CN108533272A - A kind of minimum clear-distance tunnel goes out cavity construction method - Google Patents

A kind of minimum clear-distance tunnel goes out cavity construction method Download PDF

Info

Publication number
CN108533272A
CN108533272A CN201810278614.4A CN201810278614A CN108533272A CN 108533272 A CN108533272 A CN 108533272A CN 201810278614 A CN201810278614 A CN 201810278614A CN 108533272 A CN108533272 A CN 108533272A
Authority
CN
China
Prior art keywords
line
section
tunnel
hole
top bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810278614.4A
Other languages
Chinese (zh)
Other versions
CN108533272B (en
Inventor
母进伟
张学民
杨旭
陈进
韩光钦
袁立
胡涛
杨国富
许召强
阳军生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Guizhou Highway Engineering Group Co Ltd
Original Assignee
Central South University
Guizhou Highway Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University, Guizhou Highway Engineering Group Co Ltd filed Critical Central South University
Priority to CN201810278614.4A priority Critical patent/CN108533272B/en
Publication of CN108533272A publication Critical patent/CN108533272A/en
Application granted granted Critical
Publication of CN108533272B publication Critical patent/CN108533272B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention provides a kind of minimum clear-distance tunnels to go out cavity construction method, belongs to small-clear-distance tunnel and appears technical field of construction, includes the following steps:Left line top bar section is excavated, excavates that left line gets out of a predicament or an embarrassing situation left section and left line is got out of a predicament or an embarrassing situation right section respectively;Left line inverted arch and left line filled layer are applied, left line secondary lining is beaten in jump;The small pilot tunnel section of right line is excavated, the right section of right line top bar, the left section of right line top bar and right line top bar left hand edge section is digged respectively, applies right line top bar preliminary bracing;Small pilot tunnel preliminary bracing is removed, excavates that right line gets out of a predicament or an embarrassing situation left section and right line is got out of a predicament or an embarrassing situation right section, applies the preliminary bracing of right line lower face;Right line inverted arch and right line filled layer are applied, whole mould builds right line secondary lining.The present invention is unidirectionally appeared using leading hole, solves the problems, such as that the construction of outlet section steep cliff is inconvenient;Centering rock pillar is reinforced after left wide open digging, and the lining of left line two is beaten in jump, and right hole is appeared using advanced small pilot tunnel, and section digs, and reduces construction risk, ensures safety for tunnel engineering.

Description

A kind of minimum clear-distance tunnel goes out cavity construction method
Technical field
It appears technical field of construction the present invention relates to small-clear-distance tunnel, particularly, is related to a kind of minimum clear-distance tunnel and appears Construction method.
Background technology
In the prior art, the considerations of being limited for layout of roads demand and landform, traffic route is inevitably adopted sometimes Take small-clear-distance tunnel.The problem of traditional small-clear-distance tunnel influences each other there is structure safety and construction, it is necessary to take measures It solves.
The old toft tunnel overall length about 393m of Guizhou Province Xingyi belt high speed, for the formula short tunnel that diverges.Its tunnel line spacing goes out Mouthful section is minimized profile line clear distance 0.6m, is then drifted apart from as minimum clear distance, small interval, separate tunnel, between inducer line Away from about 35m.It is Maling River Gorge after tunnel outlet, outlet section construction and excavation is inconvenient.
When conventional double-hole tunnel interval rock thickness is less than 2 meters, all using structure of twin-arch tunnel with composite middle partition wall. The structure has following deficiency:(1) excavated volume is larger, and material input amount is big.The excavation for first carrying out small pilot tunnel, interval pillar is replaced At intensity, the higher armored concrete of rigidity, the excavated volume of the cubic metre of earth and stone is increased, while also increasing the amount of pouring of concrete.(2) face When support it is more, dismounting it is cumbersome.Due to first carrying out the excavation of small pilot tunnel, preliminary bracing is carried out to it, while to prevent mid-board It is not destroyed, to carrying out unilateral plus cross-brace on the right side of middle drift;In addition, when carrying out the excavation of main hole side pilot tunnel, to prevent Larger sedimentation convergence occurs for country rock, ensures construction safety, has also carried out applying for temporary support.Before applying two linings, these face When support must all be removed.(3) waterproof problem of the multiple-arch tunnel in middle wall top portion is difficult to solve, and cannot be formed perfect anti- Drainage system is easy leak, has seriously affected the applicability and durability in tunnel after building up.(4) construction period is longer, cost compared with It is high.The construction of small pilot tunnel is carried out, supporting could carry out the construction in main hole after applying;The construction and dismounting of temporary support, increase Construction workload delays the construction period.And tunnel exit end orographic condition is more severe, construction site difficulty is carried out, each material The transfer (turning to outlet from import) of the input of material, the input of labour and big machinery, goods and materials is so that cost is very high.
Using traditional multiple-arch tunnel form, working procedure is more, and structure stress is complicated, long in time limit, and cost is high.
Number of patent application is that the patent of CN201410708082.5 discloses a kind of steep cliffs tunnel outlet engineering method, barrel It is excavated using interval wall approach, and carries out gib and preliminary bracing.When face is away from outlet cavitation face 7-9m, in upper Small pilot tunnel is appeared from inside to outside to hole, then digs barrel or more section to hole to both sides, this method is led in advance in excavation When hole, Portal Section unstability is easily caused.
The patent that number of patent application is CN201210036640.9 discloses the wide open excavation of row after a kind of minimum clear-distance tunnel Method beats shock relieve vent along close to mid-board side at gang drill first, and Cut Blasting is carried out simultaneously to 1-2m is deviateed far from mid-board side Scarfing cinder.Then to rear row hole perimeter blasting scarfing cinder.Last centering dike carries out grouting and reinforcing.This method one side shock relieve vent reduces Effect is limited, influence of the wide open digging of row to leading hole surrouding rock deformation after controlled blasting cannot reduce.
Invention content
Present invention aims at a kind of minimum clear-distance tunnels of offer to go out cavity construction method, to solve existing minimum clear-distance tunnel It is more to go out cavity construction method working procedure, structure stress is complicated, long in time limit, the high technical problem of cost.
To achieve the above object, the present invention provides a kind of minimum clear-distance tunnels to go out cavity construction method, includes the following steps:
Step 1:Left line top bar section is excavated, left line top bar preliminary bracing is applied, left line top bar preliminary bracing is adopted With Length discrepancy bolt anchorage, excavate that left line gets out of a predicament or an embarrassing situation left section and left line is got out of a predicament or an embarrassing situation right section respectively, left line is got out of a predicament or an embarrassing situation left section It is staggered excavation with left line right section of getting out of a predicament or an embarrassing situation, the distance that is staggered about 5~15m applies left line and gets out of a predicament or an embarrassing situation preliminary bracing, middle thickness To carry out grouting and reinforcing when 0.6~3.0m;
Step 2:Left line inverted arch and left line filled layer are applied, left line secondary lining is beaten in jump, and left line hole inverted arch and left line are filled out It fills after the completion of layer, secondary lining trolley, which is moved to left line, to be exported, and the secondary lining of left line Portal Section is preferentially performed;
Step 3:The small pilot tunnel section of right line is excavated, small pilot tunnel preliminary bracing is applied;
Step 4:It is disconnected that the right section of right line top bar, the left section of right line top bar and right line top bar left hand edge are digged respectively Face, applies right line top bar preliminary bracing, and right line top bar preliminary bracing uses Length discrepancy bolt anchorage;
Step 5:Small pilot tunnel preliminary bracing is removed, excavates that right line gets out of a predicament or an embarrassing situation left section and right line is got out of a predicament or an embarrassing situation right section respectively, Apply the preliminary bracing of right line lower face;
Step 6:Right line inverted arch and right line filled layer are applied, whole mould builds right line secondary lining.
The left hole is appeared using double advanced conduit, and advanced conduit specification is diameter 42mm, thick 4mm, the heat of long 4.0m Roll seamless steel pipe;Advanced conduit note proportioning is 1:0.7 non-shrinkage mud after the completion of mud jacking, is carried out in advanced catheter tip It blocks.
Double advanced conduit includes platoon leader's advanced tubule and the short advanced tubule of a row, the outer limb of long advanced tubule Degree is 30 ° -40 °, is applied per Pin, and circumferential spacing is 40 ㎝, and longitudinal pitch is 240 ㎝;Short advanced tubule extrapolation angle is It 10 ° -15 °, is applied every Pin, alternately long advanced tubule arrangement, circumferential spacing is 40 ㎝, and longitudinal pitch is 120 ㎝.
The advanced conduit includes steel pipe, is provided with injected hole on steel pipe, and steel pipe tail portion is welded with hoop of putting more energy into, injected hole with Distance between injected hole (15) is 10~20cm, and injected hole is set as blossom type, a diameter of 6~8mm of injected hole.
The wide open digging control process in a left side is, when left and right tunnel clear distance is 1.79m-1.48m, cyclic advance 2.4m, It is excavated using two benching tunnelling methods, top bar height 6.8m;When left and right tunnel clear distance is 1.48m-1.17m, cyclic advance 1.8m, It is excavated using two benching tunnelling methods, top bar height 6.8m;When left and right tunnel clear distance is 1.17m-0.88m, cyclic advance 1.2m, It is excavated using three benching tunnelling methods, top bar height 3-4m, weak blast;When left and right tunnel clear distance is 0.88m-0.59m, cyclic advance It for 0.6m, is excavated using three benching tunnelling methods, top bar height 3-4m, weak blast, outlet section uses active protecting net;Left hole outlet two The lining of mould two need to be completed before You Dong appears, and left hole inverted arch needs advanced right hole.
