
When delimiting 31 border 12m reinforcing scope of tunnel, the minimum impermeable layer thickness between 31 bottom plate of tunnel and ash difficult to understand is about For 12m, it is much larger than safe impermeable layer thickness 4.05m;Working face Ordovician karst water pressure is up to 1.1MPa, is much smaller than safe hydraulic pressure 9.82MPa, therefore the treatment range delimited is reasonable.
Meanwhile the present invention also provides drilling construction parameter lists, it is as shown in table 1 below:
1 drilling construction parameter list of table
In short, the method that the present invention uses high pressure deep hole grouting and grouting with small pipe parallel construction, so that in high pressure deep hole Grouting with small pipe is synchronous while slip casting carries out;The method that high pressure deep hole grouting uses three-wheel slip casting simultaneously, ductule, which uses, to be divided The staggered construction method of group, so that water conductive fault is effectively administered.So that water conductive fault administer the tomography duration shorten, engineering Measure that less, expense is low, accuracy rate is high.
The above description is only a preferred embodiment of the present invention, is not intended to restrict the invention, for those skilled in the art For member, the invention may be variously modified and varied.All within the spirits and principles of the present invention, it is made it is any modification, Equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of water conductive fault comprehensive treatment parallel construction system, which is characterized in that the parallel construction system includes:
High pressure deep hole grouting system, the high pressure deep hole grouting system are located on the outside of tunnel in the rock mass of surrounding;The high pressure is deep Hole grouting system includes high pressure deep hole grouting aperture apparatus, and the high pressure deep hole grouting aperture apparatus includes first sleeve, and described first Casing is arranged in the rock stratum around tunnel, for providing positioning and support;
Grouting with small pipe system, the grouting with small pipe system are located at the high pressure deep hole grouting system memory, the ductule Grouting system is connected to the inner wall in the tunnel;
The high pressure deep hole grouting system with grouting with small pipe system is parallel on the outside of tunnel constructs simultaneously.
2. a kind of water conductive fault comprehensive treatment parallel construction system as described in claim 1, which is characterized in that the high pressure is deep Hole slip casting aperture apparatus further include:
Second casing, the outer diameter of second casing are less than the internal diameter of the first sleeve;Second casing is arranged concentrically on In the first sleeve, injected hole is equipped in second casing;
Short tube, the short tube are connected to the left side of second casing, and the short tube is equipped with pressure gauge;
Plug, the plug are connected on the left of the short tube, and spherical cavity is equipped in the plug, is equipped in the spherical cavity Second gate valve.
3. a kind of water conductive fault comprehensive treatment parallel construction system as claimed in claim 2, which is characterized in that described second set The length of pipe is greater than the length of the first sleeve, and the first sleeve is concordant with the left end of second casing to be arranged;It is described The mortar of same thickness is equipped between first sleeve and second casing, between second casing and the injected hole Layer;The first sleeve and second casing are circumferentially distributed multiple through-holes, flow out out of casing for slurries, form envelope Solid entirety.
4. a kind of water conductive fault comprehensive treatment parallel construction system as claimed in claim 2, which is characterized in that the first set Pipe left end is connected with first flange, and second casing left end is connected with second flange, and the right end of the short tube is connected with third Flange;The first flange, the second flange and third flange abutting link together;The second flange is located at institute It states between first flange and the third flange;
The short tube outer wall connection is equipped with pressure-measuring pipe, is equipped with the first gate valve in the pressure-measuring pipe, the pressure-measuring pipe upper end is connected with Pressure gauge;First gate valve is for being connected to the pressure gauge and the short tube;
Preferably, the internal diameter of the short tube is identical as the internal diameter of second casing.
5. a kind of water conductive fault comprehensive treatment parallel construction system as claimed in claim 2, which is characterized in that the injected hole There are three groups, respectively first group of injected hole, second group of injected hole and third group injected hole;Injected hole described in each group is along construction The circumferential direction in tunnel is uniformly distributed, and first group of injected hole is identical as the third group injected hole distribution mode, and with described Two groups of distribution mode is different;
Preferably, first group of injected hole and third group injected hole and center line in roadway angle are 11~25 °, hole depth is 43~ 56m;
More preferably, second group of injected hole and center line in roadway angle are 15~22 °, and hole depth is 57~62m.
6. a kind of water conductive fault comprehensive treatment parallel construction system as described in claim 1, which is characterized in that the ductule Grouting system includes grouting with small pipe aperture apparatus, and the grouting with small pipe aperture apparatus includes:
S group ductule, the s group ductule are arranged in the circumferential direction in tunnel, and one end of the s group ductule is from tunnel inner wall Radiation extends to the other end around;
Q group ductule, the q group ductule and the s group ductule are arranged at the circumferential direction interval in tunnel, and the q group is small The length of conduit is greater than the length of the s group ductule;
Aqueduct, the aqueduct are located at the lower part of the left side in tunnel, the right side of the opening direction of the aqueduct towards tunnel.
