CN107288657A - The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground - Google Patents

The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground Download PDF

Info

Publication number
CN107288657A
CN107288657A CN201710660504.XA CN201710660504A CN107288657A CN 107288657 A CN107288657 A CN 107288657A CN 201710660504 A CN201710660504 A CN 201710660504A CN 107288657 A CN107288657 A CN 107288657A
Authority
CN
China
Prior art keywords
hole
slip casting
water
grouting
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710660504.XA
Other languages
Chinese (zh)
Other versions
CN107288657B (en
Inventor
张伟杰
王喆
魏久传
石守桥
尹会永
李孝朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201710660504.XA priority Critical patent/CN107288657B/en
Publication of CN107288657A publication Critical patent/CN107288657A/en
Application granted granted Critical
Publication of CN107288657B publication Critical patent/CN107288657B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of weak cementing rock mass seepage failure area slip casting integrated control method of top of underground, including conjunctive use geological analysis and geophysical exploration about exhausted means, improvement area's hydrogeologic condition is found out;Seepage failure destroys supporting reinforcing in section and the zone of influence;Sluice the resolution design of decompression delamination pour slurry;The decompression drilling construction that sluices is adjusted with delamination pour slurry engineering construction and dynamic;Sluicing decompression hole high-pressure high-flow blocking in flowing water;Strengthen the steps such as surrouding rock deformation monitoring.After being constructed using this engineering method, by to weak cementing rock mass reinforcing and high-pressure high-flow water burst closure by different level, phase in, efficiently solve work harnessing project cycle length, easily trigger the problem of secondary geological disaster, improve slip casting efficiency, create good Social benefit and economic benefit.

