CN106121675A - Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch - Google Patents

Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch Download PDF

Info

Publication number
CN106121675A
CN106121675A CN201610699191.4A CN201610699191A CN106121675A CN 106121675 A CN106121675 A CN 106121675A CN 201610699191 A CN201610699191 A CN 201610699191A CN 106121675 A CN106121675 A CN 106121675A
Authority
CN
China
Prior art keywords
excavation
tunnel
inverted arch
steelframe
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610699191.4A
Other languages
Chinese (zh)
Inventor
张晗
杨东波
李文华
贺美德
何少春
李宁
薛会青
王丽萍
王雄
张春发
刘继尧
魏英华
柳飞
尹鹏涛
刘士海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing municipal administration road and bridge limited company
Original Assignee
Beijing Municipal Engineering Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Engineering Research Institute filed Critical Beijing Municipal Engineering Research Institute
Priority to CN201610699191.4A priority Critical patent/CN106121675A/en
Publication of CN106121675A publication Critical patent/CN106121675A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses small-sized solution cavity and be positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch, concretely comprise the following steps: fill the solution cavity bottom tunnel inverted arch;Advance support, hoop excavation arc leading pit, and remaining core soil in advance are set in arch, tunnel;Step in step, right side on the left of excavation, getting out of a predicament or an embarrassing situation in left side, gets out of a predicament or an embarrassing situation in right side, and excavation cyclic advance amount, less than 1.5m, is equipped with preliminary bracing steelframe spacing;Top bar, middle step and the position remaining core soil in advance got out of a predicament or an embarrassing situation;At the bottom of circulation excavation tunnel, excavation drilling depth amount is 2 3m, after excavation, applies inverted arch preliminary bracing, after completing two tunnel excavations, supporting circulation, applies inverted arch in time, and inverted arch section length is 4 6m.This method for tunnel construction is applicable to bottom inverted arch the situation having small-sized solution cavity, it is possible to reduce the impact that tunnel subsidence is restrained by non-homogeneous stress, effectively controls tunnel deformation, the safety of balance tunnel construction, economy, speed of application, ensures the quality of constructing tunnel.

Description

Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch
Technical field
The present invention relates to technical field of tunnel construction, particularly relate to tunnel when small-sized solution cavity is positioned at the bottom of tunneling inverted arch and open Dig and karst cave treatment method.
Background technology
The formation of solution cavity is the result of the long-term corrosion of In Limestone Area subsoil water, and in limestone, insoluble calcium carbonate is by water Effect with carbon dioxide can be converted into the calcium bicarbonate of microsolubility.This geological phenomenon can affect its peripheral rock stability and Mechanics distribution situation, affects the engineering construction quality of periphery.
In engineering construction, part construction technology is relatively big to surrouding rock stress distribution influence, encounters unavoidable solution cavity, work Dangerous and the unstable factor of journey structure increases, and construction technology becomes numerous and diverse, and uncertainty and the risk of whole engineering also exist It is continuously increased.
In work progress, the case that solution cavity occurs near tunnel is of common occurrence, occurs small-sized solution cavity bottom inverted arch Situation, also can affect safety and the construction quality of constructing tunnel.
Summary of the invention
It is an object of the invention to for above-mentioned technical problem, it is provided that small-sized solution cavity is positioned at tunnel time at the bottom of tunneling inverted arch Excavating and karst cave treatment method, it can reduce the impact that tunnel subsidence is restrained by non-homogeneous stress, effectively control tunnel deformation, The safety of balance tunnel construction, economy, speed of application, ensure the quality of constructing tunnel.
Technical scheme
For solving above-mentioned technical problem, the small-sized solution cavity that the present invention provides is positioned at tunnel excavation and solution cavity time at the bottom of tunneling inverted arch Processing method, described tunnel is Karst Tunnel, specifically includes following steps:
S1, fills the solution cavity bottom tunnel inverted arch;During cavern depth < 3m, use cushion construction, dry-laid rubble is changed and fills out, starch Build slabstone and be filled in bottom and the top of solution cavity respectively;During cavern depth 3m-10m, use the construction of grouting and reinforcing method, injecting paste material C30 cement mortar need to be used;
S2, arranges advance support, hoop excavation arc leading pit, and remaining core soil in advance in arch, tunnel;Excavation cyclic advance amount is not More than 1.5m, it is equipped with preliminary bracing steelframe spacing;Should carry out after excavation spraying, anchor, net system supporting, note simultaneously Slurry is reinforced, and sets up steelframe, highly locates at the above 30cm of steelframe arch springing, is close to steelframe dual-side and sets up lock foot anchor along angle of declination 30 ° Bar, arch springing anchor pole welds with steelframe, and multiple pneumatically placed concrete is to design thickness;
S3, on the left of excavation in step in step, right side, excavation cyclic advance amount is less than 1.5m, between itself and preliminary bracing steelframe Away from being equipped with;Excavation height is 3-3.5m, and left and right sides step staggers 2-3m;Should carry out after excavation spraying, anchor, net system is propped up Protect, spreading steelframe, highly locate at the above 30cm of steelframe arch springing, be close to steelframe dual-side and set up lock foot anchoring stock, arch along angle of declination 30 ° Foot anchor pole and steelframe firmly weld, and multiple pneumatically placed concrete is to design thickness;
S4, uses the method in S3 step, gets out of a predicament or an embarrassing situation, get out of a predicament or an embarrassing situation in right side on the left of construction;
S5, tops bar, middle step and the position remaining core soil in advance got out of a predicament or an embarrassing situation, after each bench excavation, applies inverted arch preliminary bracing, complete After becoming two tunnel excavations, supporting circulation, applying inverted arch in time, inverted arch section length is 4-6m.
S6, at the bottom of circulation excavation tunnel, excavation drilling depth amount is 2-3m, after excavation, applies inverted arch preliminary bracing, completes two and open Dig, supporting circulation after, apply inverted arch in time, inverted arch section length is 4-6m.
Further, in step S1, when using cushion construction, the specification of mortar flag stone is M10.
Further, in step S1, when using the construction of grouting and reinforcing method, inject serosity, seamless steel pipe by seamless steel pipe Going deep into basement rock 1m, the distance between seamless steel pipe is 1.5m.
Further, in step S2, a length of 3-5m of remaining core soil in advance, its width is the 1/3-1/2 of tunnel excavation width.
The method have the benefit that
The small-sized solution cavity that the present invention provides is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch, and it can reduce The impact that tunnel subsidence is restrained by non-homogeneous stress, effectively controls tunnel deformation, keep tie the weighing apparatus safety of constructing tunnel, economy Property, speed of application, ensure constructing tunnel quality.
The present invention uses three seven footworks to carry out the excavation of tunnel tunnel face, it is ensured that construction under unfavorable geological condition Safety, decreases the non-homogeneous stress of surrounding formation and the sedimentation convergence in tunnel, ensure that entering of construction to greatest extent simultaneously Degree, passes through the large-scale solution cavity that hole body is dredged deeply, filling is plentiful and has highly application value constructing tunnel.
The construction method three step seven step excavating load of the present invention has evaded side heading method, median septum method and median septum of intersecting Methods etc. need to remove gib and stress check calculation causes unsafe factor, are shortened by length of bench, it is ensured that preliminary bracing Closing cyclization as early as possible, inverted arch and arch wall lining cutting simultaneously is followed up in time, forms stable support system as early as possible, has to adjust in time and closes The conjunction time, facilitate mechanical execution, beneficially the advantage of working procedure conversion.
The construction method construction space of the present invention is big, facilitates mechanized construction, can the parallel operations of many scope of operations, part is soft Rock or soil property location can use excavator directly to excavate, and work efficiency is higher;Convenient when geological conditions changes, it is simple to spirit Live, change working procedure in time, adjust construction method;Adapting to different spans and multiple form of fracture, preliminary bracing operation is grasped It is convenient to make;On the basis of benching tunnelling method excavates, remaining core soil in advance, excavation, beneficially excavated surface are staggered stably in left and right;Work as country rock When deformation is relatively big or suddenlys change, on the premise of ensureing safety and meeting Clearance requirement, closing time can be adjusted as early as possible.
The present invention is widely used in the stratum of the special geologic condition at solution cavity, needs quick, safe and effective by this The tunnel excavation construction of geological conditions, it is ensured that construction and the safety in tunnel.
Accompanying drawing explanation
By the detailed description made in conjunction with the following drawings, advantages of the present invention will be apparent from and is easier to understand, These accompanying drawings the most schematically, are not limiting as the present invention, wherein:
Fig. 1 is the structural representation of the present invention.
In accompanying drawing, the parts representated by each label are as follows:
1. ductule;2. seamless steel pipe;3. mortar flag stone;4. dry-laid rubble;5. arc leading pit;6. step on the left of;7. on the right side of Middle step;8. get out of a predicament or an embarrassing situation on the left of;9. get out of a predicament or an embarrassing situation on the right side of;10-1. tops bar;10-2. middle step;10-3. gets out of a predicament or an embarrassing situation.
Detailed description of the invention
When being positioned at the small-sized solution cavity of the present invention at the bottom of tunneling inverted arch below in conjunction with specific embodiments and the drawings, tunnel is opened Dig and be described in detail with karst cave treatment method.
The embodiment recorded at this is the specific detailed description of the invention of the present invention, for the design of the present invention being described, all It is explanatory and exemplary, should not be construed as the restriction to embodiment of the present invention and the scope of the invention.Except record at this Outside embodiment, those skilled in the art can also based on the application claims and description disclosure of that use aobvious and Other technical scheme being clear to, these technical schemes include use to the embodiment recorded at this make any obviously The technical scheme of substitutions and modifications.
The accompanying drawing of this specification is schematic diagram, aids in illustrating the design of the present invention, it is schematically indicated the shape of each several part And mutual relation.Note that the structure of each parts for the ease of clearly showing the embodiment of the present invention, between each accompanying drawing Do not draw according to identical ratio.Identical reference marker is used for representing identical part.
Fig. 1 is the structural representation of the present invention, and small-sized solution cavity is positioned at time at the bottom of tunneling inverted arch at tunnel excavation and solution cavity Reason method, described tunnel is Karst Tunnel, and maximum span is up to 18 meters, specifically includes following steps:
S1, fills the solution cavity bottom tunnel inverted arch;During cavern depth < 3m, use cushion construction, dry-laid rubble is changed and fills out 4, Mortar flag stone 3 is filled in bottom and the top of solution cavity respectively;During cavern depth 3m-10m, use the construction of grouting and reinforcing method, slip casting Material need to use C30 cement mortar;
Specifically, in step S1, when using cushion construction, the corrosion soil property of excavation solution cavity bottom, use dry-laid rubble 4 to fill out Fill, then, re-use the mortar flag stone that specification is M10 and fill at the 1m of solution cavity top.
When using the construction of grouting and reinforcing method, injecting serosity by seamless steel pipe 2, boring gos deep into basement rock about 1m, between boring Away from for 1.5m, seamless steel pipe 2 is inserted in the borehole, injects C30 cement mortar by seamless steel pipe 2.
S2, arranges advance support, hoop excavation arc leading pit 5, and remaining core soil in advance in arch, tunnel;Excavation cyclic advance Amount is less than 1.5m, and it is equipped with preliminary bracing steelframe spacing;Should spray after excavation, anchor, net system supporting, adopt simultaneously Reinforce with ductule 1 radial grouting, set up steelframe, highly locate at the above 30cm of steelframe arch springing, be close to steelframe dual-side along having a down dip Lock foot anchoring stock is set up at 30 ° of angle, and arch springing anchor pole welds with steelframe, and multiple pneumatically placed concrete is to design thickness;
Specifically, in step S2, a length of 3-5m of remaining core soil in advance, its width is the 1/3-1/2 of tunnel excavation width.
S3, on the left of excavation in step 7 in step 6, right side, excavation cyclic advance amount is less than 1.5m, itself and preliminary bracing Steelframe spacing is equipped with;Excavation height is 3-3.5m, and left and right sides step staggers 2-3m;Should spray after excavation, anchor, net system Supporting, spreading steelframe, highly locate at the above 30cm of steelframe arch springing, be close to steelframe dual-side along angle of declination 30 ° set up lock foot anchoring stock, Arch springing anchor pole and steelframe firmly weld, and multiple pneumatically placed concrete is to design thickness;
S4, uses the method in S3 step, gets out of a predicament or an embarrassing situation 8, right side gets out of a predicament or an embarrassing situation 9 on the left of construction;
S5, the 10-1 that tops bar, the position remaining core soil in advance of middle step 10-2 and the 10-3 that gets out of a predicament or an embarrassing situation, after each bench excavation, apply and face upward Arch preliminary bracing, after completing two tunnel excavations, supporting circulation, applies inverted arch in time, and inverted arch section length is 4-6m.
S6, circulation excavation tunnel at the bottom of 11, excavation drilling depth beam be 2-3m, after excavation, apply inverted arch preliminary bracing, complete two and open Dig, supporting circulation after, apply inverted arch in time, inverted arch section length is 4-6m.
Tunnel excavation method of the present invention has the following characteristics that
(1) constructing tunnel space is big, can the parallel operations of many work posts, improve work efficiency;
(2) being applicable to different spans, multiple form of fracture, preliminary bracing process operations is convenient;
(3) tunnel excavation construction is flexibly, and excavated surface is stable.
The small-sized solution cavity that the present invention provides is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch, and it can Reduce the impact that tunnel subsidence is restrained by non-homogeneous stress, effectively control tunnel deformation, the safety of balance tunnel construction, economy Property, speed of application, ensure constructing tunnel quality.
The present invention is not limited to above-mentioned embodiment, and anyone can draw other various forms under the enlightenment of the present invention Product, no matter but in its shape or structure, make any change, every have same as the present application or akin technical side Case, within all falling within protection scope of the present invention.

Claims (4)

  1. The most small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch, and described tunnel is Karst Tunnel, It is characterized in that, comprise the following steps:
    S1, fills the solution cavity bottom tunnel inverted arch;During cavern depth < 3m, use cushion construction, dry-laid rubble is changed and fills out (4), mortar flag stone (3) is filled in bottom and the top of solution cavity respectively;During cavern depth 3m-10m, grouting and reinforcing method is used to execute Work, injecting paste material uses C30 cement mortar;
    S2, arranges advance support, hoop excavation arc leading pit (5), and remaining core soil in advance in arch, tunnel;Excavation cyclic advance amount Less than 1.5m, it is equipped with preliminary bracing steelframe spacing;Should carry out after excavation spraying, anchor, net system supporting, simultaneously Use ductule (1) radial grouting to reinforce, set up steelframe, highly locate at the above 30cm of steelframe arch springing, be close to steelframe dual-side edge Angle of declination 30 ° sets up lock foot anchoring stock, and arch springing anchor pole welds with steelframe, and multiple pneumatically placed concrete is to design thickness;
    S3, on the left of excavation in step (7) in step (6), right side, excavation cyclic advance amount is less than 1.5m, itself and preliminary bracing Steelframe spacing is equipped with;Excavation height is 3-3.5m, and left and right sides step staggers 2-3m;Should spray after excavation, anchor, net system Supporting, spreading steelframe, highly locate at the above 30cm of steelframe arch springing, be close to steelframe dual-side along angle of declination 30 ° set up lock foot anchoring stock, Arch springing anchor pole and steelframe firmly weld, and multiple pneumatically placed concrete is to design thickness;
    S4, uses the method in S3 step, and (9) are got out of a predicament or an embarrassing situation in get out of a predicament or an embarrassing situation on the left of construction (8), right side;
    S5, top bar (10-1), middle step (10-2) and the position remaining core soil in advance of get out of a predicament or an embarrassing situation (10-3), after each bench excavation, Applying inverted arch preliminary bracing, after completing two tunnel excavations, supporting circulation, apply inverted arch in time, inverted arch section length is 4-6m;
    S6, at the bottom of circulation excavation tunnel (11), excavation drilling depth amount is 2-3m, after excavation, applies inverted arch preliminary bracing, completes two and open Dig, supporting circulation after, apply inverted arch in time, inverted arch section length is 4-6m.
  2. Tunnel excavation and karst cave treatment method the most according to claim 1, it is characterised in that in step S1, use cushion During construction, the specification of mortar flag stone (3) is M10.
  3. The most according to claim 1, tunnel excavation and karst cave treatment method, it is characterised in that in step S1, use slip casting to add Gu method construction, by seamless steel pipe (2) inject serosity, seamless steel pipe (2) gos deep into basement rock 1m, between seamless steel pipe (2) away from From for 1.5m.
  4. Tunnel excavation and karst cave treatment method the most according to claim 1, it is characterised in that in step S2, remaining core soil in advance A length of 3-5m, its width is the 1/3-1/2 of tunnel excavation width.
CN201610699191.4A 2016-08-22 2016-08-22 Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch Pending CN106121675A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610699191.4A CN106121675A (en) 2016-08-22 2016-08-22 Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610699191.4A CN106121675A (en) 2016-08-22 2016-08-22 Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch

Publications (1)

Publication Number Publication Date
CN106121675A true CN106121675A (en) 2016-11-16

Family

ID=57279663

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610699191.4A Pending CN106121675A (en) 2016-08-22 2016-08-22 Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch

Country Status (1)

Country Link
CN (1) CN106121675A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106640096A (en) * 2017-02-17 2017-05-10 中铁八局集团第工程有限公司 Construction method for penetrating through tunnel of backfilling soil section and transition section
CN106837371A (en) * 2017-03-23 2017-06-13 中铁五局集团成都工程有限责任公司 The step band inverted arch construction method of large deformation tunnel two
CN107013222A (en) * 2017-05-28 2017-08-04 中铁五局集团有限公司 A kind of the middle regions of the Yunnan Province red beds tunnel milling digging construction method close to existing railway
CN107387116A (en) * 2017-09-11 2017-11-24 中国矿业大学 Tunnel bottom plate concealed argillaceous filling karst replacement treatment method
CN107630706A (en) * 2017-10-24 2018-01-26 中交第二航务工程局有限公司 A kind of tunnel bottom structure and construction method for eliminating highland nip tunnel inverted arch protuberance
CN107905799A (en) * 2017-12-20 2018-04-13 中国建筑土木建设有限公司 Reinforced structure of high-speed rail tunnel bottom water passing karst cave and construction method thereof
CN108533271A (en) * 2018-03-12 2018-09-14 中铁建大桥工程局集团第四工程有限公司 A kind of two-tube tunnel radial grouting construction method in a hole
CN109555146A (en) * 2018-12-27 2019-04-02 中铁第勘察设计院集团有限公司 Karst Collapse Area peg board basement process pile foundation protects composite structure and construction method
CN111119904A (en) * 2019-12-18 2020-05-08 浙江大学城市学院 Construction method of soft surrounding rock karst section tunnel
CN111456738A (en) * 2020-03-06 2020-07-28 中国十七冶集团有限公司 Tunnel excavation method based on step method
CN111706366A (en) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 Tunnel lining structure penetrating through large full-filling karst cave and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4380098B2 (en) * 2001-08-24 2009-12-09 株式会社大林組 Expansion method of existing tunnel
CN103089270A (en) * 2013-01-23 2013-05-08 西南交通大学 Excavating method suitable for large section loess tunnels
CN103628890A (en) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 Soft phyllite tunnel excavation deformation control method
CN103628889A (en) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 Quick sealing method for excavating phyllite stratum tunnel
CN104847362A (en) * 2015-01-29 2015-08-19 中铁二院工程集团有限责任公司 Large-span subway station underground excavation construction method for hard rock stratum

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4380098B2 (en) * 2001-08-24 2009-12-09 株式会社大林組 Expansion method of existing tunnel
CN103089270A (en) * 2013-01-23 2013-05-08 西南交通大学 Excavating method suitable for large section loess tunnels
CN103628890A (en) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 Soft phyllite tunnel excavation deformation control method
CN103628889A (en) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 Quick sealing method for excavating phyllite stratum tunnel
CN104847362A (en) * 2015-01-29 2015-08-19 中铁二院工程集团有限责任公司 Large-span subway station underground excavation construction method for hard rock stratum

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
单奇伟: "某岩溶隧道施工技术研究", 《交通世界(建养.机械)》 *
蒋永冰等: "岩溶、溶洞隧道坍方分析及防坍处理", 《北方交通》 *
陈海军: "三台阶七步开挖法在大断面浅埋偏压地质条件下的应用", 《中小企业管理与科技(下旬刊)》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106640096A (en) * 2017-02-17 2017-05-10 中铁八局集团第工程有限公司 Construction method for penetrating through tunnel of backfilling soil section and transition section
CN106837371A (en) * 2017-03-23 2017-06-13 中铁五局集团成都工程有限责任公司 The step band inverted arch construction method of large deformation tunnel two
CN107013222A (en) * 2017-05-28 2017-08-04 中铁五局集团有限公司 A kind of the middle regions of the Yunnan Province red beds tunnel milling digging construction method close to existing railway
CN107387116A (en) * 2017-09-11 2017-11-24 中国矿业大学 Tunnel bottom plate concealed argillaceous filling karst replacement treatment method
CN107630706B (en) * 2017-10-24 2023-05-26 中交第二航务工程局有限公司 Tunnel bottom structure for eliminating tunnel inverted arch bulge in high-earth-pressure area and construction method
CN107630706A (en) * 2017-10-24 2018-01-26 中交第二航务工程局有限公司 A kind of tunnel bottom structure and construction method for eliminating highland nip tunnel inverted arch protuberance
CN107905799A (en) * 2017-12-20 2018-04-13 中国建筑土木建设有限公司 Reinforced structure of high-speed rail tunnel bottom water passing karst cave and construction method thereof
CN108533271A (en) * 2018-03-12 2018-09-14 中铁建大桥工程局集团第四工程有限公司 A kind of two-tube tunnel radial grouting construction method in a hole
CN109555146A (en) * 2018-12-27 2019-04-02 中铁第勘察设计院集团有限公司 Karst Collapse Area peg board basement process pile foundation protects composite structure and construction method
CN109555146B (en) * 2018-12-27 2023-11-10 中铁第一勘察设计院集团有限公司 Karst subsidence area pile plate foundation treatment pile foundation protection combined structure and construction method
CN111119904A (en) * 2019-12-18 2020-05-08 浙江大学城市学院 Construction method of soft surrounding rock karst section tunnel
CN111119904B (en) * 2019-12-18 2021-03-30 浙江大学城市学院 Construction method of soft surrounding rock karst section tunnel
CN111456738A (en) * 2020-03-06 2020-07-28 中国十七冶集团有限公司 Tunnel excavation method based on step method
CN111706366A (en) * 2020-06-30 2020-09-25 中铁二院工程集团有限责任公司 Tunnel lining structure penetrating through large full-filling karst cave and construction method

Similar Documents

Publication Publication Date Title
CN106121675A (en) Small-sized solution cavity is positioned at tunnel excavation and karst cave treatment method time at the bottom of tunneling inverted arch
CN106246201A (en) The excavation in tunnel and karst cave treatment method when small-sized solution cavity is positioned at tunneling surrounding
CN106194196B (en) A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN102562099B (en) Method for carrying out rapid face excavation construction of loess tunnel by double rows of small conduits
CN102134998B (en) Construction method for wind-blown sand tunnel
CN106246192A (en) Large-scale karst cave treatment under a kind of tunnel basis and base plate and tunnel excavation method
CN106246191B (en) A kind of hole body is dredged, fills plentiful large-scale karst cave treatment and tunnel excavation method deeply
CN104653187B (en) Method for excavating geological large-section tunnel with water-rich sand layer
CN107842368A (en) The non-quick-fried excavation technology of city tunnel Drilling milling mechanical combination
CN106703814A (en) Mined metro station hole pile construction method
CN102733827A (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN104847362B (en) Ground consisting of hard rock construction method across underground digging in subway station greatly
CN110374633A (en) The Portal Section Construction method of Tunnel Passing loose media
CN102031736A (en) Construction technology for under-passing existing line under complicated geological condition
CN103899318B (en) The milling of medium ground tunnel is dug and supporting machinery construction
CN102587922A (en) Oblique-crossing inclined shaft upper arc guide top brushing construction method for soft crushed rock layer
CN201991017U (en) Subway large-span station body structure based on arch cover method construction forming
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN106121659B (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one kind
CN107859523A (en) A kind of asymmetric supporting construction of Unevenly-pressured shallow tunnel and construction method
CN105134269A (en) Control technology for roadway surrounding rock achieving cooperative load bearing by enabling anchor cables to penetrate through sheds
CN104141500B (en) One hardens sand and gravel stratum cavern con struction method
CN109882185A (en) The construction method in the soft or hard uneven tunnel of rock matter under a kind of large ground pressure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhang Han

Inventor after: Wang Xiong

Inventor after: Zhang Chunfa

Inventor after: Lv Jia

Inventor after: Liu Jiyao

Inventor after: Wei Yinghua

Inventor after: Liu Fei

Inventor after: Yin Pengtao

Inventor after: Liu Shihai

Inventor after: Yang Dongbo

Inventor after: Li Wenhua

Inventor after: He Meide

Inventor after: He Shaochun

Inventor after: Ma Rui

Inventor after: Li Ning

Inventor after: Xue Huiqing

Inventor after: Wang Liping

Inventor before: Zhang Han

Inventor before: Zhang Chunfa

Inventor before: Liu Jiyao

Inventor before: Wei Yinghua

Inventor before: Liu Fei

Inventor before: Yin Pengtao

Inventor before: Liu Shihai

Inventor before: Yang Dongbo

Inventor before: Li Wenhua

Inventor before: He Meide

Inventor before: He Shaochun

Inventor before: Li Ning

Inventor before: Xue Huiqing

Inventor before: Wang Liping

Inventor before: Wang Xiong

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20170802

Address after: 100037 Beijing, Xicheng District, one hundred million Zhuang Street, No. 3

Applicant after: Municipal Engineering Inst. of Beijing

Applicant after: Beijing municipal administration road and bridge limited company

Address before: 100037 Beijing, Xicheng District, one hundred million Zhuang Street, No. 3

Applicant before: Municipal Engineering Inst. of Beijing

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161116