CN108018782A - The construction method of overhead box beam concrete column - Google Patents

The construction method of overhead box beam concrete column Download PDF

Info

Publication number
CN108018782A
CN108018782A CN201711387525.5A CN201711387525A CN108018782A CN 108018782 A CN108018782 A CN 108018782A CN 201711387525 A CN201711387525 A CN 201711387525A CN 108018782 A CN108018782 A CN 108018782A
Authority
CN
China
Prior art keywords
reinforcement cage
column
steel reinforcement
column steel
box beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711387525.5A
Other languages
Chinese (zh)
Inventor
王虓
余伟
陆俊华
王泳捷
李操
谈炘
周蓉峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201711387525.5A priority Critical patent/CN108018782A/en
Publication of CN108018782A publication Critical patent/CN108018782A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Abstract

The present invention provides a kind of construction method of overhead box beam concrete column, it, which has broken traditional column reinforcing bar, need to divide the form of construction work of two parts installation (embedded bar part and cushion cap are with upper pillar stand reinforcing bar part in cushion cap) at the scene, it is combined into one, it is integrally formed, mould concentrated processing whole reinforcement cage is utilized i.e. in processing workshop, scene is transported to again, and integral hoisting is in place.The construction method need not set up scaffold, eliminate the manpower and materials set up and removed needed for scaffold, reduce the security risk of construction personnel, and due to the integral type hanging method of column steel reinforcement cage so that construction quality can get a promotion, and also shorten the duration.

Description

The construction method of overhead box beam concrete column
Technical field
The present invention relates to elevated bridge Construction Technology field, more particularly to a kind of overhead box beam concrete column is applied Work method.
Background technology
With the fast development of highway construction technology, how to make quick, effective, the applying of guaranteeing both quality and quantity of highway Work becomes a new direction of elevated bridge engineering construction.And the part that highway is related to overhead box girder construction is one A construction Difficulties, the construction technology of the concrete column of major embodiment thereunder are complex.
Concrete column generally use under conventional overhead box beam sets up console construction technology and carries out scene Reinforcing bar, template construction, in traditional console form of construction work, generally first set up scaffold as constructing operation face, so Scattered reinforcing bar scene is bound afterwards and (is divided into the reinforcing bar of embedded bar binding and cushion cap surface above section in cushion cap to tie up Prick) and model sheetinstallat work, finally carry out pouring for concrete.Not only security risk is big for this method, but also by environmental constraints, Simultaneously because manual site's operative relationship, the more difficult control of quality of reinforcing bar binding, influence construction quality.In progress monitoring due to The setting up of scaffold, remove this cycle operation and greatly reduce the convenience of column construction, and need to consume a large amount of manpowers, Material resources and inevitable measure time carry out, and cost is very high, but construction efficiency is low.
The content of the invention
The present invention provides a kind of construction method of overhead box beam concrete column, with shorten the construction period, reduce in realization risk, On the basis of reducing manually, additionally it is possible to effectively improve the construction efficiency of bridge box beam concrete column.
In order to achieve the above object, the present invention provides a kind of construction method of overhead box beam concrete column, it is used for Cushion cap upper concrete column, to play a supporting role to overhead box beam, the construction method includes:
Step 1:In workshop, overall processing makes column steel reinforcement cage;
Step 2:The column steel reinforcement cage is integrally transported to construction site;
Step 3:By the column steel reinforcement cage integral hoisting on the cushion cap;
Step 4:Pour into a mould cushion cap concrete;
Step 5:In the surrounding hoisting upright column template of the column steel reinforcement cage;
Step 6:Pour into a mould column concrete;
Step 7:The model of the column is removed, and concrete is conserved.
Further, the step 3 specifically includes:
Step 31:The column steel reinforcement cage is sling, and is inserted into the reinforced mesh of the cushion cap;
Step 32:After the column steel reinforcement cage is in place, the part and the reinforced mesh that are inserted into cushion cap are tied up Prick;
Step 33:Stirrup is used in 50 cm ranges more than the cushion cap surface and to drag hook muscle to the column reinforcing bar Cage is bound;
Step 34:Floor-type support is set in the side of the column steel reinforcement cage, and one end of the floor-type support is stood with described The main reinforcement connection of column steel reinforcement cage is fixed, and the other end is fixed on the bottom bed course of the cushion cap.
Step 35:Each main reinforcement spot welding of the top layer reinforcing bar on the cushion cap surface respectively with the column steel reinforcement cage is fixed.
Further, before the step 33 is carried out, first to the stirrup close to the column steel reinforcement cage one side into Row dabbing, cleaning treatment.
Further, in the step 34, respectively set at least described in three in every side of the column steel reinforcement cage Floor-type support.
Further, the model of the column includes lower section template and the upper section template with operating platform, and the operation is flat Platform is located at the top of model of the column.
Further, the operating platform includes ring-shaped platform, bearing diagonal and safety net, and the ring-shaped platform passes through described Bearing diagonal is fixed on the top of the upper section template, and the excircle annular of the safety net along the ring-shaped platform is arranged at described On ring-shaped platform.
Optionally, the step 5 specifically includes:
Step 51:Lower section template described in side integral assembling in the column steel reinforcement cage, in the lower section Template Location Afterwards, it is fixedly connected with the column steel reinforcement cage;
Step 52:Template is saved on described in side integral assembling in the column steel reinforcement cage, is connect in the upper and lower section template After being fixed at seam using positioning pin, the upper section template is fixedly connected with the column steel reinforcement cage.
Optionally, the upper section template is divided into symmetrical two-section, the step by the cutting planes of vertical direction Five specifically include:
Step 51 ':Lower section template described in side integral assembling in the column steel reinforcement cage, in the lower section Template Location Afterwards, it is fixedly connected with the column steel reinforcement cage;
Step 52 ':Wherein one section upper section template is in place from the lifting of the side of the column steel reinforcement cage, described upper and lower Save after being fixed at form joint using positioning pin, this section of upper section template is fixedly connected with the column steel reinforcement cage;
Step 53 ':The opposite side lifting of another section of upper section template from the column steel reinforcement cage is in place, described upper and lower Save after being fixed at form joint using positioning pin, this section of upper section template is fixedly connected with the column steel reinforcement cage;
Step 54 ':Template will be saved on two-section to be fixedly connected by horizontal location pin and the contraposition of screw thread reinforcing pull rod, is made on whole Section template becomes an entirety.
Further, after saving model sheetinstallat on described, by the operating platform in the column steel reinforcement cage Top sets cable wind rope, and one end of the cable wind rope is connected with the top of the column steel reinforcement cage, and the other end is fixed on ground.
Further, an at least cable wind rope is respectively set in every side of the column steel reinforcement cage.
Compared with prior art, the invention has the advantages that:
The construction method of overhead box beam concrete column provided by the invention, which has broken traditional column reinforcing bar, to be needed at the scene Divide the form of construction work of two parts installation (embedded bar part and cushion cap are with upper pillar stand reinforcing bar part in cushion cap), being closed two is One, it is integrally formed, i.e., mould concentrated processing whole reinforcement cage is utilized in processing workshop, then scene is transported to, and integrally hang Dress is in place.The construction method need not set up scaffold, eliminate the manpower and materials set up and removed needed for scaffold, reduce and apply The security risk of worker person, and due to the integral type hanging method of column steel reinforcement cage so that construction quality can get a promotion, Also the duration is shortened.
Brief description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is that the construction method central post template construction of overhead box beam concrete column provided in an embodiment of the present invention finishes Structure diagram afterwards;
Fig. 2 is that the construction method central post template construction of overhead box beam concrete column provided in an embodiment of the present invention finishes Sectional drawing afterwards;
Fig. 3 be overhead box beam concrete column provided in an embodiment of the present invention construction method in operating platform vertical view Figure;
Fig. 4 cuts open for the side of operating platform in the construction method of overhead box beam concrete column provided in an embodiment of the present invention Figure;
Fig. 5 above saves bowing for template for one section in the construction method of overhead box beam concrete column provided in an embodiment of the present invention View.
In Fig. 1 to 5,
1:Column steel reinforcement cage;2:Cushion cap;3:Floor-type support;4:Model of the column;41:Upper section template;5:Operating platform;51: Ring-shaped platform;52:Bearing diagonal;53:Safety net.
Embodiment
The construction method of overhead box beam concrete column proposed by the present invention is made below in conjunction with the drawings and specific embodiments It is further described.According to following explanation and claims, advantages and features of the invention will become apparent from.It should be noted It is that attached drawing uses using very simplified form and non-accurate ratio, only to convenience, lucidly aids in illustrating this hair The purpose of bright embodiment.
