CN108921508A - Overall process Engineering Cost Management system - Google Patents

Overall process Engineering Cost Management system Download PDF

Info

Publication number
CN108921508A
CN108921508A CN201810655612.2A CN201810655612A CN108921508A CN 108921508 A CN108921508 A CN 108921508A CN 201810655612 A CN201810655612 A CN 201810655612A CN 108921508 A CN108921508 A CN 108921508A
Authority
CN
China
Prior art keywords
terminal
database
unit
information
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810655612.2A
Other languages
Chinese (zh)
Inventor
张思中
姚勇
林升
曹永雄
樊向玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong People Trust Engineering Consulting Co Ltd
Original Assignee
Guangdong People Trust Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong People Trust Engineering Consulting Co Ltd filed Critical Guangdong People Trust Engineering Consulting Co Ltd
Priority to CN201810655612.2A priority Critical patent/CN108921508A/en
Publication of CN108921508A publication Critical patent/CN108921508A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to Project Cost Fields, specially overall process Engineering Cost Management system, its key points of the technical solution are that including management platform, construction unit's terminal, designing unit's terminal and unit in charge of construction's terminal, management platform includes database, data transmission module, computing module and report generation module, and construction unit's terminal, designing unit's terminal and unit in charge of construction's terminal pass through wired or wireless network respectively and be connected to data transmission module with the information into database upload information or reception database;Situation and different design and when needing to be designed change at the scene, unit in charge of construction's terminal issues change solicited message, designing unit formulates design alteration information according to change solicited message, computing module is according to design alteration information and calls pricing information in database, to re-start the calculating of project cost, and project cost report is regenerated by report generation module, and be sent to database, improve the accuracy that project cost calculates.

Description

Overall process Engineering Cost Management system
Technical field
The present invention relates to Project Cost Fields, more specifically, it relates to overall process Engineering Cost Management system.
Background technique
Project cost just refers to the construction price of engineering, refers to complete the construction of an engineering, it is contemplated that or it is actually required Full payment summation.It is defined from the angle of construction unit, project cost refers to the construction cost of engineering, as builds one The complete equipment investment cost of engineering expectation payment or actual delivery.
But during constructing at the scene, since site environment is often inconsistent with design conditions, it will lead to needs pair The case where design changes, so that project cost changes.
Summary of the invention
The object of the present invention is to provide overall process Engineering Cost Management systems, re-start engineering when design alteration occurs The calculating of cost improves the accuracy that project cost calculates.
Above-mentioned technical purpose of the invention technical scheme is that:Overall process Engineering Cost Management system System, including management platform, construction unit's terminal, designing unit's terminal and unit in charge of construction's terminal, the management platform includes data Library, data transmission module, computing module and report generation module, construction unit's terminal, designing unit's terminal and work order Position terminal pass through respectively wired or wireless network be connected to data transmission module with to database upload information or receive database In information, construction unit's terminal is used to upload information on bidding to database, and designing unit's terminal is for obtaining number According to the information on bidding in library, and the design information generated according to information on bidding is uploaded, designing unit's terminal is used for data Library uploads design information and design alteration information, and unit in charge of construction's terminal is used to obtain design information from database and to data Library uploads change solicited message, and designing unit's terminal obtains the change solicited message in database, and the computing module is used According to design information and design alteration information and call database data carry out project cost calculating, the report generation mould Block is used to generate project cost report according to the calculated result of computing module, and is sent to database.
By using above-mentioned technical proposal, after the completion of bidding, construction unit passes through construction unit's terminal to number Information on bidding is uploaded according to library, designing unit receives information on bidding by designing unit's terminal, and according to information on bidding and live feelings Condition formulates design information, and is uploaded to database, and computing module is according to design information and calls pricing information in database, with The calculating of project cost is carried out, and project cost report is generated by report generation module, and be sent to database, at the scene situation With different design and when needing to be designed change, unit in charge of construction's terminal issues change solicited message, and designing unit is according to change Solicited message formulates design alteration information, and computing module is according to design alteration information and calls pricing information in database, with The calculating of project cost is re-started, and project cost report is regenerated by report generation module, and be sent to database, is mentioned The accuracy that high project cost calculates, each terminal can obtain project cost report from database.
Preferably, unit in charge of construction's terminal includes project manager's terminal and several subitem terminals, the subitem terminal to Project manager's terminal sends change solicited message, and project manager's terminal checks and to database change solicited message Change solicited message after sending verification.
By using above-mentioned technical proposal, corresponding change request letter is formulated by each subitem administrative staff of unit in charge of construction Breath, and terminal of being itemized is sent to project manager's terminal and is checked by project manager, retransmits into database, it is ensured that change The accuracy of solicited message.
Preferably, project manager's terminal sends the change solicited message after verification to construction unit's terminal, described to build If unit terminal carries out approval to the change solicited message after verification and sends the change solicited message after approval to database.
By using above-mentioned technical proposal, after project manager has checked change solicited message, by change solicited message hair It send to construction unit's terminal and is ratified, by the agreement of construction unit, reduce the case where doing over again.
Preferably, designing unit's terminal sends design alteration information, the construction unit pair to construction unit's terminal Design alteration information carries out approval and sends the design alteration information after approval to database.
By using above-mentioned technical proposal, be sent to after designing unit formulates design alteration information construction unit's terminal into Row approval reduces the case where doing over again by the agreement of construction unit.
Preferably, the management platform includes reminding module, and the reminding module is when database receives information on bidding Designing unit's terminal and unit in charge of construction's terminal are reminded, when database receives design information or design alteration information pair Construction unit's terminal and unit in charge of construction's terminal are reminded, when database receives change solicited message to designing unit's terminal It is reminded.
Counterpart terminal is reminded when database receives new information by using above-mentioned technical proposal, and When handle work, improve working efficiency.
Preferably, the management platform further includes the update module connecting with extraneous cloud and database, for obtaining in real time The pricing information carried out needed for project cost calculates in extraneous cloud is taken, and is sent to database.
By using above-mentioned technical proposal, because pricing information needed for carrying out project cost calculating is in the state floated, Using the pricing information carried out needed for project cost calculates in update module real-time update database, the accuracy of calculating is improved.
Preferably, construction unit's terminal, designing unit's terminal and unit in charge of construction's terminal are mobile phone, tablet computer and meter One of calculation machine is a variety of.
By using above-mentioned technical proposal, constituent parts is facilitated to be operated, using flexible.
Preferably, the reminding module is reminded by one of short message, mail, call voice or various ways.
By using above-mentioned technical proposal, constituent parts are effectively reminded, improve processing speed and working efficiency.
In conclusion the invention has the advantages that:
1, situation and different design and when needing to be designed change at the scene, re-start the calculating of project cost and generate work Journey cost report improves the accuracy that project cost calculates;
2, in request change and design alteration, ratify by construction unit, reduce phenomenon of doing over again;
3, when database receives new information, counterpart terminal is reminded, to handle work in time, improves work effect Rate;
4, the pricing information needed for project cost calculates is carried out in real-time update database, improves the accuracy of calculating.
Detailed description of the invention
Fig. 1 is the functional block diagram of the present embodiment.
Icon note:1, platform is managed;101, database;102, data transmission module;103, computing module;104, report is raw At module;105, update module;106, reminding module;2, construction unit's terminal;3, designing unit's terminal;4, unit in charge of construction is whole End;401, project manager's terminal;402, subitem terminal;5, extraneous cloud.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Following specific embodiments are only explanation of the invention, are not limitation of the present invention, art technology Personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as All by the protection of Patent Law in the scope of the claims invented below.
Overall process Engineering Cost Management system, as shown in Figure 1, including management platform 1, construction unit's terminal 2, designing unit Terminal 3 and unit in charge of construction's terminal 4, wherein management platform 1 include database 101, data transmission module 102, computing module 103, Report generation module 104, reminding module 106 and update module 105, if unit in charge of construction's terminal 4 include project manager's terminal 401 and Dry subitem terminal 402, and construction unit's terminal 2,3 project manager's terminal 401 of designing unit's terminal and subitem terminal 402 are One of mobile phone, tablet computer and computer are a variety of.
Data transmission module 102 and reminding module 106 by wired or wireless mode and construction unit terminal 2, set Meter unit terminal 3 is connected with 401 signal of project manager's terminal, data transmission module 102, computing module 103, report generation module 104, reminding module 106 and the equal signal of update module 105 are connected to database 101, and 104 signal of report generation module is connected to meter Module 103 is calculated, update module 105 is connected to extraneous cloud 5 by network signal, and subitem 402 signal of terminal is connected to project warp Terminal 401 is managed, project manager's terminal 401 and the equal signal of designing unit's terminal 3 are connected to construction unit's terminal 2.
The pricing information and project cost report for calculating project cost, update module 105 are stored in database 101 For obtaining the real-time pricing information carried out needed for project cost calculates in extraneous cloud 5 in real time, and it is sent to database 101, database 101 receives information on bidding from construction unit's terminal 2 by data transmission module 102, comes from designing unit The design information and design alteration information of terminal 3 and change solicited message from unit in charge of construction's terminal 4, construction unit's terminal 2 Information on bidding, design information, design alteration information and the project cost in database 101 are received by data transmission module 102 Report, designing unit receive information on bidding, change solicited message and engineering in database 101 by data transmission module 102 Cost table, unit in charge of construction receive information on bidding, design information, design alteration in database 101 by data transmission module 102 Information and project cost table.
Designing unit's terminal 3 obtains the information on bidding in database 101, and uploads and believed according to the design that information on bidding generates Breath, designing unit's terminal 3 upload design information and design alteration information to database 101, and unit in charge of construction's terminal 4 is from database 101 obtain design information and upload change solicited message to database 101, and designing unit's terminal 3 obtains the change in database 101 More solicited message, computing module 103 is according to design information and design alteration information and the data of database 101 is called to carry out engineering Cost calculates, and report generation module 104 generates project cost report according to the calculated result of computing module 103, and is sent to number According to library 101.
Each subitem terminal 402 can send the change solicited message of corresponding sub-item, project to project manager's terminal 401 respectively 401 pairs of terminal change solicited messages of manager carry out verification and send the change solicited message after verification to construction unit's terminal 2, build If the change solicited message after 2 pairs of unit terminal verifications carries out approval and sends the change request letter after approval to database 101 Change solicited message is sent to construction unit's terminal 2 and ratified by breath after project manager has checked change solicited message, By the agreement of construction unit, the case where doing over again is reduced.
Designing unit's terminal 3 to construction unit's terminal 2 send design alteration information, construction unit to design alteration information into Row approval simultaneously sends the design alteration information after approval to database 101, so that after designing unit formulates design alteration information It is sent to construction unit's terminal 2 to be ratified, by the agreement of construction unit, reduces the case where doing over again.
Wherein reminding module 106 is whole to designing unit's terminal 3 and project manager when database 101 receives information on bidding End 401 is reminded, when database 101 receives design information or design alteration information to construction unit's terminal 2 and construction Unit terminal 4 is reminded, and is reminded when database 101 receives change solicited message designing unit's terminal 3, and Reminding module 106 can be reminded by one of short message, mail, call voice or various ways, be had to constituent parts Effect is reminded, and processing speed and working efficiency are improved.
Specific work process:After the completion of bidding, construction unit passes through construction unit's terminal 2 to database 101 Information on bidding is uploaded, designing unit receives information on bidding by designing unit's terminal 3, and according to information on bidding and field condition system Determine design information, and be uploaded to database 101, computing module 103 is according to design information and the price in database 101 is called to believe Breath to carry out the calculating of project cost, and generates project cost report by report generation module 104, and be sent to database 101, each terminal can obtain project cost report from database 101.
Situation and different design and when needing to be designed change at the scene, corresponding subitem terminal 402 issues accordingly Solicited message is changed, is uploaded to database 101 after the verification of project manager's terminal 401 and construction unit's terminal 2 are ratified, design is single Design alteration information is formulated according to change solicited message in position, and is uploaded to database 101 after the approval of construction unit's terminal 2, counts Module 103 is calculated according to design alteration information and calls pricing information in database 101, to re-start in terms of project cost It calculates, and project cost report is regenerated by report generation module 104, and be sent to database 101, improve project cost and calculate Accuracy, each terminal can obtain the project cost report recalculated from database 101.

Claims (8)

1. overall process Engineering Cost Management system, it is characterized in that:It is single including management platform (1), construction unit's terminal (2), design Position terminal (3) and unit in charge of construction's terminal (4), the management platform (1) include database (101), data transmission module (102), Computing module (103) and report generation module (104), construction unit's terminal (2), designing unit's terminal (3) and work order Position terminal (4) is connected to data transmission module (102) by wired or wireless network respectively with to database (101) upload information Or the information in reception database (101), construction unit's terminal (2) are used to upload information on bidding, institute to database (101) Designing unit's terminal (3) are stated for obtaining the information on bidding in database (101), and upload the design generated according to information on bidding Information, designing unit's terminal (3) are used to upload design information and design alteration information, the construction to database (101) Unit terminal (4) is used to obtain design information from database (101) and uploads change solicited message to database (101), described Designing unit's terminal (3) obtains the change solicited message in database (101), and the computing module (103) is used for according to design Information and design alteration information simultaneously call the data of database (101) to carry out project cost calculating, the report generation module (104) for generating project cost report according to the calculated result of computing module (103), and database (101) are sent to.
2. overall process Engineering Cost Management system according to claim 1, it is characterized in that:Unit in charge of construction's terminal (4) Including project manager's terminal (401) and several subitem terminals (402), the subitem terminal (402) is to project manager's terminal (401) Change solicited message is sent, project manager's terminal (401) is checked change solicited message and sent out to database (101) Change solicited message after sending verification.
3. overall process Engineering Cost Management system according to claim 2, it is characterized in that:Project manager's terminal (401) the change solicited message after verification is sent to construction unit's terminal (2), after construction unit's terminal (2) is to verification Change solicited message carries out approval and sends the change solicited message after approval to database (101).
4. overall process Engineering Cost Management system according to claim 3, it is characterized in that:Designing unit's terminal (3) Design alteration information is sent to construction unit's terminal (2), the construction unit carries out approval to design alteration information and to data Library (101) sends the design alteration information after approval.
5. overall process Engineering Cost Management system according to claim 1, it is characterized in that:The management platform (1) includes Reminding module (106), the reminding module (106) is when database (101) receives information on bidding to designing unit's terminal (3) It is reminded with unit in charge of construction's terminal (4), it is single to construction when database (101) receives design information or design alteration information Position terminal (2) and unit in charge of construction's terminal (4) are reminded, single to design when database (101) receives change solicited message Position terminal (3) is reminded.
6. overall process Engineering Cost Management system according to claim 1, it is characterized in that:The management platform (1) is also wrapped The update module (105) connecting with extraneous cloud (5) and database (101) is included, is carried out for being obtained in extraneous cloud (5) in real time Project cost calculates required pricing information, and is sent to database (101).
7. overall process Engineering Cost Management system according to claim 1, it is characterized in that:Construction unit's terminal (2), Designing unit's terminal (3) and unit in charge of construction's terminal (4) are one of mobile phone, tablet computer and computer or a variety of.
8. overall process Engineering Cost Management system according to claim 5, it is characterized in that:The reminding module (106) is logical It crosses one of short message, mail, call voice or various ways is reminded.
CN201810655612.2A 2018-06-23 2018-06-23 Overall process Engineering Cost Management system Pending CN108921508A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810655612.2A CN108921508A (en) 2018-06-23 2018-06-23 Overall process Engineering Cost Management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810655612.2A CN108921508A (en) 2018-06-23 2018-06-23 Overall process Engineering Cost Management system

Publications (1)

Publication Number Publication Date
CN108921508A true CN108921508A (en) 2018-11-30

Family

ID=64420571

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810655612.2A Pending CN108921508A (en) 2018-06-23 2018-06-23 Overall process Engineering Cost Management system

Country Status (1)

Country Link
CN (1) CN108921508A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109978360A (en) * 2019-03-19 2019-07-05 黄河水利职业技术学院 A kind of project cost schedule management apparatus and method
CN110738458A (en) * 2019-09-07 2020-01-31 北京市建壮咨询有限公司 Engineering cost management system and method
CN110859424A (en) * 2019-11-26 2020-03-06 浙江求真工程管理咨询有限公司 Full life cycle engineering cost management method
CN111192093A (en) * 2020-01-04 2020-05-22 重庆西恒工程咨询有限公司 Engineering cost management system based on BIM
CN111553633A (en) * 2020-04-25 2020-08-18 达信建设发展有限公司 Engineering cost management system and method
CN114140072A (en) * 2021-11-29 2022-03-04 国网福建省电力有限公司 Change visa module device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5546564A (en) * 1993-02-09 1996-08-13 Horie; Kazuhiko Cost estimating system
CN103366284A (en) * 2013-07-18 2013-10-23 北京今达标正软件开发有限公司 Tender offer and expense control system
CN106127398A (en) * 2016-06-30 2016-11-16 国网山东省电力公司经济技术研究院 A kind of construction costs being applicable to project of transmitting and converting electricity calculates system
CN106875111A (en) * 2017-02-10 2017-06-20 国网江苏省电力公司泰州供电公司 Project of transmitting and converting electricity cost Whole Course Management platform
CN107944809A (en) * 2016-10-12 2018-04-20 北京地厚云图科技有限公司 Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5546564A (en) * 1993-02-09 1996-08-13 Horie; Kazuhiko Cost estimating system
CN103366284A (en) * 2013-07-18 2013-10-23 北京今达标正软件开发有限公司 Tender offer and expense control system
CN106127398A (en) * 2016-06-30 2016-11-16 国网山东省电力公司经济技术研究院 A kind of construction costs being applicable to project of transmitting and converting electricity calculates system
CN107944809A (en) * 2016-10-12 2018-04-20 北京地厚云图科技有限公司 Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device
CN106875111A (en) * 2017-02-10 2017-06-20 国网江苏省电力公司泰州供电公司 Project of transmitting and converting electricity cost Whole Course Management platform

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109978360A (en) * 2019-03-19 2019-07-05 黄河水利职业技术学院 A kind of project cost schedule management apparatus and method
CN110738458A (en) * 2019-09-07 2020-01-31 北京市建壮咨询有限公司 Engineering cost management system and method
CN110859424A (en) * 2019-11-26 2020-03-06 浙江求真工程管理咨询有限公司 Full life cycle engineering cost management method
CN111192093A (en) * 2020-01-04 2020-05-22 重庆西恒工程咨询有限公司 Engineering cost management system based on BIM
CN111553633A (en) * 2020-04-25 2020-08-18 达信建设发展有限公司 Engineering cost management system and method
CN114140072A (en) * 2021-11-29 2022-03-04 国网福建省电力有限公司 Change visa module device

Similar Documents

Publication Publication Date Title
CN108921508A (en) Overall process Engineering Cost Management system
CN107423945A (en) Intelligent energy trade managing system and method based on block chain technology
CN104636868A (en) Application management system for nuclear power station equipment maintenance information and application method thereof
US20240185233A1 (en) Blockchain-based transaction system for green certificate
CN108182479A (en) Equipment point-detecting method, device and server
CN109118224A (en) Proof of work method, apparatus, medium and the electronic equipment of block chain network
US20210350427A1 (en) Method and device for cost early warning of prefabricated building
CN108171362A (en) Power supply facilities breakdown repair method, system and terminal device
CN109299193A (en) Method of data synchronization and relevant device
CN109685479A (en) A kind of methods of exhibiting, computer installation and the computer readable storage medium of construction tunnel progress
CN110163634A (en) Withdrawing method and device, electronic equipment based on block chain
CN111461881A (en) Data management method and device, computer equipment and storage medium
CN112613724A (en) Compliance assessment method and device for enterprise, storage medium and electronic equipment
CN109685641A (en) A kind of information processing method and device
CN112328275A (en) Data updating method and device for nuclear power plant, terminal equipment and storage medium
CN107508687A (en) A kind of method, apparatus of charging, Internet of Things application platform and accounting server
CN108073699B (en) Big data aggregation analysis method and device
CN107122359A (en) Data real-time tracking visible processing method and device
CN111259002A (en) Monitoring method, monitoring system and monitoring equipment
CN116151868A (en) Intelligent price checking method, intelligent price checking device, computer equipment and storage medium
CN110399409A (en) Transaction method for monitoring abnormality and device
CN113409119A (en) Method and device for assessing capital risk of financing lease enterprise, storage medium and electronic equipment
CN108733728A (en) Time series data statistical method, device, computer equipment and readable storage medium storing program for executing
CN109472530A (en) Goods delivery task creating method and terminal device
CN110602665A (en) Method for determining sharing service index based on communication certificate sharing service

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181130