CN108385701A - Road Protection of Expansive Soil structure and its construction method - Google Patents

Road Protection of Expansive Soil structure and its construction method Download PDF

Info

Publication number
CN108385701A
CN108385701A CN201810212272.6A CN201810212272A CN108385701A CN 108385701 A CN108385701 A CN 108385701A CN 201810212272 A CN201810212272 A CN 201810212272A CN 108385701 A CN108385701 A CN 108385701A
Authority
CN
China
Prior art keywords
slope
level
side slope
stones
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810212272.6A
Other languages
Chinese (zh)
Inventor
刘英俊
张晨兮
胡力
程林
穆超宇
何永康
肖亚艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCFEB Civil Engineering Co Ltd
Original Assignee
CCFEB Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCFEB Civil Engineering Co Ltd filed Critical CCFEB Civil Engineering Co Ltd
Priority to CN201810212272.6A priority Critical patent/CN108385701A/en
Publication of CN108385701A publication Critical patent/CN108385701A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The present invention provides a kind of construction methods of road Protection of Expansive Soil structure, include the following steps:The clear table of side slope, top of the slope intercepting ditch build by laying bricks or stones, side slope earth excavation, watering moisturizing, impervious barrier is laid with, guide drainage facility is built by laying bricks or stones, metalling layings, slope protection construction, slope stability monitor;Safeguard structure includes:Impervious barrier, metalling, grey bank protection layer, level-one green protecting slope layer, water guide facility, pumping equipment.The present invention is combined using rigid protection with flexible support, easy for construction, process is simple, is also added to environmentally protective construction concept while ensureing slope stability, is met modern construction development trend.

Description

Road Protection of Expansive Soil structure and its construction method
Technical field
The invention belongs to swelling weak rock side slope protection technical fields, and in particular to road Protection of Expansive Soil structure and its Construction method.
Background technology
Three big characteristics of swelled ground:Fissurity, dilatancy and overconsolidation, thus, it is frequently encountered slope instability, landslide Equal geological disasters.
Technical measures in engineering for execavated rockmass punishment can substantially be divided into rigid retaining structure and point supporting system Two major classes.
Rigid retaining structure refers to being aided with based on masonry structure (Gravity Retaining Wall, friction pile and slabstone facing wall etc.) The processing scheme that other necessary integrated treatment measures are combined.It is current most common Treatment Methods.Its operation principle is It is answered with body of masonry dead weight to resist the overconsolidation that (balance) loses the side slope body of whole machine balancing and its generated in digging process Power discharges.Rigid retaining structure does not allow to be deformed by the retaining structure soil body, and under the action of drying and watering cycle, water, side slope Soil body certainty drying shrinkage bulking.When cannot be discharged when the dilatancy of the soil body is larger, will produce the prodigious bulbs of pressure makes just Property retaining structure destroy.
Point supporting system refers to being aided with other necessary integrated treatment measure phases based on chemical modifying, geotextile In conjunction with processing scheme.The characteristics of flexible retaining wall, which is it not only, can bear soil pressure but also the soil body is allowed to generate certain breathing change Shape, to absorb the expansive force that slope soil stress release caused by overconsolidation and change of moisture content generate.But flexible shoring knot The general working procedure of structure is complicated, construction speed is slow, is affected by rainwater weather.
Invention content
In order to overcome above-mentioned construction problem, the present invention to provide a kind of construction method of swelling weak rock slope treatment, It is combined with flexible support using rigid protection, it is easy for construction, process is simple, it is also added to while ensureing slope stability Environmentally protective construction concept meets modern construction development trend.
The present invention is achieved through the following technical solutions.
The construction method of road Protection of Expansive Soil structure, it is characterised in that include the following steps:
A, the clear table of side slope:Surveying setting-out carries out clear table to boundary of works area;
B, top of the slope intercepting ditch is built by laying bricks or stones:Before slope excavating, according to design requirement, builds top of the slope intercepting ditch by laying bricks or stones, side slope is avoided to be molded After there is wash away phenomenon;In conventional construction, the trapezoid cross section ditch of 60cm × 180cm × 60cm can be used in top of the slope intercepting ditch;
C, side slope earth excavation:As the height > 6m of side slope, two level slope is taken, it is flat to excavate level-one side slope, level-one side slope Platform and two level side slope;As height≤6m of side slope, level-one slope is taken, level-one side slope is only excavated;The step is according to the height of side slope Degree takes different digging modes, and the overall stability of side slope can be improved;In conventional construction, in slope height 0 when two level slope Level-one side slope is excavated within the scope of~6m, and the level-one plain stage of slope of 1.5~2.5m wide is excavated in the position of side slope slope height 6m, in The range of slope height > 6m excavates two level side slope;
D, watering moisturizing:It sprinkles water to level-one side slope, two level side slope and level-one plain stage of slope after slope excavating molding, controls side Slope soil water content is to make soil within natural moisture content ± 1% to ensure that the excavation face soil body will not generate cup shake because of dehydration Body strength reduction, phenomena such as causing Slope Sliding;
E, impervious barrier is laid with:It is laid with impervious barrier in level-one side slope, two level side slope and level-one plain stage of slope surface, to prevent rain Water penetrates into native side slope;
F, guide drainage facility is built by laying bricks or stones:Slope foot seepage ditch is built by laying bricks or stones prior to level-one side slope bottom end, and in slope foot seepage ditch bottom edge It is longitudinal to be laid with water-permeable pipe, then along slope foot seepage ditch no more than the drainpipe that laterally setting is connect with water-permeable pipe together at 40m, draining Pipe can access rainwater inspection well or inlet for stom water nearby;Then in level-one side slope bottom end slope foot intercepting ditch is built by laying bricks or stones and in level-one side slope Platform builds platform intercepting ditch by laying bricks or stones;
G, metalling is laid with:It is laid with metalling in the slope surface of level-one side slope, with the soil body near white-out crevice water and absorption Expansion energy;In conventional construction, the laying depth of metalling is 20cm;
H, slope protection construction:First grey bank protection layer, level-one green protecting slope are built by laying bricks or stones on metalling successively along level-one side slope surface Layer, then builds two level green protecting slope layer by laying bricks or stones in two level side slope surface;It is described while build grey bank protection layer and build by laying bricks or stones, extend transversely through ash Color bank protection layer installs tapping pipe;Metalling is wrapped up and be embedded to the water inlet end geotextiles of the tapping pipe, is contacted with tapping pipe Rubble, which changes, fills out Guamishi, and tapping pipe is arranged using the grid of 2m × 2m;In conventional construction, grey bank protection layer is built by laying bricks or stones in level-one side slope In the range of highly 0~3m, level-one green protecting slope layer is built by laying bricks or stones in the range of 3~6m of level-one slope height;
I, slope stability monitors;
It should be pointed out that although above-mentioned steps d, e, f, g, h, i provide side slope earth excavation rear stage side slope, two level The construction method of side slope and level-one plain stage of slope safeguard structure, that is, when taking two level slope, the construction method of slope protection structure As described in step d, e, f, g, h, i;And when using level-one bank protection, although only having excavated level-one side slope, level-one side slope protection knot The construction method of structure is same (to save two level side slope and level-one side slope in step d, e, f, g, h, i as described in step d, e, f, g, h, i The construction details of platform).
As optimal technical scheme, in the step c, level-one side slope and two level side slope are 1 by slope ratio:3, it takes from upper Under and, it is segmented the method for being classified rapid construction, every section of construction distance≤40m, excavation face reserves the protective layer of 1.5m~2.0m.
As optimal technical scheme, in the step e, impervious barrier is thickness 1mm, weight 200g/m2Two cloth, one film.
As optimal technical scheme, the slope foot intercepting ditch, top of the slope intercepting ditch, platform intercepting ditch, grey bank protection layer are adopted MU30 slabstones are grouted with M10 to build by laying bricks or stones;It is paved with rubble in the slope foot seepage ditch.
As optimal technical scheme, in the step f, control water-permeable pipe longitudinal slope should be not less than 1% when being laid with water-permeable pipe.
As optimal technical scheme, in the step h, the thickness of the grey bank protection layer is 0.8m, level-one green protecting slope The thickness of layer is 0.8m, the thickness of two level green protecting slope layer is 0.4m.
As optimal technical scheme, in the step h, level-one green protecting slope layer and two level green protecting slope layer pass through following sides Formula is built by laying bricks or stones:Pile plant biological bag is installed from the bottom to top, spray kind grass-seed, watering maintenance to grass-seed grow green seedling i.e. in time after installation is complete It can.
As optimal technical scheme, the specific method of the step i slope stabilities monitoring is:In top of the slope, level-one side slope Platform, slope foot every 20m arrange a monitoring point, monitoring project include top of the slope, level-one plain stage of slope, slope foot level vertical position It moves, surface cracks, top of the slope constructs composition deformation etc..
Road Protection of Expansive Soil structure, the side slope include level-one side slope, which is characterized in that the safeguard structure packet It includes:Impervious barrier, metalling, grey bank protection layer, level-one green protecting slope layer, water guide facility, pumping equipment;Wherein,
The impervious barrier covers entire level-one side slope;
The metalling is laid on along level-one side slope surface above impervious barrier;
The grey bank protection layer, the level-one green protecting slope layer are layed in broken successively from bottom to up along the slope surface of level-one side slope In rock layers;
The water guide facility include build by laying bricks or stones the slope foot seepage ditch of slope foot, the water-permeable pipe being laid with along slope foot seepage ditch bottom, The tapping pipe for extending transversely through grey bank protection layer, the drainpipe for being laterally arranged along slope foot seepage ditch and being connect with water-permeable pipe;
The pumping equipment include build by laying bricks or stones slope foot slope foot intercepting ditch, build top of the slope intercepting ditch in top of the slope by laying bricks or stones.
As optimal technical scheme, the side slope further includes level-one plain stage of slope, excavates in level-one side slope and two level side slope Between two level side slope;The safeguard structure further includes two level green protecting slope layer, platform intercepting ditch;
The impervious barrier also covers entire level-one plain stage of slope, two level side slope;
The two level green protecting slope layer is laid on above impervious barrier successively from bottom to up along the slope surface of two level side slope;
The platform intercepting ditch is built by laying bricks or stones in level-one plain stage of slope.
Compared with prior art, the invention has the advantages that:
1, patent of the present invention plays good protective action to swelling weak rock side slope, solves swelling weak rock side well The problem of slope unstability sliding;
2, patent working construction input of the present invention is small, easy for construction rapid;
3, patent combining with green environmental protection construction theory of the present invention meets the trend of modern infrastructure construction.
Description of the drawings
The schematic diagram of road Protection of Expansive Soil structure and construction method of the present invention when Fig. 1 is two level slope;
The schematic diagram of road Protection of Expansive Soil structure and construction method of the present invention when Fig. 2 is level-one slope;
The meaning respectively marked in above-mentioned figure is:
1- impervious barriers;
2- metallings;
3- grey bank protection layers;
4- level-one green protecting slope layers;
5- two level green protecting slope layers;
6- water guide facilities, 61- slope foot seepage ditch, 62- water-permeable pipes, 63- tapping pipes, 64- drainpipes;
7- pumping equipments, 71- slope foot intercepting ditch, 72- top of the slope intercepting ditch, 73- platform intercepting ditch;
The road surfaces 8-;
9- side slopes, 91- level-one side slopes, 92- level-one plain stage of slopes, 93- two level side slopes.
Specific implementation mode
The present invention is described further With reference to embodiment, it is pointed out that following implementation is only It is the indicative explaination done to the present invention in the form of enumerating, but protection scope of the present invention is not limited to that, Suo Youben The technical staff in field each falls within protection scope of the present invention with the equivalent replacement that the spirit of the present invention is the present invention.
Embodiment 1
The construction method of road Protection of Expansive Soil structure, please refers to Fig.1, Fig. 2, includes the following steps:
A, the clear table of side slope:Surveying setting-out carries out clear table to boundary of works area;
B, top of the slope intercepting ditch is built by laying bricks or stones:Before slope excavating, according to design requirement, build top of the slope intercepting ditch 72 by laying bricks or stones, avoid side slope at Occurs wash away phenomenon after type;
C, side slope earth excavation:Referring to Fig. 1, as the height > 6m of side slope 9, two level slope is taken, excavates level-one side slope 91, level-one plain stage of slope 92 and two level side slope 93;Referring to Fig. 2, as height≤6m of side slope 9, level-one slope is taken, is only excavated Level-one side slope 91;
D, watering moisturizing:It sprinkles water to level-one side slope 91, two level side slope 93 and level-one plain stage of slope 92 after slope excavating molding, It is within natural moisture content ± 1% to control side slope soil water content;
E, impervious barrier is laid with:It is laid with impervious barrier 1 in level-one side slope 91, two level side slope 93 and 92 surface of level-one plain stage of slope;
F, guide drainage facility is built by laying bricks or stones:Slope foot seepage ditch 61 is built by laying bricks or stones prior to 91 bottom end of level-one side slope, and in slope foot seepage ditch 61 Bottom is laid with water-permeable pipe 62 along longitudinal direction, then along slope foot seepage ditch 61 no more than laterally setting is connect with water-permeable pipe 62 together at 40m Drainpipe 64;Then it builds slope foot intercepting ditch 71 by laying bricks or stones in 91 bottom end of level-one side slope and builds platform by laying bricks or stones in level-one plain stage of slope 92 and intercept water Ditch 73;
G, metalling is laid with:It is laid with metalling 2 in the slope surface of level-one side slope 91;
H, slope protection construction:First grey bank protection layer 3, level-one green are built by laying bricks or stones on metalling 2 successively along 91 surface of level-one side slope Then bank protection layer 4 builds two level green protecting slope layer 5 by laying bricks or stones in 93 surface of two level side slope;While building grey bank protection layer 3 and build by laying bricks or stones, laterally Tapping pipe 63 is installed through grey bank protection layer 3;Metalling 2 is wrapped up and be embedded to the water inlet end geotextiles of tapping pipe 63, with sluicing The rubble that pipe 63 contacts, which changes, fills out Guamishi, and tapping pipe 63 is arranged using the grid of 2m × 2m;
I, slope stability monitors.
Embodiment 2
The construction method of road Protection of Expansive Soil structure, as height≤6m of side slope, referring to Fig. 2, including such as Lower step:
A, the clear table of side slope:Surveying setting-out carries out clear table to boundary of works area;
B, top of the slope intercepting ditch is built by laying bricks or stones:Before slope excavating, according to design requirement, it is 60cm × 180cm × 60cm to build section by laying bricks or stones Trapezoidal top of the slope intercepting ditch 72;
C, side slope earth excavation:Level-one slope is taken, level-one side slope 91 is only excavated;Level-one side slope 91 is 1 by slope ratio:3, it adopts Take from top to bottom, the method for segmentation classification rapid construction, every section of construction distance≤40m, excavation face reserves the guarantor of 1.5m~2.0m Sheath;Covering waterproof cloth, waterproof cloth answer horizontal cross to overlap in time later, and upper layer cloth depresses layer cloth, and the lap of splice is no less than 50cm, slope foot should fasten waterproof cloth with upper and lower gutter edge overlap joint up and down, and slope surface lap-joint should be fastened using earth bag;In addition, In digging process, large-scale excavation, roll or hanging device should not in upper level side slope or riding track operation walk;
D, watering moisturizing:After slope excavating molding, sprinkled water to level-one side slope 91 using large-scale shower, control side slope soil is aqueous Amount is within natural moisture content ± 1%;
E, impervious barrier is laid with:In 91 surface of level-one side slope be laid with impervious barrier 1, impervious barrier 1 should will include slope foot intercepting ditch 71, 91 all standing of level-one side slope of top of the slope intercepting ditch 72;Impervious barrier 1 selects thick 1mm, weight 200g/m2Two cloth, one film;
F, guide drainage facility is built by laying bricks or stones:Slope foot seepage ditch 61 is built by laying bricks or stones prior to 91 bottom end of level-one side slope, and in slope foot seepage ditch 61 Bottom is laid with water-permeable pipe 62 along longitudinal direction, and 62 longitudinal slope of control water-permeable pipe should be not less than 1%;It is not more than 40m along slope foot seepage ditch 61 again Place's drainpipe 64 that laterally setting is connect with water-permeable pipe 62 together, the rainwater inspection well or inlet for stom water of the access of drainpipe 64 nearby; Then slope foot intercepting ditch 71 is built by laying bricks or stones in 91 bottom end of level-one side slope;
G, metalling is laid with:It is laid with the metalling 2 of 20cm thickness in the slope surface of level-one side slope 91;
H, slope protection construction:First the grey bank protection that thickness is 0.8m is built by laying bricks or stones on metalling 2 successively along 91 surface of level-one side slope Layer 3, the level-one green protecting slope layer 4 that thickness is 0.8m;While grey bank protection layer 3 is built by laying bricks or stones, the peace of grey bank protection layer 3 is extended transversely through Fill tapping pipe 63;Metalling 2 is wrapped up and be embedded to the water inlet end geotextiles of tapping pipe 63, and the rubble contacted with tapping pipe 63, which changes, to be filled out Guamishi, tapping pipe 63 are arranged using the grid of 2m × 2m;
I, slope stability monitors:A monitoring point is arranged every 20m, monitoring project includes top of the slope, slope in top of the slope, slope foot The vertical displacement of foot level, surface cracks, top of the slope construct composition deformation etc.;During slope project During Initial Stage Construction and excavation, monitoring is suitable Once a day;Excavation is completed to during slope protection engineering construction is completed to be completed 1 month once a week;It is completed 1 month to half a year Monthly;It is completed half a year to 2 years 4~6 times;According to geological environment complexity, periphery construction of structures, the deformation of pipeline side slope Sensitivity, weather conditions and monitoring data adjustment monitoring time and frequency;It should reinforce monitoring when there is dangerous situation;
In the present embodiment, it is the pvc pipe of 160mm that water-permeable pipe 62, which selects outer diameter,;It is 110mm's that drainpipe 64, which selects outer diameter, Pvc pipe;Tapping pipe 63 selects the UPVC that outer diameter is 75mm to manage;Slope foot intercepting ditch 71, top of the slope intercepting ditch 72, grey bank protection layer 3 are equal MU30 slabstones are grouted using M10 to build by laying bricks or stones;Level-one green protecting slope layer 4 is built by laying bricks or stones by following manner:Installation pile plants life from the bottom to top Bag, spray kind grass-seed, watering maintenance to grass-seed grow green seedling in time after installation is complete.
Embodiment 3
The construction method of road Protection of Expansive Soil structure, as the height > 6m of side slope, referring to Fig. 1, including such as Lower step:
A, the clear table of side slope:Surveying setting-out carries out clear table to boundary of works area;
B, top of the slope intercepting ditch is built by laying bricks or stones:Before slope excavating, according to design requirement, it is 60cm × 180cm × 60cm to build section by laying bricks or stones Trapezoidal top of the slope intercepting ditch;
C, side slope earth excavation:Two level slope is taken, level-one side slope 91, level-one plain stage of slope 92 and two level side slope are excavated 93;It is 1 that level-one side slope 91 and two level side slope 93, which press slope ratio,:3, take from top to bottom, segmentation classification rapid construction method, often Section construction distance≤40m, excavation face reserve the protective layer of 1.5m~2.0m;Covering waterproof cloth, waterproof cloth answer level in time later Transverse lap, upper layer cloth depress layer cloth, and the lap of splice is no less than 50cm, and slope foot should be taken waterproof cloth with upper and lower gutter edge up and down It connects and fastens, slope surface lap-joint should be fastened using earth bag;In addition, in digging process, large-scale excavation rolls or hanging device is not answered Operation is walked in upper side slope or riding track;
D, watering moisturizing:After slope excavating molding, using large-scale shower to level-one side slope 91, two level side slope 93 and level-one side Slope platform 92 is sprinkled water, and control side slope soil water content is within natural moisture content ± 1%;
E, impervious barrier is laid with:It is laid with impervious barrier 1 in level-one side slope 91, two level side slope 93 and 92 surface of level-one plain stage of slope; Impervious barrier 1 should be by 9 all standing of side slope including slope foot intercepting ditch, platform intercepting ditch, top of the slope intercepting ditch;Impervious barrier 1 selects thickness 1mm, weight 200g/m2Two cloth, one film;
F, guide drainage facility is built by laying bricks or stones:Slope foot seepage ditch 61 is built by laying bricks or stones prior to 91 bottom end of level-one side slope, and in slope foot seepage ditch 61 Bottom is laid with water-permeable pipe 62 along longitudinal direction, and control water-permeable pipe longitudinal slope should be not less than 1%;Again along slope foot seepage ditch 61 no more than at 40m The drainpipe 64 that laterally setting is connect with water-permeable pipe 62 together, the rainwater inspection well or inlet for stom water of the access of drainpipe 64 nearby;So Slope foot intercepting ditch 71 is built by laying bricks or stones in 91 bottom end of level-one side slope and build platform intercepting ditch 73 by laying bricks or stones in level-one plain stage of slope 92 afterwards;
G, metalling is laid with:It is laid with the metalling 2 of 20cm thickness in the slope surface of level-one side slope 91;
H, slope protection construction:First the grey bank protection that thickness is 0.8m is built by laying bricks or stones on metalling 2 successively along 91 surface of level-one side slope Then layer 3, the level-one green protecting slope layer 4 that thickness is 0.8m build the two level green that thickness is 0.4m by laying bricks or stones in 93 surface of two level side slope Bank protection layer 5;While grey bank protection layer 3 is built by laying bricks or stones, extends transversely through grey bank protection layer 3 and tapping pipe 63 is installed;Tapping pipe 63 into Metalling 2 is wrapped up and be embedded to water end (W.E.) geotextiles, and the rubble contacted with tapping pipe 63, which changes, fills out Guamishi, and the use of tapping pipe 63 2m × The grid of 2m is arranged;
I, slope stability monitors:In top of the slope, level-one plain stage of slope 92, slope foot a monitoring point, monitoring are arranged every 20m Project includes top of the slope, level-one plain stage of slope 92, the vertical displacement of slope foot level, surface cracks, and top of the slope constructs composition deformation etc.;Side slope During engineering construction initial stage and excavation, monitoring is preferably once a day;Excavation is completed to slope protection engineering construction and completes to be completed 1 month Period is once a week;Be completed 1 month to half a year monthly;It is completed half a year to 2 years 4~6 times;According to geological environment complexity journey Degree, periphery construction of structures, the sensitivity of pipeline side slope deformation, weather conditions and monitoring data adjustment monitoring time and frequency Rate;It should reinforce monitoring when there is dangerous situation;
In the present embodiment, it is the pvc pipe of 160mm that water-permeable pipe 62, which selects outer diameter,;It is 110mm's that drainpipe 64, which selects outer diameter, Pvc pipe;Tapping pipe 63 selects the UPVC that outer diameter is 75mm to manage;Slope foot intercepting ditch 71, top of the slope intercepting ditch 72, grey bank protection layer 3 are equal MU30 slabstones are grouted using M10 to build by laying bricks or stones;Level-one green protecting slope layer 4, two level green protecting slope layer 5 are built by laying bricks or stones by following manner:Under Supreme installation pile plant biological bag, spray kind grass-seed, watering maintenance to grass-seed grow green seedling in time after installation is complete.
Embodiment 4
Road Protection of Expansive Soil structure, as shown in Fig. 2, side slope 9 includes level-one side slope 91, safeguard structure includes:It is anti- Infiltration layer 1, metalling 2, grey bank protection layer 3, level-one green protecting slope layer 4, water guide facility 6, pumping equipment 7;Wherein,
Impervious barrier 1 covers entire level-one side slope 91;
Metalling 2 is laid on 1 top of impervious barrier along 91 slope surface of level-one side slope;
Grey bank protection layer 3, level-one green protecting slope layer 4 are layed in metalling successively from bottom to up along the slope surface of level-one side slope 91 On 2;
Water guide facility 6 includes building slope foot seepage ditch 61 in slope foot, the water-permeable pipe that is laid with along 61 bottom of slope foot seepage ditch by laying bricks or stones 62, the tapping pipe 63 for extending transversely through grey bank protection layer 3, the draining for being laterally arranged along slope foot seepage ditch 61 and being connect with water-permeable pipe 62 Pipe 64;
Pumping equipment 7 include build by laying bricks or stones slope foot slope foot intercepting ditch 71, build top of the slope intercepting ditch 72 in top of the slope by laying bricks or stones.
Embodiment 5
In order to improve the stability of side slope and slope protection structure, different excavation sides can be taken according to the height of side slope Formula, to improve the overall stability of side slope;In general, slope height be more than 6m when need to take two level slope, to excavate level-one side slope, Two level side slope and the level-one plain stage of slope between level-one side slope and two level side slope;Therefore, on the basis of embodiment 4, such as Shown in Fig. 1, side slope 9 further includes two level side slope 93, excavates the level-one plain stage of slope between level-one side slope 91 and two level side slope 93 92;Impervious barrier 1 also covers entire level-one plain stage of slope 91, two level side slope 93;Two level green protecting slope layer 5 is along 93 slope surface of two level side slope It is laid on 1 top of impervious barrier successively from bottom to up;Platform intercepting ditch 73 is built by laying bricks or stones in level-one plain stage of slope 92.

Claims (10)

1. the construction method of road Protection of Expansive Soil structure, it is characterised in that include the following steps:
A, the clear table of side slope;
B, top of the slope intercepting ditch is built by laying bricks or stones;
C, side slope earth excavation:As the height > 6m of side slope, two level slope is taken, it is flat to excavate level-one side slope (91), level-one side slope Platform (92) and two level side slope (93);As height≤6m of side slope, level-one slope is taken, level-one side slope (91) is only excavated;
D, watering moisturizing:Level-one side slope (91), two level side slope (93) and level-one plain stage of slope (92) are spilt after slope excavating molding Water, control side slope soil water content are within natural moisture content ± 1%;
E, impervious barrier is laid with:It is laid with impervious barrier in level-one side slope (91), two level side slope (93) and level-one plain stage of slope (92) surface (1);
F, guide drainage facility is built by laying bricks or stones:Slope foot seepage ditch (61) is built by laying bricks or stones prior to level-one side slope (91) bottom end, and in slope foot seepage ditch (61) bottom is laid with water-permeable pipe (62) along longitudinal direction, then along slope foot seepage ditch (61) no more than the places 40m laterally one of setting with it is permeable Manage the drainpipe (64) of (62) connection;Then it builds slope foot intercepting ditch (71) by laying bricks or stones in level-one side slope (91) bottom end and is put down in level-one side slope Platform (92) builds platform intercepting ditch (73) by laying bricks or stones;
G, metalling is laid with:It is laid with metalling (2) in the slope surface of level-one side slope (91);
H, slope protection construction:It is green first grey bank protection layer (3), level-one to be built by laying bricks or stones on metalling (2) successively along level-one side slope (91) surface Color bank protection layer (4) then builds two level green protecting slope layer (5) by laying bricks or stones in two level side slope (93) surface;It is described to build grey bank protection layer (3) block While building, grey bank protection layer (3) installation tapping pipe (63) is extended transversely through;The geotechnological cloth bag of the water inlet end of the tapping pipe (63) Metalling (2) is wrapped up in and is embedded to, the rubble contacted with tapping pipe (63), which changes, fills out Guamishi, and tapping pipe (63) uses the grid of 2m × 2m Arrangement;
I, slope stability monitors.
2. the construction method of road Protection of Expansive Soil structure as described in claim 1, it is characterised in that the step c In, level-one side slope (91) and two level side slope (93) they are 1 by slope ratio:3, take from top to bottom, segmentation classification rapid construction side Method, every section of construction distance≤40m, excavation face reserve the protective layer of 1.5m~2.0m.
3. the construction method of road Protection of Expansive Soil structure as described in claim 1, it is characterised in that the step e In, impervious barrier (1) is thickness 1mm, weight 200g/m2Two cloth, one film.
4. the construction method of road Protection of Expansive Soil structure as described in claim 1, it is characterised in that the slope foot is cut Ditch (71), top of the slope intercepting ditch (72), platform intercepting ditch (73), grey bank protection layer (3) are all made of M10 and grout MU30 piece barnacles It builds;It is paved with rubble in the slope foot seepage ditch (61).
5. the construction method of road Protection of Expansive Soil structure as described in claim 1, it is characterised in that the step f In, control water-permeable pipe longitudinal slope is not less than 1% when being laid with water-permeable pipe (62).
6. the construction method of road Protection of Expansive Soil structure as described in claim 1, it is characterised in that the step h In, the thickness of the grey bank protection layer (3) is 0.8m, and the thickness of level-one green protecting slope layer (4) is 0.8m, two level green protecting slope layer (5) thickness is 0.4m.
7. the construction method of road Protection of Expansive Soil structure as described in claim 1 or 6, it is characterised in that the step In h, level-one green protecting slope layer (4) and two level green protecting slope layer (5) are built by laying bricks or stones by following manner:Installation pile plants life from the bottom to top Bag, spray kind grass-seed, watering maintenance to grass-seed grow green seedling in time after installation is complete.
8. the construction method of road Protection of Expansive Soil structure as described in claim 1, it is characterised in that the sides the step i Slope stability monitoring specific method be:In top of the slope, level-one plain stage of slope (92), slope foot a monitoring point, prison are arranged every 20m Survey project includes top of the slope, level-one plain stage of slope (92), the vertical displacement of slope foot level, surface cracks, and top of the slope constructs composition deformation etc..
9. road Protection of Expansive Soil structure, the side slope (9) includes level-one side slope (91), which is characterized in that the protection Structure includes:Impervious barrier (1), metalling (2), grey bank protection layer (3), level-one green protecting slope layer (4), water guide facility (6), draining Facility (7);Wherein,
The impervious barrier (1) covers entire level-one side slope (91);
The metalling (2) is laid on along level-one side slope (91) slope surface above impervious barrier (1);
The grey bank protection layer (3), the level-one green protecting slope layer (4) spread successively from bottom to up along the slope surface of level-one side slope (91) On metalling (2);
The water guide facility (6) includes building by laying bricks or stones to be laid in the slope foot seepage ditch (61) of slope foot, along slope foot seepage ditch (61) bottom Water-permeable pipe (62), the tapping pipe (63) for extending transversely through grey bank protection layer (3), along slope foot seepage ditch (61) laterally setting and with it is permeable Manage the drainpipe (64) of (62) connection;
The pumping equipment (7) include build by laying bricks or stones slope foot slope foot intercepting ditch (71), build top of the slope intercepting ditch (72) in top of the slope by laying bricks or stones.
10. road Protection of Expansive Soil structure as claimed in claim 9, which is characterized in that the side slope (9) further includes two Grade side slope (93) excavates the level-one plain stage of slope (92) between level-one side slope (91) and two level side slope (93);The protection knot Structure further includes two level green protecting slope layer (5), platform intercepting ditch (73);
The impervious barrier (1) also covers entire level-one plain stage of slope (91), two level side slope (93);
The two level green protecting slope layer (5) is laid on along two level side slope (93) slope surface above impervious barrier (1) successively from bottom to up;
The platform intercepting ditch (73) is built by laying bricks or stones in level-one plain stage of slope (92).
CN201810212272.6A 2018-03-14 2018-03-14 Road Protection of Expansive Soil structure and its construction method Pending CN108385701A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810212272.6A CN108385701A (en) 2018-03-14 2018-03-14 Road Protection of Expansive Soil structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810212272.6A CN108385701A (en) 2018-03-14 2018-03-14 Road Protection of Expansive Soil structure and its construction method

Publications (1)

Publication Number Publication Date
CN108385701A true CN108385701A (en) 2018-08-10

Family

ID=63067497

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810212272.6A Pending CN108385701A (en) 2018-03-14 2018-03-14 Road Protection of Expansive Soil structure and its construction method

Country Status (1)

Country Link
CN (1) CN108385701A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930613A (en) * 2019-04-23 2019-06-25 中国电建集团贵阳勘测设计研究院有限公司 Construction method and structure of drainage system of permeable roadbed slope
CN111576451A (en) * 2020-06-11 2020-08-25 长沙理工大学 Expansive soil cutting slope prevention and control structure and construction method thereof
CN112627203A (en) * 2020-12-25 2021-04-09 南昌航空大学 Construction method of ecological protection structure of soil slope
CN113846659A (en) * 2021-11-10 2021-12-28 中国电建集团成都勘测设计研究院有限公司 Method for treating expansive soil slope and application thereof
CN114875936A (en) * 2022-05-30 2022-08-09 中国二十冶集团有限公司 Construction method for drainage and protection of high cut slope side ditch
CN115323862A (en) * 2022-08-24 2022-11-11 中国十七冶集团有限公司 Drainage construction process for slope tops around anti-infiltration foundation pit

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338027A (en) * 1995-06-13 1996-12-24 Ohbayashi Corp Construction of slope of embankment
CN101613195A (en) * 2009-07-28 2009-12-30 长江水利委员会长江科学院 Quick slope protection material of expansive rocks and soils
CN102444134A (en) * 2011-10-09 2012-05-09 东南大学 Slope protecting method based on slope with soil layer as upper part and rock layer as lower part
CN105569058A (en) * 2016-02-16 2016-05-11 中国建筑第六工程局有限公司 Expansive soil cutting structure and construction method thereof
CN106703053A (en) * 2016-12-19 2017-05-24 上海市政工程设计研究总院(集团)有限公司 Construction method for reinforced soil drainage composite revetment structure
CN106703050A (en) * 2016-11-30 2017-05-24 中铁二院昆明勘察设计研究院有限责任公司 Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN206873464U (en) * 2017-04-26 2018-01-12 谢东 A kind of expansive soil slope ruggedized construction
CN207079601U (en) * 2017-07-10 2018-03-09 湖南省建筑工程集团设计研究院 A kind of point supporting system for administering swelled ground execavated rockmass landslide

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08338027A (en) * 1995-06-13 1996-12-24 Ohbayashi Corp Construction of slope of embankment
CN101613195A (en) * 2009-07-28 2009-12-30 长江水利委员会长江科学院 Quick slope protection material of expansive rocks and soils
CN102444134A (en) * 2011-10-09 2012-05-09 东南大学 Slope protecting method based on slope with soil layer as upper part and rock layer as lower part
CN105569058A (en) * 2016-02-16 2016-05-11 中国建筑第六工程局有限公司 Expansive soil cutting structure and construction method thereof
CN106703050A (en) * 2016-11-30 2017-05-24 中铁二院昆明勘察设计研究院有限责任公司 Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN106703053A (en) * 2016-12-19 2017-05-24 上海市政工程设计研究总院(集团)有限公司 Construction method for reinforced soil drainage composite revetment structure
CN206873464U (en) * 2017-04-26 2018-01-12 谢东 A kind of expansive soil slope ruggedized construction
CN207079601U (en) * 2017-07-10 2018-03-09 湖南省建筑工程集团设计研究院 A kind of point supporting system for administering swelled ground execavated rockmass landslide

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930613A (en) * 2019-04-23 2019-06-25 中国电建集团贵阳勘测设计研究院有限公司 Construction method and structure of drainage system of permeable roadbed slope
CN111576451A (en) * 2020-06-11 2020-08-25 长沙理工大学 Expansive soil cutting slope prevention and control structure and construction method thereof
CN111576451B (en) * 2020-06-11 2022-01-07 长沙理工大学 Expansive soil cutting slope prevention and control structure and construction method thereof
CN112627203A (en) * 2020-12-25 2021-04-09 南昌航空大学 Construction method of ecological protection structure of soil slope
CN113846659A (en) * 2021-11-10 2021-12-28 中国电建集团成都勘测设计研究院有限公司 Method for treating expansive soil slope and application thereof
CN114875936A (en) * 2022-05-30 2022-08-09 中国二十冶集团有限公司 Construction method for drainage and protection of high cut slope side ditch
CN115323862A (en) * 2022-08-24 2022-11-11 中国十七冶集团有限公司 Drainage construction process for slope tops around anti-infiltration foundation pit

Similar Documents

Publication Publication Date Title
CN108385701A (en) Road Protection of Expansive Soil structure and its construction method
CN100464034C (en) Flexible reinforced retaining structure and construction method therefor
CN103669399B (en) Concrete slab reinforced soil retaining wall and construction method thereof
CN105464056A (en) Anti-seepage structure capable of adapting to settlement of earth and rockfill dam
CN109024458B (en) Construction method for landscape revetment and underwater seepage prevention of coal mining subsidence land
CN105569058A (en) Expansive soil cutting structure and construction method thereof
CN107938692A (en) A kind of draining and recharge construction method and structure
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN209011090U (en) A kind of hydraulic engineering irrigates, flood control dam
CN111139840B (en) Ecological restoration method for tableland slope of fixed ditch in gully region of loess plateau of longdong
CN105544576A (en) Foundation ditch dewatering and drainage excavation structure and application method
CN110438999A (en) A kind of deep basal pit slope excavation construction method of rich groundwater
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN106120822B (en) A kind of method for protecting support and device that prevent mud stone from coming down
CN209066468U (en) A kind of base pit dewatering device
CN205399440U (en) Inflation dirt road moat structure
CN109235469A (en) A kind of Cut Slopes of Expansive Soil structure and its construction method
CN109610429A (en) Sedimentation treatment method under a kind of Collapsible Loess District prevention gas collection station ground and terrace
CN109162291A (en) Big thickness collapsible loess area blower foundation foundation structure and its construction method
CN209412838U (en) A kind of Cut Slopes of Expansive Soil structure
CN108951557B (en) Irrigation and flood control dam for hydraulic engineering
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN111379273A (en) Construction method of corrugated steel comprehensive pipe gallery
CN106149736B (en) The stable construction method of hillside fields bury excavation slope is kept based on draining is cut
CN115162347A (en) Deep foundation pit pipe network construction process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180810