CN108999142A - The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater - Google Patents

The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater Download PDF

Info

Publication number
CN108999142A
CN108999142A CN201810944787.5A CN201810944787A CN108999142A CN 108999142 A CN108999142 A CN 108999142A CN 201810944787 A CN201810944787 A CN 201810944787A CN 108999142 A CN108999142 A CN 108999142A
Authority
CN
China
Prior art keywords
caisson
pile foundation
dome
breakwater
rectangular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810944787.5A
Other languages
Chinese (zh)
Inventor
肖忠
刘莺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201810944787.5A priority Critical patent/CN108999142A/en
Publication of CN108999142A publication Critical patent/CN108999142A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/40Foundations for dams across valleys or for dam constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

The present invention relates to a kind of construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater, such breakwater includes caisson and pile foundation, and the caisson is the rectangular caisson of dome made of being poured based on combined steel formwork.Construction method includes: to utilize combined steel formwork, the rectangular caisson of dome is poured by the sequence layering substep of bottom plate, vertical plate and floor, two straight wall sections, dome portion, wherein in integral prefabricated vertical plate and floor, vertical plate and floor intersection service sleeve, to form the mounting hole of pile foundation, and prefabricated pile foundation;It is filled the water in caisson in job location through the tapping of caisson dome portion, caisson sinking is sat into bottom in designated position;Pile foundation is squeezed into designated depth;Cement slurry is injected between pile foundation and the gap of pile foundation installation hole wall.It is short and reusable that the present invention is suitable for soft soil foundation and deep water conditions and having the advantages that rubble-mound foundation of constructing that convenient, no setting is required, Potential Working Time For Operation At Sea.

