CN108343102A - 一种桩基础沉降加固顶升调平结构及其施工方法 - Google Patents

一种桩基础沉降加固顶升调平结构及其施工方法 Download PDF

Info

Publication number
CN108343102A
CN108343102A CN201810385674.6A CN201810385674A CN108343102A CN 108343102 A CN108343102 A CN 108343102A CN 201810385674 A CN201810385674 A CN 201810385674A CN 108343102 A CN108343102 A CN 108343102A
Authority
CN
China
Prior art keywords
pile foundation
slip casting
pile
cushion cap
reinforced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810385674.6A
Other languages
English (en)
Other versions
CN108343102B (zh
Inventor
吴继光
崔腾跃
崔学栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Technology Co Ltd Beijing Hengxiang Hongye Foundation Reinforcement
Original Assignee
Technology Co Ltd Beijing Hengxiang Hongye Foundation Reinforcement
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Technology Co Ltd Beijing Hengxiang Hongye Foundation Reinforcement filed Critical Technology Co Ltd Beijing Hengxiang Hongye Foundation Reinforcement
Priority to CN201810385674.6A priority Critical patent/CN108343102B/zh
Publication of CN108343102A publication Critical patent/CN108343102A/zh
Priority to PCT/CN2019/084388 priority patent/WO2019206241A1/zh
Priority to DE112019002113.3T priority patent/DE112019002113T5/de
Priority to US17/037,730 priority patent/US11453992B2/en
Application granted granted Critical
Publication of CN108343102B publication Critical patent/CN108343102B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • E02D35/005Lowering or lifting of foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/34Foundations for sinking or earthquake territories
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material

Abstract

本发明公开了一种桩基础沉降加固顶升调平结构及其施工方法,该结构包括桩基础承台,所述桩基础承台下部固定连接有多根桩基础;承台下方软弱土加固层;桩端持力层。采用加固顶升法进行施工,具体是通过“桩基础承台顶升调平”和“桩端持力层加固补强”等新型技术工艺综合运用,桩基础承台下部形成扩大的复合地基承载体,桩端持力层增加强度,使上部荷载均匀传递至持力层,本方案成功解决了工业厂房桩基础沉降和顶升调平的目的,使其达到地基承载力要求和设计允许偏差范围内。具有施工工作面小,无干扰施工,能提高地基承载力和顶升调平双重效果等优点。

Description

一种桩基础沉降加固顶升调平结构及其施工方法
技术领域
本发明涉及建筑设施技术领域,特别是涉及一种适用于工业厂房有承台的桩基础沉降加固顶升调平结构及其施工方法。
背景技术
在建筑施工前,对存在较大深度的回填土层或软弱地基进行处理,在不具备天然地基的条件下,大多数建筑需打桩做基础,再施工上部建筑结构。由于地基处理不密实,地基土层具有较大的压缩性,地基承载力不足;或随着地下水的排泄条件的改变,形成地下水侵蚀现象,导致地基承载力降低;或由于桩端与基岩存在软弱夹层;或岩面倾斜度大,桩端入岩深度不够导致侧滑;或桩周土层松,软摩擦系数低等因素导致桩基础发生不均匀沉降。故而需对桩基础承重台顶升调平和桩端持力层压浆补强,达到地基承载力要求和设计允许沉降偏差范围内,缩小建筑桩基础之间的高差,保证厂房的结构安全。
发明内容
本发明提供了一种桩基础沉降加固顶升调平结构及其施工方法。
本发明提供了如下方案:
一种桩基础沉降加固顶升调平结构,包括:
桩基础承重台,所述桩基础承重台下部固定连接有多根桩基础;
承台下方软弱土加固层,所述桩基础承台位于所述承台下方软弱土加固层上方;所述承台下方软弱土加固层开设有多个第一注浆孔,所述第一注浆孔穿过所述桩基础承台与外部导通;所述第一注浆孔用于向所述承台下方软弱土加固层内进行第一次注浆以便形成以便完成对所述承台下方软弱土加固层的加固,通过注浆压力形成向上的反力缓慢顶升所述桩基础台至设计允许偏差范围内;
桩端持力层,所述桩端持力层位于所述承台下方软弱土加固层下方,所述桩端持力层开设有多个第二注浆孔,所述第二注浆孔穿过所述桩基础承台以及桩基础承台下方软弱土加固层与外部导通;所述第二注浆孔用于向所述桩端持力层内进行第二次注浆以便形成用于托举所述桩基础的复合地基。
优选的:多个所述第一注浆孔以及多个所述第二注浆孔分别均匀对称布置。
优选的:所述第一注浆孔以及所述第二注浆孔的孔径均为42毫米。
优选的:所述第一次注浆以及第二次注浆采用的浆液为高铝铁复合浆液。
一种所述桩基础沉降加固顶升调平结构的施工方法,所述方法包括:
确定注浆孔的孔位以及数量;所述孔位设置于桩基础两侧且对称布置;所述注浆孔的数量为2~4个;
使用水钻在所有孔位处分别进行开孔形成多个第一注浆孔;多个第一注浆孔形成后分别使用钻注一体机通过多个所述第一注浆孔分别采用分段钻进注浆的方式向所述承重台下方软弱土加固层同时进行第一次注浆,使所述桩基础承重台均匀缓慢顶升至允许偏差范围内为止;
待所述桩基础承重台稳定后,所有钻注一体机均继续向下钻进至桩基础下端后形成多个第二注浆孔;
多个第二注浆孔形成后分别使用钻注一体机通过多个所述第二注浆孔采用分段钻进注浆的方式向所述桩端持力层同时进行第二次注浆,使所述桩端持力层形成用于托举所述桩基础的凹字型复合地基为止。
优选的:所述第一次注浆采用的分段注浆包括第一注浆段、第二注浆段、第三注浆段以及第四注浆段,所述第一注浆段深度为2米,所述第二注浆段、第三注浆段以及第四注浆段深度均为1米。
优选的:所述第一次注浆时使用的浆液为第一高铝铁复合浆液,所述第一高铝铁复合浆液的初凝时间为10~20秒,浆液扩散半径为1.5~2.0米。
优选的:所述第一次注浆的注浆压力为0.8~1.5兆帕。
优选的:所述第二次注浆时使用的浆液为第二高铝铁复合浆液,所述第二高铝铁复合浆液的初凝时间为20~40秒,浆液扩散半径为2.0~3.0米。
优选的:所述第一次注浆的注浆压力为0.6~1.2兆帕。
根据本发明提供的具体实施例,本发明公开了以下技术效果:
通过本发明,可以实现一种桩基础沉降加固顶升调平结构及其施工方法,在一种实现方式下,该结构可以包括桩基础承重台,所述桩基础承重台下部固定连接有多根桩基础;承台下方软弱土加固层,所述桩基础承台位于所述承台下方软弱土加固层上方;所述承台下方软弱土加固层开设有多个第一注浆孔,所述第一注浆孔穿过所述桩基础承台与外部导通;所述第一注浆孔用于向所述承台下方软弱土加固层内进行第一次注浆以便形成以便完成对所述承台下方软弱土加固层的加固,通过注浆压力形成向上的反力缓慢顶升所述桩基础台至设计允许偏差范围内;桩端持力层,所述桩端持力层位于所述承台下方软弱土加固层下方,所述桩端持力层开设有多个第二注浆孔,所述第二注浆孔穿过所述桩基础承台以及桩基础承台下方软弱土加固层与外部导通;所述第二注浆孔用于向所述桩端持力层内进行第二次注浆以便形成用于托举所述桩基础的复合地基。采用加固顶升法进行施工,具体是通过“桩基础承重台顶升调平”和“桩端持力层加固补强”等新型技术工艺综合运用,桩基础承重台下部形成扩大的复合地基承载体,桩端持力层增加强度,使上部荷载均匀传递至持力层,本方案成功解决了工业厂房桩基础沉降和顶升调平的目的,使其达到地基承载力要求和设计允许偏差范围内。具有施工工作面小,无干扰施工,能提高地基承载力和顶升调平双重效果等优点。
当然,实施本发明的任一产品并不一定需要同时达到以上所述的所有优点。
附图说明
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。
图1是本发明实施例提供的一种桩基础沉降加固顶升调平结构的结构示意图;
图2是本发明实施例提供的一种桩基础沉降加固顶升调平结构的俯视图。
图中:桩基础承重台1、桩基础2、承重台下方软弱土加固层3、第一注浆孔4、桩端持力层5、第二注浆孔6。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员所获得的所有其他实施例,都属于本发明保护的范围。
实施例
参见图1、图2,为本发明实施例提供的一种桩基础沉降加固顶升调平结构,如图1、图2所示,该结构包括桩基础承重台1,所述桩基础承重台1下部固定连接有多根桩基础2;
承重台下方软弱土加固层3,所述桩基础承重台1位于所述承重台下方软弱土加固层3上方;所述承重台下方软弱土加固层3开设有多个第一注浆孔4,所述第一注浆孔4穿过所述桩基础承重台1与外部导通;所述第一注浆孔4 用于向所述承重台下方软弱土加固层3内进行第一次注浆以便形成以便完成对所述承重台下方软弱土加固层3的加固,并形成向上的反力缓慢顶升所述桩基础承重台1至设计允许偏差范围内;
桩端持力层5,所述桩端持力层5位于所述承重台下方软弱土加固层3下方,所述桩端持力层5开设有多个第二注浆孔6,所述第二注浆孔6穿过所述承重台下方软弱土加固层3以及桩基础承重台1与外部导通;所述第二注浆孔用于向所述桩端持力层5内进行第二次注浆以便形成用于托举所述桩基础2 的凹字型复合地基。
进一步的,所述多个所述第一注浆孔以及多个所述第二注浆孔分别均匀对称布置。所述第一注浆孔以及所述第二注浆孔的孔径均为42毫米。压密注浆以及压浆补强采用的浆料为高铝铁复合浆料。
本申请实施例还可以提供一种所述桩基础沉降加固顶升调平结构的施工方法,所述方法包括:
确定注浆孔的孔位以及数量;所述孔位设置于桩基础两侧且对称布置;所述注浆孔的数量为2~4个;
使用专用钻机在所有孔位处分别进行开孔形成多个第一注浆孔;多个第一注浆孔形成后分别使用钻注一体机通过多个所述第一注浆孔分别采用分段钻进注浆的方式向所述承台下方软弱土加固层同时进行第一次注浆,使所述桩基础承台均匀缓慢顶升至允许偏差范围内为止;桩基础承台顶升调平标高控制:根据顶升标准设定相对基准标高线,根据相对基准标高线进行标高监测,采用高精度水准仪和水平激光仪实时监测,顶升标准与要求顶升高度偏差在± 10mm。
待所述桩基础承台稳定后,所有钻注一体机均继续向下钻进至桩基础下端后形成多个第二注浆孔;
多个第二注浆孔形成后分别使用钻注一体机通过多个所述第二注浆孔采用分段钻进注浆的方式向所述桩端持力层同时进行第二次注浆,使所述桩端持力层形成用于托举所述桩基础的复合地基为止。厂房框架柱垂直度观测:在桩基础承重台顶升调平加固过程中,采用精密经纬仪实时观测框架柱的垂直度,由两个方向交叉观测,避免出现倾斜现象。
进一步的,所述第一次注浆采用的分段注浆包括第一注浆段、第二注浆段、第三注浆段以及第四注浆段,所述第一注浆段深度为1米-2米,所述第二注浆段、第三注浆段以及第四注浆段深度均约1米。所述第一次注浆时使用的浆液为第一高铝铁复合浆液,所述第一高铝铁特种复合浆液的初凝时间为10~ 20秒,浆液扩散半径为1.5~2.0米。所述第一次注浆的注浆压力为0.8~1.5 兆帕。
进一步的,所述第二次注浆时使用的浆液为第二高铝铁复合浆液,所述第二高铝铁特种复合浆液的初凝时间为20~40秒,浆液扩散半径为2.0~3.0 米。所述第一次注浆的注浆压力为0.6~1.2兆帕。
本申请提供的方案目的是根据既有建筑有承台的桩基础产生不均匀沉降,提供一种建筑桩基础沉降加固顶升调平技术,采用加固顶升法进行施工,具体是通过“桩基础承台顶升调平”和“桩端持力层加固补强”等新型技术工艺综合运用,桩基础承台下部形成扩大的复合地基承载体,桩端持力层增加强度,使上部荷载均匀传递至持力层,本方案成功解决了工业厂房桩基础沉降和顶升调平的目的,使其达到地基承载力要求和设计允许偏差范围内。
本申请提供的方案通过如下技术方案来实现的:①桩基础承台顶升调平:先对桩基础承台下软弱土层进行压密注浆加固,浆液通过填充→挤密,提高软弱土层的密实度和强度,增加桩周土层对桩的握裹力,再适当增大注浆压力,使其形成向上的反力,随之桩基础承台均匀缓慢顶升至允许偏差范围内。②桩端持力层压浆补强:在桩基础承重台顶升调平后,桩端与桩端持力层会存在软弱夹层,待桩基础承台复合地基固化形成强度后,继续向下施钻至桩端持力层,针对桩端持力层进行压浆补强,避免桩基础再次沉降。达到顶升调平和稳固地基的目的。
本申请提供的方案通过如下步骤来完成的:①采用钢筋混凝土探测仪,主要探测桩基础承台钢筋分布情况,开孔时避开钢筋,避免开孔时对钢筋的破坏。②在桩基础两侧布孔(布置2-4个孔位),对称布置,选用专用钻机开孔,开孔直径42mm。③开孔后选用钻注一体机对桩基础承台下软弱土层进行施钻高压注浆,使桩基础承台均匀缓慢顶升至允许偏差范围内。④待桩基础承台稳定后,继续向下钻进至桩端,针对桩端持力层进行压浆补强,增加桩端持力层承载力。
本申请提供的方案整体施工工艺采用钻注一体前进式分层注浆加固顶升,加固深度由浅至深分层向下,第一注浆段1.0m~2.0m,该段采取高压顶升调平桩基础承台;第二至第四注浆段分别约1.0m,该段以加固桩周软弱土层为主,稳固桩基础承台,提高桩周土层对桩基的握裹力。最后钻进至桩端持力层,对桩端与持力层间软弱夹层进行压浆补强,提高桩端持力层承载力。第一注浆段完成后,继续分层钻进并注浆,逐段向下,完成整体桩基础加固顶升调平。本申请提供的方案孔位对称布置,同时钻进,同时注浆,避免在压力注浆时受力不均,导致桩基础偏移。
本申请提供的方案工程材料选用高铝铁特种复合浆液。该浆液渗透性强,能渗透到小的裂隙或空隙中;浆液初凝时间和浆液扩散半径可控;浆液凝结硬化后强度高,具有一定的抗压、抗剪强度,抗渗性好,,抗冲刷及耐久性好;浆液固化后不收缩,固化后与岩体和混凝土等有很好的粘结力;浆液对注浆设备、管道、混凝土结构物等无腐蚀性,并容易清洗;浆液无毒、无臭、不污染环境,对人体无害。该浆液初凝时间和浆液扩散半径可控,桩基础承重台顶升调平时,浆液初凝时间控制在10s~20s,浆液扩散半径控制在1.5m~2.0m;桩端持力层压浆补强,浆液初凝时间控制在20s~40s,浆液扩散半径控制在 2.0m~3.0m,使浆液扩散更均匀。浆液胶结能力强,硬化后强度高,不收缩,可避免二次沉降问题;浆液环保无污染。桩基础承重台顶升调平注浆压力控制在0.8~1.5MPa,桩端持力层压浆补强注浆压力控制在0.6~1.2MPa。
本申请提供的方案钻孔孔径42mm,小孔径破坏性小,容易恢复,施工作业区域小,不影响正常运营。
总之,本申请提供的桩基础沉降加固顶升调平结构,施工工作面小,无干扰施工。能提高地基承载力和顶升调平双重效果。
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。
以上所述仅为本发明的较佳实施例而已,并非用于限定本发明的保护范围。凡在本发明的精神和原则之内所作的任何修改、等同替换、改进等,均包含在本发明的保护范围内。

Claims (10)

1.一种桩基础沉降加固顶升调平结构,其特征在于,包括:桩基础承重台,所述桩基础承重台下部固定连接有多根桩基础;承台下方软弱土加固层,所述桩基础承台位于所述承台下方软弱土加固层上方;所述承台下方软弱土加固层开设有多个第一注浆孔,所述第一注浆孔穿过所述桩基础承台与外部导通;所述第一注浆孔用于向所述承台下方软弱土加固层内进行第一次注浆以便形成以便完成对所述承台下方软弱土加固层的加固,通过注浆压力形成向上的反力缓慢顶升所述桩基础台至设计允许偏差范围内;桩端持力层,所述桩端持力层位于所述承台下方软弱土加固层下方,所述桩端持力层开设有多个第二注浆孔,所述第二注浆孔穿过所述桩基础承台以及桩基础承台下方软弱土加固层与外部导通;所述第二注浆孔用于向所述桩端持力层内进行第二次注浆以便形成用于托举所述桩基础的复合地基。
2.根据权利要求1所述的桩基础沉降加固顶升调平结构,其特征在于,多个所述第一注浆孔以及多个所述第二注浆孔分别均匀对称布置。
3.根据权利要求2所述的桩基础沉降加固顶升调平结构,其特征在于,所述第一注浆孔以及所述第二注浆孔的孔径均为42毫米。
4.根据权利要求1所述的桩基础沉降加固顶升调平结构,其特征在于,所述第一次注浆以及第二次注浆采用的浆液为高铝铁复合浆液。
5.一种权利要求1至4任意一项所述桩基础沉降加固顶升调平结构的施工方法,其特征在于,所述方法包括:确定注浆孔的孔位以及数量;所述孔位设置于桩基础两侧且对称布置;所述注浆孔的数量为2~4个;使用水钻在所有孔位处分别进行开孔形成多个第一注浆孔;多个第一注浆孔形成后分别使用钻注一体机通过多个所述第一注浆孔分别采用分段钻进注浆的方式向所述承重台下方软弱土加固层同时进行第一次注浆,使所述桩基础承重台均匀缓慢顶升至允许偏差范围内为止;待所述桩基础承重台稳定后,所有钻注一体机均继续向下钻进至桩基础下端后形成多个第二注浆孔;
多个第二注浆孔形成后分别使用钻注一体机通过多个所述第二注浆孔采用分段钻进注浆的方式向所述桩端持力层同时进行第二次注浆,使所述桩端持力层形成用于托举所述桩基础的凹字型复合地基为止。
6.根据权利要求5所述的桩基础沉降加固顶升调平结构的施工方法,其特征在于,所述第一次注浆采用的分段注浆包括第一注浆段、第二注浆段、第三注浆段以及第四注浆段,所述第一注浆段深度为2米,所述第二注浆段、第三注浆段以及第四注浆段深度均为1米。
7.根据权利要求6所述的桩基础沉降加固顶升调平结构的施工方法,其特征在于,所述第一次注浆时使用的浆液为第一高铝铁复合浆液,所述第一高铝铁复合浆液的初凝时间为10~20秒,浆液扩散半径为1.5~2.0米。
8.根据权利要求7所述的桩基础沉降加固顶升调平结构的施工方法,其特征在于,所述第一次注浆的注浆压力为0.8~1.5兆帕。
9.根据权利要求5所述的桩基础沉降加固顶升调平结构的施工方法,其特征在于,所述第二次注浆时使用的浆液为第二高铝铁复合浆液,所述第二高铝铁复合浆液的初凝时间为20~40秒,浆液扩散半径为2.0~3.0米。
10.根据权利要求9所述的桩基础沉降加固顶升调平结构的施工方法,其特征在于,所述第一次注浆的注浆压力为0.6~1.2兆帕。
CN201810385674.6A 2018-04-26 2018-04-26 一种桩基础沉降加固顶升调平结构及其施工方法 Active CN108343102B (zh)

Priority Applications (4)

Application Number Priority Date Filing Date Title
CN201810385674.6A CN108343102B (zh) 2018-04-26 2018-04-26 一种桩基础沉降加固顶升调平结构及其施工方法
PCT/CN2019/084388 WO2019206241A1 (zh) 2018-04-26 2019-04-25 一种桩基础承台结构沉降加固顶升调平结构及其施工方法
DE112019002113.3T DE112019002113T5 (de) 2018-04-26 2019-04-25 Struktur zum Senken, Verstärken, Anheben und Nivellieren der Pfahlgründungsplattformstruktur und Bauverfahren dafür
US17/037,730 US11453992B2 (en) 2018-04-26 2020-09-30 Pile foundation bearing platform settlement, reinforcement, lift-up and leveling structure, and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810385674.6A CN108343102B (zh) 2018-04-26 2018-04-26 一种桩基础沉降加固顶升调平结构及其施工方法

Publications (2)

Publication Number Publication Date
CN108343102A true CN108343102A (zh) 2018-07-31
CN108343102B CN108343102B (zh) 2024-02-27

Family

ID=62956033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810385674.6A Active CN108343102B (zh) 2018-04-26 2018-04-26 一种桩基础沉降加固顶升调平结构及其施工方法

Country Status (4)

Country Link
US (1) US11453992B2 (zh)
CN (1) CN108343102B (zh)
DE (1) DE112019002113T5 (zh)
WO (1) WO2019206241A1 (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109138011A (zh) * 2018-09-26 2019-01-04 严军 既有建筑物地基加固与纠偏方法
WO2019206241A1 (zh) * 2018-04-26 2019-10-31 北京恒祥宏业基础加固技术有限公司 一种桩基础承台结构沉降加固顶升调平结构及其施工方法
CN110847184A (zh) * 2019-11-20 2020-02-28 温州浙南地质工程有限公司 一种桩基础沉降加固顶升调平结构
CN110965595A (zh) * 2019-12-30 2020-04-07 北京恒祥宏业基础加固技术有限公司 一种腐蚀性地质环境下筏板基础建筑抬升加固结构及方法
CN112343104A (zh) * 2019-08-09 2021-02-09 北京恒祥宏业基础加固技术有限公司 一种高铁大型墩台的加固抬升方法
CN112343105A (zh) * 2019-08-09 2021-02-09 北京恒祥宏业基础加固技术有限公司 一种高铁桥墩加固抬升方法
WO2021027025A1 (zh) * 2019-08-09 2021-02-18 北京恒祥宏业基础加固技术有限公司 一种高层建筑沉降加固抬升纠偏的施工方法
CN112942455A (zh) * 2019-12-11 2021-06-11 北京恒祥宏业基础加固技术有限公司 一种岩溶地基高层建筑物的加固抬升方法

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343078B (zh) * 2019-08-09 2022-07-08 北京恒祥宏业基础加固技术有限公司 一种厂房设备基础精密抬升方法
CN111749198B (zh) * 2020-05-30 2022-11-25 郑州安源工程技术有限公司 渠道板水下注浆稳固与抬升方法
CN113216676B (zh) * 2021-04-02 2022-08-30 广州市鲁班建筑科技集团股份有限公司 一种带有穿孔的高强承压结构
CN114032887B (zh) * 2021-08-31 2023-04-07 山东高速股份有限公司 一种软弱地层在役桩基注浆加固材料及其注浆工艺

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203284791U (zh) * 2013-06-06 2013-11-13 中鼎国际工程有限责任公司 可以进行顶升纠偏的柱下独立柱基础
WO2015135471A1 (zh) * 2014-03-14 2015-09-17 香港强光海洋工程有限公司 水上平台结构水底固定用空心筒墩及其安装施工方法
CN105862721A (zh) * 2016-03-29 2016-08-17 广东华固工程有限公司 一种适用于高层建筑结构加固纠偏具有可调性预埋钢管的注浆复合地基及其施工方法
CN107435346A (zh) * 2017-08-18 2017-12-05 北京恒祥宏业基础加固技术有限公司 一种适用于高层建筑结构的注浆加固纠偏方法
CN208501762U (zh) * 2018-04-26 2019-02-15 北京恒祥宏业基础加固技术有限公司 一种桩基础沉降加固顶升调平结构

Family Cites Families (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4124982A (en) * 1976-09-22 1978-11-14 Raymond International Inc. Method of stabilizing soil in pile bearing regions
US4370077A (en) * 1980-08-04 1983-01-25 Colgate Stirling A Method of pressurizing and stabilizing rock by periodic and repeated injections of a settable fluid of finite gel strength
US6192649B1 (en) * 1995-05-12 2001-02-27 General Electric Company Elastomeric seismic isolation of structures and components
US5800090A (en) * 1996-04-09 1998-09-01 Geotechnics America, Inc. Apparatus and method for liquefaction remediation of liquefiable soils
US6012874A (en) * 1997-03-14 2000-01-11 Dbm Contractors, Inc. Micropile casing and method
US7073980B2 (en) * 1998-05-27 2006-07-11 Stanley Merjan Piling
EP0964113A1 (en) * 1998-06-11 1999-12-15 N.V. Bekaert S.A. Combination reinforcement for floor on piles
JP2980604B1 (ja) * 1998-11-19 1999-11-22 中村物産有限会社 建造物における防振基礎構造及びその構築工法
US6672015B2 (en) * 1999-02-25 2004-01-06 Menard Soltraitement Concrete pile made of such a concrete and method for drilling a hole adapted for receiving the improved concrete pile in a weak ground
JP4222812B2 (ja) * 2002-11-05 2009-02-12 宏和 竹宮 防振工法
EP1565620A1 (en) * 2002-11-13 2005-08-24 E. Mete Erdemgil Method for reducing the liquefaction potential of foundation soils
JP4249046B2 (ja) * 2004-01-30 2009-04-02 財団法人鉄道総合技術研究所 支持力増加方法、シートパイル基礎の施工方法、シートパイル基礎、橋梁
US20080253845A1 (en) * 2007-04-12 2008-10-16 Kinji Takeuchi Building foundation structure formed with soil improving body and raft foundation and construction method for soil improvement and raft foundation
JP2010180633A (ja) * 2009-02-06 2010-08-19 Takenaka Komuten Co Ltd 地盤沈下により生じた空隙部を充填する工法
TR200906475A1 (tr) * 2009-08-21 2011-03-21 Mete Erdemg�L Enver Yapı destekleme sistemi.
CN101886382B (zh) * 2010-06-22 2012-05-23 中铁第四勘察设计院集团有限公司 既有铁路、公路路基工程软弱地基加固方法
FI20106346A (fi) * 2010-12-20 2012-06-21 Uretek Worldwide Oy Menetelmä ja sovitelma rakenteen tukemiseksi
US9328474B2 (en) * 2012-12-07 2016-05-03 Anoop Kumar Arya Soil anchor footing
LU92314B1 (fr) * 2013-11-26 2015-05-27 Arman Innovations Sa Procédé de réhabilitation d'un ouvrage présentant une fissure par suivi d'une courbe représentative de l'écartement des bords de la fissure
CN105464395B (zh) * 2015-10-27 2018-01-30 中冶集团武汉勘察研究院有限公司 一种扰动桩端持力层的建筑物纠倾方法
CN105924044A (zh) * 2016-04-30 2016-09-07 李程 一种建筑材料灰浆
US10161096B2 (en) * 2016-05-31 2018-12-25 Soletanche Freyssinet Ground reinforcing device
KR101678950B1 (ko) * 2016-06-23 2016-11-23 우경기술주식회사 말뚝을 활용한 구조물 보강복원방법
US20180016765A1 (en) * 2016-07-14 2018-01-18 John Baldwin Method of lifting a structure on the earth
US10138616B2 (en) * 2016-08-12 2018-11-27 Wuhan Zhihe Geotechnical Engineering Co., Ltd. Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
CN106759424A (zh) * 2017-03-10 2017-05-31 山东科技大学 一种桩间土连续加固群桩体系及其施工方法
CA2966761A1 (en) * 2017-05-10 2018-11-10 Soletanche Freyssinet Ground reinforcing device
CN207228186U (zh) * 2017-08-02 2018-04-13 北京恒祥宏业基础加固技术有限公司 建筑加固纠偏的注浆复合地基
US10760236B2 (en) * 2017-12-15 2020-09-01 Redrock Ventures B.V. System and method for real-time displacement control using expansive grouting techniques
CN108343102B (zh) * 2018-04-26 2024-02-27 北京恒祥宏业基础加固技术有限公司 一种桩基础沉降加固顶升调平结构及其施工方法
US10947694B2 (en) * 2019-07-04 2021-03-16 Korea Institute Of Civil Engineering And Building Technology Preloading apparatus for adjusting load and method of reinforcing foundation using the same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203284791U (zh) * 2013-06-06 2013-11-13 中鼎国际工程有限责任公司 可以进行顶升纠偏的柱下独立柱基础
WO2015135471A1 (zh) * 2014-03-14 2015-09-17 香港强光海洋工程有限公司 水上平台结构水底固定用空心筒墩及其安装施工方法
CN105862721A (zh) * 2016-03-29 2016-08-17 广东华固工程有限公司 一种适用于高层建筑结构加固纠偏具有可调性预埋钢管的注浆复合地基及其施工方法
CN107435346A (zh) * 2017-08-18 2017-12-05 北京恒祥宏业基础加固技术有限公司 一种适用于高层建筑结构的注浆加固纠偏方法
CN208501762U (zh) * 2018-04-26 2019-02-15 北京恒祥宏业基础加固技术有限公司 一种桩基础沉降加固顶升调平结构

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019206241A1 (zh) * 2018-04-26 2019-10-31 北京恒祥宏业基础加固技术有限公司 一种桩基础承台结构沉降加固顶升调平结构及其施工方法
US11453992B2 (en) 2018-04-26 2022-09-27 Beijing Hengxiang Hongye Foundation Reinforcement Technology Co., Ltd. Pile foundation bearing platform settlement, reinforcement, lift-up and leveling structure, and construction method thereof
CN109138011A (zh) * 2018-09-26 2019-01-04 严军 既有建筑物地基加固与纠偏方法
CN112343104A (zh) * 2019-08-09 2021-02-09 北京恒祥宏业基础加固技术有限公司 一种高铁大型墩台的加固抬升方法
CN112343105A (zh) * 2019-08-09 2021-02-09 北京恒祥宏业基础加固技术有限公司 一种高铁桥墩加固抬升方法
WO2021027025A1 (zh) * 2019-08-09 2021-02-18 北京恒祥宏业基础加固技术有限公司 一种高层建筑沉降加固抬升纠偏的施工方法
US11739495B2 (en) 2019-08-09 2023-08-29 Beijing Hengxiang Hongye Foundation Reinforcement Technology Co., Ltd. Reinforcing and lifting method and reinforcing and lifting structure for large-scale piers of high-speed rail
CN110847184A (zh) * 2019-11-20 2020-02-28 温州浙南地质工程有限公司 一种桩基础沉降加固顶升调平结构
CN112942455A (zh) * 2019-12-11 2021-06-11 北京恒祥宏业基础加固技术有限公司 一种岩溶地基高层建筑物的加固抬升方法
CN110965595A (zh) * 2019-12-30 2020-04-07 北京恒祥宏业基础加固技术有限公司 一种腐蚀性地质环境下筏板基础建筑抬升加固结构及方法
CN110965595B (zh) * 2019-12-30 2021-06-04 北京恒祥宏业基础加固技术有限公司 一种腐蚀性地质环境下筏板基础建筑抬升加固结构及方法

Also Published As

Publication number Publication date
WO2019206241A1 (zh) 2019-10-31
CN108343102B (zh) 2024-02-27
US11453992B2 (en) 2022-09-27
US20210010223A1 (en) 2021-01-14
DE112019002113T5 (de) 2021-01-07

Similar Documents

Publication Publication Date Title
CN108343102A (zh) 一种桩基础沉降加固顶升调平结构及其施工方法
CN102277867B (zh) 一种湿陷性黄土地基的施工方法
CN107503257B (zh) 一种傍山高填路堤稳定与变形控制结构及施工方法
CN105155602B (zh) 一种多支点地基加固综合纠倾方法
CN106436788A (zh) 一种高层建筑摩擦桩基础加固纠倾方法
JP5243669B1 (ja) 構造物傾動及び地盤改良の工法
CN105953078B (zh) 高压燃气管道的保护装置及保护方法
CN108547336B (zh) 一种适用于工业厂房独立桩基础的沉降加固顶升调平方法
US20060013658A1 (en) Method for reducing the liquefaction potential of foundation soils
CN102400462A (zh) 地基抗震加固处理中的二次压浆小桩施工工艺
CN109594575A (zh) 一种沉井周边注浆加固土体施工方法
CN208501762U (zh) 一种桩基础沉降加固顶升调平结构
CN111894023A (zh) 陡坡桥梁基础的施工方法
CN105133641A (zh) 一种薄壁型连续墙式地基基础加固结构及方法
CN105464395B (zh) 一种扰动桩端持力层的建筑物纠倾方法
CN208251195U (zh) 既有建筑物独立基础沉降加固抬升结构
CN208501761U (zh) 一种适用于工业厂房独立桩基础的沉降加固顶升调平结构
CN113863706B (zh) 既有建筑低净空下旋喷静压复合桩施工方法及应用装置
CN105256848B (zh) 一种协调可控的巷道内掏土纠倾方法
CN108532624B (zh) 一种化学品罐筏板基础加固结构
CN110258677A (zh) 既有建筑物独立基础沉降加固抬升方法
CN214993745U (zh) 一种适用于人工挖孔桩基础桩周注浆加固组件
CN113863705B (zh) 基于静压旋喷钢管桩托换加固既有建筑的方法及应用装置
JP2014201953A (ja) 構造物傾動及び地盤改良の工法
CN114718078B (zh) 超大深基坑软土用围护结构及施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant