CN108867547A - The construction method of semi-circular caisson and pile foundation combined type breakwater - Google Patents

The construction method of semi-circular caisson and pile foundation combined type breakwater Download PDF

Info

Publication number
CN108867547A
CN108867547A CN201810959706.9A CN201810959706A CN108867547A CN 108867547 A CN108867547 A CN 108867547A CN 201810959706 A CN201810959706 A CN 201810959706A CN 108867547 A CN108867547 A CN 108867547A
Authority
CN
China
Prior art keywords
pile foundation
semi
caisson
circular
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810959706.9A
Other languages
Chinese (zh)
Inventor
肖忠
刘莺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201810959706.9A priority Critical patent/CN108867547A/en
Publication of CN108867547A publication Critical patent/CN108867547A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Abstract

The present invention relates to the construction method of a kind of semi-circular caisson and pile foundation combined type breakwater, this breakwater includes caisson and pile foundation, and caisson is semi-circular caisson made of being poured based on combined steel formwork.Construction method includes:Using combined steel formwork, semi-circular caisson is poured by bottom plate, vertical plate and floor, semicircular arch ring, sequence layering substep in precasting yard, wherein in integral prefabricated vertical plate and floor, vertical plate and floor intersection service sleeve, to form the mounting hole of pile foundation;It is filled the water in caisson in job location through the tapping of semicircular arch ring, semi-circular caisson is sat into bottom in designated position;Pile foundation is squeezed into designated depth;Pile foundation and semi-circular caisson is set to be linked to be entirety.It is short and reusable that the present invention is suitable for soft soil foundation and deep water conditions and having the advantages that rubble-mound foundation of constructing that convenient, no setting is required, Potential Working Time For Operation At Sea.