Description

The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground
Technical field
The present invention relates to a kind of tunnels and underground engineering geological hazard control technology, the underground such as especially a kind of tunnel tunnel Weak cementing rock mass seepage failure area sluicing decompression-delamination pour slurry comprehensive processing method at the top of engineering.
Background technology
The construction of the underground engineerings such as tunnel, power station, mine working, inevitably passes through fault belt, packed type The unfavorable geologic bodies such as solution cavity, all badness geologic bodies often connect rich water water-bearing layer, as water space and containing conduit pipe, quilt Long-term water burst is tended to occur after exposure.Trace it to its cause is that excavation disturbance causes to produce plastic failure area and free face, ground in country rock Lower water penetration power causes the fine grained composition such as clay to be carried out, and the scale of conduit pipe extends and increased with open-assembly time, table It is now that at one or a few places concentrate water burst;At the same time, coffer mechanics performance runs down, top plate sedimentation, the quick increasing of side wall convergence Greatly, severe patient causes larger landslide, and induced water inrush is dashed forward mud.In addition, western each mining area coal such as China Inner Mongol, Xinjiang Aboundresources, these regional coal-bearing strata diagenesis times are short, the main cementing difference of mining coal seam adjoining rock, and in roof strata Thickness is generally dispersed with up to hundred meters of water-bearing layer.To prevent to carry out top plate water-bearing layer before top plate water damage, working face extraction Draining hook.Constantly softening, argillization country rock, and companion are limited by during cementing weak, low intensity Rock Nature, roof water white-out With hydraulic fracture, conduit pipe in rock mass is caused to gradually form and turn into the important channel type oozed under roof water;Passage extends And networking can cause large-scale roof strata to produce displacement, subregion is in water storages such as the formation absciss layers of intersection containing water barrier Construction.Under the multiple factors long terms such as lithology, groundwater seepage pressure, construction, rock mass seepage failure damage type geology calamity Evil is lasting to be occurred, serious to threaten underground engineering construction and operation security.
The disaster of underground engineering such case mainly passes through two methods of Enhanced support and grouting and reinforcing, or two methods Implement simultaneously.It presently, there are following problem:1. supporting intensity is increasing, cost more and more higher, but country rock self-strength does not have It is improved, causes calamity source and passage not to punish, still suffer from landslide, roof fall risk;2. slip casting can improve country rock self-strength, reduction Its permeability, however, space is big, infiltration is strong, low intensity, cementing weak feature because catastrophe area rock mass has, it is difficult to bear height Grouting pressure, by force static pressure grouting may cause landslide etc. secondary geological disaster.Therefore, the prominent discharge disaster of such underground engineering is controlled Managing needs to carry out under the premise of ensureing that roof rock mass is stable, i.e., supporting reinforcement+reasonable grouting process conjunctive use could obtain reason The regulation effect thought.
The content of the invention
The purpose of the present invention is to exist to overcome above-mentioned prior art to administer in weak cementing rock mass seepage failure geological disaster Such as regulation effect pay no attention to and think of the problems such as easily triggering secondary disaster there is provided a kind of weak cementing rock mass infiltration of top of underground Destroy area's slip casting integrated control method.
To achieve the above object, the present invention uses following technical proposals:
A kind of weak cementing rock mass seepage failure area slip casting integrated control method of top of underground, comprises the following steps:
A)Conjunctive use geological analysis and geophysical exploration about exhausted means, find out improvement area's hydrogeologic condition, including:
1)Research area's hydrogeological profile, analysis underground engineering superstratum lithology combination feature, it is determined that causing calamity aqueous are drawn Layer and master control conduit pipe type;
2)Top plate geophysical exploration about exhausted work, delineation overlying strata hydrous fluids form and scope are carried out, instructs hazard management to work;
B)Seepage failure destroys supporting reinforcing in section and the zone of influence, i.e., be combined using interim rigid protection with flexible support Means are destroyed to seepage failure and supporting strengthening segment are formed in the range of section and adjacent 10 ~ 20m;
C)Sluicing decompression-delamination pour slurry resolution design, i.e., in roof strata hydrous fluids construction sluicing decompression hole, around letting out Water decompression hole applies delamination pour slurry reinforced hole;Injected hole point sequence construction, and using protrusive segmenting slip casting mode to superstratum Progressively reinforce from shallow to deep;Finally the slip casting of sluicing decompression hole is blocked;
D)To step C)Sluicing decompression drilling construction and delamination pour slurry engineering construction, fully reinforce country rock mesohigh rich water structure The weak cementing rock mass between underground engineering is made, inlet well arrangement and grouting parameter are in the light of actual conditions dynamically adjusted;
E)Sluicing decompression hole high-pressure high-flow blocking in flowing water, including sluicing decompression hole is using sluicing-slip casting and static pressure grouting two Stage grouting method is carried out;Water burst controlling in hole drain by tapping pipe in spilled water hole, steel pipe by the fixation of mould bag and with Hole wall constitutes the annular diffusion space in sluicing-slip casting stage;After after grout cures, closing tapping pipe simultaneously opens static pressure grouting rank Section;
F)Surrouding rock deformation is monitored in real time, ensures that engineering safety is implemented.
The step A)In 1)Specifically include the rock that research causes the weak cementing water barrier between calamity water-bearing layer and underground engineering Property and thickness space Distribution Characteristics, qualitative analysis administer area rock mass underground aquaporin forming process and rock mass reduction deformation original Cause, judges the possibility that absciss layer occurs.
2 in the step A)Specifically include using transient electromagnetic, geological radar geophysical exploration about exhausted method to research area top Plate is detected, analysis top plate rich water zone position and form;By with hydrogeologic section joint interpretation, delineation absciss layer area or leads Water construction controlling water-containing space is conduit pipe scope, instructs inlet well and spilled water hole pattern and depth.
Interim rigid protection in the step B selects to be grillage, concrete column or I-steel according to construction condition Bracing members, per 1000 ~ 2000mm of Pin spacing;The flexible support uses thickness for C20 gunite concretes thick 250mm, built-in Individual layer bar-mat reinforcement.
