CN108729645A - Pre-fabricated one beam column core space reinforcing bar binding construction method - Google Patents

Pre-fabricated one beam column core space reinforcing bar binding construction method Download PDF

Info

Publication number
CN108729645A
CN108729645A CN201710251754.8A CN201710251754A CN108729645A CN 108729645 A CN108729645 A CN 108729645A CN 201710251754 A CN201710251754 A CN 201710251754A CN 108729645 A CN108729645 A CN 108729645A
Authority
CN
China
Prior art keywords
reinforcing bar
fabricated
beam column
core space
muscle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710251754.8A
Other languages
Chinese (zh)
Inventor
牛胜民
汪从
梁广远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201710251754.8A priority Critical patent/CN108729645A/en
Publication of CN108729645A publication Critical patent/CN108729645A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/06Consoles; Brackets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing

Abstract

A kind of pre-fabricated one beam column core space reinforcing bar binding construction method, it is characterised in that include the following steps:A, precast concrete pier; b, pre-fabricated one beam column core space reinforcing bar ring muscle; c, assembling reinforcement cylinder at prefabricated platform for making at the construction field (site); d, the assembling reinforcement ring muscle in the main reinforcement and additional muscle of precast concrete pier surrounding; stirrup presses the elongated arrangement of pillar height; e, prefabricated protective layer cushion block is tied up a banding fixed on stirrup with 3#, completes the binding of pre-fabricated one beam column core space reinforcing bar.The pre-fabricated one beam column core space reinforcing bar binding construction method of the present invention has stirrup cylinder pre-formed, easy to operate, easy to control the quality, accelerates construction progress, and saving is artificial, and construction is fast, efficient, improves the advantages of reinforcing bar operating rate is with engineering cost is reduced.

Description

Pre-fabricated one beam column core space reinforcing bar binding construction method
Technical field
The present invention relates to the method for binding reinforcing steel bars in a kind of reinforced concrete structure, specifically, being a kind of precast frame Structure Beam-column core space reinforcing bar binding construction method.
Background technology
In many China Democratic National Construction Association's projects built, the binding of bean column node reinforcing bar is always the difficult point of construction site.In reinforcement construction mistake Cheng Zhong, beam column node core area reinforcing bar is intensive, is particularly in the pillar at intermediate position, and beam column reinforcing bar is crisscross, and beam is indulged It to be placed on inside column longitudinal reinforcement to steel bar stress, intersect in groined type, the reinforcing bar binding of such pillar is not just put just.In frame In structure construction, unit in charge of construction personnel, which generally take, first installs beam-slab template, then binds installation beam steel, waits for reinforcement installation knot Beam, then whole heavy beam, such node area stirrup can not just bind, cause beam column nodal point area to occur not putting, put less or i.e. Make to put, and mixed and disorderly is crowded together.Can thus reinforced bar engineering be caused to do over again, cause economic loss or leave structural hidden danger.
Therefore known pre-fabricated one beam column core space reinforcing bar binding form of construction work there is above-mentioned various inconvenient and Problem.
Invention content
The purpose of the present invention is to propose a kind of precast frame improving construction site reinforcing bar concealment acceptance First Pass Yield Structure Beam-column core space reinforcing bar binding construction method.
To achieve the above object, technical solution of the invention is:
A kind of pre-fabricated one beam column core space reinforcing bar binding construction method, it is characterised in that include the following steps:
A, precast concrete pier and several protective layer cushion blocks
Precast concrete pier and several protective layer cushion blocks, according to the prefabricated cross section of drawing frame beam column size at the mixed of square Solidifying knoll platform, and according to the frame column type of layout design, cross dimension and column angle muscle outer edge size, determine frame column steel The main reinforcement of muscle and the jack position of additional muscle, quantity;Protective layer cushion block is several equirotal concrete pads;
B, pre-fabricated one beam column core space reinforcing bar ring muscle
It is required according to preformed core area reinforcing bar cylinder design drawing, blanking preformed core area reinforcing bar ring muscle;
C, assembling reinforcement cylinder at prefabricated platform for making at the construction field (site)
The main reinforcement and additional muscle of frame column reinforcing bar are inserted into the jack that precast concrete pier surface programming is set, main reinforcement is diameter The reinforcing bar of 20mm, additional bar use the reinforcing bar of diameter 10mm;The length of main reinforcement and additional muscle is more than frame column and depth of beam 150mm is convenient for and frame column reinforcing bar banding fixed;
D, the assembling reinforcement ring muscle in the main reinforcement and additional muscle of precast concrete pier surrounding, stirrup press the elongated arrangement of pillar height;
E, prefabricated protective layer cushion block with a banding fixed is tied up on stirrup, every layer of stirrup binds a block protection layer cushion block, complete It is bound at pre-fabricated one beam column core space reinforcing bar.
The pre-fabricated one beam column core space reinforcing bar binding construction method of the present invention can also be arranged using technology below It applies to further realize.
Method above-mentioned, wherein the concrete pier base size is 1000*1000*200mm.
Method above-mentioned, wherein jack depth >=150mm.
Method above-mentioned, wherein the main reinforcement and additional muscle of the concrete pier base frame column reinforcing bar of the square are tied up with silk is tied up It binds together.
Method above-mentioned, wherein the mutual spacing of the stirrup is 100mm.
Method above-mentioned, wherein the thickness 25mm of the protective layer cushion block, length and width is respectively 30mm*50mm.
After adopting the above technical scheme, the pre-fabricated one beam column core space reinforcing bar binding construction method of the present invention has Following advantages:
1, stirrup cylinder is pre-formed, easy to operate, easy to control the quality:It is not by form fixer that Prefabricated integral stirrup cylinder, which exempts from technology for binding, Degree system uses the high method for binding reinforcing steel bars of frame, reinforcing bar process of binding to be conveniently operated while beam column template formwork on plate, to Joint cores reinforcing bar can be easy to binding in place, thoroughly solve common quality defect existing for bean column node stirrup, improve structure The intensity and anti-seismic performance of bean column node;
2, it accelerates construction progress:It is fine strain of millet end template after installation is complete that bean column node reinforcing bar, which binds usual technique, first binds grid beam steel Muscle, bean column node construction can be controlled reliably;
3, it saves manually, construction is fast, efficient, improves reinforcing bar operating rate, reduces engineering cost.
Description of the drawings
Fig. 1 is the concrete pier base structural schematic diagram of the embodiment of the present invention;
Fig. 2 is that the pre-fabricated one beam column core space reinforcing bar of the embodiment of the present invention binds schematic diagram.
In figure:1 additional muscle, 2 main reinforcements, 3 stirrups, 4 protective layer cushion blocks, 5 concrete pier bases, 6 jacks.
Specific implementation mode
With reference to embodiments and its attached drawing illustrates further the present invention.
Embodiment 1
The pre-fabricated one beam column core space reinforcing bar binding construction method of the present invention, includes the following steps:
A, precast concrete pier and several protective layer cushion blocks
It is the concrete pier base structural schematic diagram of the embodiment of the present invention referring now to Fig. 1, Fig. 1.Precast concrete pier and several Protective layer cushion block, according to the prefabricated cross section of drawing frame beam column size at the concrete pier base 5 of square, and according to layout design Frame column type, cross dimension and column angle muscle outer edge size, determine the main reinforcement of frame column reinforcing bar and the jack 6 of additional muscle Position, quantity;The jack depth is 150mm.The concrete pier base size is 1000*1000*200mm.Protective layer pad Block is several equirotal concrete pads, and thickness 25mm, length and width is respectively 30mm*50mm.
B, pre-fabricated one beam column core space reinforcing bar ring muscle
It is required according to preformed core area reinforcing bar cylinder design drawing, blanking preformed core area reinforcing bar ring muscle 3.
C, assembling reinforcement cylinder at prefabricated platform for making at the construction field (site)
Fig. 2 is that the pre-fabricated one beam column core space reinforcing bar of the embodiment of the present invention binds schematic diagram.Precast concrete pier table The main reinforcement 2 and additional muscle 1 of frame column reinforcing bar are inserted into the jack that face pre-sets, main reinforcement 2 is the reinforcing bar of diameter 20mm, additional muscle 2 Using the reinforcing bar of diameter 10mm;The length of main reinforcement and additional muscle is more than frame column and depth of beam 150mm, is convenient for and frame column reinforcing bar Banding fixed;The main reinforcement and additional muscle of the concrete pier base frame column reinforcing bar of the square tie up silk binding together with 3#.
D, the assembling reinforcement ring muscle 3 in the main reinforcement and additional muscle of precast concrete pier surrounding, stirrup are elongated by pillar height The mutual spacing of arrangement, the stirrup is 100mm.
E, prefabricated protective layer cushion block 4 is tied up a banding fixed on stirrup with 3#, every layer of stirrup binds a block protection layer Cushion block completes the binding of pre-fabricated one beam column core space reinforcing bar.
It can determine jack number according to the frame column type and column angle muscle outer edge size of layout design in the present embodiment Amount arranges adjustment jack according to frame column cross dimensions.
The present invention has substantive distinguishing features and significant technological progress, pre-fabricated one beam column core space steel of the invention Muscle binding construction method uses preformed core area stirrup reinforcing bar cylinder, saves manually, and construction is fast, efficient, improves reinforcing bar operating rate, It can effectively avoid the binding of core space stirrup chaotic, overcome stirrup spacing mass defect unevenly distributed, enhance setting for Column border node Count effect.
Above example is used for illustrative purposes only rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent Technical solution should also belong to scope of the invention, should be limited by each claim.

Claims (6)

1. a kind of pre-fabricated one beam column core space reinforcing bar binding construction method, it is characterised in that include the following steps:
A, precast concrete pier and several protective layer cushion blocks
Precast concrete pier and several protective layer cushion blocks, according to the prefabricated cross section of drawing frame beam column size at the mixed of square Solidifying knoll platform, and according to the frame column type of layout design, cross dimension and column angle muscle outer edge size, determine frame column steel The main reinforcement of muscle and the jack position of additional muscle, quantity;Protective layer cushion block is several equirotal concrete pads;
B, pre-fabricated one beam column core space reinforcing bar ring muscle
It is required according to preformed core area reinforcing bar cylinder design drawing, blanking preformed core area reinforcing bar ring muscle;
C, assembling reinforcement cylinder at prefabricated platform for making at the construction field (site)
The main reinforcement and additional muscle of frame column reinforcing bar are inserted into the jack that precast concrete pier surface programming is set, main reinforcement is diameter The reinforcing bar of 20mm, additional bar use the reinforcing bar of diameter 10mm;The length of main reinforcement and additional muscle is more than frame column and depth of beam 150mm is convenient for and frame column reinforcing bar banding fixed;
D, the assembling reinforcement ring muscle in the main reinforcement and additional muscle of precast concrete pier surrounding, stirrup press the elongated arrangement of pillar height;
E, prefabricated protective layer cushion block with a banding fixed is tied up on stirrup, every layer of stirrup binds a block protection layer cushion block, complete It is bound at pre-fabricated one beam column core space reinforcing bar.
2. pre-fabricated one beam column core space reinforcing bar binding construction method as described in claim 1, which is characterized in that described Concrete pier base size is 1000*1000*200mm.
3. pre-fabricated one beam column core space reinforcing bar binding construction method as described in claim 1, which is characterized in that described Jack depth >=150mm.
4. pre-fabricated one beam column core space reinforcing bar binding construction method as described in claim 1, which is characterized in that described The main reinforcement and additional muscle of the concrete pier base frame column reinforcing bar of square are bound together with silk is tied up.
5. pre-fabricated one beam column core space reinforcing bar binding construction method as described in claim 1, which is characterized in that described The mutual spacing of stirrup is 100mm.
6. pre-fabricated one beam column core space reinforcing bar binding construction method as described in claim 1, which is characterized in that described The thickness 25mm of protective layer cushion block, length and width are respectively 30mm*50mm.
CN201710251754.8A 2017-04-18 2017-04-18 Pre-fabricated one beam column core space reinforcing bar binding construction method Pending CN108729645A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710251754.8A CN108729645A (en) 2017-04-18 2017-04-18 Pre-fabricated one beam column core space reinforcing bar binding construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710251754.8A CN108729645A (en) 2017-04-18 2017-04-18 Pre-fabricated one beam column core space reinforcing bar binding construction method

Publications (1)

Publication Number Publication Date
CN108729645A true CN108729645A (en) 2018-11-02

Family

ID=63925116

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710251754.8A Pending CN108729645A (en) 2017-04-18 2017-04-18 Pre-fabricated one beam column core space reinforcing bar binding construction method

Country Status (1)

Country Link
CN (1) CN108729645A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114922351A (en) * 2022-07-01 2022-08-19 瑞洲建设集团有限公司 Construction method of bidirectional protective layer cushion block for column and beam steel bar

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0693657A (en) * 1992-09-11 1994-04-05 Taisei Corp Half pc beam end structure and panel zone resinforcement method
JP2000273946A (en) * 1999-03-25 2000-10-03 Kumagai Gumi Co Ltd Method for constructing reinforced concrete structure
CN203238780U (en) * 2013-03-12 2013-10-16 中国水利水电第二工程局有限公司 Prefabricated stirrup cage of beam column core area
CN103590496A (en) * 2013-11-01 2014-02-19 广西建工集团第五建筑工程有限责任公司 Beam and column joint stirrup framework and method for installing beam and column joint steel bars by using same
CN203531248U (en) * 2013-08-27 2014-04-09 中国建筑第二工程局有限公司 Stirrup setting structure in core area of beam column
CN105297919A (en) * 2015-10-30 2016-02-03 中国十七冶集团有限公司 Seismic strengthening method for frame beam-column joint core area

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0693657A (en) * 1992-09-11 1994-04-05 Taisei Corp Half pc beam end structure and panel zone resinforcement method
JP2000273946A (en) * 1999-03-25 2000-10-03 Kumagai Gumi Co Ltd Method for constructing reinforced concrete structure
CN203238780U (en) * 2013-03-12 2013-10-16 中国水利水电第二工程局有限公司 Prefabricated stirrup cage of beam column core area
CN203531248U (en) * 2013-08-27 2014-04-09 中国建筑第二工程局有限公司 Stirrup setting structure in core area of beam column
CN103590496A (en) * 2013-11-01 2014-02-19 广西建工集团第五建筑工程有限责任公司 Beam and column joint stirrup framework and method for installing beam and column joint steel bars by using same
CN105297919A (en) * 2015-10-30 2016-02-03 中国十七冶集团有限公司 Seismic strengthening method for frame beam-column joint core area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114922351A (en) * 2022-07-01 2022-08-19 瑞洲建设集团有限公司 Construction method of bidirectional protective layer cushion block for column and beam steel bar

Similar Documents

Publication Publication Date Title
CN106677069A (en) Construction method for overall formwork one-time forming structure of pier
CN105908864B (en) Fill masonry and the construction method of frame-shear wall prevention Interface Crack structure
US10087106B2 (en) Method of constructing an axial compression steel tubular column
CN104947831A (en) Prefabricated assembly type profile steel concrete shear wall and construction method thereof
US10087629B2 (en) Seismic steel tubular column with internal local restraint and filled with high-strength compound concrete containing normal-strength demolished concrete lumps and construction process of such column
CN204920990U (en) Two lining rebar positioning fixture in tunnel
CN108265824A (en) A kind of high ductility concrete beam and column node of assembled and connection method
CN107143065A (en) Prefabricated load bearing concrete wall panel combining structure and construction method
CN103938871B (en) A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint
CN208502075U (en) A kind of constructional column upper reinforcement connection pre-embedded device
CN108729645A (en) Pre-fabricated one beam column core space reinforcing bar binding construction method
CN110130534A (en) A kind of novel energy-consumption precast shear wall and its processing installation method
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
CN109138280A (en) A kind of concrete pad and its application in control bar spacing, slab thickness
CN205476487U (en) Dismantled cyclic utilization device of centre form come -up is packed to control light block
CN108425507A (en) A method of using UHPC reinforced concrete columns
CN108316150A (en) The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam
CN104563496A (en) Construction structure of cylindrical die
CN104947853B (en) A kind of Inner standpipe formula cast-in-situ reinforced concrete column and construction method
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
JP3416612B2 (en) Construction method of reinforced concrete columns
CN201184019Y (en) Reinforcing steel bar expose-proof fixing body
CN204899041U (en) Protective layer control split heads about board muscle
CN110094015A (en) A kind of complex beam-column structure of construction
CN104988943B (en) A kind of concrete foundation pressure-resisting plate Steel bar rack and binding method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181102

RJ01 Rejection of invention patent application after publication