CN106640096A - Construction method for penetrating through tunnel of backfilling soil section and transition section - Google Patents

Construction method for penetrating through tunnel of backfilling soil section and transition section Download PDF

Info

Publication number
CN106640096A
CN106640096A CN201710087090.6A CN201710087090A CN106640096A CN 106640096 A CN106640096 A CN 106640096A CN 201710087090 A CN201710087090 A CN 201710087090A CN 106640096 A CN106640096 A CN 106640096A
Authority
CN
China
Prior art keywords
tunnel
construction
section
type
mileage direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710087090.6A
Other languages
Chinese (zh)
Inventor
李超
顾刘东
张恒
周利亚
代军
王建
王峰
彭淋漓
傅渝东
李�杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority to CN201710087090.6A priority Critical patent/CN106640096A/en
Publication of CN106640096A publication Critical patent/CN106640096A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Abstract

The invention relates to a construction method for penetrating through a tunnel of a backfilling soil section and a transition section. The construction method is characterized by comprising the following steps: step 1, draining water from a construction site, and lowering a water level to be 2.0m lower than a bottom elevation of the tunnel; step 2, digging the tunnel; constructing a right-line tunnel of the transition section in a small mileage direction and a large mileage direction; mechanically digging by adopting a bench cut method and constructing the tunnel according to a B-shaped fracture surface structure; after constructing to the backfilling soil section, constructing the tunnel at the backfilling soil section in the small mileage direction and the large mileage direction; mechanically digging by adopting a reserved core soil method; constructing the tunnel according to a C-shaped fracture surface structure; when the distance between working faces at two ends of a left-line tunnel or/and the right-line tunnel is 10m, pausing digging construction on the working faces of the left-line tunnel or/and the right-line tunnel in the large mileage direction; and continually constructing the left-line tunnel or/and the right-line tunnel in the small mileage direction in a unidirectional way until the tunnel is through. The construction method provided by the invention is simple in steps, convenient to construct and safe and reliable; and the construction quality can be guaranteed and requirements of urban rail traffic construction are met.

Description

Pass through the construction method in backfill soil section and changeover portion tunnel
Technical field
The present invention relates to Tunnel Engineering, and in particular to pass through the construction method in backfill soil section and changeover portion tunnel.
Background technology
The characteristics of constructing tunnel is that disguised big, working space is limited, operation comprehensive strong, and construction environment is severe, wind It is dangerous big;Construction method is restricted by landform, geology.Only these features are carried out after reasonable analysis, according to Tunnel Passing ground The different situations of layer, select appropriate construction method, can safely and fast complete Tunnel Engineering.Such as CN 104500077B " a kind of shallow-depth-excavation tunnel passes through cottage area construction method " of bulletin, using bench cut method from the front to the back to constructed shallow embedding The Tunnel of bored tunnel is excavated, and the Tunnel in digging process from the front to the back to excavating formation carries out preliminary bracing; Lower pilot tunnel of the Tunnel by upper pilot tunnel and immediately below upper pilot tunnel is constituted, and the rear portion of Tunnel is connected with vertical shaft;Tunnel Preliminary bracing structure include many Pin the Tunnel is supported from the front to the back grid steel frame, be mounted on Tunnel inwall One layer of bar-mat reinforcement and the concrete layer that is injected on Tunnel inwall;The Tunnel of constructed shallow-depth-excavation tunnel is opened During digging, process is as follows:First, upper pilot tunnel initial segment is excavated;2nd, lower pilot tunnel initial segment is excavated;3rd, upper and lower pilot tunnel is synchronously excavated.Should Method and step is simple, reasonable in design and easy construction, construction effect are good, can simplicity completes to pass through the shallow-depth-excavation tunnel of cottage area Work progress, and work progress is safe and reliable.With the development of Construction of Urban Rail Traffic, the location of Tunnel Passing will run into Many new situations, such as urban track traffic need to pass through backfill soil section and changeover portion.At present, backfill soil section and changeover portion are passed through Constructing tunnel arrangement and method for construction of the aspect without a set of standard, specification is available for following, and the data that can be used for reference is little.Thus, it would be highly desirable to Explore the good construction for passing through backfill soil section and changeover portion tunnel of a kind of simple reasonable in design, step, easy construction, construction effect Method, to meet the demand of Construction of Urban Rail Traffic.
Goal of the invention
It is an object of the invention to provide passing through the construction method in backfill soil section and changeover portion tunnel, its step is simple, construction It is convenient, safe and reliable, construction quality is ensure that, meet the demand of Construction of Urban Rail Traffic.
In view of the geological conditions of backfill soil section is poor, stratum is from top to bottom followed successively by plain fill layer, residual slide rock silty clay Layer, sedimentary type formations.Backfill soil section coating is larger in the thickness of gully karness band, and basement rock is the terrestrial facies chip of sandstone and mud stone alternating layers Rock, it is aqueous relatively weak.Backfill soil section hydrogeologic condition is more complicated, and the watery of underground water is received topography and geomorphology, lithology and split Gap development degree is controlled, predominantly Atmospheric precipitation, ground ditch, pool water body seepage and urban underground water drainage pipe line seepage supply, For pore ground water and perched water, and the water level disunity of underground water, water level and the water yield are in obvious seasonal variation characteristics, are moved State amplitude is big, without hydraulic connection between underground water.
Jing is examined on the spot, and the geological conditions of the changeover portion being connected with backfill soil section two ends is good compared with backfill soil section, with backfill Duan Yiduan connected changeover portion is shorter, referred to as little mileage direction, longer with the changeover portion that the backfill soil section other end is connected, referred to as greatly Mileage direction;The tunnel for requiring construction is two-way light rail, that is, be divided into left threaded list road and right threaded list road.According to above-mentioned concrete feelings Condition, first, specific planning is made in reply to job site, and pair changeover portion being connected with backfill soil section two ends adopts Type B section Structure.Due to relatively crushing uneven to soil section boundary position, rock stratum is backfilled in rock matter section, collapse to prevent digging process from causing Collapse, while reducing the sedimentation and deformation after excavating, in changeover portion Type B form of fracture is adopted, T76L × 9.5mm is adopted to Type B section Self-advancing type pipe canopy and 42 × 3.5mm of Ф slip casting ductules carry out advance support, are excavated using Mechanical Method point benching tunneling method, at the beginning of it Phase support form carries out supporting for I20a profile steel frames+injection C25 concretes, and the long steel pipes of Ф 108 of 2 8m are respectively provided with haunch As lock pin anchor tube.Simultaneously supporting is carried out using with the 600mm of backfill section equal thickness to two linings, and the thickness of the liner degree of rock matter section two is 350mm.Shorter (4-5) due to backfilling the time for backfill soil section, backfill material is uneven, and natural consolidation is not stable, backfill Area is deeper, c-type section is arranged in backfill soil section, using T76L × 9.5mm self-advancing type pipe canopies and Ф 42 × 3.5mm slip casting ductules Advance support is carried out, is excavated using remaining core soil in advance annular point benching tunneling method, be will just to prop up closing cyclization, its ground floor in time Preliminary bracing form carries out supporting for I20a profile steel frames+injection C25 concretes, and 2 8m length are respectively provided with haunch and arch springing The steel pipes of Ф 108 are used as lock pin anchor tube;Second layer preliminary bracing form carries out supporting for grid steel frame+injection steel fibre C25 concretes, this Layer preliminary bracing purpose be prevent from being applied to two linings after the completion of a just construction during tunnel there is excessive sedimentation and deformation.For backfill The soil section tunnel bottom also back filled region in pan bottom shape, depth capacity reaches more than 20m, stake footpath is adopted for Ф to C section tunnels bottom The steel-pipe pile of 500mm longitudinally presses spacing 650mm in tunnel, and arrangement 3+2 roots are quincunx, and pile foundation carries out bottom stab ilization.
The construction method for passing through backfill soil section and changeover portion tunnel of the present invention, is characterized in that, comprise the following steps:
The first step, construction site draining;
Tunnel Passing backfills soil section and changeover portion stratum has abundant underground water at rainy season, using tube well method precipitation, The a diameter of 300mm of downcast well pipe (millimeter), by water level 2.0m (rice) below the absolute altitude of tunnel bottom is down to.Tunnel Passing backfill soil section and Counter-slope draining is adopted in the hole of changeover portion, i.e., using relay-type draining, paragraph by paragraph supercharging is drawn water to arrange booster pump, drains into hole precipitation In pond, to ensure to exclude infiltration or other ponding in hole in time;
Second step, tunneling;
1) the right line constructing tunnel of little mileage direction transition, using benching tunnelling method mechanical equivalent of light excavation, tunnel is applied by Type B section structure Work, to backfill soil section, carries out the right line in little mileage direction and backfills soil section constructing tunnel, using provided core soil method mechanical equivalent of light excavation, Construct by c-type section structure in tunnel;
2) when Type B section, c-type section construct altogether 30m, start the left line constructing tunnel of little mileage direction transition, adopt Benching tunnelling method mechanical equivalent of light excavation is used, the construction of Type B section structure is pressed in tunnel, and keeps left and right line tunnel tunnel face spacing 30m (rice), after Continuous construction;
3) the left line constructing tunnel of big mileage direction transition, using benching tunnelling method mechanical equivalent of light excavation, tunnel is applied by Type B section structure Work, after big mileage direction transition left line constructing tunnel 30m (rice), carries out the right line constructing tunnel of big mileage direction transition, Using benching tunnelling method mechanical equivalent of light excavation, the construction of Type B section structure is pressed in tunnel;
4) when the right line in big mileage direction, left threaded list road are successively into the construction of c-type section, opened using provided core soil method machinery Dig, tunnel is constructed by c-type section structure;
5) when left threaded list road or/and right threaded list road two ends face are at a distance of 10m (rice), the left threaded list in big mileage direction is suspended Road or/and right line tunnel tunnel face excavation construction;
6) the left threaded list road in little mileage direction or/and right threaded list diatom unidirectionally continue construction, until tunnel holing through.
Further, the step sequence of the Type B section construction is:1., Shed-pipe Advanced Support, advanced tubule;2., top bar is excavated, Preliminary bracing semi-ring is applied, anchor tube is set;3., excavate and get out of a predicament or an embarrassing situation, apply the closing of preliminary bracing loopful, set lock foot anchoring stock;④、 Laying waterproof layer, applies inverted arch;5., waterproof layer is laid, applies arch and bent wall secondary lining.
Further, the step sequence of the c-type section construction is:1., Shed-pipe Advanced Support, advanced tubule construction;2., lonely shape base tunnel Excavate, apply radial grouting pipe and slip casting, apply ground floor preliminary bracing, set lock pin anchor tube, perform little in advance leading of getting out of a predicament or an embarrassing situation Pipe;3., open+step is dug down, radial grouting pipe and slip casting are applied, ground floor preliminary bracing of getting out of a predicament or an embarrassing situation is applied, steelframe loopful is closed, Set lock pin anchor tube;Grillage is set up, second layer preliminary bracing is applied;4. tunnel bottom pile foundation, is applied;5., waterproof layer is laid, Apply inverted arch;6., waterproof layer is laid, applies arch and bent wall secondary lining.
Beneficial effects of the present invention:Due to taking full advantage of composite lining design principle, preliminary bracing is divided into construction Two parts, Part I is shaped steel arch+gunite concrete+lock pin anchor tube, and Part II is grid steel frame+injection steel fibre Concrete, and implementing successively in order, the characteristics of excavation with reference to ringed nucleus cubsoil method in excavation method, set up Shed-pipe Advanced Support+ Advanced tubule combines to form advance support, increases lock pin anchor tube and improves preliminary bracing enabling capabilities, will just prop up close into as early as possible Ring, strengthens pre-grouting and a just backfill slip casting behind, and the self-holding ability of country rock is played as early as possible, reduces surrouding rock deformation, realizes just Stabilization is propped up, is that postorder in-cavity construction creates conditions.Simultaneously tunnel bottom increases steel-pipe pile, tunnel during can effectively reducing operation Sedimentation and deformation under the dynamic loading such as Groundwater Flow and train operation outside hole.
Description of the drawings
Plan schematic diagram in Fig. 1 job sites;
Fig. 2 dewatering wells arrange schematic diagram;
Fig. 3 is schematic diagram of the Type B bore tunnel using benching tunnelling method mechanical equivalent of light excavation;
Fig. 4 is the left view of Fig. 3;
Fig. 5 is the schematic diagram for adopting c-type bore tunnel provided core soil method mechanical equivalent of light excavation;
Fig. 6 is the left view of Fig. 5;
The little mileage direction construction schematic diagrames of Fig. 7;
The big mileage directions of Fig. 8 start the schematic diagram constructed;
Fig. 9 is the schematic diagram that large and small mileage direction enters backfill soil section construction;
Figure 10 be left threaded list road or/and right threaded list road two ends face at a distance of 10m when schematic diagram;
Figure 11 is the schematic diagram that the left threaded list road in little mileage direction or/and right threaded list diatom unidirectionally continue construction;
Figure 12 Type B section Shed-pipe Advanced Supports, advanced tubule construction schematic diagram;
The construction schematic diagram of preliminary bracing is excavated and made to Figure 13 top bars;
Figure 14 gets out of a predicament or an embarrassing situation and excavates and make the construction schematic diagram of initial stage loopful supporting;
Figure 15 laying waterproof layers, the construction schematic diagram for applying inverted arch;
Figure 16 laying waterproof layers, the Second Lining Construction schematic diagram for applying arch and bent wall;
The construction construction schematic diagram of Figure 17 c-type section Shed-pipe Advanced Supports, advanced tubule;
Figure 18 orphan's shape excavation with guide pit, applies radial grouting pipe and slip casting, applies the schematic diagram of ground floor preliminary bracing;
Figure 19 is excavated and got out of a predicament or an embarrassing situation, and applies radial grouting pipe and slip casting, applies ground floor preliminary bracing of getting out of a predicament or an embarrassing situation, steelframe loopful The schematic diagram of envelope;
Figure 20 applies the schematic diagram of tunnel bottom pile foundation;
Figure 21 lays waterproof layer, applies the construction schematic diagram of inverted arch;
Figure 22 lays waterproof layer, applies the construction schematic diagram of arch and bent wall secondary lining.
Specific embodiment
Below in conjunction with the accompanying drawings the present invention is further illustrated.
Jing is examined on the spot, and the geological conditions of the changeover portion being connected with backfill soil section two ends is good compared with backfill soil section, with backfill Duan Yiduan connected changeover portion is shorter, referred to as little mileage direction, longer with the changeover portion that the backfill soil section other end is connected, referred to as greatly Mileage direction;The tunnel for requiring construction is two-way subway, that is, be divided into left threaded list road and right threaded list road.According to above-mentioned concrete feelings Condition, first, specific planning is made in reply job site, and pair changeover portion being connected with backfill soil section two ends is tied using Type B section Structure.Due to relatively crushing uneven to soil section boundary position, rock stratum is backfilled in rock matter section, collapse to prevent digging process from causing Collapse, while reducing the sedimentation and deformation after excavating, in changeover portion Type B form of fracture is adopted, T76L × 9.5mm is adopted to Type B section Self-advancing type pipe canopy and 42 × 3.5mm of Ф slip casting ductules carry out advance support, are excavated using Mechanical Method point benching tunneling method, at the beginning of it Phase support form carries out supporting for I20a profile steel frames+injection C25 concretes, and the long steel pipes of Ф 108 of 2 8m are respectively provided with haunch As lock pin anchor tube.Simultaneously supporting is carried out using with the 600mm of backfill section equal thickness to two linings, and the thickness of the liner degree of rock matter section two is 350mm.C-type section structure is adopted to backfilling soil section tunnel:Shorter (4-5) due to backfilling the time, backfill material is uneven, natural Consolidation is not stable, and backfill area is deeper, c-type section is arranged in backfill soil section, using T76L × 9.5mm self-advancing type pipe canopies and Ф 42 × 3.5mm slip casting ductules carry out advance support, are excavated using remaining core soil in advance annular point benching tunneling method, are will just to prop up in time Closing cyclization, its ground floor preliminary bracing form carries out supporting for I20a profile steel frames+injection C25 concretes, and in haunch and arch springing Place is respectively provided with the long steel pipes of Ф 108 of 2 8m as lock pin anchor tube;Second layer preliminary bracing form is that grid steel frame+injection steel is fine The concrete of Vc 25 carries out supporting, this layer of preliminary bracing purpose be prevent from being applied to two linings after the completion of a just construction during tunnel occurred Big sedimentation and deformation.For backfilling the soil section tunnel bottom also back filled region in pan bottom shape, depth capacity reaches more than 20m, to C sections It is longitudinal by spacing 650mm in tunnel for the steel-pipe pile of Ф 500mm that tunnel bottom adopts stake footpath, and arrangement 3+2 roots are quincunx, and pile foundation carries out base Bottom reinforces.
The construction method for passing through backfill soil section and changeover portion tunnel of the present invention, referring to Fig. 1 to Figure 22, its feature It is to comprise the following steps:
The first step, construction site draining;
Tunnel Passing backfills soil section and changeover portion stratum has abundant underground water at rainy season, using tube well method precipitation, The a diameter of 300mm of downcast well pipe (millimeter), by water level 2.0m (rice) below the absolute altitude of tunnel bottom is down to.Tunnel Passing backfill soil section and Counter-slope draining is adopted in the hole of changeover portion, i.e., using relay-type draining, paragraph by paragraph supercharging is drawn water to arrange booster pump, drains into hole precipitation In pond, to ensure to exclude infiltration or other ponding in hole in time;
Second step, tunneling;
1) the right line constructing tunnel of little mileage direction transition, using benching tunnelling method mechanical equivalent of light excavation, tunnel is applied by Type B section structure Work, to backfill soil section, carries out the right line in little mileage direction and backfills soil section constructing tunnel, using provided core soil method mechanical equivalent of light excavation, Construct by c-type section structure in tunnel;
2) when Type B section, c-type section construct altogether 30m, start the left line constructing tunnel of little mileage direction transition, adopt Benching tunnelling method mechanical equivalent of light excavation is used, the construction of Type B section structure is pressed in tunnel, and keeps left and right line tunnel tunnel face spacing 30m (rice), after Continuous construction;
3) the left line constructing tunnel of big mileage direction transition, using benching tunnelling method mechanical equivalent of light excavation, tunnel is applied by Type B section structure Work, after big mileage direction transition left line constructing tunnel 30m (rice), carries out the right line constructing tunnel of big mileage direction transition, Using benching tunnelling method mechanical equivalent of light excavation, the construction of Type B section structure is pressed in tunnel;
4) when the right line in big mileage direction, left threaded list road are successively into the construction of c-type section, opened using provided core soil method machinery Dig, tunnel is constructed by c-type section structure;
5) when left threaded list road or/and right threaded list road two ends face are at a distance of 10m (rice), the left threaded list in big mileage direction is suspended Road or/and right line tunnel tunnel face excavation construction;
6) the left threaded list road in little mileage direction or/and right threaded list diatom unidirectionally continue construction, until tunnel holing through.
The step sequence of Type B section construction is:1., Shed-pipe Advanced Support, advanced tubule;2., top bar is excavated, applies the initial stage Supporting semi-ring, sets anchor tube;3., excavate and get out of a predicament or an embarrassing situation, apply the closing of preliminary bracing loopful, set lock foot anchoring stock;4., waterproof is laid Layer, applies inverted arch;5., waterproof layer is laid, applies arch and bent wall secondary lining.
The step sequence of c-type section construction is:1., Shed-pipe Advanced Support, advanced tubule construction;2., lonely shape excavation with guide pit, applies Make radial grouting pipe and slip casting, apply ground floor preliminary bracing, set lock pin anchor tube, perform advanced tubule of getting out of a predicament or an embarrassing situation;3., open + step is dug down, radial grouting pipe and slip casting are applied, ground floor preliminary bracing of getting out of a predicament or an embarrassing situation is applied, the closing of steelframe loopful sets lock pin Anchor tube;Grillage is set up, second layer preliminary bracing is applied;4. tunnel bottom pile foundation, is applied;5., waterproof layer is laid, applies and face upward Arch;6., waterproof layer is laid, applies arch and bent wall secondary lining.
Tentatively draft with reference to similar engineering experience and node construction period and pass through backfill soil section construction step pitch, in work progress It is middle to be optimized adjustment in time according to construction monitoring data:1., the step pitch of upper and lower step:Using short benching tunnelling method, top bar is advanced 5~10 Pin steelframe spacing (steelframe spacing 0.65m), carry out immediately construction of getting out of a predicament or an embarrassing situation, and steelframe closes in time cyclization;2., face With the step pitch of pile foundation:Face prebracing piles base 10.4m, excavates with after a double-deck just 10.4m, suspends area surface construction, in time Apply pile foundation;3., the step pitch of face and inverted arch:After pile foundation is qualified after testing, inverted arch is applied in time, in principle inverted arch is delayed 2~3 lining construction lengths of the cycle of face (the long 7.5m of lining trolley) 4., the lining of arch wall two and the step pitch of inverted arch:Receive in deformation Hold back on the premise of stablizing, arch wall two is served as a contrast immediately following inverted arch construction, arch wall two serves as a contrast delayed inverted arch less than 2 lining constructions circulation length Degree.
Supporting and lining project
1), Tunnel Passing backfill soil section and changeover portion geological conditions are poor, using the self-advancing type pipe canopies of φ 76, the ductules of φ 42 Advance support is carried out, wherein changeover portion adopts profile steel frame preliminary bracing, and backfill soil section is double with grillage using profile steel frame Layer preliminary bracing, backfill soil section hole bottom adopts steel pipe pile reinforced basement process.
2), bolt-spary supports must closely follow excavated surface, before construction, conscientiously check and process the danger of bolt-spary supports operation area Stone, construction equipment is arranged out of harm's way.
3), preliminary bracing is adopted and first sprays concrete, then the form of construction work for installing anchor pole.Anchor pole hole position, aperture, hole depth and arrangement shape Formula should meet design requirement, and hole internal water accumulation and rock dust should be purged totally.
4), i-beam frame, grillage make quality and have to comply with design requirement, and steel frame column must not be placed on scum silica frost.
5) operation of preliminary bracing jetting cement should be segmented, burst, layering from bottom to top carry out successively.
6) behind backfill slip casting is closely connected as principle with preliminary bracing and rock-soil layer for preliminary bracing, in time to space after first backing Slip casting is filled, and just backing grouting behind shaft or drift lining adopts cement mortar, grouting pressure to control in 0.3~0.5MPa or so.
7) preliminary bracing bow member sets longitudinally connected muscle, and dowel must reliably be welded with bow member;Anchor pole end can with bow member By welding.
8) bow member is processed into Pin outside hole and tries to spell, it is necessary to meet design requirement;In bow member installation process, it is to be ensured that each Individual node accurately in place and connects reliable.

Claims (3)

1. the construction method in backfill soil section and changeover portion tunnel is passed through, be it is characterized in that, comprised the following steps:
The first step, construction site draining;
Tunnel Passing backfills soil section and changeover portion stratum has abundant underground water at rainy season, using tube well method precipitation, precipitation The a diameter of 300mm of well casing (millimeter), by water level 2.0m (rice) below the absolute altitude of tunnel bottom is down to.Tunnel Passing backfills soil section and transition Counter-slope draining is adopted in the hole of section, i.e., using relay-type draining, paragraph by paragraph supercharging is drawn water to arrange booster pump, drains into hole sedimentation basin It is interior, to ensure to exclude infiltration or other ponding in hole in time;
Second step, tunneling;
1) the right line constructing tunnel of little mileage direction transition, using benching tunnelling method mechanical equivalent of light excavation, the construction of Type B section structure is pressed in tunnel, To backfill soil section, carry out the right line in little mileage direction and backfill soil section constructing tunnel, using provided core soil method mechanical equivalent of light excavation, tunnel Construct by c-type section structure;
2) when Type B section, c-type section construct altogether 30m, the left line constructing tunnel of little mileage direction transition is started, using platform The construction of Type B section structure is pressed in rank method mechanical equivalent of light excavation, tunnel, and keeps left and right line tunnel tunnel face spacing 30m (rice), continues to apply Work;
3) the left line constructing tunnel of big mileage direction transition, using benching tunnelling method mechanical equivalent of light excavation, the construction of Type B section structure is pressed in tunnel, After big mileage direction transition left line constructing tunnel 30m (rice), the right line constructing tunnel of big mileage direction transition is carried out, adopted Press the construction of Type B section structure in benching tunnelling method mechanical equivalent of light excavation, tunnel;
4) when the right line in big mileage direction, left threaded list road are successively into the construction of c-type section, using provided core soil method mechanical equivalent of light excavation, Construct by c-type section structure in tunnel;
5) when left threaded list road or/and right threaded list road two ends face are at a distance of 10m (rice), the left threaded list road in big mileage direction is suspended Or/and right line tunnel tunnel face excavation construction;
6) the left threaded list road in little mileage direction or/and right threaded list diatom unidirectionally continue construction, until tunnel holing through.
2. the construction method for passing through backfill soil section and changeover portion tunnel according to claim 1, is characterized in that, the Type B Section construction step sequence be:1., Shed-pipe Advanced Support, advanced tubule;2., top bar is excavated, applies preliminary bracing semi-ring, set anchor Pipe;3., excavate and get out of a predicament or an embarrassing situation, apply the closing of preliminary bracing loopful, set lock foot anchoring stock;4., waterproof layer is laid, applies inverted arch;⑤、 Laying waterproof layer, applies arch and bent wall secondary lining.
3. the construction method for passing through backfill soil section and changeover portion tunnel according to claim 1 and 2, is characterized in that, the C Type section construction step sequence be:1., Shed-pipe Advanced Support, advanced tubule construction;2., lonely shape excavation with guide pit, applies radial grouting pipe And slip casting, ground floor preliminary bracing is applied, lock pin anchor tube is set, perform advanced tubule of getting out of a predicament or an embarrassing situation;3., open+step is dug down, apply Make radial grouting pipe and slip casting, apply ground floor preliminary bracing of getting out of a predicament or an embarrassing situation, the closing of steelframe loopful sets lock pin anchor tube;Set up lattice Grid bow member, applies second layer preliminary bracing;4. tunnel bottom pile foundation, is applied;5., waterproof layer is laid, applies inverted arch;6., lay anti- Water layer, applies arch and bent wall secondary lining.
CN201710087090.6A 2017-02-17 2017-02-17 Construction method for penetrating through tunnel of backfilling soil section and transition section Pending CN106640096A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710087090.6A CN106640096A (en) 2017-02-17 2017-02-17 Construction method for penetrating through tunnel of backfilling soil section and transition section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710087090.6A CN106640096A (en) 2017-02-17 2017-02-17 Construction method for penetrating through tunnel of backfilling soil section and transition section

Publications (1)

Publication Number Publication Date
CN106640096A true CN106640096A (en) 2017-05-10

Family

ID=58845565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710087090.6A Pending CN106640096A (en) 2017-02-17 2017-02-17 Construction method for penetrating through tunnel of backfilling soil section and transition section

Country Status (1)

Country Link
CN (1) CN106640096A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503357A (en) * 2017-08-30 2017-12-22 云南工程建设总承包公司 Annular pile supporting construction
CN108533272A (en) * 2018-03-30 2018-09-14 贵州省公路工程集团有限公司 A kind of minimum clear-distance tunnel goes out cavity construction method
CN108678753A (en) * 2018-03-29 2018-10-19 中交路桥北方工程有限公司 Reverse-slope tunnel construction method
CN108798718A (en) * 2018-07-09 2018-11-13 中铁十七局集团第四工程有限公司 Subsequent grouting method is held before tunnel
CN110593893A (en) * 2019-11-01 2019-12-20 中建八局轨道交通建设有限公司 Main body structure construction method and system for intersection of main tunnel and construction transverse channel
CN111255476A (en) * 2020-01-19 2020-06-09 中交一公局第四工程有限公司 Tunnel multi-section three-dimensional intersection construction method
CN114922639A (en) * 2022-07-20 2022-08-19 中铁九局集团第七工程有限公司 Tunnel excavation construction method for penetrating existing culvert downwards

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758440A (en) * 2011-04-28 2012-10-31 成都中铁隆工程集团有限公司 Open-cut tunnel construction method
CN102767379A (en) * 2012-08-10 2012-11-07 中国建筑第四工程局有限公司 Shallow-buried unsymmetrical pressure section tunnel drilling construction method
KR101283672B1 (en) * 2012-09-18 2013-07-08 주식회사 성우사면 Non open cut method using the lifting device
CN104963689A (en) * 2015-07-07 2015-10-07 中铁十九局集团第二工程有限公司 Three-step seven-procedure excavation method for tunnel
CN105840203A (en) * 2016-03-22 2016-08-10 中铁第五勘察设计院集团有限公司 Large section loess tunnel pre-cutting method construction method
CN106121675A (en) * 2016-08-22 2016-11-16 北京市市政工程研究院 Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758440A (en) * 2011-04-28 2012-10-31 成都中铁隆工程集团有限公司 Open-cut tunnel construction method
CN102767379A (en) * 2012-08-10 2012-11-07 中国建筑第四工程局有限公司 Shallow-buried unsymmetrical pressure section tunnel drilling construction method
KR101283672B1 (en) * 2012-09-18 2013-07-08 주식회사 성우사면 Non open cut method using the lifting device
CN104963689A (en) * 2015-07-07 2015-10-07 中铁十九局集团第二工程有限公司 Three-step seven-procedure excavation method for tunnel
CN105840203A (en) * 2016-03-22 2016-08-10 中铁第五勘察设计院集团有限公司 Large section loess tunnel pre-cutting method construction method
CN106121675A (en) * 2016-08-22 2016-11-16 北京市市政工程研究院 Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘述林: "《地铁区间隧道下穿回填土及过度段施工技术》", 《江西建材》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503357A (en) * 2017-08-30 2017-12-22 云南工程建设总承包公司 Annular pile supporting construction
CN108678753A (en) * 2018-03-29 2018-10-19 中交路桥北方工程有限公司 Reverse-slope tunnel construction method
CN108678753B (en) * 2018-03-29 2019-11-08 中交路桥北方工程有限公司 Reverse-slope tunnel construction method
CN108533272A (en) * 2018-03-30 2018-09-14 贵州省公路工程集团有限公司 A kind of minimum clear-distance tunnel goes out cavity construction method
CN108798718A (en) * 2018-07-09 2018-11-13 中铁十七局集团第四工程有限公司 Subsequent grouting method is held before tunnel
CN110593893A (en) * 2019-11-01 2019-12-20 中建八局轨道交通建设有限公司 Main body structure construction method and system for intersection of main tunnel and construction transverse channel
CN110593893B (en) * 2019-11-01 2024-04-12 中建八局轨道交通建设有限公司 Main body structure construction method and system at intersection of main tunnel and construction transverse channel
CN111255476A (en) * 2020-01-19 2020-06-09 中交一公局第四工程有限公司 Tunnel multi-section three-dimensional intersection construction method
CN111255476B (en) * 2020-01-19 2021-10-22 中交一公局第四工程有限公司 Tunnel multi-section three-dimensional intersection construction method
CN114922639A (en) * 2022-07-20 2022-08-19 中铁九局集团第七工程有限公司 Tunnel excavation construction method for penetrating existing culvert downwards

Similar Documents

Publication Publication Date Title
CN106640096A (en) Construction method for penetrating through tunnel of backfilling soil section and transition section
CN105041325B (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN202969392U (en) Complex geology deep excavation pit combined support
CN108915736B (en) Method for preventing and controlling water damage of roadway tunneling under strong water-rich and weak-cementation aquifer
CN105927272A (en) Floor anchoring constraint tunnel lining structure
CN104499479B (en) It is a kind of to pass through the dug pile construction method that sand gravel backfills layer
CN105839643A (en) Tunnel in-hole construction method adopting foundation pit support
CN106437726A (en) Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN106567717A (en) Construction oblique channel structure utilizing subway exit and entrance and construction method
CN102296630A (en) Construction method of long-screw high-pressure mix jetting cement diaphragm wall
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN106869969A (en) A kind of excavation supporting construction method of soft rock large section tunnel
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN107503754A (en) A kind of construction method of VI grade of country rock rich water Shallow tunnel with large cross-section
CN109372520A (en) One kind passing through Debris Flow Deposition area tunnel support structure and its construction method
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN112663625A (en) Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN107605509A (en) Sand-pebble layer small curve radius shallow tunnel subsurface excavation method advanced supporting construction method
CN211500658U (en) Shallow tunnel supporting construction that nearly connects that buries suitable for sand ground
CN111365005A (en) Reinforcing structure and method for shield tunnel lower-penetrating elevated bridge foundation
CN109538236A (en) A kind of tunnel structure and tunnel construction method
CN102425179B (en) Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170510