CN108082839A - Novel flange ring dispenses frame - Google Patents
Novel flange ring dispenses frame Download PDFInfo
- Publication number
- CN108082839A CN108082839A CN201711182628.8A CN201711182628A CN108082839A CN 108082839 A CN108082839 A CN 108082839A CN 201711182628 A CN201711182628 A CN 201711182628A CN 108082839 A CN108082839 A CN 108082839A
- Authority
- CN
- China
- Prior art keywords
- frame
- carriage
- synchronous belt
- broach
- broach frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G15/00—Conveyors having endless load-conveying surfaces, i.e. belts and like continuous members, to which tractive effort is transmitted by means other than endless driving elements of similar configuration
- B65G15/30—Belts or like endless load-carriers
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G47/00—Article or material-handling devices associated with conveyors; Methods employing such devices
- B65G47/52—Devices for transferring articles or materials between conveyors i.e. discharging or feeding devices
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
The present invention provides a kind of novel flange ring dispatching frame, it couples finishing department and storage workshop, finishing numerical control bed is symmetrically disposed on it and is located at the both sides of the finishing department part, including carriage, be arranged between finishing numerically-controlled machine tool and the carriage for the hoisting mechanism on work piece hoisting to the carriage on numerically-controlled machine tool will to be finished, it is arranged at the job stacking mechanism of the carriage output terminal, the workpiece epicyclical mechanism being arranged between the carriage and the job stacking mechanism, it can be by the large-sized flange ring automatic transport machined in finishing department to storage workshop, without manually lifting, conveying is convenient, it is efficient.
Description
Technical field
The present invention relates to a kind of novel flange rings to dispense frame.
Background technology
Large-sized flange ring finishing department complete processing after need to remove stage makeup and costume from board, after be distributed to storage workshop progress
Storage, existing mode of operation is lifted by large size driving, and can only lift a product every time, and efficiency is low
Under, and since finishing department to driving between storage workshop can not be by also needing to carry out by tote cart in centre defeated
It send, heap is carried out, it is necessary to will again be lifted after the workpiece discharging on tote cart first to suitable position by driving in storage workshop
It is folded, it is cumbersome, and multiple operators is needed to coordinate and are completed.
The content of the invention
It, can so as to provide a kind of novel flange ring dispatching frame it is an object of the invention to overcome the shortcomings of above-mentioned technology
By the large-sized flange ring automatic transport machined in finishing department to storage workshop, without manually lifting, conveying is convenient, effect
Rate is high.
Technical solution is such used by invention:Novel flange ring dispenses frame, connection finishing department and storage
Workshop, finishing numerical control bed are symmetrically disposed on it and are located at the both sides of the finishing department part, including carriage, are arranged at essence
Between numerical control machine for processing and the carriage for work piece hoisting on numerically-controlled machine tool will to be finished to the carriage
Hoisting mechanism, be arranged at the job stacking mechanism of the carriage output terminal, be arranged at the carriage and the workpiece heap
Workpiece epicyclical mechanism between folded mechanism;
There are two the carriage tools, and two carriages are symmetrical arranged, and carriage described in per side includes rack, rotation is set
The first synchronizing wheel and the second synchronizing wheel that are placed in the rack are set around first synchronizing wheel and described second synchronous
Synchronous belt on wheel, the supporting rack being mutually fixedly connected with the rack, support frame as described above with the synchronous belt in similar figures, it is described
Medial surface of the upper and lower surface of supporting rack respectively with the synchronous belt fits, and uniformly divides along its length on the synchronous belt
Several conveying broach framves are furnished with, are mutually fixedly connected with synchronous belt described in both sides respectively per the both ends of the conveying broach frame, it is described
It is mutually fixedly connected by vertically disposed connecting rod between conveying broach frame and the synchronous belt, the lower end of the connecting rod turns
It is dynamic to be provided with support pulley, it is offered described in confession in support frame as described above and first synchronizing wheel, second synchronizing wheel
Support pulley by escape groove;
The hoisting mechanism includes lifting extend along the width of the synchronous belt and above the synchronous belt
Frame slides the platform sling set, the guiding axis for being fixedly installed on the mast-up one side along the length direction of the mast-up, turns
Dynamic the first movement leading screw for being arranged at the mast-up opposite side, offers on the platform sling and the guiding axis is matched leads
Xiang Kong, with the described first movement matched threaded hole of leading screw, be provided with hoist engine on the platform sling, winding on the hoist engine
There is steel wire rope, the end of the steel wire rope is connected with hanging ring, locating rod is fixedly installed on the hanging ring, is had in the locating rod
There is the perforation for the steel wire penetrating, guiding mechanism is provided between the locating rod and the platform sling, is slided on the hanging ring
Dynamic to be provided with several sliding parts, the lower end of the sliding part is provided with sucker, and the sliding part is driven by the first cylinder and slided,
It is rotated on the hanging ring and is provided with several L-shaped hooks, the upper end of the grab rotates with the hanging ring and is connected, lower end
For free end, the grab is driven by the second cylinder and rotated;
The pedestal, the turntable being vertically rotatably dispose on the pedestal, fixation that the workpiece epicyclical mechanism includes fixed setting are set
It is placed on the turntable and is slideably positioned in along radially extend rotating arm of the turntable, along vertical direction described
The turnover broach frame of rotating arm end, the end of the rotating arm, which rotates, is provided with vertically disposed driving leading screw, the turnover
It is provided on broach frame and the driving matched lifting swivel nut of leading screw, the turnover broach frame and the conveying broach frame phase
Cooperation;
The job stacking mechanism includes stacking shelf, the shifting roller for being rotatably dispose in the stacking shelf bottom, vertically rotation is set
It is placed in the first elevating screw of the stacking shelf both sides and the second elevating screw, along vertical direction is slideably positioned in the heap
If dried layer in superimposed stacks broach frame, the both sides for stacking broach frame offer respectively with first elevating screw and
The matched threaded hole of second elevating screw, the stacking broach frame are engaged with the turnover broach frame.
It is further improved to be:The upper surface of the conveying broach frame is provided with anti-skidding reticulate pattern.
It is further improved to be:The elevating mechanism includes vertically being rotatably dispose in first sliding rack/described second
The 3rd elevating screw on sliding rack, offers on first crane/second crane and the described 3rd lifting silk
The matched threaded hole of thick stick.
It is further improved to be:The end of the broach of the turnover broach frame is tapered.
By using preceding solution, the beneficial effects of the invention are as follows:When finishing numerically-controlled machine tool is completed to add to workpiece
After work, will be conveyed by hoisting mechanism on work piece hoisting to carriage, and the operation directly by numerically-controlled machine tool operative employee just
It can complete, workpiece is fed directly to storage workshop by carriage, since carriage includes synchronous belt and supporting rack, supporting rack
Rigid support is provided, and synchronous belt is mainly used for conveying workpiece, and by setting resistance during support pulley reduction movement,
Workpiece epicyclical mechanism and job stacking mechanism are set in storage workshop, due to being provided with conveying broach frame on synchronous belt, same
It is under the cooperation of having enough to meet the need broach frame of the conveying broach frame with workpiece epicyclical mechanism, workpiece is direct when step band is sent to output terminal
It is placed on turnover broach frame, then has enough to meet the need broach frame and rise the heap that a station avoids turning to after carriage job stacking mechanism
Folded position, the transhipment of the lifting implementation workpiece by stacking broach frame then substantially increase the dispatching efficiency of workpiece, save labor
Power.
Description of the drawings
Fig. 1 is top view of the present invention;
Fig. 2 is the side view of carriage;
Fig. 3 is hoisting mechanism schematic diagram.
Wherein:1st, synchronous belt;2nd, supporting rack;3rd, broach frame is conveyed;4th, pulley is supported;5th, escape groove;7th, platform sling;8th, first
Mobile leading screw;9th, guiding axis;10th, hoist engine;11st, steel wire rope;12nd, hanging ring;13rd, locating rod;14th, sliding part;15th, turntable;16、
Rotating arm;17th, broach frame is had enough to meet the need;18th, broach frame is stacked;19th, sucker;20th, the first cylinder;21st, L-shaped hook;22nd, the second gas
Cylinder.
Specific embodiment
It is further illustrated the present invention below in conjunction with the drawings and specific embodiments.
As shown in Figure 1-Figure 3, the present invention discloses a kind of novel flange ring dispatching frame, connection finishing department and storage vehicle
Between, finishing numerical control bed is symmetrically disposed on it and is located at the both sides of the finishing department part, including carriage, is arranged at finishing
It is used to finish on work piece hoisting to the carriage on numerically-controlled machine tool between work numerically-controlled machine tool and the carriage
Hoisting mechanism, the job stacking mechanism for being arranged at the carriage output terminal are arranged at the carriage and the job stacking
Workpiece epicyclical mechanism between mechanism;
There are two the carriage tools, and two carriages are symmetrical arranged, and carriage described in per side includes rack, rotation is set
The first synchronizing wheel and the second synchronizing wheel that are placed in the rack are set around first synchronizing wheel and described second synchronous
Synchronous belt 1 on wheel, the supporting rack 2 being mutually fixedly connected with the rack, support frame as described above 2 and the synchronous belt 1 in similar figures,
Medial surface of the upper and lower surface of support frame as described above 2 respectively with the synchronous belt 1 fits, square along its length on the synchronous belt 1
To several conveying broach framves 3 are evenly distributed with, the both ends per the conveying broach frame 3 are consolidated respectively with 1 phase of synchronous belt described in both sides
Fixed connection is mutually fixedly connected, the company between the conveying broach frame 3 and the synchronous belt 1 by vertically disposed connecting rod
The lower end of extension bar, which rotates, is provided with support pulley 4, support frame as described above 2 and first synchronizing wheel, second synchronizing wheel
On offer for it is described support pulley 4 by escape groove 5;
The hoisting mechanism includes lifting extend along the width of the synchronous belt and above the synchronous belt
Frame, along the mast-up length direction slide set platform sling 7, be fixedly installed on the mast-up one side guiding axis 9,
The first movement leading screw 8 of the mast-up opposite side is rotatably dispose in, offers on the platform sling 7 and matches with the guiding axis 9
The pilot hole of conjunction moves 8 matched threaded hole of leading screw with described first, and hoist engine 10, the volume are provided on the platform sling 7
It raises and steel wire rope 11 is arranged on machine 10, the end of the steel wire rope 11 is connected with hanging ring 12, is fixedly installed on the hanging ring 12
Locating rod 13, has the perforation passed through for the steel wire rope 11 in the locating rod 13, the locating rod 13 and the platform sling 7 it
Between be provided with guiding mechanism, slided on the hanging ring 12 and be provided with several sliding parts 14, the lower end of the sliding part 14 is set
There is sucker 19, the sliding part 14 drives slip by the first cylinder 20, rotated on the hanging ring 12 and be provided with several L-shaped hooks
21, the upper end of the grab rotates with the hanging ring 12 and is connected, and lower end is free end, and the grab is by the second cylinder
22 drivings rotate;
The workpiece epicyclical mechanism includes the pedestal being fixedly installed, the turntable 15 being vertically rotatably dispose on the pedestal, fixes
It is arranged on the turntable 15 and is set along radially extend rotating arm 16 of the turntable 15, along vertical direction slip
The turnover broach frame 17 of 16 end of rotating arm is placed in, the end of the rotating arm 16, which rotates, is provided with vertically disposed driving
Leading screw, is provided on the turnover broach frame 17 and the driving matched lifting swivel nut of leading screw, the turnover broach frame 17
It is engaged with the conveying broach frame 3;
The job stacking mechanism includes stacking shelf, the shifting roller for being rotatably dispose in the stacking shelf bottom, vertically rotation is set
It is placed in the first elevating screw of the stacking shelf both sides and the second elevating screw, along vertical direction is slideably positioned in the heap
If the dried layer in superimposed stacks broach frame 18, the both sides for stacking broach frame 18 offer and first elevating screw respectively
And the matched threaded hole of the second elevating screw, the stacking broach frame 18 are engaged with the turnover broach frame 17.
The course of work:After numerically-controlled machine tool is finished to workpiece completion processing, work piece hoisting is extremely conveyed by hoisting mechanism
It is conveyed on frame, and the operation can directly be completed by the operative employee of numerically-controlled machine tool, workpiece is fed directly to by carriage
Storage workshop, since carriage includes synchronous belt 1 and supporting rack 2, supporting rack 2 provides rigid support, and synchronous belt 1 is mainly used
Resistance when being conveyed in by workpiece, and reducing mobile by setting support pulley 4, workpiece epicyclical mechanism is set in storage workshop
And job stacking mechanism, due to being provided with conveying broach frame 3 on synchronous belt 1, when synchronous belt 1 is sent to output terminal, defeated
Broach frame 3 is sent under the cooperation of the turnover broach frame 17 of workpiece epicyclical mechanism, workpiece is placed directly on turnover broach frame 17, and
Broach frame 17 is had enough to meet the need afterwards and rises the stacked position that a station avoids turning to after carriage job stacking mechanism, is passed through and is stacked comb
The transhipment of the lifting implementation workpiece of braces 18 then substantially increases the dispatching efficiency of workpiece, saves labour.
Slip phenomenon occurs in transmission process for workpiece in order to prevent, and the upper surface for conveying broach frame 3 is provided with anti-
Sliding reticulate pattern.
Preferred embodiment is in the present embodiment, and the elevating mechanism includes vertically being rotatably dispose in first slip
The 3rd elevating screw described in frame 9/ on second sliding rack 10 opens up described in first crane 11/ on second crane 12
Have and the matched threaded hole of the 3rd elevating screw.
Preferred embodiment is in the present embodiment, and the end of the broach of the turnover broach frame 17 is tapered.
Basic principle of the invention and main feature and its advantage has been shown and described above, the technical staff of the industry should
The understanding, the present invention is not limited to the above embodiments, the original for simply illustrating the present invention described in above-described embodiment and explanation
Reason, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these changes and improvements
It all fall within the protetion scope of the claimed invention, the claimed scope of the invention is by appended claims and its equivalent circle
It is fixed.
Claims (4)
1. novel flange ring dispenses frame, couple finishing department and storage workshop, finishing numerical control bed is symmetrically disposed on its position
In the both sides of the finishing department part, it is characterised in that:Including carriage, be arranged at finishing numerically-controlled machine tool with it is described defeated
Send between frame for will finish the hoisting mechanism on work piece hoisting to the carriage on numerically-controlled machine tool, be arranged at it is described
The job stacking mechanism of carriage output terminal, the workpiece being arranged between the carriage and job stacking mechanism week favourable turn
Structure;
There are two the carriage tools, and two carriages are symmetrical arranged, and carriage described in per side includes rack, rotation is set
The first synchronizing wheel and the second synchronizing wheel that are placed in the rack are set around first synchronizing wheel and described second synchronous
Synchronous belt on wheel, the supporting rack being mutually fixedly connected with the rack, support frame as described above with the synchronous belt in similar figures, it is described
Medial surface of the upper and lower surface of supporting rack respectively with the synchronous belt fits, and uniformly divides along its length on the synchronous belt
Several conveying broach framves are furnished with, are mutually fixedly connected with synchronous belt described in both sides respectively per the both ends of the conveying broach frame, it is described
It is mutually fixedly connected by vertically disposed connecting rod between conveying broach frame and the synchronous belt, the lower end of the connecting rod turns
It is dynamic to be provided with support pulley, it is offered described in confession in support frame as described above and first synchronizing wheel, second synchronizing wheel
Support pulley by escape groove;
The hoisting mechanism includes lifting extend along the width of the synchronous belt and above the synchronous belt
Frame slides the platform sling set, the guiding axis for being fixedly installed on the mast-up one side along the length direction of the mast-up, turns
Dynamic the first movement leading screw for being arranged at the mast-up opposite side, offers on the platform sling and the guiding axis is matched leads
Xiang Kong, with the described first movement matched threaded hole of leading screw, be provided with hoist engine on the platform sling, winding on the hoist engine
There is steel wire rope, the end of the steel wire rope is connected with hanging ring, locating rod is fixedly installed on the hanging ring, is had in the locating rod
There is the perforation for the steel wire penetrating, guiding mechanism is provided between the locating rod and the platform sling, is slided on the hanging ring
Dynamic to be provided with several sliding parts, the lower end of the sliding part is provided with sucker, and the sliding part is driven by the first cylinder and slided,
It is rotated on the hanging ring and is provided with several L-shaped hooks, the upper end of the grab rotates with the hanging ring and is connected, lower end
For free end, the grab is driven by the second cylinder and rotated;
The pedestal, the turntable being vertically rotatably dispose on the pedestal, fixation that the workpiece epicyclical mechanism includes fixed setting are set
It is placed on the turntable and is slideably positioned in along radially extend rotating arm of the turntable, along vertical direction described
The turnover broach frame of rotating arm end, the end of the rotating arm, which rotates, is provided with vertically disposed driving leading screw, the turnover
It is provided on broach frame and the driving matched lifting swivel nut of leading screw, the turnover broach frame and the conveying broach frame phase
Cooperation;
The job stacking mechanism includes stacking shelf, the shifting roller for being rotatably dispose in the stacking shelf bottom, vertically rotation is set
It is placed in the first elevating screw of the stacking shelf both sides and the second elevating screw, along vertical direction is slideably positioned in the heap
If dried layer in superimposed stacks broach frame, the both sides for stacking broach frame offer respectively with first elevating screw and
The matched threaded hole of second elevating screw, the stacking broach frame are engaged with the turnover broach frame.
2. novel flange ring according to claim 1 dispenses frame, it is characterised in that:The upper surface of the conveying broach frame is set
It is equipped with anti-skidding reticulate pattern.
3. novel flange ring according to claim 1 dispenses frame, it is characterised in that:The elevating mechanism includes vertical rotate
The 3rd elevating screw being arranged on first sliding rack/second sliding rack, first crane/second liter described
It is offered and the matched threaded hole of the 3rd elevating screw on drop frame.
4. novel flange ring according to claim 1 dispenses frame, it is characterised in that:The end of the broach of the turnover broach frame
Portion is tapered.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711182628.8A CN108082839A (en) | 2017-11-23 | 2017-11-23 | Novel flange ring dispenses frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711182628.8A CN108082839A (en) | 2017-11-23 | 2017-11-23 | Novel flange ring dispenses frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108082839A true CN108082839A (en) | 2018-05-29 |
Family
ID=62173007
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711182628.8A Withdrawn CN108082839A (en) | 2017-11-23 | 2017-11-23 | Novel flange ring dispenses frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108082839A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115092630A (en) * | 2022-06-24 | 2022-09-23 | 保利长大工程有限公司 | Automatic climbing conveying equipment for small prefabricated blocks for protecting slope surfaces of side slopes |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0840522A (en) * | 1994-08-01 | 1996-02-13 | Toray Ind Inc | Supply method for ring-shaped packing and its device |
CN102874595A (en) * | 2012-11-01 | 2013-01-16 | 宁波摩科机器人科技有限公司 | Combined type material picking hand device |
CN105109908A (en) * | 2015-07-20 | 2015-12-02 | 杭州斗源机械电子有限公司 | Chain conveying mechanism |
CN105460642A (en) * | 2015-12-29 | 2016-04-06 | 江阴市恒润环锻有限公司 | Automatic large flange stacking and loading machine |
CN205294048U (en) * | 2016-01-18 | 2016-06-08 | 谢泽波 | Novel automatically, pile up dolly |
CN205367519U (en) * | 2015-12-01 | 2016-07-06 | 重庆福丹环保建材有限公司 | Prefabricated plate hoist and mount driving |
CN206217316U (en) * | 2016-10-26 | 2017-06-06 | 呼和浩特市兴捷成科技有限公司 | Swinging auto-laminate machine |
-
2017
- 2017-11-23 CN CN201711182628.8A patent/CN108082839A/en not_active Withdrawn
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0840522A (en) * | 1994-08-01 | 1996-02-13 | Toray Ind Inc | Supply method for ring-shaped packing and its device |
CN102874595A (en) * | 2012-11-01 | 2013-01-16 | 宁波摩科机器人科技有限公司 | Combined type material picking hand device |
CN105109908A (en) * | 2015-07-20 | 2015-12-02 | 杭州斗源机械电子有限公司 | Chain conveying mechanism |
CN205367519U (en) * | 2015-12-01 | 2016-07-06 | 重庆福丹环保建材有限公司 | Prefabricated plate hoist and mount driving |
CN105460642A (en) * | 2015-12-29 | 2016-04-06 | 江阴市恒润环锻有限公司 | Automatic large flange stacking and loading machine |
CN205294048U (en) * | 2016-01-18 | 2016-06-08 | 谢泽波 | Novel automatically, pile up dolly |
CN206217316U (en) * | 2016-10-26 | 2017-06-06 | 呼和浩特市兴捷成科技有限公司 | Swinging auto-laminate machine |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115092630A (en) * | 2022-06-24 | 2022-09-23 | 保利长大工程有限公司 | Automatic climbing conveying equipment for small prefabricated blocks for protecting slope surfaces of side slopes |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207222624U (en) | A kind of conveying Nisc changing device for Full-automatic double-deck continuous wire coiler | |
CN107671222A (en) | Full-automatic ring forging pipeline | |
CN203411255U (en) | Crane for bulk cargo ship | |
CN114634094B (en) | Annular forging is with transporting loading device | |
CN215626323U (en) | Lifting device for robot production | |
CN211870705U (en) | Automatic blanking stacking device for coil pipe | |
CN108016856A (en) | Full-automatic flange ring dispatching frame | |
CN103693567A (en) | Wheel product coating hanging system | |
CN108082839A (en) | Novel flange ring dispenses frame | |
CN214053160U (en) | Steel cylinder discharging device of uncoiler | |
CN207226680U (en) | A kind of automatic Nisc changing device | |
CN108147006A (en) | Full-automatic flange ring carriage | |
CN107934495A (en) | Full-automatic ring forging matches somebody with somebody line sending | |
CN108190503A (en) | Novel flange dispenses frame | |
CN108082933A (en) | Novel flange carriage | |
CN218145539U (en) | Transport saddle conveyor is placed to spray booth packing box | |
CN108082953A (en) | Novel flange ring carriage | |
CN107902389A (en) | Ring forging automatic conveyor line | |
CN108163459A (en) | Flange ring dispenses frame automatically | |
CN107973113A (en) | Full-automatic ring forging carriage | |
CN108190387A (en) | Flange dispenses frame | |
CN108217115A (en) | Annulus dispenses frame | |
CN108147037A (en) | Full-automatic flange ring delivery system | |
CN108033243A (en) | Flange ring carriage | |
CN107973061A (en) | Flange ring dispenses frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20180529 |