The left and right line top bar preliminary bracing uses the method that long Short bolt combines, and trigonum uses at the top of middle rock pillar The hollow grouting anchor of Length discrepancy (4-6m) carries out reinforcing
The grouting and reinforcing of the middle rock pillar uses φ for 42mm, and thickness is the slip casting ductule of 4mm, and slip casting ductule is circumferential Spacing is 120cm, longitudinal pitch 60cm, and whole is in quincuncial arrangement, and slurries use 1:0.7 superfine cement single slurry, note Slurry pressure is 1~1.5Mpa;Slip casting ductule is 45 ° with tunnel axial angle.
Increase advanced inspecting hole 6,3 radial direction advanced inspecting holes when leading tunnel outlet is away from hole 10m, 3 levels are visited in advance Hole.
Face closure will be excavated before the steel arch-shelf of left line inverted arch and right line inverted arch using jetting cement by applying, steel arch-shelf with get out of a predicament or an embarrassing situation Steelframe connection;It needs to clear up empty slag and ponding before applying left line inverted arch or right line inverted arch.
The wide 7.0m of small pilot tunnel, the high 4.5m, small pilot tunnel top is away from tunnel vault 2.7m, and left side is far from rock pillar in tunnel Row hole top bar digs after being carried out again after 3.9m, small pilot drive 10-15m, and when right hole top bar digs, right line top bar is right Section part uses Blasting Excavation, the right left section part of line top bar to use Presplitting Blasting Excavation, right line top bar left hand edge Section is excavated using the cold digging method of machinery.
After first having dug two sections of two linings on left line hole, the left line secondary lining for making the last period and a latter section of left side are returned again to Line secondary lining, stringent controlled blasting parameter in construction carry out monitoring of blasting vibration in blasting process, while in the construction process Monitor on time ground settlement, in hole the sedimentation of hole top, tunnel convergence deformation and steelframe internal stress data.
The invention has the advantages that:
The present invention unidirectionally appears in leading hole, solves the problems, such as that the construction of outlet section steep cliff is inconvenient;Left and right hole top bar uses The method that long Short bolt combines, rock pillar top Delta Region, provides load-carrying capacity of surrounding rock in reinforcing;After left wide open digging centering rock pillar into Row is reinforced, using superfine cement single slurry, rock pillar in effectively reinforcing;Left hole, which is jumped, in advance makes a call to two linings, controls Portal Section surrouding rock deformation, Influence of the right hole of row to leading left hole blasting vibration after avoiding;Right hole is gone afterwards using pilot heading excavation, and pilot heading can be effective Reduce the disturbance to country rock, so that it is given full play to self-bearing capacity, while stress is partially descended to discharging in advance, it can be effective Reduce the sedimentation convergence in country rock later stage;When right hole digs, using presplit blasting, controlled blasting vibration velocity;It is adopted close to middle rock pillar side With the cold digging of machinery, centering rock pillar is avoided to cause larger damage
Other than objects, features and advantages described above, the present invention also has other objects, features and advantages. Below with reference to figure, the present invention is described in further detail.
Description of the drawings
The attached drawing constituted part of this application is used to provide further understanding of the present invention, schematic reality of the invention Example and its explanation are applied for explaining the present invention, is not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is the lining construction Step design figure of the present invention, and figure (a) is left hole schematic diagram, and figure (b) is right hole schematic diagram;
Fig. 2 is that the middle rock pillar of the present invention reinforces schematic diagram, and figure (a) is left hole schematic diagram, and figure (b) is right hole schematic diagram;
Fig. 3 is the hollow grouting anchor and the more than schematic diagram of slip casting ductule of the present invention;
Fig. 4 is the lining cutting bilayer advanced tubule layout drawing of the present invention;
Fig. 5 is that the left line of the present invention is appeared on the stage stage face sectional view;
Fig. 6 is the construction section of the present invention away from figure;
Fig. 7 is the steel floral tube structural schematic diagram of the present invention;
Fig. 8 is the horizontal inspecting hole arrangement schematic diagram of the present invention.
Figure label:1 left line top bar preliminary bracing, 2 left lines are got out of a predicament or an embarrassing situation preliminary bracing, 21 left line inverted arch, 3 left lines fillings Layer, 4 left line secondary linings, 5 small pilot tunnel preliminary bracings, 6 right line top bar preliminary bracings, 7 right line lower face preliminary bracings, 71 right sides Line inverted arch, 8 right line filled layers, 9 right line secondary linings, 10 slip casting ductules, 11 hollow grouting anchors, 12 long advanced tubules, 13 short advanced tubules, 14 I-steel, 15 injected holes, 16 steel pipes, 17 put more energy into hoop, I left line top bar section, II 1 left lines are left office Get out of a predicament or an embarrassing situation right section, the small pilot tunnel section of III right line, the right section of IV 1 right line top bars, IV 2 right lines of the left section of rank, II 2 left lines are appeared on the stage Get out of a predicament or an embarrassing situation left section, V 2 right lines of the left section of rank, IV 3 right line top bar left hand edge sections, V 1 right lines are got out of a predicament or an embarrassing situation right section.
Specific implementation mode
The embodiment of the present invention is described in detail below in conjunction with attached drawing, but the present invention can be limited according to claim Fixed and covering multitude of different ways is implemented.
A kind of minimum clear-distance tunnel goes out cavity construction method, and embodiment is said by the tunnelling process of practical application It is bright.That implement is the construction old toft tunnel overall length about 393m of Guizhou Province Xingyi belt high speed, for the formula short tunnel that diverges.Its tunnel line Spacing outlet section is minimized profile line clear distance 0.6m, is then drifted apart from as minimum clear distance, small interval, separate tunnel, import Section line is spaced about 35m.During practice of construction, significant effect, the existing minimum clear-distance tunnel of solution, which goes out cavity construction method, to be applied Work process is more, and structure stress is complicated, long in time limit, the high technical problem of cost, has good economic benefit.As shown in figures 1-8, Working procedure includes the following steps:
Step 1:Left line top bar section I is excavated, left line top bar preliminary bracing 1 is applied, excavates left line respectively and get out of a predicament or an embarrassing situation Left section II 1 and left line are got out of a predicament or an embarrassing situation right section II 2, and left line gets out of a predicament or an embarrassing situation left section II 1 and left line is got out of a predicament or an embarrassing situation, and right section II 2 is staggered out It digs, the distance that is staggered about 5~15m applies left line and gets out of a predicament or an embarrassing situation preliminary bracing 2, slip casting is carried out when middle thickness is 0.6~3.0m and is added Gu.