Description

The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater
Technical field
The present invention relates to a kind of caissons and pile foundation combined type breakwater.
Background technique
A kind of semicircle breakwater (such as: semicircle breakwater, 206736844 U of Publication No. CN) is that a kind of adaptation is soft The novel light type breakwater structure of soil base, it is semicircle wave screening structure that feature, which essentially consists in its top surface, compared to Stalk wave screening structure, the wave force acted on semicircle breakwater is smaller, and stability against sliding is good;It acts on semicircle dike simultaneously Wave pressure pass through the center of circle, foundation stress distribution uniform, but its arc radius is usually 4-10m, semicircle breakwater The adaptable depth of water range of structure institute is smaller;Rectangular caisson breakwater is (such as: a kind of Acting on Perforated Caisson vertical breakwater, publication number It is vertical breakwater for 106592516 A of CN), can be used for deep water conditions, sand material can be backfilled in caisson, supported by self weight Anti- wave force, since the wave force on stalk face is big, the self weight of structure is also larger, and rectangular caisson breakwater is often unsuitable for weak soil Ground;When building, wall is both placed on rubble-mound foundation existing semicircle or rectangular caisson breakwater, because to build jackstone Bedding need to exploit a large amount of building stones, and exploitation of stone can destroy ecological environment, while the setting of rubble-mound foundation not only increases cost, To foundation bearing capacity added burden is caused simultaneously, be easy to make breakwater that settlement failure occur, in addition either semi-circular caisson Or the stability against sliding of rectangular caisson is provided by the frictional force between caisson bottom and rubble-mound foundation top, and water is worked as It when the wave is high deeply, in order to maintain the stability against sliding of breakwater, needs to fill more sand materials in caisson, leads to oneself of structure Increase again, so that the bearing capacity of ground is threatened, so the increase of the factor of safety against sliding of traditional caisson breakwater but reduces The safety coefficient of its vertical bearing capacity, so that application of this structure in deep water breakwater is limited, and because there is riprap work, Construction time increases.
Summary of the invention
The purpose of the present invention is to propose to a kind of caissons and pile foundation combined type deep water breakwater, are applicable to soft soil foundation and depth Water bar part and have that convenient, no setting is required rubble-mound foundation of constructing, Potential Working Time For Operation At Sea is short, project cost is low, environmental-friendly and can The advantages of reuse.Technical solution is as follows:
A kind of construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater, such breakwater include heavy Case and pile foundation, which is characterized in that the caisson is the rectangular caisson of dome made of being poured based on combined steel formwork, including bottom plate With the low straight wall sections being parallel to each other and high straight wall sections and dome portion being erected on bottom plate, the dome portion The top of high straight wall sections, low straight wall sections and dome portion are stretched over along smooth surface from the top of low straight wall sections As the upstream face of breakwater, be provided in the space that two straight wall sections, dome portion and bottom plate surround floor and For supporting the vertical plate of dome portion;The casing for forming pile foundation mounting hole, stake are embedded in vertical plate and floor intersection Base mounting hole squeezes into ground with for foundation pile vertically;In dome portion, aperture is set.Construction method includes the following steps:
(1) combined steel formwork is utilized, is layered by the sequence of bottom plate, vertical plate and floor, two straight wall sections, dome portion Substep pours the rectangular caisson of dome, wherein in integral prefabricated vertical plate and floor, vertical plate and floor intersection service sleeve, with Form the mounting hole of pile foundation, and prefabricated pile foundation;
(2) the prefabricated rectangular caisson of dome integrally is gone out to transport, transportation by driving to job location positions;
(3) it is filled the water in caisson in job location through the tapping of caisson dome portion, caisson sinking is sat into bottom in specified Position;There is the rectangular caisson of dome of filling ballast requirement for design, filling in case should be carried out after component installation in time, filled It is blocked after;
(4) pile foundation is placed in pile foundation mounting hole, then pile foundation is squeezed into designated depth;In the seam of pile foundation and pile foundation installation hole wall Cement slurry is injected between gap, and pile foundation and the rectangular caisson of dome is made to be linked to be entirety.
The section of the smooth surface is in one section of arc-shaped.
The rectangular caisson of dome can keep off wave, baffle, and the dome portion of caisson is located near the water surface, in this general altitude range Wave force is maximum, and the semicircular in shape of dome portion can reduce the wave force acted on caisset, and makes foundation stress point Cloth is more uniform than stalk wave screening structure;Since wave pressure is small near the bottom, so lower part uses rectangular caisson, in this way in breakwater knot Total wave force for being acted on structure increase it is few in the case where, the setting of the rectangular caisson in lower part but can effectively increase entire breakwater knot The height of structure, makes it be applicable to deep water conditions;According to the demand of stability, part sand material can not be filled out or filled out in caisson;Rib Plate and vertical plate can reinforcement structure globality and rigidity, while its intersection prefabricated can form vertical stake by service sleeve Base mounting hole;The effect of pile foundation mounting hole is to squeeze into ground vertically for pile foundation;The effect of pile foundation is the antiskid of enhancing structure, resists and incline It covers and vertical bearing stability.
Detailed description of the invention
Fig. 1 (a) and (b) be respectively dome rectangular light-duty caisson and pile foundation combined type breakwater sectional view and outside drawing.
The rectangular light-duty caisson of Fig. 2 dome and pile foundation combined type deep water breakwater structure figure.
Specific embodiment
Semicircle breakwater can reduce wave force, and the foundation stress below breakwater structure is made to be more evenly distributed, rectangular Caisson breakwater is applicable to deepwater regions, avoids to mention using rubble-mound foundation escapable cost, duration and protection environment, pile foundation For vertical force and horizontal force.In conjunction with the advantage of semicircle, rectangular caisson and pile foundation respectively, the present invention proposes that a kind of dome is rectangular light Type caisson and pile foundation combined type deep water breakwater, this Novel breakwater structure be applicable to soft soil foundation and deep water conditions and With convenient, no setting is required rubble-mound foundation of constructing, Potential Working Time For Operation At Sea is short, project cost is low, environmental-friendly and reusable The advantages of.Fig. 1 and Fig. 2 is respectively the rectangular light-duty caisson of dome and pile foundation combined type deep water breakwater outside drawing and structure chart, figure In, 1 is the rectangular caisson dome portion of dome, and 2 be floor, and 3 be vertical plate, and 4 be the rectangular caisson straight wall sections of dome, and 5 be bottom plate, 6 be pile foundation, wherein the dome portion of caisson can appropriate aperture, as the back-up sand hole of the rectangular caisson of dome, while rectangular in dome It when caisson sinking, can be filled the water by aperture, convenient for its sinking and sit bottom.
The rectangular light-duty caisson of dome and the main working procedure of pile foundation combined type deep water breakwater are as follows: first with combining Steel form presses the sequence point of bottom plate 5, vertical plate 3 and the rectangular caisson straight wall sections 4 of floor 2, dome, dome portion 1 in precasting yard Layer substep pours the rectangular caisson of dome, wherein vertical plate 3 and 2 intersection of floor are pre-buried in integral prefabricated vertical plate 3 and floor 2 Casing, to form the mounting hole of pile foundation 6, and prefabricated pile foundation 6, pile foundation 6 preferentially selects prestress high intensity concrete stake (PHC); That then uses for reference caisson goes out fortune and setting method, the prefabricated rectangular caisson of dome integrally is gone out to transport, transportation by driving is fixed to job location Position;Then it is filled the water in caisson in job location through the tapping of caisson dome portion, caisson sinking is sat into bottom in designated position; Have the rectangular caisson of dome of filling ballast requirement for design, should carry out filling in case after component installation in time, filling should it is symmetrical, Uniformly, pack hole should be blocked immediately after the completion of filling, and it is ensured that blocked tight, secured;Pile foundation 6 is finally placed in stake Base mounting hole, then pile foundation 6 is squeezed into designated depth using equipment such as pile driving barges;Between pile foundation 6 and the gap of pile foundation installation hole wall Cement slurry is injected, pile foundation and the rectangular caisson of dome is made to be linked to be entirety.
Breakwater engineering is gradually to deep-water developments at present;In addition, all there is soft for the seashore of many offshore areas and seabed Soil layer, several meters to tens meters of thickness are differed, such as the active Bohai Sea Gulf of China's economic development, entrance of Changjiang River, the mouth of the Zhujiang River and Zhejiang, Fujian edge All widely distributed the soft soil foundation in Haiti area.The rectangular light-duty caisson of dome can fit well with pile foundation combined type deep water breakwater It answers deep water, severe wave and Soft Soil, without excavating ground or carrying out foundation stabilization when construction, ground need to only be carried out Simple leveling, structure is relatively easy, construction is convenient, project cost is cheap, the offshore construction time is shorter, it combines semicircle The Common advantages of shape, rectangular caisson and pile foundation are a kind of excellent new type of deep-water breakwater structures, have in silt coast wide General application prospect.

Claims (2)

1. a kind of construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater, such breakwater includes caisson And pile foundation, which is characterized in that the caisson be poured based on combined steel formwork made of the rectangular caisson of dome, including bottom plate and The low straight wall sections being parallel to each other and high straight wall sections and dome portion being erected on bottom plate, the dome portion from The top of low straight wall sections is stretched over the top of high straight wall sections along smooth surface, and low straight wall sections and circular top part are allocated as For the upstream face of breakwater, floor and use are provided in the space that two straight wall sections, dome portion and bottom plate surround To support the vertical plate of dome portion;The casing for forming pile foundation mounting hole, pile foundation are embedded in vertical plate and floor intersection Mounting hole squeezes into ground with for pile foundation vertically;In dome portion, aperture is set.Construction method includes the following steps:
(1) combined steel formwork is utilized, is layered substep by the sequence of bottom plate, vertical plate and floor, two straight wall sections, dome portion The rectangular caisson of dome is poured, wherein in integral prefabricated vertical plate and floor, vertical plate and floor intersection service sleeve, to be formed The mounting hole of pile foundation, and prefabricated pile foundation;
(2) the prefabricated rectangular caisson of dome integrally is gone out to transport, transportation by driving to job location positions;
(3) it is filled the water in caisson in job location through the tapping of caisson dome portion, caisson sinking is sat into bottom in designated position; There is the rectangular caisson of dome of filling ballast requirement for design, filling in case should be carried out after component installation in time, after the completion of filling It is blocked;
(4) pile foundation is placed in pile foundation mounting hole, then pile foundation is squeezed into designated depth;Between pile foundation and the gap of pile foundation installation hole wall Cement slurry is injected, pile foundation and the rectangular caisson of dome is made to be linked to be entirety.
2. the construction method of breakwater according to claim 1, which is characterized in that the section of the smooth surface is in one Section arc-shaped.
CN201810944787.5A 2018-08-19 2018-08-19 The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater Pending CN108999142A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810944787.5A CN108999142A (en) 2018-08-19 2018-08-19 The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810944787.5A CN108999142A (en) 2018-08-19 2018-08-19 The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater

Publications (1)

Publication Number Publication Date
CN108999142A true CN108999142A (en) 2018-12-14

Family

ID=64593170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810944787.5A Pending CN108999142A (en) 2018-08-19 2018-08-19 The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater

Country Status (1)

Country Link
CN (1) CN108999142A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487750A (en) * 2018-12-18 2019-03-19 中交上海航道勘察设计研究院有限公司 Pile formula semicircular wave breaker structure and construction method
CN113186889A (en) * 2021-02-02 2021-07-30 中国海洋大学 Combined pile plate structure for reinforcing and protecting artificial island reef and construction method thereof
CN114182681A (en) * 2021-11-26 2022-03-15 中交第四航务工程局有限公司 Sheet pile gravity combined breakwater construction method
CN114960732A (en) * 2022-06-09 2022-08-30 交通运输部天津水运工程科学研究所 Single-pile wind power foundation and semicircular breakwater combined structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2758147A1 (en) * 1997-01-03 1998-07-10 Bouygues Offshore Semi=submerged caisson=type breakwater
CN1970888A (en) * 2005-11-23 2007-05-30 天津得鑫电机有限公司 Semicircular breakwater
CN101314942A (en) * 2008-07-18 2008-12-03 天津大学 Wave breaker of inverse T shaped pipe wall pile
CN101713181A (en) * 2009-11-26 2010-05-26 中交第一航务工程勘察设计院有限公司 Novel caisson composite levee of curve breast wall
CN203080470U (en) * 2013-02-21 2013-07-24 重庆交通大学 Pile-bearing platform-barricade combined supporting and retaining structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2758147A1 (en) * 1997-01-03 1998-07-10 Bouygues Offshore Semi=submerged caisson=type breakwater
CN1970888A (en) * 2005-11-23 2007-05-30 天津得鑫电机有限公司 Semicircular breakwater
CN101314942A (en) * 2008-07-18 2008-12-03 天津大学 Wave breaker of inverse T shaped pipe wall pile
CN101713181A (en) * 2009-11-26 2010-05-26 中交第一航务工程勘察设计院有限公司 Novel caisson composite levee of curve breast wall
CN203080470U (en) * 2013-02-21 2013-07-24 重庆交通大学 Pile-bearing platform-barricade combined supporting and retaining structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487750A (en) * 2018-12-18 2019-03-19 中交上海航道勘察设计研究院有限公司 Pile formula semicircular wave breaker structure and construction method
CN113186889A (en) * 2021-02-02 2021-07-30 中国海洋大学 Combined pile plate structure for reinforcing and protecting artificial island reef and construction method thereof
CN114182681A (en) * 2021-11-26 2022-03-15 中交第四航务工程局有限公司 Sheet pile gravity combined breakwater construction method
CN114960732A (en) * 2022-06-09 2022-08-30 交通运输部天津水运工程科学研究所 Single-pile wind power foundation and semicircular breakwater combined structure

Similar Documents

Publication Publication Date Title
CN203603105U (en) Wall plate type ecological retaining wall bank protection structure
CN108999142A (en) The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater
CN210104758U (en) Foundation pit supporting system of soil nail bored concrete pile anchor cable combination
CN109750571A (en) A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method
KR20100118705A (en) Mode of life restoration shore protection slope side reinforcement construct and the method which existent shore protection and material framing of soil in interior of shore protection slope that become new birth in rivers lake
CN108867547A (en) The construction method of semi-circular caisson and pile foundation combined type breakwater
JP2011032815A (en) Retaining wall and method of constructing the same
CN102733407A (en) Two-ring grouted single pile foundation
CN208965494U (en) The rectangular light-duty caisson of dome and pile foundation combined type breakwater
CN109024470A (en) The rectangular light-duty caisson of dome and pile foundation combined type breakwater
CN208857762U (en) Semi-circular caisson and pile foundation combined type breakwater
CN106400814A (en) Foundation pit supporting method
CN102605801A (en) Suspension semi-reverse-construction method for underground circular water tank
KR20110046209A (en) Method Of Construction For Scour Prevension And Reinforcement Of Bridge Pier, And Structure Of The Same
CN210368867U (en) Superimposed structure of homogeneity earth dam and rock-fill dam
CN205062744U (en) Half gravity type two -stage view anti -flood wall on half cantilever
CN201738286U (en) Tetrapod pier type structure
CN213625433U (en) A link up transition structure that is used for gravity type and sheet pile formula combination pier
CN108867546A (en) Semi-circular caisson and pile foundation combined type breakwater
CN108677999A (en) A kind of Muddy Bottoms packeted soil barrier wall structure and construction method
KR102294870B1 (en) Core wall structure of composite cassion for offshore runway
KR100704460B1 (en) Device for harbor revetment construction
JP2007032003A (en) Wall structure and method of constructing the same
CN110656576A (en) Pier structure and construction method thereof
CN206457856U (en) A kind of ground crack resistence structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181214

WD01 Invention patent application deemed withdrawn after publication