7. a kind of water conductive fault comprehensive treatment parallel construction system as claimed in claim 6, which is characterized in that the s group is small Conduit includes s1 group ductule, s2 group ductule, s3 group ductule, s4 group ductule, s5 group ductule, s6 group ductule, s7 Group ductule, s8 group ductule and s9 group ductule;One end of the s1 group ductule is connected at the left side in the tunnel, institute The one end for stating s2 group ductule is connected to the left side in the tunnel and the crown junction in tunnel;One end of the s5 group ductule It is connected to the crown junction of the tunnel right side and tunnel;The s3 group ductule and the s4 group ductule are evenly distributed on Between the s2 group ductule and the s5 group ductule;One end of the s6 group ductule is connected to the right side in the tunnel Place;The s7 group ductule to s9 group ductule is uniformly arranged on the tunnel bottom;
The q group ductule include q1 group ductule, q2 group ductule, q3 group ductule, q4 group ductule, q5 group ductule, Q6 group ductule, q7 group ductule, q8 group ductule and q9 group ductule;One end of the q1 group ductule is connected to the lane The left side in road and the bottom junction in tunnel;One end of the q7 group ductule is connected to right side and the bottom in tunnel in the tunnel Portion junction;The q8 group ductule and q9 group ductule are arranged perpendicular to the bottom in the tunnel;The q4 group ductule connects Connect the highest point in the arch in the tunnel;The q2 group ductule is between the s1 group ductule and s2 group ductule; The q3 group ductule is between the s2 group ductule and s3 group ductule;It is small that the q5 group ductule is located at the s4 group Between conduit and s5 group ductule;The q6 group ductule is between the s5 group ductule and s6 group ductule;
The aqueduct is connected on the U-shaped canopy leg, is connected with one section of exposed pipe on the right side of the aqueduct, the exposed pipe with The internal diameter of the aqueduct is identical, is connected with ring flange on the right side of the exposed pipe;
The s group ductule and q group ductule are extended towards tunnelling direction in country rock with 60~90 ° of inclination angles;
The s group ductule and q group ductule are the steel floral tube of one end sealing, and the other end of the steel floral tube is equipped with screw thread, The sealed end of the steel floral tube is in coniform, for creeping into rock mass;The surrounding of the steel floral tube offers through-hole, is used for pulp;
It is also connected with water guide gate valve on the right side of the aqueduct, for controlling the opening and closing of water flow;
Preferably, the liftoff spacing of the aqueduct is not less than 300mm.
8. a kind of construction method of water conductive fault comprehensive treatment parallel construction system as described in any one of claims 1 to 7, It is characterized in that, the construction method includes the following steps:
Step 1, high pressure deep hole grouting:
Step 11, drill construction technique program is determined:
Drilling tool aperture drilling and tripping in first sleeve → note dual slurry sealing → pressure-bearing pass the test after → drilling tool aperture drilling simultaneously After the second casing of tripping in → note dual slurry sealing → pressure-bearing pass the test → drilling tool super hole cutter proceeds to the water outlet of projected depth → observation Water, hydraulic pressure and the water temperature in the whole hole of drilling;
Step 12, it tripping in first sleeve and the second casing and is fixed:
It is first crept into forward using drill bit A, then tripping in first sleeve, then infuses rapid hardening expansion hole sealing agent and carry out sealing;
It is first crept into forward using drill bit B, then the second casing of tripping in, note dual slurry carries out sealing;
Step 13, sealing inspection:
After first sleeve and the second casing sealing in step 12, using high pressure slurry pump respectively to first sleeve and the second casing Sealing quality examination is carried out, then is crept into drill bit C;
Step 2, grouting with small pipe:
Step 21, ductule is chosen:
Ductule synchronous construction when roadway construction deep hole grouting drills, ductule are not less than 1.5m, the spray of molten steel that material is 1 cun of Φ Pipe, steel pipe exposed junction is threaded, surrounding should open up uniform through-hole;
Step 22, ductule is installed:
Two groups of ductules of s group ductule and q group ductule are constructed in channel spacing, every group of spacing 4m, can be according to the practical feelings in scene Condition arrangement group number, general arrangement group number should cover entire construction area;A, two groups of b each 9 holes, with 60~90 ° of inclination angles towards driving Front is squeezed into country rock;It squeezes into after country rock, slip casting can be carried out to ductule;
Step 23, aqueduct is installed:
Aqueduct is securely taken root on U-shaped canopy leg, so that the exposed 200mm of aqueduct, revealed section needs welding flange, liftoff Away from 300mm is not less than, to install control Water gate valve;Installing for aqueduct is not limited to design position, according to practical water exit position It installs;
Step 3, high pressure deep hole grouting and grouting with small pipe parallel construction:
While high pressure deep hole grouting, grouting with small pipe is constructed while being carried out.
9. a kind of construction method of water conductive fault comprehensive treatment parallel construction system as claimed in claim 8, which is characterized in that Drill bit A described in the step 12 uses the drill bit of Φ 168mm, and the distance crept into forward is 6m;
The drill bit B uses the drill bit of Φ 127mm, and the distance crept into forward is 12m;
Cement slurry ratio of mud 1:1 in double slurries, cement slurry and waterglass volume ratio 1:0.6.
10. a kind of construction method of water conductive fault comprehensive treatment parallel construction system as claimed in claim 8, feature exist In in the step 11, cement slurry and waterglass volume ratio are 1:1~1:0.6 in the dual slurry;
In the step 12, the slip casting strengthening material of sealing is the water of P.O42.5 portland cement, water and 35~40 Baume degrees Glass, final grouting pressure 9MPa;
In the step 22, in grouting with small pipe, grouting pressure is not less than 6MPa;
There are two aqueducts in the step 23, and distance is 800mm between two pipes.
CN201811156915.6A 2018-09-30 2018-09-30 A kind of water conductive fault comprehensive treatment parallel construction system and construction method Pending CN109139053A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811156915.6A CN109139053A (en) 2018-09-30 2018-09-30 A kind of water conductive fault comprehensive treatment parallel construction system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811156915.6A CN109139053A (en) 2018-09-30 2018-09-30 A kind of water conductive fault comprehensive treatment parallel construction system and construction method

Publications (1)

Publication Number Publication Date
CN109139053A true CN109139053A (en) 2019-01-04

Family

ID=64814152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811156915.6A Pending CN109139053A (en) 2018-09-30 2018-09-30 A kind of water conductive fault comprehensive treatment parallel construction system and construction method

Country Status (1)

Country Link
CN (1) CN109139053A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110454200A (en) * 2019-09-06 2019-11-15 贵州桥梁建设集团有限责任公司 A kind of double-walled grouting with small pipe device and its construction method
CN111022088A (en) * 2019-12-23 2020-04-17 天地科技股份有限公司 Interception and injection method for roadway pressure-bearing flowing water fault

Citations (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09158690A (en) * 1995-12-13 1997-06-17 Taisei Corp Forming method for slide arch center for tunnel lining and grout filling hole
KR20030034629A (en) * 2001-10-26 2003-05-09 김정윤 method and device and structure tunnel formation tunnel construction spacetime
KR100847352B1 (en) * 2007-05-11 2008-07-21 (주)지중공영 Supporting tube assembly for tunnel supporting method with grouted steel pipe in the borehole and supporting method of using thereof
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Strengthening and reinforcing method of high-ground-pressure soft rock laneway by hierarchical grouting
CN102926770A (en) * 2012-11-08 2013-02-13 中国神华能源股份有限公司 Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN103061785A (en) * 2012-12-28 2013-04-24 山东大学 Borehole casing pressure-proof seepage sealing grouting device and process for roadway breaking water burst surrounding rock
CN103089275A (en) * 2013-01-16 2013-05-08 山东大学 Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN103628894A (en) * 2013-10-24 2014-03-12 重庆大学 Water-rich fault fracture zone collapsed roadway repairing method based on angle-variable umbrella-shaped advancing grouting
CA2791585A1 (en) * 2012-10-05 2014-04-05 7092601 Canada Inc. Drill hole plug system
CN103899329A (en) * 2014-03-24 2014-07-02 中国矿业大学 Large-deformation broken surrounding rock roadway management method
CN104141470A (en) * 2014-07-01 2014-11-12 中煤科工集团西安研究院有限公司 Pore-forming and sealing method for hydraulic fracturing borehole casing section in underground coal mine
CN104453943A (en) * 2014-10-27 2015-03-25 山东科技大学 Method for controlling water-rich fractured rock mass comprehensive grouting under effective sealing batholite shortage condition
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
CN104533467A (en) * 2014-12-18 2015-04-22 淮北市平远软岩支护工程技术有限公司 High confined water and fault broken roadway supporting method
CN104632249A (en) * 2014-12-05 2015-05-20 中国电建集团成都勘测设计研究院有限公司 Tunnel system supporting technology used in loose and soft broken surrounding rock
CN105178981A (en) * 2015-09-30 2015-12-23 中国矿业大学 Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway
CN205876348U (en) * 2016-07-28 2017-01-11 中国建筑第六工程局有限公司 Multi -level advance support structure of transverse passage -way vault under complex geological condition
CN106761392A (en) * 2016-12-20 2017-05-31 淮北矿业(集团)勘探工程有限责任公司 It is a kind of for the hole structure with grouting filling in hyperbaric environment
CN107083977A (en) * 2017-06-23 2017-08-22 中国矿业大学 A kind of grouting strengthening method of many granularities of argillaceous soft rock tunnel subregion
CN107642360A (en) * 2017-07-25 2018-01-30 彭峰 Tunneling boring front pre-grouting construction method
CN206942786U (en) * 2017-06-26 2018-01-30 中铁第一勘察设计院集团有限公司 A kind of advanced pre-add fixing structure of high-moisture percentage loess tunnel
CN108374662A (en) * 2018-01-31 2018-08-07 鄂尔多斯市国源矿业开发有限责任公司 The conduction method of artesian water tomography is crossed in a kind of tunnel
CN209025677U (en) * 2018-09-30 2019-06-25 淮矿西部煤矿投资管理有限公司 A kind of water conductive fault comprehensive treatment parallel construction system

Patent Citations (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09158690A (en) * 1995-12-13 1997-06-17 Taisei Corp Forming method for slide arch center for tunnel lining and grout filling hole
KR20030034629A (en) * 2001-10-26 2003-05-09 김정윤 method and device and structure tunnel formation tunnel construction spacetime
KR100847352B1 (en) * 2007-05-11 2008-07-21 (주)지중공영 Supporting tube assembly for tunnel supporting method with grouted steel pipe in the borehole and supporting method of using thereof
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Strengthening and reinforcing method of high-ground-pressure soft rock laneway by hierarchical grouting
CA2791585A1 (en) * 2012-10-05 2014-04-05 7092601 Canada Inc. Drill hole plug system
CN102926770A (en) * 2012-11-08 2013-02-13 中国神华能源股份有限公司 Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN103061785A (en) * 2012-12-28 2013-04-24 山东大学 Borehole casing pressure-proof seepage sealing grouting device and process for roadway breaking water burst surrounding rock
CN103089275A (en) * 2013-01-16 2013-05-08 山东大学 Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN103628894A (en) * 2013-10-24 2014-03-12 重庆大学 Water-rich fault fracture zone collapsed roadway repairing method based on angle-variable umbrella-shaped advancing grouting
CN103899329A (en) * 2014-03-24 2014-07-02 中国矿业大学 Large-deformation broken surrounding rock roadway management method
CN104141470A (en) * 2014-07-01 2014-11-12 中煤科工集团西安研究院有限公司 Pore-forming and sealing method for hydraulic fracturing borehole casing section in underground coal mine
CN104453943A (en) * 2014-10-27 2015-03-25 山东科技大学 Method for controlling water-rich fractured rock mass comprehensive grouting under effective sealing batholite shortage condition
CN104632249A (en) * 2014-12-05 2015-05-20 中国电建集团成都勘测设计研究院有限公司 Tunnel system supporting technology used in loose and soft broken surrounding rock
CN104481560A (en) * 2014-12-09 2015-04-01 中煤第一建设有限公司 Roadway roof aquifer treatment method
CN104533467A (en) * 2014-12-18 2015-04-22 淮北市平远软岩支护工程技术有限公司 High confined water and fault broken roadway supporting method
CN105178981A (en) * 2015-09-30 2015-12-23 中国矿业大学 Total-section closed type deep-shallow coupling yielding, bolting-grouting and supporting method for incompact and fractured soft-rock roadway
CN205876348U (en) * 2016-07-28 2017-01-11 中国建筑第六工程局有限公司 Multi -level advance support structure of transverse passage -way vault under complex geological condition
CN106761392A (en) * 2016-12-20 2017-05-31 淮北矿业(集团)勘探工程有限责任公司 It is a kind of for the hole structure with grouting filling in hyperbaric environment
CN107083977A (en) * 2017-06-23 2017-08-22 中国矿业大学 A kind of grouting strengthening method of many granularities of argillaceous soft rock tunnel subregion
CN206942786U (en) * 2017-06-26 2018-01-30 中铁第一勘察设计院集团有限公司 A kind of advanced pre-add fixing structure of high-moisture percentage loess tunnel
CN107642360A (en) * 2017-07-25 2018-01-30 彭峰 Tunneling boring front pre-grouting construction method
CN108374662A (en) * 2018-01-31 2018-08-07 鄂尔多斯市国源矿业开发有限责任公司 The conduction method of artesian water tomography is crossed in a kind of tunnel
CN209025677U (en) * 2018-09-30 2019-06-25 淮矿西部煤矿投资管理有限公司 A kind of water conductive fault comprehensive treatment parallel construction system