Step 2:Left line inverted arch 21 and left line filled layer 3 are applied, whole mould builds left line secondary lining 4.
Step 3:The small pilot tunnel section III of right line is excavated, small pilot tunnel preliminary bracing 5 is applied.
Step 4:It is left that the right section IV 1 of right line top bar, the left section IV 2 of right line top bar and right line top bar are digged respectively Edge section IV 3 applies right line top bar preliminary bracing 6.
Step 5:Remove small pilot tunnel preliminary bracing 5, excavate respectively right line get out of a predicament or an embarrassing situation left section V 1 and right line get out of a predicament or an embarrassing situation it is right disconnected Face V 2 applies right line lower face preliminary bracing 7.
Step 6:Right line inverted arch 7 and right line filled layer 8 are applied, whole mould builds right line secondary lining 9.
Extra small clear-distance tunnel appear construction be using to " middle rock pillar " consolidation process and using controlled blasting to left and right hole mistake A kind of construction technology that position excavating load is combined.As left hole " up/down steps excavate, and unidirectionally appear ";Carry out " small pilot tunnel in right hole In advance, rear section digs " construction and excavation technology
Up/down steps excavate, and for left hole, are excavated using benching tunneling method, are the parts 0.6~3.0m in middle thickness Carry out grouting and reinforcing.It unidirectionally appears, top bar is appeared using the double-deck ductule advance support, and appropriate reduction top bar of appearing is closed on Highly, weak blast, reduce hole to greatest extent and face upward slope influence, prevent slungshot from falling valley using active protecting net in outlet end. Small pilot tunnel is leading, small area tunneling, applies supporting and forms small pilot tunnel.The excavation of small pilot tunnel can be effectively reduced to country rock Disturbance, makes it give full play to self-bearing capacity, while partially descending stress to discharging in advance, can effectively reduce the country rock later stage Sedimentation convergence, ensure construction safety.Construction operation in small pilot tunnel, the appropriate intensity for reinforcing rock pillar, to improve holding for rock pillar Loading capability reduces disturbance of the subsequent construction to country rock, avoids causing roof fall, cave-in accident.Section digs, and small pilot tunnel is digged to just Normal off face, applies Tunnel.After rock pillar reinforcing, using rock drill or hand excavation close to the rock mass of rock pillar side, Blasting method excavation can be used far from rock pillar side, when excavation must be noted that the protection (using weak blast) to interval pillar.It opens Supporting is carried out after digging in time, especially proximate to rock pillar side rock mass, temporary support can be increased when necessary or increase supporting intensity.
Technology safeguard measure
1) the left hole in leading hole is appeared using double advanced conduit, and advanced tubule specification is diameter 42mm, thick 4mm, 4.0m Hot rolled seamless steel tube.Make sharp cone distal, tail portion welding in ductule front endReinforcing bar is put more energy into hoop, on tube wall every 10~ 20cm blossom type jewel holes, a diameter of 6~8mm of eyelet, tail length is not less than 30cm as the only slurry section not drilled.
2) the double-deck advanced tubule injection angle is:Tiltedly advanced conduit extrapolation angle is 40o, is applied per Pin.It is horizontal advanced Conduit extrapolation angle is 15o, applies, is alternately arranged every Pin.Advance support ductule end is welded with steel arch-shelf after the completion of injection Get up.
3) slip casting.Advance support ductule ensures that pressure injection proportioning is 1:0.7 cement mortar.After the completion of mud jacking, noting in advance Slurry ductule end is effectively blocked.Grouting pump, Grouting Pipe and the ductule of grouting methol take reliable connection.
4) left wide open digging control
5) both sides of getting out of a predicament or an embarrassing situation are staggered excavation, the distance that is staggered about 5~15m.
6) rock pillar uses φ for 42mm in reinforcing, and thickness is the slip casting ductule of 4mm, and ductule circumferential direction spacing is 120cm, Longitudinal pitch is 60cm, and whole is in quincuncial arrangement, and slurries use 1:0.7 superfine cement single slurry, grouting pressure be 1~ 1.5MPa。
7) grouting pipe that rock pillar is reinforced in is 45 ° with tunnel axial angle.
8) leading tunnel outlet away from hole 10m when increase advanced inspecting hole 6,3 advanced inspecting holes of radial direction, 3 levels are advanced Inspecting hole.
9) use jetting cement that will excavate face closure before applying steel arch-shelf.
9) inverted arch construction ensures that steel arch-shelf is effectively connect with steelframe of getting out of a predicament or an embarrassing situation.
10) it needs to clear up empty slag and ponding before inverted arch performs.
11) right hole YK15+627-YK15+677 sections, specific section reference symbol enters Figure of description diagram, starts using advanced Small pilot drive.
12) the advanced small wide 7.0m of pilot tunnel, high 4.5m, pilot heading top is away from tunnel vault 2.7m, and left side is far from tunnel Zhong Yan Column 3.9m.
13) row hole top bar digs after being carried out again after the advanced small pilot drive 10-15m in row hole afterwards
14) when right hole top bar digs, the parts IV1 use Blasting Excavation, the parts IV2 that Presplitting Blasting Excavation, IV3 is used to adopt It is excavated with the cold digging method of machinery.
15) when the lining of left hole two is excavated to ZK15+640, two lining of pause performs, and two lining trolleys are then moved on to hole, are performed Portal Section ZK15+697~679 2 is served as a contrast, and is then back to ZK15+640 and is performed two linings.
16) when gunite concrete, ensure closely knit no cavity everywhere;
17) stringent controlled blasting parameter in constructing carries out monitoring of blasting vibration in the process, reduces disturbing for explosion centering dike Dynamic and tunnel-liner influence;
18) ground settlement, the sedimentation of hole top, tunnel convergence deformation and steelframe internal stress in hole are monitored on time in the construction process Deng data, to effectively avoid due to the raw construction risk of rear row hole construction, it is ensured that construction safety
The present invention is by using small-clear-distance tunnel construction form rather than multiple-arch tunnel form;Row hole is to leading hole after control Surrouding rock deformation, the influence of support earth pressure, blasting vibration.
Leading hole is excavated using up/down steps, double advanced tubule supporting is unidirectionally appeared.
To carrying out rock pillar in grouting with small pipe on the right side of leading hole, slurries use superfine cement single slurry, grouting pressure 1.0 ~1.5MPa.Grouting Pipe circumferential direction spacing and longitudinal pitch are respectively 0.8m and 0.6m, and grouting pipe uses 42 steel floral tube.
Pre-pouring grout construction technology and construction parameter are strictly controlled in work progress, especially middle dike grouting parameter, it is ensured that Grouting quality;Stringent controlled blasting parameter in construction carries out monitoring of blasting vibration in the process, reduces the disturbance of explosion centering dike With the influence of tunnel-liner;Step pitch is excavated in stringent control, and supporting is closely followed, and reduces country rock exposure duration;When gunite concrete, ensure Closely knit no cavity everywhere;When inverted arch is constructed, it is ensured that steel arch-shelf is effectively connect with steelframe of getting out of a predicament or an embarrassing situation, and clears up empty slag and ponding.It applies Face closure will be excavated using jetting cement before steel arch-shelf.When tunnel outlet, stringent control loop drilling depth and excavation height, supporting are closely followed And stringent control sets up precision, prevents tunnel bias-pressure phenomenon.Monitor ground settlement, hole top in hole on time in the construction process The data of sedimentation, tunnel convergence deformation and steelframe internal stress etc..
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, any made by repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of minimum clear-distance tunnel goes out cavity construction method, which is characterized in that include the following steps:
Step 1:Left line top bar section (I) is excavated, left line top bar preliminary bracing (1), left line top bar preliminary bracing are applied (1) Length discrepancy bolt anchorage is used, excavates that left line gets out of a predicament or an embarrassing situation left section (II 1) and left line is got out of a predicament or an embarrassing situation right section (II 2), a left side respectively Line gets out of a predicament or an embarrassing situation left section (II 1) and left line is got out of a predicament or an embarrassing situation right section (II 2) is staggered excavation, the distance that is staggered about 5~15m apply left line It gets out of a predicament or an embarrassing situation preliminary bracing (2), middle thickness carries out grouting and reinforcing when being 0.6~3.0m;
Step 2:Left line inverted arch (21) and left line filled layer (3) are applied, left line secondary lining (4), left line hole inverted arch are beaten in jump (21) and after the completion of left line filled layer (3), secondary lining trolley is moved into left line and is exported, the secondary of left line Portal Section is preferentially performed Lining cutting (4);
Step 3:The small pilot tunnel section (III) of right line is excavated, small pilot tunnel preliminary bracing (5) is applied;
Step 4:It is left that the right right section of line top bar (IV 1), the right left section of line top bar (IV 2) and right line top bar are digged respectively Edge section (IV 3), applies right line top bar preliminary bracing (6), and right line top bar preliminary bracing (6) is added using Length discrepancy anchor pole Gu;
Step 5:Remove small pilot tunnel preliminary bracing (5), excavate respectively right line get out of a predicament or an embarrassing situation left section (V 1) and right line get out of a predicament or an embarrassing situation it is right disconnected Face (V 2) applies right line lower face preliminary bracing (7);
Step 6:Right line inverted arch (7) and right line filled layer (8) are applied, whole mould builds right line secondary lining (9).
2. a kind of minimum clear-distance tunnel according to claim 1 goes out cavity construction method, which is characterized in that the left hole uses Double advanced conduit is appeared, and advanced conduit specification is diameter 42mm, thick 4mm, the hot rolled seamless steel tube of long 4.0m;Advanced conduit note Proportioning is 1:0.7 non-shrinkage mud after the completion of mud jacking, is blocked in advanced catheter tip.
3. a kind of minimum clear-distance tunnel according to claim 2 goes out cavity construction method, which is characterized in that described double advanced Conduit includes platoon leader's advanced tubule (12) and the short advanced tubule of a row (13), and long advanced tubule (12) extrapolation angle is It 30 ° -40 °, is applied per Pin, circumferential spacing is 40 ㎝, and longitudinal pitch is 240 ㎝;Short advanced tubule (13) extrapolation angle is It 10 ° -15 °, is applied every Pin, alternately long advanced tubule (12) arrangement, circumferential spacing is 40 ㎝, and longitudinal pitch is 120 ㎝.
4. a kind of minimum clear-distance tunnel according to claim 2 goes out cavity construction method, which is characterized in that the advanced conduit Including steel pipe (16), injected hole (15) is provided on steel pipe (16), steel pipe (16) tail portion is welded with hoop (17) of putting more energy into, injected hole (15) between injected hole (15) at a distance from be 10~20cm, injected hole (15) is set as blossom type, injected hole (15) a diameter of 6~ 8mm。
5. a kind of minimum clear-distance tunnel according to claim 1 goes out cavity construction method, which is characterized in that the wide open digging in a left side Control process is that, when left and right tunnel clear distance is 1.79m-1.48m, cyclic advance 2.4m is excavated using two benching tunnelling methods, appeared on the stage Rank height 6.8m;When left and right tunnel clear distance is 1.48m-1.17m, cyclic advance 1.8m is excavated using two benching tunnelling methods, is appeared on the stage Rank height 6.8m;When left and right tunnel clear distance is 1.17m-0.88m, cyclic advance 1.2m is excavated using three benching tunnelling methods, is appeared on the stage Rank height 3-4m, weak blast;When left and right tunnel clear distance is 0.88m-0.59m, cyclic advance 0.6m is opened using three benching tunnelling methods It digs, top bar height 3-4m, weak blast, outlet section uses active protecting net;Two mould two of left hole outlet lining need to be before You Dong appears It completes, left hole inverted arch needs advanced right hole.
6. a kind of minimum clear-distance tunnel according to claim 1 goes out cavity construction method, which is characterized in that the middle rock pillar Grouting and reinforcing uses φ for 42mm, and thickness is the slip casting ductule (10) of 4mm, and slip casting ductule (10) circumferential direction spacing is 120cm, Longitudinal pitch is 60cm, and whole is in quincuncial arrangement, and slurries use 1:0.7 superfine cement single slurry, grouting pressure be 1~ 1.5Mpa;Slip casting ductule (10) is 45 ° with tunnel axial angle.
7. a kind of minimum clear-distance tunnel according to claim 1 goes out cavity construction method, which is characterized in that leading tunnel outlet Increase advanced inspecting hole 6,3 advanced inspecting holes of radial direction, 3 level advanced inspecting holes when away from hole 10m.
8. a kind of minimum clear-distance tunnel according to claim 1 goes out cavity construction method, which is characterized in that apply left line inverted arch (21) and before the steel arch-shelf of right line inverted arch (71) face closure will be excavated using jetting cement, steel arch-shelf is connect with the steelframe got out of a predicament or an embarrassing situation; It needs to clear up empty slag and ponding before applying left line inverted arch (21) or right line inverted arch (71).
9. a kind of minimum clear-distance tunnel according to claim 1 goes out cavity construction method, which is characterized in that the small pilot tunnel is wide 7.0m, high 4.5m, away from tunnel vault 2.7m at the top of small pilot tunnel, left side is far from rock pillar 3.9m in tunnel, after small pilot drive 10-15m Row hole top bar digs after carrying out again, and when right hole top bar digs, the right right section of line top bar (IV 1) is partly opened using explosion It digs, the right left section of line top bar (IV 2) partly uses Presplitting Blasting Excavation, right line top bar left hand edge section (IV 3) to use The cold digging method of machinery is excavated.
10. a kind of minimum clear-distance tunnel according to claim 1 goes out cavity construction method, which is characterized in that left line is got out of a predicament or an embarrassing situation After appearing, 20m (about 2 mould) secondary lining (4) is performed into hole from left hole outlet immediately, returns again in the holes Zuo Dong and performs secondary lining It builds (4), stringent controlled blasting parameter in construction, carries out monitoring of blasting vibration in blasting process, while in the construction process on time The data of whole body displacement and the strain of preliminary bracing steelframe, first branch and the contact between country rock in monitoring ground settlement, hole.
CN201810278614.4A 2018-03-30 2018-03-30 Exit construction method for tunnel with extremely small clear distance Active CN108533272B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810278614.4A CN108533272B (en) 2018-03-30 2018-03-30 Exit construction method for tunnel with extremely small clear distance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810278614.4A CN108533272B (en) 2018-03-30 2018-03-30 Exit construction method for tunnel with extremely small clear distance

Publications (2)

Publication Number Publication Date
CN108533272A true CN108533272A (en) 2018-09-14
CN108533272B CN108533272B (en) 2020-04-21

Family

ID=63482099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810278614.4A Active CN108533272B (en) 2018-03-30 2018-03-30 Exit construction method for tunnel with extremely small clear distance

Country Status (1)

Country Link
CN (1) CN108533272B (en)

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184704A (en) * 2018-09-28 2019-01-11 北京市市政三建设工程有限责任公司 A kind of small-clear-distance tunnel excavation and middle folder rock reinforcement technique
CN109339797A (en) * 2018-09-04 2019-02-15 贵州省公路工程集团有限公司 A kind of minimum clear-distance tunnel is appeared damping construction method
CN109470101A (en) * 2018-12-27 2019-03-15 中国地质大学(武汉) The research method closed on Tunnel Blasting and existing tunnel is influenced based on site-models
CN109630135A (en) * 2019-01-16 2019-04-16 交通运输部公路科学研究所 A kind of method for tunnel construction of system supporting
CN109707394A (en) * 2018-12-17 2019-05-03 同济大学 A kind of construction method for subway tunnel shield receiving end portal
CN109751063A (en) * 2019-02-26 2019-05-14 中铁第四勘察设计院集团有限公司 A kind of large section tunnel supporting construction and its construction method
CN109812277A (en) * 2019-02-28 2019-05-28 中铁十八局集团有限公司 A kind of vertical cliff tunnel active defense bimetallic tube canopy of high drop is appeared safely method
CN110017143A (en) * 2019-05-10 2019-07-16 兰州铁道设计院有限公司 A kind of auxiliary method of small interval loess tunnel construction of central division wall
CN111335914A (en) * 2020-04-09 2020-06-26 中铁二院工程集团有限责任公司 Rock pillar replacement system in weak surrounding rock small-clear-distance tunnel and construction method
CN111810200A (en) * 2020-08-11 2020-10-23 中铁第一勘察设计院集团有限公司 Shield tunnel expanding and excavating system and method based on middle upright posts and inverted arches
CN112177635A (en) * 2020-11-05 2021-01-05 中国建筑第四工程局有限公司 Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN112253176A (en) * 2020-10-29 2021-01-22 中铁第一勘察设计院集团有限公司 Combined supporting structure system for realizing large-span and small-clear-distance tunnel and construction method thereof
CN112267899A (en) * 2020-10-12 2021-01-26 广东冠粤路桥有限公司 Tunnel exit construction method
CN112443331A (en) * 2020-11-25 2021-03-05 中交路桥建设有限公司 Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN112459804A (en) * 2020-11-25 2021-03-09 中交二航局第二工程有限公司 Synchronous tunneling construction method for overlapped tunnels
CN112523759A (en) * 2020-11-30 2021-03-19 中铁十八局集团有限公司 Construction method for converting double-arch tunnel and small-clear-distance tunnel in underground transverse channel
CN112610250A (en) * 2020-12-14 2021-04-06 中铁隧道局集团有限公司 Method for dismantling three rock pillar supports of large-span underground cave depot
CN112647978A (en) * 2020-12-29 2021-04-13 中国科学院武汉岩土力学研究所 Construction method for leading small pilot tunnel of soft rock large-deformation tunnel
CN112682061A (en) * 2020-12-29 2021-04-20 四川省交通勘察设计研究院有限公司 Tunnel structure and construction method
CN112682047A (en) * 2020-12-31 2021-04-20 中铁大桥局集团第五工程有限公司 Construction method for parallel small-clear-distance tunnel
CN113153317A (en) * 2021-05-11 2021-07-23 北华航天工业学院 Construction method and grouting device suitable for soft rock large-section tunnel
CN113153375A (en) * 2021-04-08 2021-07-23 济南城建集团有限公司 Construction method of support system for preventing support drop and settlement of primary support of ultra-small clear distance tunnel of soft foundation
CN113216976A (en) * 2021-04-09 2021-08-06 中交第一公路勘察设计研究院有限公司 Tunnel HCD excavation method suitable for soft rock and gravel soil
CN113236293A (en) * 2021-03-30 2021-08-10 解长渊 Deformation control supporting method for urban trunk road weak surrounding rock shallow-buried large-span small-clear-distance tunnel
CN113431588A (en) * 2021-07-30 2021-09-24 中铁十四局集团第三工程有限公司 Construction method for branch tunnel
CN113482630A (en) * 2021-08-06 2021-10-08 中铁二局第四工程有限公司 Pilot construction method applied to small-clear-distance double-hole tunnel
CN114352291A (en) * 2022-01-07 2022-04-15 贵州路桥集团有限公司 Construction method of proximity tunnel
CN114718582A (en) * 2022-06-08 2022-07-08 中铁九局集团第七工程有限公司 Construction method for small-clear-distance horizontal joint shale geological tunnel portal section
CN114810129A (en) * 2022-06-28 2022-07-29 中铁九局集团第七工程有限公司 Construction method for shallow-buried bias section of small-clear-distance horizontal joint shale geological tunnel
CN115263319A (en) * 2022-07-06 2022-11-01 中铁一局集团(广州)建设工程有限公司 Steep-dip bedding limestone tunnel out-of-tunnel construction method
CN117780362A (en) * 2024-02-27 2024-03-29 中铁十七局集团第五工程有限公司 Rock column replacement and reinforcement structure in ultra-small clear distance tunnel and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120014283A (en) * 2010-08-09 2012-02-17 (주)현이앤씨 Method of grouting by double packer in pre-stressed tunnel and hydrauric type automatic inserting device for linear member
CN205477660U (en) * 2016-02-02 2016-08-17 中铁十九局集团轨道交通工程有限公司 Little clean apart from tunnel in rock pillar reinforcerment system
CN106640096A (en) * 2017-02-17 2017-05-10 中铁八局集团第工程有限公司 Construction method for penetrating through tunnel of backfilling soil section and transition section
CN107218044A (en) * 2017-06-20 2017-09-29 中铁十局集团有限公司 A kind of excavation method of extrusion rock small-clear-distance tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120014283A (en) * 2010-08-09 2012-02-17 (주)현이앤씨 Method of grouting by double packer in pre-stressed tunnel and hydrauric type automatic inserting device for linear member
CN205477660U (en) * 2016-02-02 2016-08-17 中铁十九局集团轨道交通工程有限公司 Little clean apart from tunnel in rock pillar reinforcerment system
CN106640096A (en) * 2017-02-17 2017-05-10 中铁八局集团第工程有限公司 Construction method for penetrating through tunnel of backfilling soil section and transition section
CN107218044A (en) * 2017-06-20 2017-09-29 中铁十局集团有限公司 A kind of excavation method of extrusion rock small-clear-distance tunnel

Cited By (44)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339797A (en) * 2018-09-04 2019-02-15 贵州省公路工程集团有限公司 A kind of minimum clear-distance tunnel is appeared damping construction method
CN109339797B (en) * 2018-09-04 2020-06-19 贵州省公路工程集团有限公司 Extremely-small-clear-distance tunnel exit shock absorption construction method
CN109184704A (en) * 2018-09-28 2019-01-11 北京市市政三建设工程有限责任公司 A kind of small-clear-distance tunnel excavation and middle folder rock reinforcement technique
CN109707394A (en) * 2018-12-17 2019-05-03 同济大学 A kind of construction method for subway tunnel shield receiving end portal
CN109470101A (en) * 2018-12-27 2019-03-15 中国地质大学(武汉) The research method closed on Tunnel Blasting and existing tunnel is influenced based on site-models
CN109630135B (en) * 2019-01-16 2021-05-25 交通运输部公路科学研究所 Tunnel construction method for system support
CN109630135A (en) * 2019-01-16 2019-04-16 交通运输部公路科学研究所 A kind of method for tunnel construction of system supporting
CN109751063A (en) * 2019-02-26 2019-05-14 中铁第四勘察设计院集团有限公司 A kind of large section tunnel supporting construction and its construction method
CN109812277A (en) * 2019-02-28 2019-05-28 中铁十八局集团有限公司 A kind of vertical cliff tunnel active defense bimetallic tube canopy of high drop is appeared safely method
CN109812277B (en) * 2019-02-28 2020-07-17 中铁十八局集团有限公司 Active protection double-layer pipe shed safety hole-exiting method for high-fall vertical suspended rock tunnel
CN110017143A (en) * 2019-05-10 2019-07-16 兰州铁道设计院有限公司 A kind of auxiliary method of small interval loess tunnel construction of central division wall
CN111335914A (en) * 2020-04-09 2020-06-26 中铁二院工程集团有限责任公司 Rock pillar replacement system in weak surrounding rock small-clear-distance tunnel and construction method
CN111810200A (en) * 2020-08-11 2020-10-23 中铁第一勘察设计院集团有限公司 Shield tunnel expanding and excavating system and method based on middle upright posts and inverted arches
CN112267899A (en) * 2020-10-12 2021-01-26 广东冠粤路桥有限公司 Tunnel exit construction method
CN112253176A (en) * 2020-10-29 2021-01-22 中铁第一勘察设计院集团有限公司 Combined supporting structure system for realizing large-span and small-clear-distance tunnel and construction method thereof
CN112177635A (en) * 2020-11-05 2021-01-05 中国建筑第四工程局有限公司 Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN112443331A (en) * 2020-11-25 2021-03-05 中交路桥建设有限公司 Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN112459804A (en) * 2020-11-25 2021-03-09 中交二航局第二工程有限公司 Synchronous tunneling construction method for overlapped tunnels
CN112443331B (en) * 2020-11-25 2022-08-23 中交路桥建设有限公司 Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN112523759A (en) * 2020-11-30 2021-03-19 中铁十八局集团有限公司 Construction method for converting double-arch tunnel and small-clear-distance tunnel in underground transverse channel
CN112523759B (en) * 2020-11-30 2022-11-08 中铁十八局集团有限公司 Construction method for converting double-arch tunnel and small-clear-distance tunnel in underground transverse channel
CN112610250B (en) * 2020-12-14 2021-12-24 中铁隧道局集团有限公司 Method for dismantling three rock pillar supports of large-span underground cave depot
CN112610250A (en) * 2020-12-14 2021-04-06 中铁隧道局集团有限公司 Method for dismantling three rock pillar supports of large-span underground cave depot
CN112682061A (en) * 2020-12-29 2021-04-20 四川省交通勘察设计研究院有限公司 Tunnel structure and construction method
CN112647978A (en) * 2020-12-29 2021-04-13 中国科学院武汉岩土力学研究所 Construction method for leading small pilot tunnel of soft rock large-deformation tunnel
CN112682047A (en) * 2020-12-31 2021-04-20 中铁大桥局集团第五工程有限公司 Construction method for parallel small-clear-distance tunnel
CN113236293A (en) * 2021-03-30 2021-08-10 解长渊 Deformation control supporting method for urban trunk road weak surrounding rock shallow-buried large-span small-clear-distance tunnel
CN113236293B (en) * 2021-03-30 2024-04-05 解长渊 City trunk weak surrounding rock shallow-buried large-span small-clear-distance tunnel deformation control supporting method
CN113153375B (en) * 2021-04-08 2022-12-02 济南城建集团有限公司 Construction method of soft foundation ultra-small clear distance tunnel primary support anti-drop support settlement-reducing support system
CN113153375A (en) * 2021-04-08 2021-07-23 济南城建集团有限公司 Construction method of support system for preventing support drop and settlement of primary support of ultra-small clear distance tunnel of soft foundation
CN113216976A (en) * 2021-04-09 2021-08-06 中交第一公路勘察设计研究院有限公司 Tunnel HCD excavation method suitable for soft rock and gravel soil
CN113153317A (en) * 2021-05-11 2021-07-23 北华航天工业学院 Construction method and grouting device suitable for soft rock large-section tunnel
CN113431588B (en) * 2021-07-30 2022-07-22 中铁十四局集团第三工程有限公司 Construction method for branch tunnel
CN113431588A (en) * 2021-07-30 2021-09-24 中铁十四局集团第三工程有限公司 Construction method for branch tunnel
CN113482630A (en) * 2021-08-06 2021-10-08 中铁二局第四工程有限公司 Pilot construction method applied to small-clear-distance double-hole tunnel
CN113482630B (en) * 2021-08-06 2024-01-12 中铁二局第四工程有限公司 Advanced pilot pit construction method applied to small-clear-distance double-hole tunnel
CN114352291A (en) * 2022-01-07 2022-04-15 贵州路桥集团有限公司 Construction method of proximity tunnel
CN114352291B (en) * 2022-01-07 2024-05-07 贵州路桥集团有限公司 Construction method of near tunnel
CN114718582A (en) * 2022-06-08 2022-07-08 中铁九局集团第七工程有限公司 Construction method for small-clear-distance horizontal joint shale geological tunnel portal section
CN114718582B (en) * 2022-06-08 2022-09-06 中铁九局集团第七工程有限公司 Construction method for small-clear-distance horizontal joint shale geological tunnel portal section
CN114810129A (en) * 2022-06-28 2022-07-29 中铁九局集团第七工程有限公司 Construction method for shallow-buried bias section of small-clear-distance horizontal joint shale geological tunnel
CN115263319A (en) * 2022-07-06 2022-11-01 中铁一局集团(广州)建设工程有限公司 Steep-dip bedding limestone tunnel out-of-tunnel construction method
CN117780362A (en) * 2024-02-27 2024-03-29 中铁十七局集团第五工程有限公司 Rock column replacement and reinforcement structure in ultra-small clear distance tunnel and construction method thereof
CN117780362B (en) * 2024-02-27 2024-04-30 中铁十七局集团第五工程有限公司 Rock column replacement and reinforcement structure in ultra-small clear distance tunnel and construction method thereof

Also Published As

Publication number Publication date
CN108533272B (en) 2020-04-21

Similar Documents

Publication Publication Date Title
CN108533272A (en) A kind of minimum clear-distance tunnel goes out cavity construction method
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
CN101929340B (en) Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN105781571A (en) Construction method for soft rock deformation tunnel lining support dismantling-replacing arch
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN104533453A (en) Substep dynamic coupling support method for roadway fault fracture zone
CN110374633A (en) The Portal Section Construction method of Tunnel Passing loose media
CN106437726A (en) Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN107201908A (en) A kind of construction method of the regional buried Central drain in tunnel of bitter cold
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN113073983B (en) Enclosure type grouting construction method for submarine tunnel to penetrate through water-rich fault fracture zone
CN107288642A (en) PBA construction technologies
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN110159298A (en) A kind of first branch button arch construction method of Underground Subway Station
CN109578007B (en) Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and drainage and construction method
CN106246191B (en) A kind of hole body is dredged, fills plentiful large-scale karst cave treatment and tunnel excavation method deeply
CN110284885A (en) Shield inspection-pit construction method
CN106884665A (en) A kind of Double Multi-Arch start tunneling method based on arch set arch
CN107191206B (en) A kind of six step construction method of Shallow-buried Large-span Tunnel Unit two
CN112177635A (en) Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel
CN109139018A (en) The method for tunnel construction and system that deep hole sleeve valve barrel grouting is combined with horizontal jet grouting
CN114562289A (en) Rapid treatment method for large-scale cavity collapse of soft broken surrounding rock tunnel vault
CN107514266A (en) Shield export & import bolt anchorage soil body construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant