CN108951655A - 预应力张拉情况下的地下室支护施工方法 - Google Patents
预应力张拉情况下的地下室支护施工方法 Download PDFInfo
- Publication number
- CN108951655A CN108951655A CN201810927295.5A CN201810927295A CN108951655A CN 108951655 A CN108951655 A CN 108951655A CN 201810927295 A CN201810927295 A CN 201810927295A CN 108951655 A CN108951655 A CN 108951655A
- Authority
- CN
- China
- Prior art keywords
- basement
- concrete
- suspension cable
- angled intersection
- arch brace
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0046—Production methods using prestressing techniques
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810927295.5A CN108951655B (zh) | 2017-07-30 | 2017-07-30 | 预应力张拉情况下的地下室支护结构 |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710635355.1A CN107227741B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护结构 |
| CN201810927295.5A CN108951655B (zh) | 2017-07-30 | 2017-07-30 | 预应力张拉情况下的地下室支护结构 |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710635355.1A Division CN107227741B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护结构 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108951655A true CN108951655A (zh) | 2018-12-07 |
| CN108951655B CN108951655B (zh) | 2020-09-15 |
Family
ID=59956648
Family Applications (5)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810920784.8A Active CN108951654B (zh) | 2017-07-30 | 2017-07-30 | 不同开挖深度地下室支护施工方法 |
| CN201810920743.9A Active CN108930273B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护施工方法 |
| CN201810920824.9A Active CN108930274B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护施工方法 |
| CN201810927295.5A Active CN108951655B (zh) | 2017-07-30 | 2017-07-30 | 预应力张拉情况下的地下室支护结构 |
| CN201710635355.1A Active CN107227741B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护结构 |
Family Applications Before (3)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810920784.8A Active CN108951654B (zh) | 2017-07-30 | 2017-07-30 | 不同开挖深度地下室支护施工方法 |
| CN201810920743.9A Active CN108930273B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护施工方法 |
| CN201810920824.9A Active CN108930274B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护施工方法 |
Family Applications After (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710635355.1A Active CN107227741B (zh) | 2017-07-30 | 2017-07-30 | 地下室支护结构 |
Country Status (1)
| Country | Link |
|---|---|
| CN (5) | CN108951654B (zh) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107605172B (zh) * | 2017-10-16 | 2020-04-17 | 叶长青 | 一种混凝土屋面梁的加固结构施工方法 |
| CN108487261A (zh) * | 2018-04-10 | 2018-09-04 | 江西科技学院 | 一种拱形钢结构支撑 |
| CN110397042A (zh) * | 2019-07-13 | 2019-11-01 | 济邦建设集团有限公司 | 一种深基坑的支撑体系 |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2835351Y (zh) * | 2005-10-14 | 2006-11-08 | 浙江中成建工集团有限公司 | 深大基坑钢筋混凝土圆环桁架水平支撑结构 |
| CN101615212A (zh) * | 2009-07-28 | 2009-12-30 | 武汉理工大学 | 一种排桩-内支撑支护体系简化设计计算方法 |
| CN101666095A (zh) * | 2009-09-11 | 2010-03-10 | 朱奎 | 不规则基坑支护及施工方法 |
| KR20110024554A (ko) * | 2009-09-02 | 2011-03-09 | (주)이랜드건설 | 흙막이벽체 지보 구조물과 그 시공방법 |
| CN203834487U (zh) * | 2014-04-10 | 2014-09-17 | 中国十五冶金建设集团有限公司 | 型钢内支撑拉森桩哑铃形深大基坑开挖支护 |
| CN105862878A (zh) * | 2016-05-30 | 2016-08-17 | 建研地基基础工程有限责任公司 | 一种深基坑的支撑体系 |
| CN105887891A (zh) * | 2016-04-16 | 2016-08-24 | 朱奎 | 深地下室支护的施工方法 |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102660955B (zh) * | 2012-05-17 | 2015-05-13 | 上海强劲地基工程股份有限公司 | 一种基坑边坡支护的快速施工方法 |
| CN102828520A (zh) * | 2012-09-11 | 2012-12-19 | 中煤科工集团武汉设计研究院中汉岩土工程分公司 | 一种应用于深厚泥炭土深基坑中的环形内支撑结构 |
| KR20150060081A (ko) * | 2013-11-25 | 2015-06-03 | (주)써포텍 | 흙막이 가시설용 띠장 구조체 |
| KR20160057747A (ko) * | 2014-11-14 | 2016-05-24 | 우경기술주식회사 | 추가반력 도입이 가능한 흙막이 가시설용 프리스트레스 띠장 |
| CN104727324B (zh) * | 2015-03-20 | 2016-08-03 | 朱奎 | 不规则地下室支护施工方法 |
| CN107130609B (zh) * | 2015-11-24 | 2018-10-12 | 叶长青 | 无对撑的地下室支护 |
| CN105926637B (zh) * | 2016-06-28 | 2017-10-31 | 中国建筑一局(集团)有限公司 | 一种保护既有地铁的预应力支护体系及设计 |
-
2017
- 2017-07-30 CN CN201810920784.8A patent/CN108951654B/zh active Active
- 2017-07-30 CN CN201810920743.9A patent/CN108930273B/zh active Active
- 2017-07-30 CN CN201810920824.9A patent/CN108930274B/zh active Active
- 2017-07-30 CN CN201810927295.5A patent/CN108951655B/zh active Active
- 2017-07-30 CN CN201710635355.1A patent/CN107227741B/zh active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2835351Y (zh) * | 2005-10-14 | 2006-11-08 | 浙江中成建工集团有限公司 | 深大基坑钢筋混凝土圆环桁架水平支撑结构 |
| CN101615212A (zh) * | 2009-07-28 | 2009-12-30 | 武汉理工大学 | 一种排桩-内支撑支护体系简化设计计算方法 |
| KR20110024554A (ko) * | 2009-09-02 | 2011-03-09 | (주)이랜드건설 | 흙막이벽체 지보 구조물과 그 시공방법 |
| CN101666095A (zh) * | 2009-09-11 | 2010-03-10 | 朱奎 | 不规则基坑支护及施工方法 |
| CN203834487U (zh) * | 2014-04-10 | 2014-09-17 | 中国十五冶金建设集团有限公司 | 型钢内支撑拉森桩哑铃形深大基坑开挖支护 |
| CN105887891A (zh) * | 2016-04-16 | 2016-08-24 | 朱奎 | 深地下室支护的施工方法 |
| CN105862878A (zh) * | 2016-05-30 | 2016-08-17 | 建研地基基础工程有限责任公司 | 一种深基坑的支撑体系 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN108930274B (zh) | 2020-10-27 |
| CN108951654B (zh) | 2020-09-15 |
| CN108930273A (zh) | 2018-12-04 |
| CN108930274A (zh) | 2018-12-04 |
| CN108930273B (zh) | 2020-09-15 |
| CN108951654A (zh) | 2018-12-07 |
| CN107227741B (zh) | 2018-12-14 |
| CN108951655B (zh) | 2020-09-15 |
| CN107227741A (zh) | 2017-10-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103485363B (zh) | 立体连续框架式钢筋混凝土结构挡土墙 | |
| CN107313431A (zh) | 临近不等高基坑同步施工方法 | |
| CN103938634B (zh) | 一种深基坑支护结构及施工方法 | |
| CN105587320B (zh) | 富水砂卵石地层异型深竖井结构体系及其施工方法 | |
| CN109610508B (zh) | 下穿已建管廊的管廊施工方法及其换撑结构 | |
| CN112195779A (zh) | 一种适用于厚卵石层的多功能栈桥施工方法 | |
| CN108951655A (zh) | 预应力张拉情况下的地下室支护施工方法 | |
| CN207685879U (zh) | 一种抬桩加固用承台施工平台 | |
| CN211172000U (zh) | 支护桩与混凝土主体结构组合的基坑围护体系 | |
| CN108360535A (zh) | 基于排桩与内支撑的基坑支护结构及其施工方法 | |
| CN207567784U (zh) | 深基坑复合式支护 | |
| CN203498863U (zh) | 立体连续框架式钢筋混凝土结构挡土墙 | |
| CN206189447U (zh) | 半支护式挡土墙 | |
| CN108005086A (zh) | 一种用于基坑支护的高支墩反拉式斜撑结构 | |
| CN201176597Y (zh) | 一种沉井结构 | |
| CN203821399U (zh) | 一种深基坑支护结构 | |
| CN207244633U (zh) | 基坑围护顶圈梁上砖砌挡土墙钢筋桁架加固系统 | |
| CN207260158U (zh) | 一层地下室支护结构 | |
| CN217105109U (zh) | 一种人行天桥下深基坑同步施工的支护结构 | |
| CN212956547U (zh) | 一种基坑支护塔吊基础一体式结构 | |
| CN209555962U (zh) | 一种适用于钻孔灌注桩ⅲ类桩与承台连接结构 | |
| CN211395688U (zh) | 一种双排桩支护结构 | |
| CN210033432U (zh) | 一种盾构隧道下穿既有建筑物的加固结构 | |
| CN102444131B (zh) | 基坑支护方法 | |
| CN106120853A (zh) | 一种框架桥的逆序施工方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB02 | Change of applicant information |
Address after: 325000, No. 48, Jingshan Hill Road, Ouhai District, Wenzhou, Zhejiang Applicant after: Ye Changqing Address before: 325000 No. 4, Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, China Applicant before: Ye Changqing |
|
| CB02 | Change of applicant information | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20240412 Address after: No. 98-1, Group 2, Yuying Village, Longshi Town, Hechuan District, Chongqing, 401544 Patentee after: Zeng Bin Country or region after: China Address before: 325000 No. 48 Xinghai Road, Jingshan Street, Ouhai District, Wenzhou City, Zhejiang Province Patentee before: Ye Changqing Country or region before: China |
|
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20240424 Address after: 401320, No. 24-36 Jiaolong Road, Lijiatuo Street, Banan District, Chongqing (double number) Patentee after: Chongqing Kaitou Construction Engineering Co.,Ltd. Country or region after: China Address before: No. 98-1, Group 2, Yuying Village, Longshi Town, Hechuan District, Chongqing, 401544 Patentee before: Zeng Bin Country or region before: China |
|
| TR01 | Transfer of patent right |