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
丁常国,贺淑焕: "高压富水铁路隧道综合施工技术", 地下空间, no. 03 *
刘广超;: "高水压大断层时效性注浆加固技术研究", 煤炭工程, no. 09, pages 2 - 3 *
王威;: "水平孔钻进结合高压注浆治理导水陷落柱技术", 内蒙古煤炭经济, no. 16 *
陈胜然;李世超;杜乐乐;: "构造破碎带"三维"立体加固技术", 中国科技信息, no. 12 *
陶文朋;陈酩知;: "松软围岩巷道高承压突水过断层注浆加固技术", 能源技术与管理, no. 04 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110454200A (en) * 2019-09-06 2019-11-15 贵州桥梁建设集团有限责任公司 A kind of double-walled grouting with small pipe device and its construction method
CN111022088A (en) * 2019-12-23 2020-04-17 天地科技股份有限公司 Interception and injection method for roadway pressure-bearing flowing water fault

Similar Documents

Publication Publication Date Title
CN109139052A (en) A kind of slip casting aperture apparatus and construction method based on high pressure deep hole grouting
CN105041325B (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN103510964B (en) A kind of method when using shield formula TBM to construct to beans gravel rockfill grouting
CN106014201B (en) A kind of outer release hole safe construction technique of tunnel grouting curtain
CN106703692A (en) Method using surface orientation bedding drilling grouting to reinforce laminar limestone
CN107288657A (en) The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground
CN106979012B (en) Hidden conduit pipe Comprehensive Treatment method in shaft of vertical well freezing hole
CN101525881B (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN105888673B (en) The operating method of deep hole modeling pipe high-pressure slip-casting explosion-protection equipment in soft rich water country rock
CN103603689A (en) Curtain grouting construction method for treating mined-out areas
CN107119669A (en) For shield, the pre-pouring grout consolidated subsoil method in house is worn in side in water-rich sand layer
CN103334770A (en) Construction method of superhigh water pressure water-affluent crushed zones of long-large counter-slope tunnels
CN108915736A (en) The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN105909259B (en) Existing shield tunnel pipe curtain construction settlement control system and method are closely worn down
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN109322699A (en) Pollution isolation blocking technology under a kind of mine
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN106320354A (en) Anti-seepage construction method for karst cave development stratum under overburden
CN105909265B (en) Pass through the anti-protuberance retrusive deep hole grouting system and method for existing shield tunnel
CN108952727B (en) A kind of grouting water blocking method of the vertical creviced formation of high inclination-angle
CN105134254B (en) A kind of tunnel surface drilling sleeve pipe sealing device and its operating procedure
CN109139053A (en) A kind of water conductive fault comprehensive treatment parallel construction system and construction method
CN107034874A (en) Double-screw type slip casting type freezing plant and construction method
CN109139018A (en) The method for tunnel construction and system that deep hole sleeve valve barrel grouting is combined with horizontal jet grouting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination