CN107944809A - Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device - Google Patents

Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device Download PDF

Info

Publication number
CN107944809A
CN107944809A CN201610890871.4A CN201610890871A CN107944809A CN 107944809 A CN107944809 A CN 107944809A CN 201610890871 A CN201610890871 A CN 201610890871A CN 107944809 A CN107944809 A CN 107944809A
Authority
CN
China
Prior art keywords
task
unit
negotiation
personnel
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610890871.4A
Other languages
Chinese (zh)
Inventor
谢远玉
薛奇辉
单立新
肖发权
卢平
卢一平
徐福兵
陈小东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Thick Cloud Technology Co Ltd
Original Assignee
Beijing Thick Cloud Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Thick Cloud Technology Co Ltd filed Critical Beijing Thick Cloud Technology Co Ltd
Priority to CN201610890871.4A priority Critical patent/CN107944809A/en
Publication of CN107944809A publication Critical patent/CN107944809A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of design alteration, engineering negotiation or Site visa-an important chain task exchange method and device, wherein method is included according to the characteristics of projects, and when project initiation presets personnel in a manner of team management to the post of flow Zhong Ge units of taking part in building automatic flow (multiple process steps realize automatic flow).The side that takes part in building initiates change, negotiation or visa task and Internal Transfer examination & approval, it is subsequently formed task and proposes that technical proposal and expense are declared (Internal Transfer examination & approval) by unit in charge of construction, system will declares restoring files and be audited to management/consulting unit (inside can assign subtask) automatically;The examination & verification achievement automatic flow of management/consulting unit is audited to construction unit's (inside can assign subtask) and formality is improved after finally examining and filing, statistics.The present invention can make to take part in building each side when change, negotiation or visa task interact, and be adjusted flexibly design or the unit in charge of construction of participation, more rigorous in flow, technology and cost files sign confirmation more in time with accurately.

Description

Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device
Technical field
The present invention relates to building field, more particularly to a kind of design alteration, engineering negotiation or Site visa-an important chain task interaction side Method and device.
Background technology
Change, negotiate or visa flow is substantially uniform and more specification, but existing change in all kinds of companies and project More, negotiation or visa management mostly rest on OA patterns inside the folk prescription of local side, and the circulation of each side is interactive or relies on papery File turns label.Existing OA management modes just correspond to the sum of the single task role of this platform or wherein several tasks.
Therefore, for meet design alteration, engineering negotiation or Site visa-an important chain task interaction, it is necessary to design a kind of new design Change, engineering negotiation or Site visa-an important chain task exchange method and device.
The content of the invention
It is an object of the present invention to provide a kind of design alteration, engineering is negotiated or Site visa-an important chain task exchange method and device, its Enable to take part in building each side when design alteration and engineering negotiation or Site visa-an important chain task interact in engineering management, in flow more Rigorous, technology and cost files sign confirmation more in time with accurately, and can truly record implementation status, and can chase after Trace back.
The present invention solves technical problem and adopts the following technical scheme that:A kind of design alteration, engineering negotiation or Site visa-an important chain are appointed Business exchange method, it includes:
S10, construction unit team management person are in the team management of project to flow Zhong Ge units of taking part in building automatic flow Post carries out the setting of counterpart personnel;
S20, the side personnel that take part in building create design alteration, engineering negotiation or Site visa-an important chain task, by being preset in team management Initiator administrative staff first draft is audited;
Design alteration, engineering negotiation or the Site visa-an important chain first draft that S30, basis have been audited form assignable task, and will The task is distributed to corresponding unit in charge of construction personnel;Unit in charge of construction personnel receive can be told off after task multiple subtasks to Its corresponding personnel proposes content and expense opinion, is finally confirmed by unit in charge of construction administrative staff after completing each subtask and forms Shen Achievement is reported to upload;
Achievement circulation default management/consulting unit management into team management is declared by S40, system automatically by unit in charge of construction Personnel;Management/consulting unit management personnel declare achievement as annex using what unit in charge of construction uploaded, and can create subtask assignment Internally hold to corresponding personnel and audited, and the parallel cost personnel that is dispatched in the subtask audits expense;Examination & verification Afterwards, finally confirmed by management/consulting unit management personnel and upload examination & verification achievement;
The examination & verification achievement of management/consulting unit management personnel is circulated and is built to default in team management by S50, system automatically If unit personnel;Examination & verification task can be dispatched to engineer and carry out content auditing by construction unit personnel, and parallel distribute to is made Valency personnel carry out expense auditing;
System automatic flow builds list to default in team management after S60, construction unit personnel complete each examination & verification task Position director, final examination & approval are carried out by construction unit director.
Optionally, wherein in step S50, construction unit's cost personnel can create subtask and be dispatched to budgeter pair Expense is audited, and is finally audited and confirmed by cost department head, and this examination & verification task achievement is uploaded to construction unit's pipe Reason personnel.
Optionally, wherein in step S60, such as construction unit director judgement suspension, then edit and release information and be sent to participation originally The all personnel of design alteration, engineering negotiation or the interaction of Site visa-an important chain task;Such as confirm to perform, then construction unit director confirms Afterwards, which is sent to default construction unit donor startup label in team management and recognizes program.
Optionally, the label, which recognize program, includes:Default construction unit donor label recognize design alteration, work in team management Journey is negotiated or Site visa-an important chain assignment file and annex, and selects corresponding designing unit and unit in charge of construction, and system is automatically by task flow Default designing unit donor in team management is gone to, after designing unit donor label are recognized, task flow is given to by system automatically Default supervisor donor in team management, after supervisor donor completion label are recognized, task flow is given to by system automatically Default unit in charge of construction donor completion label recognize formality in team management.
Optionally, the design alteration, engineering negotiation or Site visa-an important chain task exchange method further include:S70, automatic archiving The perfect design alteration of final formality, engineering negotiation or Site visa-an important chain assignment file.
Optionally, the design alteration, engineering negotiation or Site visa-an important chain task exchange method further include:S80, team management In default construction unit personnel assigned according to design alteration, engineering negotiation and Site visa-an important chain task to management/corresponding engineer The task of change negotiation visa implementation status tracking, is finally confirmed by the corresponding personnel of construction unit;This design alteration, engineering negotiation Or the tracking achievement system of Site visa-an important chain task establishes association link with change negotiation visa account automatically, in order to settle accounts when combs Reason.
The present invention solves technical problem and also adopts the following technical scheme that:A kind of design alteration, engineering negotiation or Site visa-an important chain Task interactive device, it is characterised in that including:
Task creation module, for creating design alteration, engineering negotiation or Site visa-an important chain task;
Task generation module, forms assignable according to the design alteration, engineering negotiation or Site visa-an important chain first draft audited Task, and the task is distributed to corresponding unit in charge of construction personnel;Unit in charge of construction personnel receive can be told off after task it is more A subtask proposes content and expense opinion to its corresponding personnel, completes finally true by unit in charge of construction administrative staff behind each subtask Recognize and formed and declare achievement upload;
Task flow revolving die block, achievement circulation default prison into team management is declared for system by unit in charge of construction automatically Reason/consulting unit personnel;Management/consulting unit personnel declares achievement as annex using what unit in charge of construction uploaded, and can create son Task is dispatched to corresponding personnel, and internally appearance is audited, and the parallel cost personnel that is dispatched in the subtask examines expense Core;After examination & verification, finally confirmed by management/consulting unit management personnel and uploaded examination & verification achievement;
Confirm achievement circulation module, for system automatically by the examination & verification achievement of management/consulting unit management personnel circulate to Default construction unit personnel in team management;Examination & verification task can be dispatched to engineer's progress content and examined by construction unit personnel Core, and parallel cost personnel of distributing to carry out expense auditing;
Approval module, system automatic flow is preset in team management after completing each examination & verification task for construction unit personnel Construction unit director, final examination & approval are carried out by construction unit director;Such as construction unit director judgement suspension, it is then The automatic information of editing and releasing of system is sent to all personnel for participating in the design change, engineering negotiation or the interaction of Site visa-an important chain task;As really Recognize execution, then after construction unit director confirms, which is sent to construction unit donor automatically and starts label by system Recognize program.
Optionally, the design alteration, engineering negotiation or Site visa-an important chain task interactive device further include:
Automatic archiving module, the change task perfect for the final formality of automatic archiving, engineering negotiation or Site visa-an important chain are appointed Business file, the perfect design alteration of final formality, engineering negotiation or Site visa-an important chain assignment file are by system automatic archiving to design In file module;The cost files confirmed through construction unit director are pushed to default construction in team management by system automatically The corresponding personnel of unit, improve expense by the corresponding personnel of construction unit and confirm formality;After completing written confirmation formality, construction unit's phase Answer personnel to upload expense to confirm formality scanned copy and click on completion, relevant information is collected corresponding change negotiation by system automatically Visa account forms statistics and finally includes in platform big data.
Optionally, the design alteration, engineering negotiation or Site visa-an important chain task interactive device further include:Tasks carrying mould Block, for performing design alteration, engineering negotiation or Site visa-an important chain task, default construction unit administrative staff root in team management According to design alteration, engineering negotiation and Site visa-an important chain task to management/corresponding engineer assign change negotiation visa implementation status with The task of track, is finally confirmed by the corresponding personnel of default construction unit in team management;This design alteration, engineering negotiation or scene The tracking achievement system of visa task establishes association link with change negotiation visa account automatically, and in order to settle accounts when combs.
The present invention has the advantages that:The present invention enables to taking part in building respectively in engineering management by above-mentioned steps Side design alteration and engineering negotiation or Site visa-an important chain task interact when, can flexible transformation adjustment participate in design or work order Position, more rigorous in flow, technology and cost files sign confirmation more in time with accurately, and can truly record execution feelings Condition, and can trace.
Brief description of the drawings
Fig. 1 is design alteration and the flow chart of engineering negotiation or Site visa-an important chain task exchange method of the present invention;
Fig. 2 is design alteration and engineering negotiation or the Site visa-an important chain task interactive device structure diagram of the present invention;
Fig. 3 is shown according to the design alteration of the embodiment of the present application 3 and engineering negotiation or Site visa-an important chain task interactive device Equipment logic diagram.
Embodiment
Technical scheme is further elaborated with reference to embodiment and attached drawing.
Embodiment 1
A kind of design alteration, engineering negotiation and/or Site visa-an important chain task exchange method are present embodiments provided, it is according to item The specific feature of purpose, in project initiation, 1 grade of user of construction unit is (such as:Vice president) to the small composition of change negotiation visa module Member carries out the post personnel selection setting (automatic flow for realizing process step) of each process step, and comprises the following steps:
S10, construction unit team management person are in the team management of project to flow Zhong Ge units of taking part in building automatic flow Post carries out the setting of counterpart personnel.
It is small to this that S20, the side that takes part in building create design alteration, engineering negotiation or Site visa-an important chain task, (system) automatic flow Default initiator administrative staff audit first draft in group management.In the present embodiment, the side that takes part in building can think construction Unit personnel.
The notice that design alteration is due to the error of design or design idea changes and reissued by designing unit, engineering negotiation It is single to design when not having the drawing problem found when construction unit or unit in charge of construction construct or are found that for convenience drawing joint examination Position presents one's view, and therefore, in the present embodiment, design alteration and engineering negotiation, Site visa-an important chain task can appointing by construction unit Meaning personnel propose;And the personnel of construction unit arbitrarily create design alteration, engineering negotiation or Site visa-an important chain task in order to prevent, , it is necessary to default construction unit's project in by team management after the design alteration, engineering negotiation or Site visa-an important chain task creation Chief engineer is audited and is ratified to the design alteration, engineering negotiation or Site visa-an important chain task first draft;If project chief engineer audits it Afterwards, ratify the task, then perform step S20;If on the contrary, not ratifying the task, terminate this design alteration, engineering is in harmony Business or the interaction of Site visa-an important chain task.
Design alteration, engineering negotiation or the Site visa-an important chain first draft that S30, basis have been audited form assignable task, and will The corresponding unit in charge of construction personnel that the task distributes;Unit in charge of construction personnel receive can be told off after task multiple subtasks to Its corresponding personnel proposes content and expense opinion, finally confirms and formed to declare into by unit in charge of construction personnel after completing each subtask Fruit uploads.
Such as:Construction unit Engineering Supervisor needs the design for initiating one " floor increase hole to be provided " to become in engineering progress More task, after initiation design alteration item is created, (system) is automatically pushed to default construction unit's project in team management Chief engineer is audited, which pushes away the information of the initiation task after construction unit project chief engineer audits approval manually Corresponding unit in charge of construction project manager is given, unit in charge of construction project manager forms subtask and distributes to subordinate's progress as the case may be Technology, business analysis and opinion, unit in charge of construction project manager make a report on to upload after main task opinion and declare into according to subtask achievement Fruit.
Unit in charge of construction, is declared achievement (system) automatic flow default management/consulting unit tube into team management by S40 Reason personnel.
Management/consulting unit chief inspector (management/consulting unit management personnel) using unit in charge of construction upload declare achievement as Annex, creates new task, and the new task (can be split as new subtask) is dispatched to corresponding supervising engineer to content Audited, and the new task is dispatched to management cost personnel expense is audited;After examination & verification, by management/consulting After unit chief inspector final review confirms, it will confirm that examination & verification achievement uploads.
S50, that the confirmation of management/consulting unit chief inspector is audited to achievement (system) automatic flow is default into team management Construction unit engineering manager (construction unit personnel).
Examination & verification task is dispatched to expert engineer and carries out content auditing by construction unit engineering manager, and is dispatched to close About budget portion manager (cost personnel) carries out expense auditing.
In the present embodiment, when construction unit's cost personnel audits expense, construction unit's contract budget portion Manager's (cost personnel), which can create subtask and be dispatched to budgeter, audits expense, is finally handled by contract budget portion (cost part director), which audits, to be confirmed, this subtask achievement (examination & verification task achievement) is uploaded to default in team management build If unit project general manager.
(system) automatic flow is to default construction in team management after S60, construction unit personnel complete each examination & verification task Unit project general manager (construction unit director), final examination & approval are carried out by construction unit project general manager.
As construction unit project general manager judges to stop, then (system) it is automatic edit and release information and be sent to participate in this change task With all personnel of engineering negotiation task interaction;Such as confirm to perform, then after construction unit's project general manager confirms, which is tied Fruit is sent to default construction unit donor startup label in team management and recognizes program.
Specifically, the label, which recognize program, includes:Default construction unit donor label recognize design alteration, work in team management Journey is negotiated or Site visa-an important chain assignment file, and design alteration, engineering negotiation or the Site visa-an important chain assignment file that each side will be needed to confirm As annex (system) automatic flow, into team management, default designing unit donor (project manager), designing unit authorize After people (project manager) label are recognized, (system) automatic flow is to default supervisor donor (chief inspector), management in team management After unit donor (chief inspector) completion label are recognized, (system) automatic flow is to default unit in charge of construction donor (item in team management Mesh handle) complete label recognize formality.
The perfect design alteration of the final formality of S70, automatic archiving, engineering negotiation or Site visa-an important chain assignment file.
The final perfect design alteration of formality, engineering negotiation or Site visa-an important chain assignment file are by (system) automatic archiving to setting Count in file module;The cost files confirmed through construction unit general manager are pushed to default in team management by (system) automatically Construction unit documenter, the expense that both sides are improved by construction unit documenter confirm formality.After completing written confirmation formality, build Unit documenter uploads expense and confirms formality scanned copy and click on completion, and relevant information is collected corresponding change by (system) automatically Visa account is more negotiated to form statistics and finally include in platform big data.
S80, chief inspector/construction unit engineering manager are according to design alteration or engineering negotiation, Site visa-an important chain task to corresponding Engineer assigns the task of change negotiation visa implementation status tracking, finally by default chief inspector/construction unit in team management Engineering manager confirms.This design alteration or engineering negotiation, tracking achievement and the change negotiation visa account of Site visa-an important chain task Association link is established, in order to settle accounts when combs.
The present invention by above-mentioned steps, enable in engineering management take part in building each side design alteration and engineering negotiation, Site visa-an important chain task interact when, can flexible transformation adjustment participate in design or unit in charge of construction's flow on more rigorous, technology and expense File signs confirmation more in time with accurately, and can truly record implementation status, and can trace.
Embodiment 2
A kind of design alteration and engineering negotiation, Site visa-an important chain task interactive device (system) are present embodiments provided, it is wrapped Include:
Task creation module, for creating design alteration, engineering is negotiated or Site visa-an important chain task, in the present embodiment, builds Unit personnel creates design alteration, engineering negotiation or Site visa-an important chain task, and (system) automatic flow is to default in team management Construction unit project chief engineer audits approval task;After design alteration or engineering negotiation, Site visa-an important chain task creation, construction unit Project chief engineer can audit and ratify the task by the task creation module, if after construction unit project chief engineer examination & verification, Do not ratify the task, then terminate this design alteration and engineering negotiation, the interaction of Site visa-an important chain task.
Task generation module, forms assignable according to the design alteration, engineering negotiation or Site visa-an important chain first draft audited Task, and manually selected and be distributed to corresponding unit in charge of construction project manager;Unit in charge of construction project manager receives what this was distributed After task, multiple subtasks are told off, the chief engineer's (proposing content opinion) and business manager for distributing to this unit in charge of construction (carry Go out expense), unit in charge of construction project manager finally confirms main task and uploads to declare achievement.
Task flow revolving die block, declares achievement as annex, default prison in team management for what is uploaded using unit in charge of construction Reason/consulting unit chief inspector creates new task, and the new task (can be split as new subtask) is dispatched to corresponding management work Cheng Shi audits content, and the new task is dispatched to management cost personnel expense is audited;After examination & verification, by After management/consulting unit chief inspector final review confirms, it will confirm that examination & verification achievement uploads.
Achievement circulation module is confirmed, for the confirmation of management/consulting unit chief inspector to be audited achievement (system) automatic flow Into team management, examination & verification task is dispatched to professional work by default construction unit engineering manager, construction unit engineering manager Journey Shi Jinhang content auditings, and distribute to contract budget portion manager and carry out expense auditing.
Approval module, (system) automatic flow is to default in team management after construction unit personnel complete each examination & verification task Construction unit project general manager, final examination & approval are carried out by construction unit project general manager.As construction unit project general manager sentences Fixed to stop, then (system) automatic information of editing and releasing is sent to participation the design change, engineering negotiation or the interaction of Site visa-an important chain task All personnel;Such as confirm to perform, then after construction unit's project general manager confirms, which is sent in team management in advance If construction unit donor start label recognize program.
Specifically, the label, which recognize program, includes:Default construction unit donor label recognize design alteration, work in team management Journey is negotiated or Site visa-an important chain assignment file, and design alteration, engineering negotiation or the Site visa-an important chain assignment file that each side will be needed to confirm As annex (system) automatic flow, into team management, default designing unit donor (project manager), designing unit authorize After people (project manager) label are recognized, (system) automatic flow is to default supervisor donor (chief inspector), management in team management After unit donor (chief inspector) completion label are recognized, (system) automatic flow is to default unit in charge of construction donor (item in team management Mesh handle) complete label recognize formality.
Automatic archiving module, the design alteration perfect for the final formality of automatic archiving, engineering negotiation or Site visa-an important chain are appointed Be engaged in file, in the present embodiment, the perfect design alteration of final formality, engineering negotiation or Site visa-an important chain assignment file by (system) from Dynamic filing is arrived in design document module;The cost files confirmed through construction unit general manager are pushed to group's pipe by (system) automatically Default construction unit documenter in reason, the confirmation formality of both sides is improved by construction unit documenter.Complete written confirmation formality Afterwards, construction unit documenter uploads expense confirmation formality scanned copy and clicks on completion, and (system) automatically collects relevant information Corresponding change negotiation visa account forms statistics and finally includes in platform big data.
Task execution module, is negotiated, Site visa-an important chain task for performing design alteration or engineering, in the present embodiment, group Default chief inspector/construction unit engineering manager gives corresponding according to design alteration or engineering negotiation, Site visa-an important chain task in management Engineer assigns the task of change negotiation visa implementation status tracking, finally by default chief inspector/construction unit in team management Engineering manager confirms.This design alteration or engineering negotiation, tracking achievement and the change negotiation visa account of Site visa-an important chain task Association link is established, in order to settle accounts when combs.
Embodiment 3
Fig. 3 is the structure diagram for showing the equipment according to the embodiment of the present application 2, and the application specific embodiment pair is not set Standby 400 specific implementation limits.As shown in figure 3, the equipment 400 can include:
Processor (processor) 410, communication interface (Communications Interface) 420, memory (memory) 430 and communication bus 440.Wherein:
Processor 410, communication interface 420 and memory 430 complete mutual communication by communication bus 440.
Communication interface 420, for communicating with the network element of such as client etc..
Processor 410, for executive program 432, can specifically perform the correlation step in above method embodiment.
Specifically, program 432 can include program code, and said program code includes computer-managed instruction.
Processor 410 is probably a central processor CPU, or specific integrated circuit ASIC (Application Specific Integrated Circuit), or be arranged to implement the embodiment of the present application one or more integrate electricity Road.
Memory 430, for storing program 432.Memory 430 may include high-speed RAM memory, it is also possible to further include Nonvolatile memory (non-volatile memory), for example, at least a magnetic disk storage.Program 432 can specifically be used Following operation is performed in causing the equipment 400:
Construction unit personnel create design alteration or engineering negotiation, Site visa-an important chain task, system automatic flow are managed to group Default construction unit's project chief engineer audits approval task in reason;According to the design alteration of approved or engineering negotiation, scene label Card task forms assignable task, and it is distributed to corresponding unit in charge of construction project manager manually;Unit in charge of construction project manager After receiving the task that this is distributed, multiple subtasks are told off, distribute to corresponding chief engineer's (proposing content opinion) and commercial affairs Handle (proposition expense), after each subtask is completed, unit in charge of construction project manager finally confirms each subtask and uploads achievement; By main task achievement automatic flow into team management default management/consulting unit chief inspector;Management/consulting unit chief inspector is really Recognize achievement automatic flow default construction unit engineering manager into team management;Construction unit engineering manager is completed Task information automatic flow carries out last examine to default construction unit general manager in team management by construction unit general manager Batch;The perfect design alteration of the final formality of automatic archiving and engineering negotiation, Site visa-an important chain file;It is default total in team management Prison/construction unit engineering manager assigns change according to design alteration or engineering negotiation, Site visa-an important chain task to corresponding engineer The task of visa implementation status tracking is negotiated, is finally confirmed by default chief inspector in team management/construction unit engineering manager. Association link is established in this design alteration or engineering negotiation, tracking achievement and the change negotiation visa account of Site visa-an important chain task, with Combed during easy to settle accounts.
The specific implementation of each step may refer to corresponding in corresponding steps and the unit in above-described embodiment in program 432 Description, this will not be repeated here.
The sequencing of above example only for ease of describing, does not represent the quality of embodiment.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that:It still may be used To modify to the technical solution described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic; And these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical solution spirit and Scope.

Claims (9)

1. a kind of design alteration, engineering negotiation or Site visa-an important chain task exchange method, it is characterised in that including:
S10, construction unit team management person are in the team management of project to the post of flow Zhong Ge units of taking part in building automatic flow Carry out the setting of counterpart personnel;
S20, the side personnel that take part in building create design alteration, engineering negotiation or Site visa-an important chain task, by default hair in team management Square administrative staff are played to audit first draft;
S30, according to the design alteration, engineering negotiation or Site visa-an important chain first draft audited form assignable task, and by this Business is distributed to corresponding unit in charge of construction personnel;Unit in charge of construction personnel can be told off multiple subtasks to its phase after receiving task Answer personnel to propose content and expense opinion, finally confirm and formed to declare into by unit in charge of construction administrative staff after completing each subtask Fruit uploads;
Achievement circulation default management/consulting unit management people into team management is declared by S40, system automatically in unit in charge of construction Member;Management/consulting unit management personnel declare achievement as annex using what unit in charge of construction uploaded, and can create subtask and be dispatched to Corresponding personnel, which internally hold, to be audited, and the parallel cost personnel that is dispatched in the subtask audits expense;Audit it Afterwards, finally confirmed by management/consulting unit management personnel and upload examination & verification achievement;
The examination & verification achievement of management/consulting unit management personnel is circulated and builds list to default in team management by S50, system automatically Position personnel;Examination & verification task can be dispatched to engineer and carry out content auditing by construction unit personnel, and parallel distribute to cost people Member carries out expense auditing;
System automatic flow is born to default construction unit in team management after S60, each examination & verification task of construction unit personnel completion People is blamed, final examination & approval are carried out by construction unit director.
2. design alteration according to claim 1, engineering negotiation or Site visa-an important chain task exchange method, it is characterised in that In wherein step S50, construction unit's cost personnel, which can create subtask and be dispatched to budgeter, audits expense, most Audited and confirmed by cost department head eventually, and this examination & verification task achievement is uploaded to construction unit administrative staff.
3. design alteration according to claim 1, engineering negotiation or Site visa-an important chain task exchange method, it is characterised in that In wherein step S60, as construction unit director judges to stop, then edit and release information be sent to participate in the design change, engineering is in harmony Business or all personnel of Site visa-an important chain task interaction;Such as confirm to perform, then after construction unit director confirms, which is audited As a result default construction unit donor startup label in team management are sent to and recognize program.
4. design alteration according to claim 3, engineering negotiation or Site visa-an important chain task exchange method, it is characterised in that The label, which recognize program, to be included:Default construction unit donor label recognize design alteration, engineering negotiation or scene label in team management Assignment file and annex are demonstrate,proved, and selects corresponding designing unit and unit in charge of construction, system automatically to go to task flow in team management Default designing unit donor, after designing unit donor label are recognized, task flow is given in team management and is preset by system automatically Supervisor donor, supervisor donor completed after label recognize, and task flow is given in team management and is preset by system automatically Unit in charge of construction donor complete label recognize formality.
5. design alteration according to claim 4, engineering negotiation or Site visa-an important chain task exchange method, it is characterised in that Further include:The perfect design alteration of the final formality of S70, automatic archiving, engineering negotiation or Site visa-an important chain assignment file.
6. design alteration according to claim 5, engineering negotiation or Site visa-an important chain task exchange method, it is characterised in that Further include:Default construction unit personnel give according to design alteration, engineering negotiation and Site visa-an important chain task in S80, team management Management/corresponding engineer assigns the task of change negotiation visa implementation status tracking, is finally confirmed by the corresponding personnel of construction unit; The tracking achievement system of this design alteration, engineering negotiation or Site visa-an important chain task is established with change negotiation visa account and associated automatically Link, in order to settle accounts when, comb.
7. a kind of design alteration, engineering negotiation or Site visa-an important chain task interactive device, it is characterised in that including:
Task creation module, for creating design alteration, engineering negotiation or Site visa-an important chain task;
Task generation module, assignable task is formed according to the design alteration, engineering negotiation or Site visa-an important chain first draft audited, And the task is distributed to corresponding unit in charge of construction personnel;Unit in charge of construction personnel can be told off more height times after receiving task It is engaged in proposing content and expense opinion to its corresponding personnel, simultaneously shape is finally confirmed by unit in charge of construction administrative staff after completing each subtask Uploaded into achievement is declared;
Task flow revolving die block, achievement circulation default management/official communication into team management is declared for system by unit in charge of construction automatically Ask unit personnel;Management/consulting unit personnel declares achievement as annex using what unit in charge of construction uploaded, and can create subtask point Tasking corresponding personnel, internally appearance is audited, and the parallel cost personnel that is dispatched in the subtask audits expense;Examine After core, finally confirmed by management/consulting unit management personnel and uploaded examination & verification achievement;
Confirm achievement circulation module, the examination & verification achievement of management/consulting unit management personnel circulates to group automatically for system Default construction unit personnel in management;Examination & verification task can be dispatched to engineer and carry out content auditing by construction unit personnel, with And parallel cost personnel of distributing to carries out expense auditing;
Approval module, system automatic flow is built to default in team management after completing each examination & verification task for construction unit personnel If head of the unit, final examination & approval are carried out by construction unit director;As construction unit director judge stop, then system from Dynamic information of editing and releasing is sent to all personnel for participating in the design change, engineering negotiation or the interaction of Site visa-an important chain task;As confirmed to hold OK, then after construction unit director confirms, which is sent to construction unit donor startup label automatically and recognizes journey by system Sequence.
8. design alteration according to claim 7, engineering negotiation or Site visa-an important chain task interactive device, it is characterised in that Further include:
Automatic archiving module, the change task perfect for the final formality of automatic archiving, engineering negotiation or Site visa-an important chain task text Part, the perfect design alteration of final formality, engineering negotiation or Site visa-an important chain assignment file are by system automatic archiving to design document In module;The cost files confirmed through construction unit director are pushed to default construction unit in team management by system automatically Corresponding personnel, improve expense by the corresponding personnel of construction unit and confirm formality;After completing written confirmation formality, construction unit's corresponding human Member's upload expense confirms formality scanned copy and clicks on completion, and relevant information is collected corresponding change negotiation visa by system automatically Account forms statistics and finally includes in platform big data.
9. design alteration according to claim 8, engineering negotiation or Site visa-an important chain task interactive device, it is characterised in that Further include:Task execution module, it is default in team management for performing design alteration, engineering negotiation or Site visa-an important chain task Construction unit administrative staff assign change according to design alteration, engineering negotiation and Site visa-an important chain task to management/corresponding engineer The task of visa implementation status tracking is negotiated, is finally confirmed by the corresponding personnel of default construction unit in team management;This design The tracking achievement system of change, engineering negotiation or Site visa-an important chain task establishes association link with change negotiation visa account automatically, Combed during in order to settle accounts.
CN201610890871.4A 2016-10-12 2016-10-12 Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device Pending CN107944809A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610890871.4A CN107944809A (en) 2016-10-12 2016-10-12 Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610890871.4A CN107944809A (en) 2016-10-12 2016-10-12 Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device

Publications (1)

Publication Number Publication Date
CN107944809A true CN107944809A (en) 2018-04-20

Family

ID=61928741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610890871.4A Pending CN107944809A (en) 2016-10-12 2016-10-12 Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device

Country Status (1)

Country Link
CN (1) CN107944809A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108921508A (en) * 2018-06-23 2018-11-30 广东人信工程咨询有限公司 Overall process Engineering Cost Management system
CN109284919A (en) * 2018-09-13 2019-01-29 深圳市栋森工程项目管理有限公司 A kind of project cost project management system
CN109978502A (en) * 2019-03-21 2019-07-05 广州翔实工程咨询有限公司 Automatic budget method, system and computer storage medium are changed in engineering design
CN110570294A (en) * 2019-08-30 2019-12-13 北京安锐卓越信息技术股份有限公司 Method, device and storage medium for managing settlement
CN110852635A (en) * 2019-11-14 2020-02-28 上海新蕴力电子商务有限公司 Platform system in electricity merchant operation
CN111353758A (en) * 2020-03-04 2020-06-30 海南金盘智能科技股份有限公司 Flow changing method and device
CN111815108A (en) * 2020-05-30 2020-10-23 国网上海市电力公司 Evaluation method for power grid engineering design change and on-site visa approval sheet
CN113689090A (en) * 2021-08-04 2021-11-23 中国二十冶集团有限公司 Alteration and drawing management method based on engineering management and control platform
CN114140072A (en) * 2021-11-29 2022-03-04 国网福建省电力有限公司 Change visa module device

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1503174A (en) * 2002-11-25 2004-06-09 英业达股份有限公司 Process method for engineering design change application and system thereof
US20050251433A1 (en) * 2004-04-16 2005-11-10 Orifici Joseph M Method and system to assess, track and implement capital projects by municipalities
CN105931022A (en) * 2016-04-19 2016-09-07 成都晨越建设项目管理股份有限公司 Change supervision method for project supervision

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1503174A (en) * 2002-11-25 2004-06-09 英业达股份有限公司 Process method for engineering design change application and system thereof
US20050251433A1 (en) * 2004-04-16 2005-11-10 Orifici Joseph M Method and system to assess, track and implement capital projects by municipalities
CN105931022A (en) * 2016-04-19 2016-09-07 成都晨越建设项目管理股份有限公司 Change supervision method for project supervision

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
雍承鑫: "《基于全过程造价管理的设计变更管理方法与实施研究》", 《成都大学学报(自然科学版)》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108921508A (en) * 2018-06-23 2018-11-30 广东人信工程咨询有限公司 Overall process Engineering Cost Management system
CN109284919A (en) * 2018-09-13 2019-01-29 深圳市栋森工程项目管理有限公司 A kind of project cost project management system
CN109978502A (en) * 2019-03-21 2019-07-05 广州翔实工程咨询有限公司 Automatic budget method, system and computer storage medium are changed in engineering design
CN110570294A (en) * 2019-08-30 2019-12-13 北京安锐卓越信息技术股份有限公司 Method, device and storage medium for managing settlement
CN110852635A (en) * 2019-11-14 2020-02-28 上海新蕴力电子商务有限公司 Platform system in electricity merchant operation
CN111353758A (en) * 2020-03-04 2020-06-30 海南金盘智能科技股份有限公司 Flow changing method and device
CN111353758B (en) * 2020-03-04 2023-08-08 海南金盘智能科技股份有限公司 Flow changing method and device
CN111815108A (en) * 2020-05-30 2020-10-23 国网上海市电力公司 Evaluation method for power grid engineering design change and on-site visa approval sheet
CN113689090A (en) * 2021-08-04 2021-11-23 中国二十冶集团有限公司 Alteration and drawing management method based on engineering management and control platform
CN114140072A (en) * 2021-11-29 2022-03-04 国网福建省电力有限公司 Change visa module device

Similar Documents

Publication Publication Date Title
CN107944809A (en) Design alteration, engineering negotiation or Site visa-an important chain task exchange method and device
Liu et al. Understanding effects of BIM on collaborative design and construction: An empirical study in China
Heikkilä et al. Operational release planning in large-scale Scrum with multiple stakeholders–A longitudinal case study at F-Secure Corporation
Paasivaara et al. Towards rapid releases in large-scale xaas development at ericsson: A case study
Smits et al. Implementing scrum in a distributed software development organization
Nakakawa et al. Supplementing enterprise architecture approaches with support for executing collaborative tasks—A case of TOGAF ADM
Hamad et al. Scalable agile transformation process (SATP) to convert waterfall project management office into agile project management office
Grapenthin et al. Reducing complexity using an interaction room: An experience report
US8131579B2 (en) Web-based system and application for collaborative planning of a networked program schedule
Chen et al. Qualitatively exploring the impact of BIM on construction performance
Linåker et al. Requirements engineering in open innovation: a research agenda
Srinivasan et al. Using agile methods in software product development: A case study
Krejci et al. Idea management in a digital world: An adapted framework
Davis et al. Designing thinkLets for convergence
Norton Applying cross-functional evolutionary methodologies to web development
Khanna Experiential team learning in software startups
Oliveira et al. FaMoSim: a facilitated discrete event simulation framework to support online studies
Al-Rashid et al. Exploring enterprise resource planning (ERP) implementation from stakeholder perspective-a case study
Anderson Evaluating the ROI of coaching: Telling a story, not just producing a number
Alharthi et al. Value-based modeling of an addiction recovery healthcare system
Tai A communication architecture from rapid prototyping
Aksenova et al. Cultural-historical activity theory to introduce transformations in architecture and construction: a case study
Walter An approach to transforming requirements into evaluable UI design for contextual practice-a design science research perspective
Wagner et al. Making software work: producing social order via problem solving in a troubled ERP implementation
Purwandi Scrum Integration in Cloud-based Human Capital Management (HCM) Project Development

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180420

RJ01 Rejection of invention patent application after publication