The step C)In, if top plate hydrous fluids are separated strata seeper area, sluice and drop directly against construction in the middle part of absciss layer area Press hole;If surrounding rock deterioration is mainly caused by tomography class permeable structure, sluicing decompression hole is applied in master control containing on permeable structure Trip, to block Groundwater movement passage, forces underground water mainly to be discharged along spilled water hole.
The step D)In, sluicing decompression hole is applied for the roof strata hydrous fluids in underground engineering superstratum, is let out Water decompression hole is using geological drilling rig construction elevation angle hole, and step is as follows:
First by Noncoring drill bit perforate to 6m, the long 5m external diameters seamless steel pipe of tripping in makees one-level orifice tube;
It is cased with the 1# moulds bag processed by geotextiles on the outside of the one-level orifice tube, and mould bag is located at and is welded on one-level orifice tube Between two 1# limiters;
The 1# moulds bag upper/lower terminal head is fixed on one-level outside of sleeve, lower end connection 1# slip castings using wire binding mode Pipe;
Pass through the slip casting into 1# moulds bag of 1# Grouting Pipes behind one-level orifice tube tripping in hole;
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R light waters Mud mass ratio is 1:1;Concentration of sodium silicate is between 35 ~ 42Be, and modulus is 2.3 ~ 3.0,42.5R ordinary cements single slurry and water glass Glass volume ratio is 2:1, the selection of slip casting termination pressure is 2.5MPa;
1# moulds bag is propped up after the grout cures of injection, while broken soft rock mass around extruding, reaches one-level orifice tube and broken The close occlusion of country rock and the purpose of fixed orifice pipe;
After one-level orifice tube is fixed, constructed using Noncoring drill bit to design hole depth, the second hole mouthful pipe that tripping in seamless steel pipe makes; Fixing seal is rolled up by quick-hardening cement between described second hole mouthful pipe and one-level orifice tube;
Second hole mouthful length of tube is 10 ~ 15m, and 5 ~ 10m of front end is fabricated to floral tube, is drilled with multigroup water seepage hole, both plays borehole wall-protection Effect, prevents drilling from blocking, and underground water in water abundant ground can again discharged.
The step D)In, around sluicing, delamination pour slurry reinforced hole is laid in decompression drilling, lays mode according to site operation Condition is arranged as annular or rectangle;Described grouting and reinforcing hole is divided into 3 sequences, wherein I sequence pitch of holes is 4 ~ 6m, II sequence hole Spacing is 2 ~ 3m, and III sequence pitch of holes is 1m, implements slip casting to each sequence hole successively according to I ~ III order in work progress.
Injecting paste material selects cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud is that water and 42.5R are general Logical cement quality ratio is 0.8:1~1:1;Concentration of sodium silicate is between 35 ~ 42Be, and modulus is 2.3 ~ 3.0,42.5R ordinary cement lists Slurry and waterglass volume ratio are 1:1~3:1, the selection of slip casting termination pressure is 2 ~ 3MPa.
The step E)In, the closure of sluicing decompression hole uses sluicing-slip casting and static pressure grouting two benches grouting method, including Following steps:
Tapping pipe is processed into first with seamless steel pipe, tapping pipe two ends thread is connected to each other by screw thread;
The 2# moulds bag processed by geotextiles is cased with the outside of the tapping pipe of the top, and 2# moulds bag is located between 2# limiters;
2# moulds bag upper/lower terminal head is fixed on the outside of tapping pipe using wire binding mode, lower end connection 2# Grouting Pipes;
Tapping pipe is sent to precalculated position, i.e. 2# moulds bag through screwed connection rig, by rig and is arranged to master control water guide in drilling 1 ~ 2m below channel position;
After tapping pipe tripping in, using 2# Grouting Pipes to the bag slip casting of 2# moulds;
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R light waters Mud mass ratio is 1:1;Concentration of sodium silicate is between 35 ~ 42Be, and modulus is 2.3 ~ 3.0,42.5R ordinary cements single slurry and water glass Glass volume ratio is 2:1, the selection of slip casting termination pressure is 2 ~ 3MPa;
2# moulds bag is propped up after injection grout cures, while crushing soft rock mass around extruding to fix tapping pipe, and is forced in hole Water burst flows out through tapping pipe;
Tapping pipe lower end is connected with second hole mouthful pipe through 1# filling adaptors;
1# filling adaptors are managed by screwed connection second hole mouthful, and its bottom plate processes two circular holes and is each passed through tapping pipe and 2# slip castings Pipe, treats that tapping pipe installs latter three and is welded and fixed;
Annular space between tapping pipe and hole wall turns into the slurries diffusion admittance of first stage slip casting;
First stage slip casting is sluicing-slip casting stage, by the 3# Grouting Pipes being connected with 1# filling adaptors, is sluiced in tapping pipe Implement in journey, reinforce spilled water hole superficial part country rock;
Injecting paste material uses cement single slurry, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R ordinary cement mass ratioes 0.8:1~1:1,3 ~ 4MPa of grouting pressure.
Sluicing-slip casting stage terminated after 48 hours, and slurries gelinite can bear grouting pressure;
It is the static pressure grouting stage to be blocked using tapping pipe slip casting containing conduit pipe, is sluiced through 2# filling adaptors by screwed connection Tube end, water burst can be closed by closing high-pressure ball valve;
Through 4# Grouting Pipes implement static pressure grouting, static pressure grouting be mainly filling tapping pipe and its exposure contain conduit pipe, and will High pressure ground water preservation space metathesis is slurries, so as to reach closure passage, intercepts water source, reinforces the multipurpose of water barrier.
Injecting paste material selects cement single slurry, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R light water shales Amount compares 0.8:1~1:1,4 ~ 5MPa of grouting pressure.
The step F)In, during drilling is applied and Grouting engineering is implemented, according to country rock situation in seepage failure damage type Catastrophe area and zone of influence arrangement monitoring section, catastrophe area monitoring section spacing is 3 ~ 5m, and zone of influence monitoring section is 5 ~ 10m, with Top plate sedimentation and lateral wall convergent deformation situation during supervision control engineering is implemented;Monitoring curve is drawn simultaneously, instructs the dynamic of grouting pressure State is adjusted.
The beneficial effects of the invention are as follows:The present invention solves existing method and punishes roof rock mass because seepage failure triggers simultaneously Concentrate that improvement cycle length, the effect of the geological disasters such as water burst and rock stratum large deformation are undesirable, easily trigger secondary geological disaster etc. to ask Topic.Take after this engineering method constructs, by weak cementing rock mass reinforcing and the closure of high-pressure high-flow water burst by different level, it is real stage by stage Apply, shorten the punishment duration of the weak cementing country rock seepage failure type geological disaster of top of underground, ensured surrounding rock consolidation model Enclose and intensity, particularly centralized high voltage big flow concentrates water burst area country rock to be reinforced by different level, it is to avoid mandatory static pressure note Starch the secondary geological disaster caused to occur, effectively increase governance quality, create good Social benefit and economic benefit.
Brief description of the drawings
Fig. 1 is the construction technology process block diagram of the present invention;
Fig. 2 is the diagrammatic cross-section of resolution of the present invention;
Fig. 3 is the sluicing decompression hole structural representation of the present invention;
Fig. 4 is the sluicing decompression hole closure schematic diagram of the present invention;
In figure, 1, rich water water-bearing layer;2nd, weak cementing rock mass(Relative water resisting layer);3rd, the underground space;4th, separated strata seeper area;5th, water guide Construction;6th, sluicing decompression hole;7th, interim rigid protection;8th, temporary flexible supporting;9th, delamination pour slurry reinforced hole;10th, one-level aperture Pipe;11st, 1# moulds bag;12nd, 1# limiters;13rd, 1# Grouting Pipes;14th, second hole mouthful pipe;15th, spout hole;16th, quick-hardening cement is rolled up; 17th, tapping pipe;18th, 2# moulds bag;19th, 2# limiters;20th, 2# Grouting Pipes;21st, 1# filling adaptors;22nd, slurries diffusion annular is empty Between;23rd, 3# Grouting Pipes;24th, 2# filling adaptors;25th, high-pressure ball valve;26th, 4# Grouting Pipes;27th, monitoring section.
Embodiment
The present invention is further described with reference to the accompanying drawings and examples.
Structure, ratio, size depicted in this specification institute accompanying drawings etc., only to coordinate in disclosed in specification Hold, so that those skilled in the art is understood with reading, be not limited to enforceable qualifications of the invention, therefore do not have skill Essential meaning in art, the modification of any structure, the change of proportionate relationship or the adjustment of size can be produced not influenceing the present invention Under raw effect and the purpose that can reach, all should still it fall in the range of disclosed technology contents are obtained and can covered. Meanwhile, the term of cited such as " on ", " under " in this specification, "left", "right", " centre " and " one " is merely convenient to Narration understands, and be not used to limit enforceable scope of the invention, and its relativeness is altered or modified, without substantive change Under technology contents, when being also considered as enforceable category of the invention.
As Figure 1-Figure 4, the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground, including with Lower step:
1st, conjunctive use geological analysis and geophysical exploration about exhausted means, find out improvement area's hydrogeologic condition
According to the geological prospecting borehole data near the underground engineerings such as tunnel or tunnel, draw and administer area's large scale hydrogeology Profile, analyze superstratum lithology combination feature and geological structure developmental state, it is determined that cause calamity water-bearing layer (body) 1 layer of position and Geological structure type.Research causes the weak cementing rock mass between calamity water-bearing layer (body) 1 and underground engineering 3(Relative water resisting layer)2 rock Property and thickness space Distribution Characteristics, qualitative analysis administer area rock mass underground aquaporin forming process and rock mass reduction deformation original Cause, judges the possibility that absciss layer 4 occurs.
Research area's top plate is detected using the geophysical exploration about exhausted such as transient electromagnetic, geological radar method, top plate is analyzed Rich water zone position and form.By with hydrogeologic section joint interpretation, the controlling such as delineation absciss layer area 4 or permeable structure 5 contains Hydrospace(Conduit pipe)Scope, instructs inlet well and spilled water hole pattern and depth.
2nd, seepage failure destroys supporting reinforcing in section and the zone of influence
Seepage failure is destroyed in the range of section and adjacent 10 ~ 20m with the means that flexible support is combined using interim rigid protection Form supporting strengthening segment.
Described interim rigid protection can select be that grillage, cross section are the mixed of 500 × 500mm according to construction condition Solidifying earth pillar or 25b I-steel bracing members, per 1000 ~ 2000mm of Pin spacing.Described flexible support uses thickness for 250mm thickness C20 gunite concretes, built-in individual layer length is multiplied by wide 400m × 400m, φ 8mm bar-mat reinforcement.
3rd, sluicing decompression-delamination pour slurry resolution design
According to geological analysis and geophysical exploration about exhausted synthesis result, in roof strata hydrous fluids construction sluicing decompression hole 6.Described The purpose of sluicing decompression hole 6 is that roof overburden mesohigh water, to the penetration of rock stratum, prevents shape in roof strata during reducing slip casting Country rock compressive deformation is caused to destroy into the Lentic environment of sealing high pressure.
If top plate hydrous fluids are separated strata seeper area 4, directly against construction sluicing decompression hole in the middle part of absciss layer area;
If surrounding rock deterioration is mainly caused by the permeable structures such as tomography 5, sluicing decompression hole is applied in master control containing on permeable structure Trip, to block Groundwater movement passage, forces underground water mainly to be discharged along spilled water hole.
Delamination pour slurry reinforced hole 9, injected hole point sequence construction are applied around sluicing decompression hole 6, and note is segmented using protrusive Slurry mode is progressively reinforced from shallow to deep to superstratum.Finally the slip casting of sluicing decompression hole is blocked, harnessing project is completed.
4th, sluice decompression drilling construction and delamination pour slurry engineering construction and dynamic adjustment
Sluicing decompression hole is applied for the concentration hydrous fluids in underground engineering superstratum, sluicing decompression hole 6 uses geological drilling rig Construct elevation angle hole, step is:
First by external diameter φ 168mm Noncoring drill bits perforates to 6m, the long 5m external diameters φ 146mm seamless steel pipes of tripping in make one-level aperture Pipe 10.
It is cased with the 1# moulds bag 11 processed by geotextiles on the outside of one-level orifice tube, and mould bag is located at and is welded on one-level orifice tube Two 1# limiters 12 between.
1# moulds 11 upper/lower terminal heads of bag are fixed on one-level outside of sleeve, lower end connection 1# notes using wire binding mode Starch pipe 13.
Pass through the slip casting into 1# moulds bag 11 of 1# Grouting Pipes 13 behind one-level orifice tube tripping in hole.
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud(Water is common with 42.5R Cement quality ratio)For 1:1;Concentration of sodium silicate between 35 ~ 42Be, modulus be 2.3 ~ 3.0,42.5R ordinary cements single slurry and Waterglass volume ratio is 2:1, the selection of slip casting termination pressure is 2.5MPa.
The grout cures back brace molding bag of injection, while broken soft rock mass around extruding, reaches one-level orifice tube and broken The close occlusion of broken country rock and the purpose of fixed orifice pipe.
After one-level orifice tube is fixed, constructed using external diameter φ 137mm Noncoring drill bits to design hole depth, tripping in external diameter φ The second hole mouthful pipe 14 that 108mm seamless steel pipes make.
Second hole mouthful length of tube is fixed according to actual conditions, and generally 10 ~ 15m, 5 ~ 10m of front end is fabricated to floral tube, is drilled with many Group water seepage hole 15, had both played borehole wall-protection effect, and had prevented drilling from blocking, and underground water in water abundant ground can again discharged.
16 fixing seals are rolled up by quick-hardening cement between second hole mouthful pipe 14 and one-level orifice tube, the encapsulating method is known Engineering method;After the completion of the construction of sluicing decompression hole, disaster area underground water is mainly by spilled water hole centralized discharge, and other locations of country rock are oozed Discharge reduction.
Around sluicing, delamination pour slurry reinforced hole is laid in decompression drilling, and laying mode is arranged as annular according to construction condition Or rectangle.
Grouting and reinforcing hole is divided into 3 sequences, wherein the spacing of I sequence hole 3 is 4 ~ 6m, the spacing of II sequence hole 4 is 2 ~ 3m, III sequence hole 5 spacing are 1m, implement slip casting to each sequence hole successively according to I ~ III order in work progress.
Grouting process is protrusive segmenting slip casting technique, and this method is known engineering method, is repeated no more.
Injecting paste material selects cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud(Water is common with 42.5R Cement quality ratio)For 0.8:1~1:1;Concentration of sodium silicate is between 35 ~ 42Be, and modulus is 2.3 ~ 3.0,42.5R ordinary cement lists Slurry and waterglass volume ratio are 1:1~3:1, the selection of slip casting termination pressure is 2 ~ 3MPa.Above-mentioned grout coordinate ratio and grouting parameter are Applicant by long-term engineering practice and summary of experience obtained by, it is ensured that slip casting effect.
Sluicing decompression drilling hole amount, position etc. can be adjusted according to field condition;Inlet well lays mode, grouting sequence Dynamic adjustment need to be needed according to scene.
5th, sluicing decompression hole high-pressure high-flow blocking in flowing water
After underground engineering roof cracking rock mass is reinforced, it need to be blocked in time as the sluicing decompression hole of issue is concentrated.Let out Water burst has high-pressure high-flow feature in water decompression hole, and long-time water burst will cause to wash away to hole wall rock mass, and cause slip casting to add Gu area's rock mass water content increases, slip casting effect is reduced under long term, or even seepage failure damage type disaster occurs again.This Outside, unless as dewatering orifice, the presence of sluicing decompression hole will cause condition of work to deteriorate, and be unfavorable for safety in production, it is therefore necessary to Blocked.
The closure of sluicing decompression hole is carried out using sluicing-slip casting and static pressure grouting two benches grouting method.
Single long 1500mm tapping pipe 17 is processed into first with external diameter Φ 63.5mm, wall thickness 8mm seamless steel pipe, is let out Water pipe two ends thread, is connected to each other by screw thread.The 2# moulds bag 18 processed by geotextiles, and 2# are cased with the outside of the tapping pipe of the top Mould bag is located between 2# limiters 19.
2# moulds bag upper/lower terminal head is fixed on the outside of tapping pipe using wire binding mode, lower end connection 2# Grouting Pipes 20。
Tapping pipe is sent to precalculated position, i.e. 2# moulds bag 18 through screwed connection rig, by rig and is arranged to main in drilling 1 ~ 2m below conduct aquaporin position.
After tapping pipe tripping in, using 2# Grouting Pipes 20 to 19 slip castings of bag of 2# moulds.
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud(Water is common with 42.5R Cement quality ratio)For 1:1;Concentration of sodium silicate between 35 ~ 42Be, modulus be 2.3 ~ 3.0,42.5R ordinary cements single slurry and Waterglass volume ratio is 2:1, the selection of slip casting termination pressure is 2 ~ 3MPa.
2# moulds bag is propped up after injection grout cures, while crushing soft rock mass around extruding to fix tapping pipe, and is forced Water burst flows out through tapping pipe in hole.
The lower end of tapping pipe 17 is connected with second hole mouthful pipe through 1# filling adaptors 21.1# filling adaptors pass through two grades of screwed connection Orifice tube, its bottom plate processes two circular holes and is each passed through tapping pipe 17 and 2# Grouting Pipes 20, treats that tapping pipe installs latter three It is welded and fixed.
Annular space 22 between tapping pipe 17 and hole wall turns into the slurries diffusion admittance of first stage slip casting.
First stage slip casting be sluicing-slip casting stage, by the 3# Grouting Pipes 23 be connected with 1# filling adaptors, in sluicing Pipe is implemented under the conditions of sluicing, and reinforces spilled water hole superficial part country rock.Injecting paste material uses cement single slurry, and grouting parameter is as follows:Cement Pulp-water gray scale(Water and 42.5R ordinary cement mass ratioes)0.8:1~1:1,3 ~ 4MPa of grouting pressure.
Sluicing-slip casting stage terminated after 48 hours, and slurries gelinite has some strength, and Surrounding Rock Strength is higher, Neng Goucheng By grouting pressure.
It is the static pressure grouting stage to be blocked using tapping pipe slip casting containing conduit pipe.
Through 2# filling adaptors 24 by screwed connection sluicing tube end, water burst can be closed by closing high-pressure ball valve 25.Through 4# Grouting Pipe 26 implements static pressure grouting, and what static pressure grouting was mainly filling tapping pipe and its exposure contains conduit pipe, and by underground water The space metathesis of presence is slurries, so as to reach closure passage, intercepts water source, reinforces the multipurpose of water barrier.Injecting paste material Cement single slurry is selected, grouting parameter is as follows:The cement mortar ratio of mud(Water and 42.5R ordinary cement mass ratioes)0.8:1~1:1, 4 ~ 5MPa of grouting pressure.
6th, surrouding rock deformation is monitored in real time, ensures that engineering safety is implemented
During drilling is applied and Grouting engineering is implemented, arranged according to country rock situation in seepage failure damage type catastrophe area and the zone of influence Monitoring section, catastrophe area monitoring section spacing is 3 ~ 5m, and zone of influence monitoring section is 5 ~ 10m, is pushed up during being implemented with supervision control engineering Plate is settled and lateral wall convergent deformation situation.Monitoring curve is drawn simultaneously, instructs the dynamic adjustment of grouting pressure.
Although above-mentioned the embodiment of the present invention is described with reference to accompanying drawing, not to present invention protection model The limitation enclosed, one of ordinary skill in the art should be understood that on the basis of technical scheme those skilled in the art are not Need to pay various modifications or deform still within protection scope of the present invention that creative work can make.

Claims (10)

1. a kind of weak cementing rock mass seepage failure area slip casting integrated control method of top of underground, it is characterized in that, including it is following Step:
A)Conjunctive use geological analysis and geophysical exploration about exhausted means, find out improvement area's hydrogeologic condition, including:
1)Research area's hydrogeological profile, analysis underground engineering superstratum lithology combination feature, it is determined that causing calamity aqueous are drawn Layer and master control conduit pipe type;
2)Top plate geophysical exploration about exhausted work, delineation overlying strata hydrous fluids form and scope are carried out, instructs hazard management to work;
B)Seepage failure destroys supporting reinforcing in section and the zone of influence, i.e., be combined using interim rigid protection with flexible support Means are destroyed to seepage failure and supporting strengthening segment are formed in the range of section and adjacent 10 ~ 20m;
C)Sluicing decompression-delamination pour slurry resolution design, i.e., in roof strata hydrous fluids construction sluicing decompression hole, around letting out Water decompression hole applies delamination pour slurry reinforced hole, injected hole point sequence construction, and uses protrusive segmenting slip casting mode to superstratum Progressively reinforce from shallow to deep;Finally the slip casting of sluicing decompression hole is blocked;
D)To step C)Sluicing decompression drilling construction and delamination pour slurry engineering construction, fully reinforce the aqueous structure of country rock mesohigh The weak cementing rock mass made between underground engineering is filled, and inlet well arrangement and grouting parameter are in the light of actual conditions dynamically adjusted;
E)Sluicing decompression hole high-pressure high-flow blocking in flowing water, including sluicing decompression hole is using sluicing-slip casting and static pressure grouting two Stage grouting method is carried out;Water burst controlling in hole drain by tapping pipe in spilled water hole, steel pipe by the fixation of mould bag and with Hole wall constitutes the annular diffusion space in sluicing-slip casting stage;After after grout cures, closing tapping pipe simultaneously opens static pressure grouting rank Section;
F)Surrouding rock deformation is monitored in real time, ensures that engineering safety is implemented.
2. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, the step A)In 1)Specifically include research cause weak cementing water barrier between calamity water-bearing layer and underground engineering lithology and The reason for area rock mass underground aquaporin forming process and rock mass reduction deformation, is administered in thickness space Distribution Characteristics, qualitative analysis, Judge the possibility that absciss layer occurs.
3. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, 2 in the step A)Specifically include and research area's top plate is entered using transient electromagnetic, geological radar geophysical exploration about exhausted method Row is detected, analysis top plate rich water zone position and form;By with hydrogeologic section joint interpretation, delineation absciss layer area or water guide structure Controlling water-containing space i.e. conduit pipe scope is made, inlet well and spilled water hole pattern and depth is instructed.
4. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, the interim rigid protection in the step B is grillage, concrete column or I-steel steel branch according to construction condition selection Support, per 1000 ~ 2000mm of Pin spacing;The flexible support uses thickness for C20 gunite concretes thick 250mm, built-in individual layer Bar-mat reinforcement.
5. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, the step C)In, if top plate hydrous fluids are separated strata seeper area, sluice and be depressured directly against construction in the middle part of absciss layer area Hole;If surrounding rock deterioration is mainly caused by tomography class permeable structure, sluicing decompression hole is applied in master control upstream containing permeable structure, To block Groundwater movement passage, underground water is forced mainly to be discharged along spilled water hole.
6. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, the step D)In, sluicing decompression hole is applied for the roof strata hydrous fluids in underground engineering superstratum, sluice drop Press hole using geological drilling rig construction elevation angle hole, step is as follows:
First by Noncoring drill bit perforate to 6m, the long 5m external diameters seamless steel pipe of tripping in makees one-level orifice tube;
It is cased with the 1# moulds bag processed by geotextiles on the outside of the one-level orifice tube, and mould bag is located at and is welded on one-level orifice tube Between two 1# limiters;
The 1# moulds bag upper/lower terminal head is fixed on one-level outside of sleeve, lower end connection 1# slip castings using wire binding mode Pipe;
Pass through the slip casting into 1# moulds bag of 1# Grouting Pipes behind one-level orifice tube tripping in hole;
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R light waters Mud mass ratio is 1:1;Concentration of sodium silicate is between 35 ~ 42Be, and modulus is 2.3 ~ 3.0,42.5R ordinary cements single slurry and water glass Glass volume ratio is 2:1, the selection of slip casting termination pressure is 2.5MPa;
1# moulds bag is propped up after the grout cures of injection, while broken soft rock mass around extruding, reaches one-level orifice tube and broken The close occlusion of country rock and the purpose of fixed orifice pipe;
After one-level orifice tube is fixed, constructed using Noncoring drill bit to design hole depth, the second hole mouthful pipe that tripping in seamless steel pipe makes; Fixing seal is rolled up by quick-hardening cement between described second hole mouthful pipe and one-level orifice tube.
7. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 6, it is special Levying is, the second hole mouthful length of tube is 10 ~ 15m, and 5 ~ 10m of front end is fabricated to floral tube, is drilled with multigroup water seepage hole.
8. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, the step D)In, around sluicing, delamination pour slurry reinforced hole is laid in decompression drilling, lays mode according to construction condition It is arranged as annular or rectangle;Described grouting and reinforcing hole is divided into 3 sequences, wherein I sequence pitch of holes is 4 ~ 6m, II sequence pitch of holes For 2 ~ 3m, III sequence pitch of holes is to implement slip casting to each sequence hole successively according to I ~ III order in 1m, work progress;
Injecting paste material selects cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R light waters Mud mass ratio is 0.8:1~1:1;Concentration of sodium silicate is between 35 ~ 42Be, and modulus is 2.3 ~ 3.0,42.5R ordinary cement single slurries It is 1 with waterglass volume ratio:1~3:1, the selection of slip casting termination pressure is 2 ~ 3MPa.
9. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, the step E)In, sluicing decompression hole, which is blocked, uses sluicing-slip casting and static pressure grouting two benches grouting method, including with Lower step:
Tapping pipe is processed into first with seamless steel pipe, tapping pipe two ends thread is connected to each other by screw thread;
The 2# moulds bag processed by geotextiles is cased with the outside of the tapping pipe of the top, and 2# moulds bag is located between 2# limiters;
2# moulds bag upper/lower terminal head is fixed on the outside of tapping pipe using wire binding mode, lower end connection 2# Grouting Pipes;
Tapping pipe is sent to precalculated position, i.e. 2# moulds bag through screwed connection rig, by rig and is arranged to master control water guide in drilling 1 ~ 2m below channel position;
After tapping pipe tripping in, using 2# Grouting Pipes to the bag slip casting of 2# moulds;
Injecting paste material uses cement-sodium silicate double liquid, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R light waters Mud mass ratio is 1:1;Concentration of sodium silicate is between 35 ~ 42Be, and modulus is 2.3 ~ 3.0,42.5R ordinary cements single slurry and water glass Glass volume ratio is 2:1, the selection of slip casting termination pressure is 2 ~ 3MPa;
2# moulds bag is propped up after injection grout cures, while crushing soft rock mass around extruding to fix tapping pipe, and is forced in hole Water burst flows out through tapping pipe;
Tapping pipe lower end is connected with second hole mouthful pipe through 1# filling adaptors;
1# filling adaptors are managed by screwed connection second hole mouthful, and its bottom plate processes two circular holes and is each passed through tapping pipe and 2# slip castings Pipe, treats that spilled water hole is fixed latter three and is welded and fixed;
Annular space between tapping pipe and hole wall turns into the slurries diffusion admittance of first stage slip casting;
First stage slip casting is sluicing-slip casting stage, by the 3# Grouting Pipes being connected with 1# filling adaptors, in tapping pipe sluicing bar Implement under part, reinforce spilled water hole superficial part country rock;
Injecting paste material uses cement single slurry, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R ordinary cement mass ratioes 0.8:1~1:1,3 ~ 4MPa of grouting pressure;
Sluicing-slip casting stage terminated after 48 hours, and slurries gelinite can bear grouting pressure;
It is the static pressure grouting stage to be blocked using tapping pipe slip casting containing conduit pipe, is sluiced through 2# filling adaptors by screwed connection Tube end, water burst can be closed by closing high-pressure ball valve;
Through 4# Grouting Pipes implement static pressure grouting, static pressure grouting be mainly filling tapping pipe and its exposure contain conduit pipe, and will The space metathesis that underground water is present is slurries, so as to reach closure passage, intercepts water source, reinforces the multipurpose of water barrier;
Injecting paste material selects cement single slurry, and grouting parameter is as follows:The cement mortar ratio of mud is water and 42.5R ordinary cement mass ratioes 0.8:1~1:1,4 ~ 5MPa of grouting pressure.
10. the weak cementing rock mass seepage failure area slip casting integrated control method of top of underground as claimed in claim 1, it is special Levying is, the step F)In, during drilling is applied and Grouting engineering is implemented, according to country rock situation in seepage failure damage type catastrophe Area and zone of influence arrangement monitoring section, catastrophe area monitoring section spacing is 3 ~ 5m, and zone of influence monitoring section is 5 ~ 10m, to monitor Top plate sedimentation and lateral wall convergent deformation situation during engineering construction;Monitoring curve is drawn simultaneously, instructs the dynamic tune of grouting pressure It is whole.
CN201710660504.XA 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground Active CN107288657B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710660504.XA CN107288657B (en) 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710660504.XA CN107288657B (en) 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground

Publications (2)

Publication Number Publication Date
CN107288657A true CN107288657A (en) 2017-10-24
CN107288657B CN107288657B (en) 2019-01-29

Family

ID=60105256

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710660504.XA Active CN107288657B (en) 2017-08-04 2017-08-04 The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground

Country Status (1)

Country Link
CN (1) CN107288657B (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956225A (en) * 2017-11-22 2018-04-24 中国煤炭地质总局水文地质局 Discarded small-size coal mine top panel area administers the processing method for reducing the increment of groundwater
CN108412498A (en) * 2018-03-06 2018-08-17 山东科技大学 Freeze sinking construction pit shaft annular causes calamity channel grouting treatment design method
CN108487918A (en) * 2018-03-06 2018-09-04 山东科技大学 Tunneling and underground engineering wall-rock crack water grouting treatment design method
CN108915736A (en) * 2018-07-13 2018-11-30 中煤科工集团西安研究院有限公司 The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN109611109A (en) * 2018-11-05 2019-04-12 青岛市地铁号线有限公司 Tunnel TBM constructed crushed zone disaster source controls in advance method and system
CN109611146A (en) * 2018-11-29 2019-04-12 山东科技大学 A kind of unrestrained grouting method of absciss layer water
CN110017155A (en) * 2019-05-23 2019-07-16 合肥工业大学 A kind of coal working face top plate rich water gravel layer grouting and reinforcing erection water-proof method
CN110159307A (en) * 2019-05-16 2019-08-23 北京市政建设集团有限责任公司 A kind of tunnel multilayer grouting process
CN110331994A (en) * 2019-04-30 2019-10-15 宁夏久威矿山安全工程有限责任公司 A kind of digging laneway absciss layer breaking roof water drenching control method
CN110499757A (en) * 2019-08-27 2019-11-26 中铁二局集团有限公司 A kind of water-rich sand layer three axes agitating pile construction method
CN110905556A (en) * 2019-12-20 2020-03-24 山东科技大学 Novel efficient mixing alternating type double-hole sectional grouting method
CN112049139A (en) * 2020-08-28 2020-12-08 浙大城市学院 Drainage grouting guide pipe and using method thereof
CN112281878A (en) * 2020-08-28 2021-01-29 浙大城市学院 Positioning grouting reinforcement method for treating underground water seepage damage of foundation pit engineering
CN112832810A (en) * 2021-03-04 2021-05-25 淮北市平远软岩支护工程技术有限公司 Support method for fractured-interval argillization rheological rock mass and application
CN114837608A (en) * 2022-05-31 2022-08-02 中国矿业大学 Method for reconstructing mining overburden rock water barrier by multi-section graded grouting

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02215887A (en) * 1989-02-17 1990-08-28 Taguchi Kenkyusho:Kk Grouting
CN101839139A (en) * 2010-02-09 2010-09-22 铁道部工程管理中心 Information tracking grouting method
CN102493822A (en) * 2011-12-29 2012-06-13 中铁二十三局集团有限公司 Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN104370508A (en) * 2014-10-15 2015-02-25 山东科技大学 Coal mine floor rock mass grouting reinforcement method and grouting slurry
CN105625292A (en) * 2016-02-03 2016-06-01 山东科技大学 Grouting reinforcement effect three-dimensional spatial data acquisition method for weak broken rock body

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02215887A (en) * 1989-02-17 1990-08-28 Taguchi Kenkyusho:Kk Grouting
CN101839139A (en) * 2010-02-09 2010-09-22 铁道部工程管理中心 Information tracking grouting method
CN102493822A (en) * 2011-12-29 2012-06-13 中铁二十三局集团有限公司 Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN104370508A (en) * 2014-10-15 2015-02-25 山东科技大学 Coal mine floor rock mass grouting reinforcement method and grouting slurry
CN105625292A (en) * 2016-02-03 2016-06-01 山东科技大学 Grouting reinforcement effect three-dimensional spatial data acquisition method for weak broken rock body

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107956225A (en) * 2017-11-22 2018-04-24 中国煤炭地质总局水文地质局 Discarded small-size coal mine top panel area administers the processing method for reducing the increment of groundwater
CN108412498A (en) * 2018-03-06 2018-08-17 山东科技大学 Freeze sinking construction pit shaft annular causes calamity channel grouting treatment design method
CN108487918A (en) * 2018-03-06 2018-09-04 山东科技大学 Tunneling and underground engineering wall-rock crack water grouting treatment design method
CN108915736A (en) * 2018-07-13 2018-11-30 中煤科工集团西安研究院有限公司 The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN109611109A (en) * 2018-11-05 2019-04-12 青岛市地铁号线有限公司 Tunnel TBM constructed crushed zone disaster source controls in advance method and system
CN109611146A (en) * 2018-11-29 2019-04-12 山东科技大学 A kind of unrestrained grouting method of absciss layer water
CN110331994B (en) * 2019-04-30 2023-08-15 宁夏久威矿山安全工程有限责任公司 Method for preventing and controlling water spraying of separation broken roof of tunneling roadway
CN110331994A (en) * 2019-04-30 2019-10-15 宁夏久威矿山安全工程有限责任公司 A kind of digging laneway absciss layer breaking roof water drenching control method
CN110159307A (en) * 2019-05-16 2019-08-23 北京市政建设集团有限责任公司 A kind of tunnel multilayer grouting process
CN110017155A (en) * 2019-05-23 2019-07-16 合肥工业大学 A kind of coal working face top plate rich water gravel layer grouting and reinforcing erection water-proof method
CN110499757A (en) * 2019-08-27 2019-11-26 中铁二局集团有限公司 A kind of water-rich sand layer three axes agitating pile construction method
CN110905556A (en) * 2019-12-20 2020-03-24 山东科技大学 Novel efficient mixing alternating type double-hole sectional grouting method
CN110905556B (en) * 2019-12-20 2021-01-05 山东科技大学 Efficient mixing alternating type double-hole sectional grouting method
CN112281878A (en) * 2020-08-28 2021-01-29 浙大城市学院 Positioning grouting reinforcement method for treating underground water seepage damage of foundation pit engineering
CN112049139B (en) * 2020-08-28 2021-07-09 浙大城市学院 Drainage grouting guide pipe and using method thereof
CN112281878B (en) * 2020-08-28 2021-07-09 浙大城市学院 Positioning grouting reinforcement method for treating underground water seepage damage of foundation pit engineering
CN112049139A (en) * 2020-08-28 2020-12-08 浙大城市学院 Drainage grouting guide pipe and using method thereof
CN112832810A (en) * 2021-03-04 2021-05-25 淮北市平远软岩支护工程技术有限公司 Support method for fractured-interval argillization rheological rock mass and application
CN114837608A (en) * 2022-05-31 2022-08-02 中国矿业大学 Method for reconstructing mining overburden rock water barrier by multi-section graded grouting
CN114837608B (en) * 2022-05-31 2022-12-23 中国矿业大学 Method for reconstructing mining overburden rock water barrier by multi-section graded grouting

Also Published As

Publication number Publication date
CN107288657B (en) 2019-01-29

Similar Documents

Publication Publication Date Title
CN107288657B (en) The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground
CN105041325B (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN108915736B (en) Method for preventing and controlling water damage of roadway tunneling under strong water-rich and weak-cementation aquifer
CN103603689B (en) Curtain grouting construction method for treating mined-out areas
CN105422170B (en) Middle deep goaf grouting reinforcing and processing method under a kind of building foundation
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN103061785B (en) Grouting process for borehole casing pressure-proof seepage sealing grouting device for drilling roadway breaking water burst surrounding rock
CN105201448B (en) Block water slip casting method for blocking in a kind of high-pressure high-flow water gushing channelway
CN103821544B (en) Tunneling and underground engineering high-pressure high-flow is dashed forward Water outburst treatment method
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN103628912B (en) The construction method of filling grouting is processed in a kind of goaf
CN108240234A (en) A kind of Along Railway underlies coal mine gob Grouting method
CN105155563A (en) Reinforcing and treating method for water burst of soft-flow muddy stratum of foundation pit
CN107060834A (en) Grout injection control technique is oozed in drainage slowly under back rich water broken condition
CN108708743B (en) Method for treating tunnel collapse by grouting
CN102561950B (en) Process for realizing grouting consolidation for aggregates filled in cavities of strata and jetting drill bit
CN105888673B (en) The operating method of deep hole modeling pipe high-pressure slip-casting explosion-protection equipment in soft rich water country rock
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN107313745B (en) Well cementation method for reinforcing coal-bed gas well through multi-node intensive grouting in goaf
CN114233385A (en) Treatment method for mud burst and water burst of inclined shaft
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN107313744A (en) A kind of small guide hole grouting and reinforcing coal bed gas well passes through the construction method in goaf
CN111287769A (en) Tunnel surrounding rock advanced grouting reinforcement structure and construction method thereof
CN105926589A (en) Steel pipe pile applicable to coral reef geology and grouting method of steel pipe pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant