WO2021027025A1 - 一种高层建筑沉降加固抬升纠偏的施工方法 - Google Patents
一种高层建筑沉降加固抬升纠偏的施工方法 Download PDFInfo
- Publication number
- WO2021027025A1 WO2021027025A1 PCT/CN2019/107378 CN2019107378W WO2021027025A1 WO 2021027025 A1 WO2021027025 A1 WO 2021027025A1 CN 2019107378 W CN2019107378 W CN 2019107378W WO 2021027025 A1 WO2021027025 A1 WO 2021027025A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- grouting
- lifting
- building
- hole
- foundation
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 30
- 230000003014 reinforcing effect Effects 0.000 title abstract description 4
- 239000002689 soil Substances 0.000 claims abstract description 85
- 230000002787 reinforcement Effects 0.000 claims abstract description 62
- 239000002002 slurry Substances 0.000 claims abstract description 32
- 238000005553 drilling Methods 0.000 claims abstract description 23
- 239000011435 rock Substances 0.000 claims description 38
- 239000011440 grout Substances 0.000 claims description 26
- 239000002131 composite material Substances 0.000 claims description 21
- 238000007711 solidification Methods 0.000 claims description 12
- 230000008023 solidification Effects 0.000 claims description 12
- 230000001788 irregular Effects 0.000 claims description 5
- 239000007787 solid Substances 0.000 claims description 5
- 238000002347 injection Methods 0.000 abstract description 9
- 239000007924 injection Substances 0.000 abstract description 9
- 230000000149 penetrating effect Effects 0.000 abstract 1
- 230000000630 rising effect Effects 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 63
- 239000004567 concrete Substances 0.000 description 14
- 238000000034 method Methods 0.000 description 12
- 239000000243 solution Substances 0.000 description 12
- 239000007788 liquid Substances 0.000 description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 10
- 230000008569 process Effects 0.000 description 8
- 235000019994 cava Nutrition 0.000 description 7
- 238000010586 diagram Methods 0.000 description 6
- 230000005484 gravity Effects 0.000 description 6
- 239000004575 stone Substances 0.000 description 6
- 238000009412 basement excavation Methods 0.000 description 5
- 241000923606 Schistes Species 0.000 description 4
- 239000013530 defoamer Substances 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 4
- 238000001125 extrusion Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- KWYUFKZDYYNOTN-UHFFFAOYSA-M Potassium hydroxide Chemical compound [OH-].[K+] KWYUFKZDYYNOTN-UHFFFAOYSA-M 0.000 description 3
- 238000006243 chemical reaction Methods 0.000 description 3
- 239000003638 chemical reducing agent Substances 0.000 description 3
- 239000011229 interlayer Substances 0.000 description 3
- 238000002955 isolation Methods 0.000 description 3
- RTZKZFJDLAIYFH-UHFFFAOYSA-N Diethyl ether Chemical compound CCOCC RTZKZFJDLAIYFH-UHFFFAOYSA-N 0.000 description 2
- 229910019142 PO4 Inorganic materials 0.000 description 2
- 239000000872 buffer Substances 0.000 description 2
- 239000006172 buffering agent Substances 0.000 description 2
- 238000005056 compaction Methods 0.000 description 2
- 150000001875 compounds Chemical class 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 229910044991 metal oxide Inorganic materials 0.000 description 2
- 150000004706 metal oxides Chemical class 0.000 description 2
- NBIIXXVUZAFLBC-UHFFFAOYSA-K phosphate Chemical compound [O-]P([O-])([O-])=O NBIIXXVUZAFLBC-UHFFFAOYSA-K 0.000 description 2
- 239000010452 phosphate Substances 0.000 description 2
- 229920000056 polyoxyethylene ether Polymers 0.000 description 2
- 229940051841 polyoxyethylene ether Drugs 0.000 description 2
- 238000007712 rapid solidification Methods 0.000 description 2
- 239000002994 raw material Substances 0.000 description 2
- 230000000452 restraining effect Effects 0.000 description 2
- 239000004094 surface-active agent Substances 0.000 description 2
- CDMGNVWZXRKJNS-UHFFFAOYSA-N 2-benzylphenol Chemical compound OC1=CC=CC=C1CC1=CC=CC=C1 CDMGNVWZXRKJNS-UHFFFAOYSA-N 0.000 description 1
- 239000004721 Polyphenylene oxide Substances 0.000 description 1
- 229920002472 Starch Polymers 0.000 description 1
- 239000002253 acid Substances 0.000 description 1
- 125000000217 alkyl group Chemical group 0.000 description 1
- 150000008052 alkyl sulfonates Chemical class 0.000 description 1
- 229940024548 aluminum oxide Drugs 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004202 carbamide Substances 0.000 description 1
- XNEYCQMMVLAXTN-UHFFFAOYSA-N carbonic acid;magnesium Chemical group [Mg].OC(O)=O XNEYCQMMVLAXTN-UHFFFAOYSA-N 0.000 description 1
- 229920003086 cellulose ether Polymers 0.000 description 1
- 229960000541 cetyl alcohol Drugs 0.000 description 1
- 239000006084 composite stabilizer Substances 0.000 description 1
- MNNHAPBLZZVQHP-UHFFFAOYSA-N diammonium hydrogen phosphate Chemical compound [NH4+].[NH4+].OP([O-])([O-])=O MNNHAPBLZZVQHP-UHFFFAOYSA-N 0.000 description 1
- 229910000388 diammonium phosphate Inorganic materials 0.000 description 1
- 235000019838 diammonium phosphate Nutrition 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 230000009977 dual effect Effects 0.000 description 1
- 229920003063 hydroxymethyl cellulose Polymers 0.000 description 1
- 229940031574 hydroxymethyl cellulose Drugs 0.000 description 1
- 239000012669 liquid formulation Substances 0.000 description 1
- 239000000395 magnesium oxide Substances 0.000 description 1
- 229960000869 magnesium oxide Drugs 0.000 description 1
- CPLXHLVBOLITMK-UHFFFAOYSA-N magnesium oxide Inorganic materials [Mg]=O CPLXHLVBOLITMK-UHFFFAOYSA-N 0.000 description 1
- GVALZJMUIHGIMD-UHFFFAOYSA-H magnesium phosphate Chemical compound [Mg+2].[Mg+2].[Mg+2].[O-]P([O-])([O-])=O.[O-]P([O-])([O-])=O GVALZJMUIHGIMD-UHFFFAOYSA-H 0.000 description 1
- 239000004137 magnesium phosphate Substances 0.000 description 1
- 229960002261 magnesium phosphate Drugs 0.000 description 1
- 229910000157 magnesium phosphate Inorganic materials 0.000 description 1
- 235000010994 magnesium phosphates Nutrition 0.000 description 1
- AXZKOIWUVFPNLO-UHFFFAOYSA-N magnesium;oxygen(2-) Chemical compound [O-2].[Mg+2] AXZKOIWUVFPNLO-UHFFFAOYSA-N 0.000 description 1
- 229910000000 metal hydroxide Inorganic materials 0.000 description 1
- 150000004692 metal hydroxides Chemical class 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 229910000402 monopotassium phosphate Inorganic materials 0.000 description 1
- 235000019796 monopotassium phosphate Nutrition 0.000 description 1
- BXWNKGSJHAJOGX-UHFFFAOYSA-N n-hexadecyl alcohol Natural products CCCCCCCCCCCCCCCCO BXWNKGSJHAJOGX-UHFFFAOYSA-N 0.000 description 1
- TWNQGVIAIRXVLR-UHFFFAOYSA-N oxo(oxoalumanyloxy)alumane Chemical compound O=[Al]O[Al]=O TWNQGVIAIRXVLR-UHFFFAOYSA-N 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- PJNZPQUBCPKICU-UHFFFAOYSA-N phosphoric acid;potassium Chemical compound [K].OP(O)(O)=O PJNZPQUBCPKICU-UHFFFAOYSA-N 0.000 description 1
- 229920000570 polyether Polymers 0.000 description 1
- 229920001296 polysiloxane Polymers 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 235000019832 sodium triphosphate Nutrition 0.000 description 1
- 230000007480 spreading Effects 0.000 description 1
- 238000003892 spreading Methods 0.000 description 1
- 239000003381 stabilizer Substances 0.000 description 1
- 239000008107 starch Substances 0.000 description 1
- 235000019698 starch Nutrition 0.000 description 1
- 239000003351 stiffener Substances 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- XSQUKJJJFZCRTK-UHFFFAOYSA-N urea group Chemical group NC(=O)N XSQUKJJJFZCRTK-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
- E02D35/005—Lowering or lifting of foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/18—Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/34—Foundations for sinking or earthquake territories
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D35/00—Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
Definitions
- the invention relates to the technical field of uplifting correction and reinforcement of subsidence buildings, in particular to a construction method for settlement reinforcement, lifting and correction of high-rise buildings.
- a high-rise building 1 is a raft foundation.
- Below the raft foundation ie, bottom plate 2 are a 50cm thick plain concrete layer 95, a 5-6m thick rubble concrete layer 94 and a broken bedrock layer 91. .
- the small karst caves 7 in the range of the bottom plate 2 were filled before the construction of the building 1, but the surrounding karst caves 7 outside the range of the bottom plate 2 were not processed.
- the surrounding caves 7 are squeezed and deformed, thereby causing the settlement of the building 1.
- FIGs 2 and 3 there is an 11-storey small high-rise building 1 located in a half-excavated and half-filled area.
- the west side of the building 1 is the excavation area, and the east side is the filling area.
- the original geographical feature below the river is 10.
- the foundation form of building 1 is a raft foundation (namely bottom plate 2).
- the purpose of the present invention is to provide a construction method for the settlement reinforcement and lifting correction of high-rise buildings. Its advantage is that it can lift and correct the subsidence of the building and strengthen it, and the lifting process has little impact on the building. , The foundation of the building is strengthened after lifting to prevent secondary settlement.
- Step 1 Form the curtain wall: Drill holes vertically downwards around the bottom plate of the building foundation to form multiple spaced curtain holes; grouting into the curtain holes, and the grouting ranges of two adjacent curtain holes overlap each other. Forming a curtain wall, which encloses the foundation soil below the bottom plate of the building foundation;
- Step 2 Open multiple vertical reinforcement grouting holes on the bottom plate of the building foundation, and grouting in the reinforcement grouting holes to reinforce all the soil near the bottom plate to form reinforcement;
- Step 3 Lifting grouting: Drill down to form a lifting hole.
- the lifting hole penetrates from the ground to a certain depth below the bottom of the solidification.
- the bottom of the lifting hole is higher than the bottom of the curtain wall.
- Pressure injection is carried out to the bottom of the lifting hole.
- the injected grout quickly solidifies and continuously fills and compacts the foundation soil in the curtain wall.
- the foundation soil in the curtain wall forms with the increase in pressure and density. Lifting force, the building gradually rises to the set lifting height.
- the present invention is further configured as follows: in step 2, the solidification grouting is carried out by a drilling-injection integrated machine, and the forward grouting is adopted, and the grouting is carried out in multiple sections in the vertical direction. After the grout is sprayed from the nozzle of the grouting pipe, 30- Solidified within 60s.
- one section of drilling is to reinforce one section, and the foundation soil at the bottom of the building is reinforced in time, which effectively avoids the disturbance of the foundation soil due to drilling, which causes accelerated building settlement.
- the present invention is further configured as follows: the pressure grouting to the bottom of the lifting hole is carried out by using a drilling and injection integrated machine, and the stepwise backward grouting is lifted.
- the present invention is further configured as follows: the foundation soil includes a backfilled soil and rock layer, and the bottom of the backfilled soil and rock layer includes a soft soil layer; in step 2, the reinforcement grouting hole is deepened to the bottom of the backfilled soil and rock layer, so that the backfilled soil and rock in the curtain wall All the solids are formed; in step 3, the lifting grouting hole extends into the soft soil layer for pressure grouting.
- pressure grouting in the interlayer between the reinforcement and the bedrock layer makes the uplifting more effective; the soft soil layer is more easily deformed than the backfilled schist, and can be compressed on the curtain wall
- the upward lifting force is formed more efficiently within the building; in addition, the backfilled soil and rock layers under the bottom of the building's floor are all reinforced to form a dense foundation structure, which effectively prevents the secondary settlement of the building.
- the present invention is further arranged as follows: the curtain hole goes deep into the bedrock layer.
- the grouting leakage at the junction of the curtain wall and the bedrock layer can be effectively prevented, and the curtain wall embedded in the bedrock layer can effectively prevent the bottom of the curtain wall from being displaced outward when the grouting is lifted.
- the present invention is further configured as follows: when there is a cave just below the curtain hole, the curtain hole goes deep to the bottom of the cave.
- the karst caves are simultaneously grouted and filled compactly to prevent the karst caves from affecting the building.
- the present invention is further configured as follows: in step 3, a hole is drilled obliquely downward from the edge of the bottom plate of the building foundation and the curtain wall to form a lifting hole, and the lifting hole extends to the bottom of the reinforcement.
- the present invention is further configured as follows: the lifting hole extends directly under the bearing wall or structural column of the building.
- the upward force is better transmitted to the vertical main force-receiving structure, which makes the lifting more efficient and saves materials.
- the present invention is further arranged as follows: the foundation soil includes a backfilled soil and rock layer, after the lifting height reaches the requirement, the hole position of the original reinforced grouting hole of the building is continuously drilled down to the bottom of the backfilled soil and rock layer, and the grouting is returned in layers. All backfilled earth and rocks within the scope of the bottom plate will be fully reinforced.
- the voids formed under the indoor floor after the building is lifted are filled, and the existing backfilled earth and rock are fully grouted and filled at the same time, so that the foundation is more dense and the secondary settlement of the building is prevented.
- the invention is further configured to: after the lifting height reaches the requirement, grouting is drilled under the four corners of the building and/or the main indoor load-bearing wall to form an irregular composite pile foundation, and the building is supported and reinforced.
- the present invention has the following beneficial effects:
- the curtain wall isolates the soil below the bottom plate from the soil outside the bottom plate, providing a closed environment for solidification and lifting grouting, avoiding interference from the surrounding environment and saving grouting materials; suitable for river channels The uplift of buildings constructed on the fill and on the foundation of the karst cave;
- the reinforcement can protect the bottom plate while transmitting the upward lifting force, and on the other hand, it can strengthen the soil below the bottom plate and prevent the building from secondary settlement;
- Supplementary grouting and composite pile foundation effectively strengthen the foundation and prevent secondary settlement of the building
- Figure 1 is a schematic diagram of the structure of a settlement building with karst caves in the foundation in the background technology
- Figure 2 is a schematic plan view of half of the buildings built on the backfilled river in the background technology
- Figure 3 is a schematic diagram of the geological section of the bottom half of the building built on the backfilled channel in the background technology
- Figure 4 is a schematic diagram of the grouting hole for the construction curtain in the first embodiment
- Figure 5 is a schematic diagram of the construction of curtain wall formation and solidification and lifting and grouting in the first embodiment
- Figure 6 is a schematic diagram of grouting reinforcement construction in the first embodiment
- Figure 7 is a schematic diagram of composite pile foundation construction
- 8-9 is a schematic plan view of the curtain wall and reinforcement grouting hole and lifting hole in the second embodiment
- 10 is a schematic cross-sectional view of reinforcement and lifting in the second embodiment
- Figure 11 is a schematic plan view of a corner of a building located on a backfilled river in the third embodiment
- FIG. 12 is a schematic plan view of the L-shaped curtain wall, reinforced grouting holes and lifting holes in the third embodiment
- FIG. 13 is a schematic plan view of the enclosed curtain wall formed around the floor of the building in the fourth embodiment
- Fig. 14 is a schematic plan view of the enclosed curtain wall formed on the raised side of the building in the fourth embodiment.
- the bottom plate 2 of the building 1 represents the raft foundation in the background, and the bottom concrete slab of the foundation such as the box foundation of the building 1.
- the foundation soil including the original foundation or the foundation processed by the process of compaction piles or dynamic compaction, can also be the "backfilled soil and rock layer” foundation formed by backfilling on the original foundation.
- "Backfilled soil and rock layer” represents one or more backfill structures such as backfilled soil, backfilled crushed stone, backfilled rubble, or backfilled rubble concrete.
- the "base rock layer 91" in this application not only represents a high-strength bedrock in the true sense, but also represents an undisturbed soil layer with a high bearing capacity.
- a construction method for settlement reinforcement, lifting and correction of high-rise buildings includes the following construction steps:
- Step 1 Form the curtain wall 3: As shown in Figures 4 and 5, drill holes vertically down around the bottom plate 2 of the foundation of the building 1 to form a plurality of spaced curtain holes 31; the holes are located about 2.0m away from the outer wall ⁇ 2.7m, the hole spacing is 2.0m.
- the drilling depth is determined according to the geological survey data and the actual drilling situation on site.
- the curtain hole 31 penetrates 1m into the base rock layer 91.
- the curtain hole 31 goes deep to the cave 7.
- the curtain hole 31 is constructed by the skip hole method, and the curtain hole 31 is grouted with a drilling and injection integrated machine.
- the grouting ranges of two adjacent curtain holes 31 overlap each other to form a curtain wall 3 with an effective thickness of 3.0m.
- the curtain wall 3 encloses the rubble concrete layer 94 below the range of the bottom plate 2 of the foundation of the building 1.
- the grouting pressure in the curtain hole 31 is determined according to the design thickness of the curtain wall and the stratum, and is generally 0.3-0.5 MPa.
- Step 2 Open a plurality of vertical reinforcement grouting holes 41 on the bottom plate 2 of the building 1, and the reinforcement grouting holes 41 are arranged in a plum blossom shape of 3.0 ⁇ 2.8m, and the holes are drilled vertically. Extend into the rubble concrete layer 94. Then grouting is carried out in the reinforced grouting hole 41, and the range of 2.0m below the bottom plate 2 is grouted and reinforced, and the voids in the rubble concrete in this range are filled and compacted to form a solid 4; the purpose is to improve the backfilling The compactness and rigidity of the stone concrete layer 94; it acts as a buffer zone during the lifting operation, so that the lifting force is more uniform.
- the grouting of the solid 4 is carried out by a drilling and injection integrated machine, using forward grouting, and grouting is carried out in multiple sections in the vertical direction. After the grout is sprayed from the nozzle of the grouting pipe, it solidifies within 30-60 seconds. The depth of each advancement can be 30-50cm.
- Step 3 Lifting grouting: As shown in Figure 5, after the construction of the reinforcement 4 in step 2 is completed for 12 hours to 24 hours, holes are laid on the settlement side of the building 1, and the lifting holes 6 are drilled. 2.89m, the hole spacing is 4m. The lifting hole 6 is inclined downward from the ground and reaches 3-5m below the bottom of the reinforcement 4, and the angle of the hole is such that the bottom of the hole extends directly below the load-bearing wall or structural column of the building 1. The bottom of the lifting hole 6 is higher than the bottom of the curtain wall 3. The drilling and grouting of the lifting hole 6 is carried out by a drilling and grouting integrated machine, and the reinforced concrete structure such as the raft foundation is avoided during the drilling process to prevent the sticking of the drill.
- the grout is continuously injected into the curtain wall 3 Inside, the backfilled earth and rocks in the range are filled and compacted, so that the building 1 is continuously raised to the set lifting height.
- the bottom of the lifting hole 6 extends to 3-5m below the bottom of the reinforcement 4, each time The distance of retreat can also be adjusted according to the actual situation.
- the grouting pressure should be greater than the reference pressure and less than 1.8 times the reference pressure.
- the grouting pressure in the reinforced grouting hole 41 in step 2 and the reinforcing grouting pressure in step 4 should be less than or equal to the reference pressure.
- the original hole position of the reinforced grouting hole 41 in the building 1 is continued to be drilled down to the bottom of the backfilled rubble concrete, the grouting is returned in layers, and the bottom plate 2 All backfilled earth and rocks within the range are fully reinforced to improve the stiffness, density and bearing capacity of the foundation, and prevent secondary subsidence.
- the pressure of filling and grouting is 0.3-0.5MPa.
- Step 5 Grouting to form composite pile foundation 5: As shown in Figure 7, in order to ensure the overall stability and durability of the building foundation, 8 irregular composite pile foundations were constructed at the four corners of building 1 and under the main indoor load-bearing walls 5. Through repeated backward and forward grouting, the composite pile foundation 5 is formed and filled with karst cracks. The effective diameter of the irregular composite pile foundation 5 is not less than 3.0m, and the depth of the composite pile foundation 5 is 15.0m below the bottom plate 2.
- the irregular composite pile foundation 5 and the composite foundation reinforcement body formed by grouting in steps 2 and 4 form a whole to bear the upper load, and support and strengthen the building 1 to meet the overall stability and durability requirements of the reinforcement area.
- the application numbers are: 2019105172878 and 2019105180291 respectively.
- the implementation principle of this embodiment is as follows: lifting grouting is carried out in the enclosed curtain wall 3, and the grout injected into the curtain continuously solidifies and squeezes the surrounding soil. Due to the isolation of the curtain wall 3, the grout will not disperse. Moreover, the direction of soil extrusion is restricted by the curtain wall 3, so that the extrusion direction is mainly concentrated downward and upward. The upward force acts on the stiffening body 4, and the stiffening body 4 moves upward and drives the building 1 above it to rise synchronously to achieve the purpose of lifting and correcting tilt.
- the curtain wall 3 also forms a barrel structure, which changes the distribution of the gravity of the building 1 in the foundation. Comparing Fig. 1 with Fig. 7, in Fig. 1, before the lifting and reinforcement, the gravity of the building 1 starts from the bottom plate 2 and distributes downward in a horn shape, which will squeeze the cave 7 around the building 1 and cause the settlement of the building 1 . In Figure 7, after the construction of the curtain wall 3 and the internal composite foundation reinforcement body, the gravity of the building 1 can extend down to the bottom of the curtain wall 3 as a whole, and then it starts to distribute downward in a horn shape, thereby effectively reducing As a result, the building 1 is affected by the surrounding karst cave 7, forming a more stable foundation structure.
- the method of reinforcement and elevation includes the following construction steps:
- Step 1 Form the curtain wall 3: Combining Figures 8-10, drill a hole vertically downwards around the bottom plate 2 of the foundation of the building 1 to form a plurality of spaced curtain holes 31 in the filling area. The bottom of the square. Then grouting is injected into the curtain hole 31. The grouting ranges overlap each other to form a U-shaped curtain wall 3.
- the curtain wall 3 encloses the backfill soil and stone layer below the base plate 2 of the foundation of the building 1, and covers the scope of the building 1. Backfill earth and rock inside and outside are isolated.
- the curtain hole 31 penetrates into the base rock layer 91 below the bottom of the fill, and the bottom end of the curtain wall 3 after grouting can form a connecting pile 32 that extends into the base rock layer 91, thereby preventing the curtain wall 3
- the bottom of the bottom moves horizontally.
- Step 2 Form reinforcement 4: In the filling area inside the curtain wall 3, a number of vertical reinforcement grouting holes 41 are opened on the bottom plate 2 of the foundation of the building 1, and the reinforcement grouting holes 41 penetrate deep to the bottom of the backfilled soil and rock layer. At the bottom, pressure grouting is performed in the reinforcement grouting hole 41 to reinforce the backfilled rubble concrete layer 94, the rubble layer 93 and the soft soil layer 92 below the bottom plate 2 to form a reinforcement 4.
- Step 3 Lifting and grouting:
- step 3 a hole is drilled obliquely downward from the edge of the bottom plate 2 of the foundation of the building 1 and the curtain wall 3 to form a lifting hole 6, which extends into the soft soil at the bottom of the reinforcement 4.
- pressure grouting is performed in the interlayer between the reinforcement 4 and the bedrock layer 91 (ie, the soft soil layer 92).
- the force Push the stiffener 4 upwards vertically and drive the building 1 above it to move upwards synchronously.
- the building 1 is gradually raised to the set lifting height, then the grouting is stopped, and the lifting grouting pipe is pulled out.
- the soft soil layer 92 is easier to deform than backfilled rubble, and after being compressed, it can form an upward lifting force in the curtain wall more efficiently.
- the lifting hole 6 extends directly below the outer bearing wall 11 of the building 1 so that the lifting force can lift the building 1 more efficiently.
- the grouting pressure of various grouting in this embodiment refers to the first embodiment.
- the implementation principle of this embodiment is: forming a three-sided curtain wall 3 by grouting, and forming an enclosure after being connected to the excavation area, and at the same time lifting the building 1 to the bottom soil of the side floor 2 and the outside of the building 1. Fill soil for isolation. Lifting grouting is carried out in the enclosed curtain wall 3. The grout injected into the curtain continuously solidifies and squeezes the surrounding soil. Due to the isolation of the curtain wall 3, the grout will not spread out, and the direction of soil squeezing is affected The constraints of the curtain wall 3 make the extrusion direction mainly focus on downward and upward. The upward force acts on the stiffening body 4, and the stiffening body 4 moves upward and drives the building 1 above it to rise synchronously to achieve the purpose of lifting and correcting tilt.
- the curtain wall 3 also plays the role of isolating the internal and external soil, avoiding the influence of the external environment on the grouting when the curtain wall 3 is grouted. For example, it can isolate the interference of underground rivers and prevent the grouting liquid from being Washed away.
- the bottom plate 2 of the foundation of the building 1 is all located on the backfilled soil and rock layer.
- the figure shows the overall settlement of building 1, which needs to be lifted as a whole. Therefore, a closed curtain wall 3 is constructed around the bottom plate 2 of the foundation of the building 1, and the soil below the bottom plate 2 is grouted to form a reinforcement 4, and then a lifting hole 6 is used, and lifting grouting is performed.
- the curtain hole 31 may be selected not to go deep into the base rock layer 91.
- the composite pile foundation 5 to the base rock layer 91 and other supporting layers are constructed to prevent secondary settlement of the building 1.
- the schematic situation in the figure is that the building 1 is all located on the backfilled soil and rock layer in the fill area, but only one side has settlement, and only that side needs to be raised. Therefore, a curtain wall 3 can be constructed on the bottom plate 2 on the lifting side of the building 1 and the periphery of the bottom plate 2, and then the reinforcement 4 can be carried out under the bottom plate 2 in the curtain, or all the soil below the bottom plate 2 can be reinforced. Finally, the lifting hole 6 is constructed on the lifting side to the bottom of the load-bearing wall, and pressure grouting is performed to lift the building 1.
- the slurry used for the solidification 4 grouting is a quick-setting type.
- the slurry is sprayed from the nozzle of the grouting pipe and solidifies within 30-60 seconds.
- the slurry used for grouting can be a single slurry or a double slurry. When dual grouts are used, different grouts reach the grout outlet through different channels of the double-layer grouting pipe, and are pressed into the soil together after the grout outlet merges, and a solidification reaction occurs.
- drilling machines such as water drills can be used to open the bottom plate 2, and then use a drilling and injection integrated machine to reinforce the grouting hole 41 and the reinforcement 4, and perform multiple injections in multiple vertical sections.
- Pulp The backward grouting process can be used, that is, one-time drilling to the designed hole depth, and then the drill pipe (that is, the grouting pipe) is retracted and grouted in sections; or the forward grouting process can be used, that is, drilling for one section, A section of grouting.
- the distance that the drill rod advances or retreats should be less than the spreading radius of the slurry.
- the backfilled soil and rock layer includes schist or block stone
- forward drilling and grouting is preferred, because when drilling the block stone, too much water from the end of the drill pipe will cause the surrounding soil to soften.
- One-stage grouting can effectively prevent the accelerated settlement of the building 1.
- the backward grouting process can be used, which is convenient and more efficient.
- the grouting liquid in the lifting hole 6 is also preferably a quick-setting type, which can solidify within 5-30 seconds.
- double grout grouting is used. Different slurries reach the grout outlet through different channels of the double-layer grouting pipe, and are pressed into the soil together after the grout outlet merges, and a solidification reaction occurs.
- the two slurries mentioned above are named A slurry and B slurry respectively.
- the two slurries reach the grout outlet of the grouting pipe from different passages of the drill pipe, and are pressed into the surrounding soil at the grout outlet.
- the two slurries are in the soil.
- a chemical reaction occurs after the middle confluence, and the initial setting is completed in a short time.
- the grouting solution can meet the requirements of the initial setting time and has good permeability, it can be any of the existing technologies.
- the solidification of the grouting liquid mentioned above represents the initial setting.
- the main purpose is to prevent the liquid grouting liquid from affecting the building. The softening effect caused by the foundation.
- a slurry is composed of the following raw materials by weight: 70-90 parts of metal oxides and/or metal hydroxides, 0.5-1.2 parts of composite retarder, 0.5-1.2 parts of water reducing agent 0.7, acid-base buffering agent 0.7-1.5, compound stabilizer 3-5, compound surfactant 0.5-1.5.
- the metal oxide can be a combination of any two of magnesium oxide, aluminum oxide, and magnesium phosphate;
- the composite retarder is urea and sodium tripolyphosphate;
- the water reducing agent is a polycarboxylic acid water reducing agent;
- the acid-base buffering agent is carbonic acid Magnesium or potassium hydroxide;
- composite stabilizer is at least two of hydroxymethyl cellulose, n-alkyl cetyl alcohol, starch ether and cellulose ether;
- composite surfactant is alkyl polyoxyethylene ether, benzyl phenol At least two of polyoxyethylene ether and alkyl sulfonate.
- the B slurry is composed of the following raw materials in parts by weight: 30-40 parts of phosphate and 0.2-1 part of defoamer.
- the phosphate can be diammonium hydrogen phosphate or potassium dihydrogen phosphate
- the defoamer can be a silicone defoamer or a polyether defoamer.
- a slurry and B slurry are mixed with water in a weight ratio of 100:40 ⁇ 50 to form a slurry, which is pressed into the grouting pipe through different pipelines until the slurry outlet merges and reacts and solidifies in the soil.
- the difference in the initial setting time of the composite slurry is mainly realized by adjusting the specific gravity of the composite retarder.
- less water is added to increase the concentration of the grouting liquid to better squeeze the surrounding soil (for example, the ratio of A slurry and B slurry to water is 100:40 by weight respectively. );
- add more water and lower the concentration of the grouting liquid for example, the ratio of A slurry and B slurry to water is 100:50 by weight).
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Agronomy & Crop Science (AREA)
- Soil Sciences (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Foundations (AREA)
Abstract
Description
Claims (10)
- 一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:包括以下步骤:步骤1、形成帷幕墙(3):在建筑物(1)基础的底板(2)四周竖直向下钻孔,形成多个间隔的帷幕孔(31);向帷幕孔(31)内注浆,相邻两个帷幕孔(31)的注浆范围相互咬合重叠,形成帷幕墙(3),所述帷幕墙(3)将建筑物(1)基础的底板(2)范围以下的地基土进行围闭;步骤2、形成加固体(4):在建筑物(1)基础的底板(2)上开设多个竖向的加固注浆孔(41),在加固注浆孔(41)内注浆,将靠近底板(2)的土体全部加固,形成加固体(4);步骤3、抬升注浆:向下钻孔,形成抬升孔(6),抬升孔(6)从地面深入至加固体(4)的底部以下一定深度,抬升孔(6)的孔底高于位于帷幕墙(3)的墙底,向抬升孔(6)底部进行压力注浆,随着帷幕墙(3)内浆液的不断增加,注入的浆液快速凝固并对帷幕墙(3)内地基土不断的填充、挤密,帷幕墙(3)内的地基土随着压力的升高和密实度的增加,形成抬升力,建筑物(1)逐渐抬升至设定的抬升高度。
- 根据权利要求1所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:步骤2中,加固体(4)的注浆采用钻注一体机进行,采用前进式注浆,在竖向分多段进行注浆,浆液从注浆管管口喷出后,30-60s内凝固。
- 根据权利要求1所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:向抬升孔(6)底部进行压力注浆采用钻注一体机进行,并分段后退式注浆抬升。
- 根据权利要求1所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:地基土包括回填土石层,回填土石层的最底部包括一层软土层(92);步骤2中,加固注浆孔(41)深入至回填土石层的最底部,使帷幕墙(3)内的回填土石全部形成加固体(4);步骤3中,抬升注浆孔伸入至软土层(92)内进行压力注浆。
- 根据权利要求1-4任一所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:帷幕孔(31)深入至基岩层(91)内部。
- 根据权利要求1-4任一所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:当帷幕孔(31)的正下方存在溶洞(7)时,帷幕孔(31)深入至溶洞(7)底部。
- 根据权利要求1-4任一所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:步骤3中从建筑物(1)基础的底板(2)边沿与帷幕墙(3)之间倾斜向下钻孔,形成抬升孔(6),抬升孔(6)伸入至加固体(4)的底部。
- 根据权利要求1-4任一所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:抬升孔(6)伸入至建筑物(1)的承重墙或结构柱的正下方。
- 根据权利要求1-3任一所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:地 基土包括回填土石层,抬升高度达到要求后,在建筑物(1)原加固注浆孔(41)的孔位继续向下施钻至回填土石层的最底部,分层回退注浆,将底板(2)范围内的所有回填土石进行全面补强加固。
- 根据权利要求1-3任一所述的一种高层建筑沉降加固抬升纠偏的施工方法,其特征是:抬升高度达到要求后,在建筑物(1)的四角和/或室内主要承重墙下钻孔注浆,形成不规则复合桩基(5),将建筑物(1)进行支撑加固。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US17/580,782 US11732434B2 (en) | 2019-08-09 | 2022-01-21 | High-rise building settling reinforcing and lifting correcting construction method |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910736655.8A CN112343106A (zh) | 2019-08-09 | 2019-08-09 | 一种高层建筑沉降加固抬升纠偏的施工方法 |
CN201910736655.8 | 2019-08-09 |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US17/580,782 Continuation US11732434B2 (en) | 2019-08-09 | 2022-01-21 | High-rise building settling reinforcing and lifting correcting construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2021027025A1 true WO2021027025A1 (zh) | 2021-02-18 |
Family
ID=74367645
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2019/107378 WO2021027025A1 (zh) | 2019-08-09 | 2019-09-23 | 一种高层建筑沉降加固抬升纠偏的施工方法 |
Country Status (3)
Country | Link |
---|---|
US (1) | US11732434B2 (zh) |
CN (1) | CN112343106A (zh) |
WO (1) | WO2021027025A1 (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113863276A (zh) * | 2021-09-16 | 2021-12-31 | 国网河北省电力有限公司沧州供电分公司 | 高压电塔基础施工方法 |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112343078B (zh) * | 2019-08-09 | 2022-07-08 | 北京恒祥宏业基础加固技术有限公司 | 一种厂房设备基础精密抬升方法 |
CN113833012B (zh) * | 2021-10-13 | 2023-02-03 | 山东电力工程咨询院有限公司 | 一种桩式可调风机基础及施工方法 |
CN114319472A (zh) * | 2022-02-16 | 2022-04-12 | 北京恒祥宏业基础加固技术有限公司 | 一种住宅楼基础沉降加固抬升的工程方法 |
CN114960617A (zh) * | 2022-05-21 | 2022-08-30 | 浙江华云电力工程设计咨询有限公司 | 一种隧道基坑坑底错位暗墩加固系统及其加固方法 |
CN114837455B (zh) * | 2022-06-09 | 2023-06-23 | 水利部交通运输部国家能源局南京水利科学研究院 | 一种沉陷水工建筑物的复建方法 |
CN114991198A (zh) * | 2022-08-03 | 2022-09-02 | 山西龙炘电力工程有限公司 | 一种采空区输电铁塔基础和基础加固及调整方法 |
CN115859453B (zh) * | 2023-02-24 | 2023-04-28 | 陕西华邦建设工程有限公司 | 基于bim的地基防水帷幕设计方法及系统 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101487274A (zh) * | 2009-02-23 | 2009-07-22 | 北京交通大学 | 一种城市隧道穿越既有建(构)筑物注浆抬升方法 |
JP2013231329A (ja) * | 2012-05-01 | 2013-11-14 | Sumitomo Forestry Co Ltd | 建物の沈下修正工法 |
CN103643705A (zh) * | 2013-12-12 | 2014-03-19 | 中石化上海工程有限公司 | 钢储罐环墙基础地基局部沉陷补强方法 |
US20180016765A1 (en) * | 2016-07-14 | 2018-01-18 | John Baldwin | Method of lifting a structure on the earth |
CN108343260A (zh) * | 2018-04-08 | 2018-07-31 | 湖南化工地质工程勘察院有限责任公司 | 倾斜建筑物纠偏加固结构及其施工方法 |
CN108343102A (zh) * | 2018-04-26 | 2018-07-31 | 北京恒祥宏业基础加固技术有限公司 | 一种桩基础沉降加固顶升调平结构及其施工方法 |
Family Cites Families (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100549312C (zh) * | 2005-10-09 | 2009-10-14 | 中国水电顾问集团华东勘测设计研究院 | 一种高密度少浆量注浆加固地基的方法 |
CN105908697A (zh) * | 2016-05-16 | 2016-08-31 | 中科院广州化灌工程有限公司 | 一种采用水平孔灌浆的地基加固方法 |
KR101803336B1 (ko) * | 2017-01-03 | 2017-12-06 | (주)지오서비스 | 구근형 반력말뚝을 활용한 지반 보강 및 침하 구조물의 복원 방법 |
US10487473B2 (en) * | 2017-06-20 | 2019-11-26 | Charles L. Asplin | Wall lifting methods |
CN107435346B (zh) * | 2017-08-18 | 2020-02-14 | 北京恒祥宏业基础加固技术有限公司 | 一种适用于高层建筑结构的注浆加固纠偏方法 |
CN108842840A (zh) * | 2018-07-04 | 2018-11-20 | 湖南大学 | 一种补偿地铁隧道下穿导致建筑沉降的软弱夹层注浆抬升方法 |
CN109056859B (zh) * | 2018-09-11 | 2024-07-26 | 中国电建集团华东勘测设计研究院有限公司 | 一种管式注浆风机基础纠偏方法 |
CN112081155B (zh) * | 2019-06-14 | 2022-02-18 | 北京恒祥宏业基础加固技术有限公司 | 一种条形或箱形基础建筑物的加固抬升方法 |
CN112081158B (zh) | 2019-06-14 | 2022-02-18 | 北京恒祥宏业基础加固技术有限公司 | 一种高层建筑前进式注浆形成加固复合桩基的施工方法 |
CN112081153B (zh) * | 2019-06-14 | 2022-08-23 | 北京恒祥宏业基础加固技术有限公司 | 一种筏板基础高层建筑物的抬升方法 |
CN112081157B (zh) | 2019-06-14 | 2022-02-18 | 北京恒祥宏业基础加固技术有限公司 | 一种高层建筑后退式注浆形成加固复合桩基的施工方法 |
CN112081154B (zh) * | 2019-06-14 | 2021-10-12 | 北京恒祥宏业基础加固技术有限公司 | 一种筏板基础高层建筑物加固抬升方法 |
CN112343104B (zh) * | 2019-08-09 | 2022-06-17 | 北京恒祥宏业基础加固技术有限公司 | 一种高铁大型墩台的加固抬升方法 |
CN112343078B (zh) * | 2019-08-09 | 2022-07-08 | 北京恒祥宏业基础加固技术有限公司 | 一种厂房设备基础精密抬升方法 |
CN112942455A (zh) * | 2019-12-11 | 2021-06-11 | 北京恒祥宏业基础加固技术有限公司 | 一种岩溶地基高层建筑物的加固抬升方法 |
CN110965595B (zh) * | 2019-12-30 | 2021-06-04 | 北京恒祥宏业基础加固技术有限公司 | 一种腐蚀性地质环境下筏板基础建筑抬升加固结构及方法 |
CN113818500B (zh) * | 2021-09-14 | 2023-05-12 | 杭州圣基建筑特种工程有限公司 | 高层建筑基础与结构整体提升纠倾施工方法 |
CN114032976A (zh) * | 2021-12-07 | 2022-02-11 | 国网河南省电力公司洛阳供电公司 | 一种变电站设备基础修复装置和方法 |
-
2019
- 2019-08-09 CN CN201910736655.8A patent/CN112343106A/zh active Pending
- 2019-09-23 WO PCT/CN2019/107378 patent/WO2021027025A1/zh active Application Filing
-
2022
- 2022-01-21 US US17/580,782 patent/US11732434B2/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101487274A (zh) * | 2009-02-23 | 2009-07-22 | 北京交通大学 | 一种城市隧道穿越既有建(构)筑物注浆抬升方法 |
JP2013231329A (ja) * | 2012-05-01 | 2013-11-14 | Sumitomo Forestry Co Ltd | 建物の沈下修正工法 |
CN103643705A (zh) * | 2013-12-12 | 2014-03-19 | 中石化上海工程有限公司 | 钢储罐环墙基础地基局部沉陷补强方法 |
US20180016765A1 (en) * | 2016-07-14 | 2018-01-18 | John Baldwin | Method of lifting a structure on the earth |
CN108343260A (zh) * | 2018-04-08 | 2018-07-31 | 湖南化工地质工程勘察院有限责任公司 | 倾斜建筑物纠偏加固结构及其施工方法 |
CN108343102A (zh) * | 2018-04-26 | 2018-07-31 | 北京恒祥宏业基础加固技术有限公司 | 一种桩基础沉降加固顶升调平结构及其施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113863276A (zh) * | 2021-09-16 | 2021-12-31 | 国网河北省电力有限公司沧州供电分公司 | 高压电塔基础施工方法 |
Also Published As
Publication number | Publication date |
---|---|
US11732434B2 (en) | 2023-08-22 |
US20220145575A1 (en) | 2022-05-12 |
CN112343106A (zh) | 2021-02-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021027025A1 (zh) | 一种高层建筑沉降加固抬升纠偏的施工方法 | |
CN205742213U (zh) | 基坑支护结构 | |
CN103233454A (zh) | 湿陷性黄土地基的砂桩浸水真空预压及注浆处理方法 | |
CN112663694B (zh) | 一种淤泥地质上的建构筑物抬升纠偏的施工方法 | |
CN108412503A (zh) | 偏压浅埋隧道洞口施工防护结构及其施工方法 | |
WO2020248429A1 (zh) | 一种筏板基础高层建筑物加固抬升方法 | |
CN112081155B (zh) | 一种条形或箱形基础建筑物的加固抬升方法 | |
CN105804007B (zh) | 一种基于滩涂软基的加筋土岸墙结构 | |
CN112942455A (zh) | 一种岩溶地基高层建筑物的加固抬升方法 | |
CN111636417A (zh) | 一种注浆型钢管桩及其施工方法 | |
CN106368219A (zh) | 一种深基坑的支护加固结构与施工方法 | |
CN112081157B (zh) | 一种高层建筑后退式注浆形成加固复合桩基的施工方法 | |
CN101793027A (zh) | 一种桩心注浆静压锚杆桩 | |
CN108487331B (zh) | 一种集廊道排水和肥槽防渗为一体的地下结构抗浮系统 | |
CN213448541U (zh) | 深厚圆砾层下伏灰岩地基拱桥基础 | |
CN112081158B (zh) | 一种高层建筑前进式注浆形成加固复合桩基的施工方法 | |
CN111810185B (zh) | 一种隧道隧底预加固施工方法 | |
CN113718752A (zh) | 地连墙复合式注浆方法及注浆结构 | |
WO2021027696A1 (zh) | 一种高铁大型墩台的加固抬升方法及加固抬升结构 | |
CN217419736U (zh) | 一种用于地下工程修建的补偿式施工结构 | |
CN116290003B (zh) | 复合承载式斜支撑方法及系统 | |
CN111485571A (zh) | 深厚圆砾层下伏灰岩地基拱桥基础及其修建方法 | |
CN211523179U (zh) | 地铁车站永临一体化围护结构 | |
CN217352573U (zh) | 一种固定流沙层联合桩基结构 | |
CN201635072U (zh) | 一种桩心注浆静压锚杆桩成桩装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 19941282 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 202237003559 Country of ref document: IN |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19941282 Country of ref document: EP Kind code of ref document: A1 |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19941282 Country of ref document: EP Kind code of ref document: A1 |
|
32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC DATED 10.02.23 AND 25.04.23 . |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19941282 Country of ref document: EP Kind code of ref document: A1 |