Description

The construction method of semi-circular caisson and pile foundation combined type breakwater
Technical field
The present invention relates to a kind of caissons and pile foundation combined type breakwater.
Background technique
Semicircle breakwater is (such as:A kind of semicircle breakwater, publication number CN206736844U) it is a kind of adaptation weak soil The Novel breakwater structure of base, is usually made of prefabricated semi-circular member or semi-circular caisson and rubble-mound foundation.With it is traditional straight Vertical breakwater, sloping breakwater are compared, semicircle breakwater have from heavy and light, easy construction, it is reusable, beautiful, The advantages that foundation stress is evenly distributed, suffered wave force is small and antiskid and stability against overturning are good.
When building, semi-circular caisson need to be placed on rubble-mound foundation existing semicircle breakwater.On soft soil foundation When construction, needs first to excavate ground or reinforcing soft foundation, then semi-circular caisson is placed on rubble-mound foundation.Have four among these A main problem, first is that the building stones needed are more since it is desired that building rubble-mound foundation, exploitation of stone can destroy ecological environment;Second is that throwing The setting of ground mass bed not only increases cost, while causing added burden to foundation bearing capacity, is easy that breakwater is made to occur to sink It falls into and destroys;Third is that the stability against sliding of existing semicircle breakwater is by between semi-circular caisson bottom and rubble-mound foundation top Frictional force, when the wave is high for the depth of water, in order to maintain the stability against sliding of breakwater, needs to fill in semi-circular caisson come what is provided More sand material, increase cost and duration, while the increase of dead load, can threaten foundation bearing capacity, factor of safety against sliding Increase but reduce the vertical bearing capacity of this structure, to limit application of this structure in deep water breakwater;Four It is to increase the construction time because there is riprap work.
Summary of the invention
The purpose of the present invention is overcoming the above-mentioned deficiency of the prior art, provide a kind of suitable for soft soil foundation and deep water item Part, simple and reasonable, construction is convenient, project cost is low, environmental-friendly and reusable new type of deep-water breakwater applies Work method.Breakwater of the invention is a kind of semi-circular caisson and pile foundation novel combined type breakwater, can be to avoid using jackstone Bedding, the setting of pile foundation not only increases this new structural stability against sliding, while increasing its vertical bearing capacity.Skill Art scheme is as follows:
A kind of construction method of semi-circular caisson and pile foundation combined type breakwater, this breakwater include caisson and pile foundation, institute The caisson stated is semi-circular caisson made of being poured based on combined steel formwork, the semi-circular arch including bottom plate and on bottom plate Circle, is provided with floor and the vertical plate for supporting semicircular arch ring between semicircular arch ring and bottom plate;In vertical plate and floor Intersection is embedded with the casing for forming pile foundation mounting hole, and pile foundation mounting hole squeezes into ground with for foundation pile vertically;Semicircle Aperture is set on shape arch ring.The construction method of above-mentioned breakwater, includes the following steps:
(1) combined steel formwork is utilized, presses the sequence layering substep of bottom plate, vertical plate and floor, semicircular arch ring in precasting yard Semi-circular caisson is poured, wherein in integral prefabricated vertical plate and floor, vertical plate and floor intersection service sleeve, to form stake The mounting hole of base, and prefabricated pile foundation;
(2) assembled good semi-circular caisson integrally is gone out to transport, transportation by driving to job location;
(3) it is filled the water in caisson in job location through the tapping of semicircular arch ring, semi-circular caisson is sat into bottom in specified Position;There is the semi-circular caisson of filling ballast requirement for design, filling in case is carried out after component installation, should be stood after the completion of filling Tapping is blocked;
(4) pile foundation is placed in pile foundation mounting hole, pile foundation is squeezed into designated depth using equipment such as pile driving barges;In pile foundation and stake Cement slurry is injected between the gap of base installation hole wall, pile foundation and semi-circular caisson is made to be linked to be entirety.
In the present invention, semi-circular caisson can keep off wave, baffle, earth-retaining, and semicircular in shape can reduce wave force, and answer ground Power distribution uniform;Its base areas is larger, can expand the contact area with ground, reduces foundation stress;Floor and vertical plate can The globality and rigidity of reinforcement structure, while its intersection prefabricated can form vertical pile foundation mounting hole by service sleeve; The effect of pile foundation mounting hole is to squeeze into ground vertically for foundation pile;The effect of pile foundation be enhance ground bearing capacity and structure antiskid with Stability against overturning.
Detailed description of the invention
(a) and (b) of Fig. 1 is respectively the sectional view and outside drawing of single group semi-circular caisson and pile foundation combined type breakwater
Fig. 2 single group semi-circular caisson and pile foundation combined type breakwater three-view diagram
Specific embodiment
Fig. 1 is single group semi-circular caisson and pile foundation combined type breakwater outside drawing;Fig. 2 is single group semi-circular caisson and pile foundation Combined type breakwater structure figure.In Fig. 2,1 is vertical plate, and 2 be semicircular arch ring, and 3 be floor, and 4 be bottom plate, and 5 be pile foundation, wherein half On round arch ring can appropriate aperture, as the back-up sand hole of semi-circular caisson, at the same semi-circular caisson sink when, aperture can be passed through Water filling sits bottom convenient for semi-circular caisson.
The main working procedure of semi-circular caisson and pile foundation combined type breakwater is as follows:First with combined steel formwork, Precasting yard pours semi-circular caisson by the sequence layering substep of bottom plate 4, vertical plate 1 and floor 3, semicircular arch ring 2, wherein in entirety When prefabricated vertical plate 1 and floor 3,3 intersection service sleeve of vertical plate 1 and floor, to form the mounting hole of pile foundation 5, and prefabricated pile Base 5, pile foundation 5 preferentially select prestress high intensity concrete stake (PHC);That then uses for reference caisson goes out fortune and setting method, will spell The semi-circular caisson installed integrally goes out to transport, transportation by driving to job location;Then past through the tapping of semicircular arch ring in job location Semi-circular caisson is sat bottom in designated position by water filling in caisson;There are the semi-circular caisson of filling ballast requirement, component for design Filling in case should be carried out after installation in time, filling should symmetrically, uniformly should immediately block pack hole after the completion of filling, and It is ensured that blocking tight, secured;Pile foundation 5 is finally placed in pile foundation mounting hole, is squeezed into pile foundation 5 using equipment such as pile driving barges specified Depth;Cement slurry is injected between pile foundation 5 and the gap of pile foundation installation hole wall, pile foundation and semi-circular caisson is made to be linked to be entirety.
Breakwater engineering is gradually to deep-water developments at present;In addition, the seashore of many offshore areas and seabed all there is Soft Soil Layer, several meters to tens meters of thickness are differed, such as the active Bohai Sea Gulf of China's economic development, entrance of Changjiang River, the mouth of the Zhujiang River and Zhejiang, Fujian All widely distributed the soft soil foundation in coastal area.Semi-circular caisson and pile foundation combined type breakwater can be perfectly suitable for badly Wave and Soft Soil build breakwater using the new structure without excavating ground or carrying out ground on soft foundation Reinforce, only ground need to simply be flattened, can be applicable in soft soil foundation and deep water conditions, structure it is simple, it is easy for construction, Project cost is low, is a kind of excellent new type of deep-water structure, is with a wide range of applications in silt coast.

Claims (1)

1. the construction method of a kind of semi-circular caisson and pile foundation combined type breakwater, this breakwater includes caisson and pile foundation, described Caisson be poured based on combined steel formwork made of semi-circular caisson, the semicircular arch ring including bottom plate and on bottom plate, Floor and the vertical plate for supporting semicircular arch ring are provided between semicircular arch ring and bottom plate;Intersect in vertical plate and floor Part is embedded with the casing for forming pile foundation mounting hole, and pile foundation mounting hole squeezes into ground with for foundation pile vertically;Semi-circular arch Aperture is set on circle.The construction method of above-mentioned breakwater, includes the following steps:
(1) combined steel formwork is utilized, is poured in precasting yard by the sequence layering substep of bottom plate, vertical plate and floor, semicircular arch ring Semi-circular caisson, wherein in integral prefabricated vertical plate and floor, vertical plate and floor intersection service sleeve, to form pile foundation Mounting hole, and prefabricated pile foundation;
(2) assembled good semi-circular caisson integrally is gone out to transport, transportation by driving to job location;
(3) it is filled the water in caisson in job location through the tapping of semicircular arch ring, semi-circular caisson is sat into bottom in designated position; There is the semi-circular caisson of filling ballast requirement for design, filling in case is carried out after component installation, it should be right immediately after the completion of filling Tapping is blocked;
(4) pile foundation is placed in pile foundation mounting hole, pile foundation is squeezed into designated depth using equipment such as pile driving barges;Pacify in pile foundation and pile foundation Cement slurry is injected between the gap of dress hole wall, pile foundation and semi-circular caisson is made to be linked to be entirety.
CN201810959706.9A 2018-08-19 2018-08-19 The construction method of semi-circular caisson and pile foundation combined type breakwater Pending CN108867547A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810959706.9A CN108867547A (en) 2018-08-19 2018-08-19 The construction method of semi-circular caisson and pile foundation combined type breakwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810959706.9A CN108867547A (en) 2018-08-19 2018-08-19 The construction method of semi-circular caisson and pile foundation combined type breakwater

Publications (1)

Publication Number Publication Date
CN108867547A true CN108867547A (en) 2018-11-23

Family

ID=64321537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810959706.9A Pending CN108867547A (en) 2018-08-19 2018-08-19 The construction method of semi-circular caisson and pile foundation combined type breakwater

Country Status (1)

Country Link
CN (1) CN108867547A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487750A (en) * 2018-12-18 2019-03-19 中交上海航道勘察设计研究院有限公司 Pile formula semicircular wave breaker structure and construction method
CN109555078A (en) * 2018-12-25 2019-04-02 广州粤科工程技术有限公司 A kind of Gravity Type Casisson Berth and its construction method
CN114960732A (en) * 2022-06-09 2022-08-30 交通运输部天津水运工程科学研究所 Single-pile wind power foundation and semicircular breakwater combined structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001288725A (en) * 2000-04-04 2001-10-19 Nippon Steel Corp Pile-type foundation structure and method for constructing the same
CN101294394A (en) * 2008-05-28 2008-10-29 中交公路规划设计院有限公司 Steel cavity stranded caisson-pile inverse-way composite base and construction method
CN101314942A (en) * 2008-07-18 2008-12-03 天津大学 Wave breaker of inverse T shaped pipe wall pile
CN103967031A (en) * 2013-01-24 2014-08-06 中交公路规划设计院有限公司 Caisson and pile combined foundation of consolidated subsoil and construction method of caisson and pile combined foundation
CN206736844U (en) * 2017-04-28 2017-12-12 中交第四航务工程勘察设计院有限公司 A kind of semicircle breakwater

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001288725A (en) * 2000-04-04 2001-10-19 Nippon Steel Corp Pile-type foundation structure and method for constructing the same
CN101294394A (en) * 2008-05-28 2008-10-29 中交公路规划设计院有限公司 Steel cavity stranded caisson-pile inverse-way composite base and construction method
CN101314942A (en) * 2008-07-18 2008-12-03 天津大学 Wave breaker of inverse T shaped pipe wall pile
CN103967031A (en) * 2013-01-24 2014-08-06 中交公路规划设计院有限公司 Caisson and pile combined foundation of consolidated subsoil and construction method of caisson and pile combined foundation
CN206736844U (en) * 2017-04-28 2017-12-12 中交第四航务工程勘察设计院有限公司 A kind of semicircle breakwater

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487750A (en) * 2018-12-18 2019-03-19 中交上海航道勘察设计研究院有限公司 Pile formula semicircular wave breaker structure and construction method
CN109555078A (en) * 2018-12-25 2019-04-02 广州粤科工程技术有限公司 A kind of Gravity Type Casisson Berth and its construction method
CN114960732A (en) * 2022-06-09 2022-08-30 交通运输部天津水运工程科学研究所 Single-pile wind power foundation and semicircular breakwater combined structure

Similar Documents

Publication Publication Date Title
CN107419630A (en) A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
CN103015367B (en) High-efficiency economical construction method for revetment
CN108999142A (en) The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater
CN108867547A (en) The construction method of semi-circular caisson and pile foundation combined type breakwater
CN210104758U (en) Foundation pit supporting system of soil nail bored concrete pile anchor cable combination
CN104452829A (en) Piled raft foundation anti-floating structure and construction method
KR20120012504A (en) Cast in place concrete pile With precast type Caisson
CN103233444A (en) Underwater riprap foundation bed and side slope erosion resisting structure and construction method thereof
CN102733407A (en) Two-ring grouted single pile foundation
CN112627208B (en) Assembled cofferdam suitable for rock foundation and construction method thereof
CN208857762U (en) Semi-circular caisson and pile foundation combined type breakwater
CN108867546A (en) Semi-circular caisson and pile foundation combined type breakwater
CN208965494U (en) The rectangular light-duty caisson of dome and pile foundation combined type breakwater
KR20210047482A (en) Core wall structure of independent cassion for offshore runway
CN102605801A (en) Suspension semi-reverse-construction method for underground circular water tank
CN109024470A (en) The rectangular light-duty caisson of dome and pile foundation combined type breakwater
CN106149624A (en) A kind of gravity type quay being applicable to roadbed of alluvial silt and construction method thereof
CN201738286U (en) Tetrapod pier type structure
CN210368867U (en) Superimposed structure of homogeneity earth dam and rock-fill dam
CN204326119U (en) A kind of pile-raft foundation float Structure
KR100704460B1 (en) Device for harbor revetment construction
KR20210047481A (en) Core wall structure of composite cassion for offshore runway
KR100487140B1 (en) Y-shaped structure element, construction methods of deep foundations and retaining structures by using the Y-shaped structure element
CN218204294U (en) Soft soil foundation composite reinforcing structure
CN217298998U (en) Cushion structure of material stacking area arranged on foundation cushion of garage in foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181123