The core concept of the present invention is, there is provided a kind of construction method of overhead box beam concrete column, it has broken biography The column reinforcing bar of system need to divide two parts installation at the scene (embedded bar part and cushion cap are with upper pillar stand reinforcing bar part in cushion cap) Form of construction work, is combined into one, and is integrally formed, i.e., mould concentrated processing whole reinforcement cage is utilized in processing workshop, then will It is transported to scene, and integral hoisting is in place.The construction method need not set up scaffold, eliminate and set up and remove needed for scaffold Manpower and materials, reduce the security risk of construction personnel, and due to the integral type hanging method of column steel reinforcement cage so that apply Working medium amount can get a promotion, and also shorten the duration.
Please refer to Fig.1 neutral to the construction method that 5, Fig. 1 is overhead box beam concrete column provided in an embodiment of the present invention Structure diagram after column template construction;Fig. 2 is the construction of overhead box beam concrete column provided in an embodiment of the present invention Sectional drawing after method central post template construction;Fig. 3 is overhead box beam concrete column provided in an embodiment of the present invention The top view of operating platform in construction method;Fig. 4 is the construction party of overhead box beam concrete column provided in an embodiment of the present invention The sectional side view of operating platform in method;Fig. 5 is in the construction method of overhead box beam concrete column provided in an embodiment of the present invention one Cut the top view of upper section template.
As depicted in figs. 1 and 2, the embodiment of the present invention provides a kind of construction method of overhead box beam concrete column, it is used In in cushion cap upper concrete column, to play a supporting role to overhead box beam, the construction method includes:
Step 1:In workshop, overall processing makes column steel reinforcement cage 1;
Step 2:The entirety of column steel reinforcement cage 1 is transported to construction site;
Step 3:By 1 integral hoisting of column steel reinforcement cage on the cushion cap 2;
Step 4:The concrete that cushion cap 2 is carried out by pump truck pours into a mould work;
Step 5:In the surrounding hoisting upright column template 4 of the column steel reinforcement cage 1;
Step 6:Concrete column is poured into a mould in the model of the column 4 by pump truck;
Step 7:Remove the model of the column 4, and concrete conserved, the concrete in model of the column 4 with it is described Column steel reinforcement cage 1 collectively constitutes the concrete column.
The construction method of overhead box beam concrete column provided in an embodiment of the present invention, which has broken traditional column reinforcing bar, to be needed Divide the form of construction work of two parts installation (embedded bar part and cushion cap are with upper pillar stand reinforcing bar part in cushion cap) at the scene, closed Two be one, is integrally formed, i.e., mould concentrated processing whole reinforcement cage is utilized in processing workshop, then is transported to scene, and whole Body lifting is in place.The construction method need not set up scaffold, eliminate the manpower and materials set up and removed needed for scaffold, reduce The security risk of construction personnel, and due to the integral type hanging method of column steel reinforcement cage so that construction quality can obtain Lifting, also shortens the duration.
Specifically, overall processing making column steel reinforcement cage 1 has the following advantages in workshop:The concentration module of column reinforcing bar Change and process, make and install, broken traditional distributing processing, making and Installation Modes, made by high space-variant level land, by field Industry becomes plant working;With finished product, semi-finished product neck hair system, each work surface is dispensed into, reduces adverse weather influence, makes former material abundant Utilize, reduce loss;Using integral solder of mould shaping of shaping in workshop, when installation, only need to integrally hang column steel reinforcement cage Soldered steel reinforcement cage integral module is filled, shortens construction period, reduces in-site installation and open-assembly time, reduces what is got rusty Degree, improves speed of application and overall dimensions precision, so that the thickness of cover to reinforcement can be guaranteed, improves and apply Working medium amount.
Further, the step 3 specifically includes:
Step 31:The column steel reinforcement cage 1 is sling, and is inserted into the reinforced mesh of the cushion cap 2;
Step 32:After the column steel reinforcement cage 1 is in place, the part and the reinforced mesh that are inserted into cushion cap 2 carry out Binding;
Step 33:Stirrup is used in 50 cm ranges more than 2 surface of cushion cap and to drag hook muscle to the column steel Muscle cage 1 is bound;
Step 34:The column steel reinforcement cage 1 side set floor-type support 3, one end of the floor-type support 3 with it is described Main reinforcement connection in column steel reinforcement cage 1 is fixed, and the other end is fixed on the bottom bed course of the cushion cap 2, the floor-type support 3 To control stability of the cushion cap 2 during its concreting, while strengthen the control of 1 verticality of column steel reinforcement cage, this falls Ground support 3 can be removed when installing model of the column 4.
Step 35:By each main reinforcement point solid welding with the column steel reinforcement cage 1 respectively of the top layer reinforcing bar on 2 surface of cushion cap It is fixed.
In the present embodiment, the concrete structure of the cushion cap 2 is the prior art, therefore is just repeated no more herein.
Further, before the step 33 is carried out, first to the stirrup close to the column steel reinforcement cage 1 one side into Row dabbing, cleaning treatment, effect is bound to increase it.
Further, since overall 1 weight of column steel reinforcement cage is larger, in construction, its weight can all act on cushion cap On 2 reinforced mesh, easily it is allowed to deform, therefore in the step 34, is respectively set in every side of the column steel reinforcement cage 1 At least three floor-type supports 3 are put, in the present embodiment, the floor-type support 3 is that anchor pole adds cable wind rope, makes column reinforcing bar The main reinforcement of cage 1 can be supported directly on the bottom bed course of cushion cap 2 by the floor-type support 3, and keeps verticality.
Further, the model of the column 4 includes lower section template and the upper section template 41 with operating platform 5, the behaviour Make the top that platform 5 is located at model of the column 4.As shown in Figure 3 and Figure 4, the operating platform 5 includes ring-shaped platform 51, bearing diagonal 52 and safety net 53, the ring-shaped platform 51 is fixed on the top of the upper section template 41, the peace by the bearing diagonal 52 The excircle annular of the whole network 53 along the ring-shaped platform 51 is arranged on the ring-shaped platform 51.
In the present embodiment, it just can complete the installation of operating platform 5 at the same time by hoisting upright column template 4, save Set up the time required to scaffold and on the basis of manpower, which can also play some of scaffold in the prior art Purposes, such as the gate spool of pump truck can be fixed on column top by staff by the operating platform 5 when pouring into a mould column concrete, And cable wind rope etc. is manually set in column top after completing to pour into a mould.
As shown in Figures 1 to 4, in one embodiment of the invention, the step 5 specifically includes:
Step 51:Lower section template described in side integral assembling in the column steel reinforcement cage 1, in the lower section Template Location Afterwards, it is fixedly connected with the column steel reinforcement cage 1;
Step 52:Template 41 is saved on described in side integral assembling in the column steel reinforcement cage 1, in the upper and lower section mould After plate seam crossing is fixed using positioning pin, the upper section template 41 is fixedly connected with the column steel reinforcement cage 1.
As shown in Figure 4 and Figure 5, in another embodiment of the present invention, for can not integral assembling vase-shaped column, The upper section template 41 is divided into symmetrical two-section by the cutting planes of vertical direction, and the step 5 specifically includes:
Step 51 ':Lower section template described in side integral assembling in the column steel reinforcement cage 1, determines in the lower section template Behind position, it is fixedly connected with the column steel reinforcement cage 1;
Step 52 ':Wherein one section upper section template 41 is in place from the lifting of the side of the column steel reinforcement cage 1, on described, After being fixed at lower section form joint using positioning pin, this section of upper section template 41 is fixedly connected with the column steel reinforcement cage 1;
Step 53 ':The opposite side lifting of another section of upper section template 41 from the column steel reinforcement cage 1 is in place, on described, After being fixed at lower section form joint using positioning pin, this section of upper section template 41 is fixedly connected with the column steel reinforcement cage 1;
Step 54 ':Template 41 will be saved on two-section to be fixedly connected by horizontal location pin and the contraposition of screw thread reinforcing pull rod, is made whole Upper section template 41 becomes an entirety.
Further, in upper two embodiments, after section template 41 installs on described, the operating platform is passed through 5 respectively set an at least guy in every side of the top of the column steel reinforcement cage 1 towards the column steel reinforcement cage 1 Rope, one end of the cable wind rope are connected with the top of the column steel reinforcement cage 1, and the other end is fixed on ground, to adjust column Verticality, and prevent column from being tilted under strong wind or typhoon weather.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art God and scope.In this way, if these modification and variations of the present invention belong to the scope of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to comprising including these modification and variations.

Claims (10)

1. a kind of construction method of overhead box beam concrete column, in cushion cap upper concrete column, with to overhead box Beam is played a supporting role, it is characterised in that including:
Step 1:In workshop, overall processing makes column steel reinforcement cage;
Step 2:The column steel reinforcement cage is integrally transported to construction site;
Step 3:By the column steel reinforcement cage integral hoisting on the cushion cap;
Step 4:Pour into a mould cushion cap concrete;
Step 5:In the surrounding hoisting upright column template of the column steel reinforcement cage;
Step 6:Pour into a mould column concrete;
Step 7:The model of the column is removed, and concrete is conserved.
2. the construction method of overhead box beam concrete column according to claim 1, it is characterised in that the step 3 tool Body includes:
Step 31:The column steel reinforcement cage is sling, and is inserted into the reinforced mesh of the cushion cap;
Step 32:After the column steel reinforcement cage is in place, the part and the reinforced mesh that are inserted into cushion cap are bound;
Step 33:More than the cushion cap surface in 50 cm ranges using stirrup and to drag hook muscle to the column steel reinforcement cage into Row binding;
Step 34:Floor-type support, one end of the floor-type support and the column steel are set in the side of the column steel reinforcement cage The main reinforcement connection of muscle cage is fixed, and the other end is fixed on the bottom bed course of the cushion cap.
Step 35:Each main reinforcement spot welding of the top layer reinforcing bar on the cushion cap surface respectively with the column steel reinforcement cage is fixed.
3. the construction method of overhead box beam concrete column according to claim 2, it is characterised in that carrying out the step Before rapid 33, dabbing, cleaning treatment first are carried out to one side of the stirrup close to the column steel reinforcement cage.
4. the construction method of overhead box beam concrete column according to claim 2, it is characterised in that in the step 34 In, at least three floor-type supports are respectively set in every side of the column steel reinforcement cage.
5. the construction method of overhead box beam concrete column according to any one of claim 1 to 4, it is characterised in that The model of the column includes lower section template and the upper section template with operating platform, the operating platform are located at the top of model of the column End.
6. the construction method of overhead box beam concrete column according to claim 5, it is characterised in that the operating platform Including ring-shaped platform, bearing diagonal and safety net, the ring-shaped platform is fixed on the top of the upper section template by the bearing diagonal End, the safety net are arranged on the ring-shaped platform along the excircle annular of the ring-shaped platform.
7. the construction method of overhead box beam concrete column according to claim 5, it is characterised in that the step 5 tool Body includes:
Step 51:Lower section template described in side integral assembling in the column steel reinforcement cage, will after the lower section Template Location It is fixedly connected with the column steel reinforcement cage;
Step 52:Template is saved on described in side integral assembling in the column steel reinforcement cage, at the upper and lower section form joint After being fixed using positioning pin, the upper section template is fixedly connected with the column steel reinforcement cage.
8. the construction method of overhead box beam concrete column according to claim 5, it is characterised in that the upper section template It is divided into symmetrical two-section by the cutting planes of vertical direction, the step 5 specifically includes:
Step 51 ':Lower section template described in side integral assembling in the column steel reinforcement cage, after the lower section Template Location, It is fixedly connected with the column steel reinforcement cage;
Step 52 ':Wherein one section upper section template is in place from the lifting of the side of the column steel reinforcement cage, in the upper and lower section mould After plate seam crossing is fixed using positioning pin, this section of upper section template is fixedly connected with the column steel reinforcement cage;
Step 53 ':The opposite side lifting of another section of upper section template from the column steel reinforcement cage is in place, in the upper and lower section mould After plate seam crossing is fixed using positioning pin, this section of upper section template is fixedly connected with the column steel reinforcement cage;
Step 54 ':Template will be saved on two-section to be fixedly connected by horizontal location pin and the contraposition of screw thread reinforcing pull rod, makes entirely upper section mould Plate becomes an entirety.
9. the construction method of the overhead box beam concrete column according to claim 7 or 8, it is characterised in that on described After saving model sheetinstallat, cable wind rope, the cable wind rope are set on the top of the column steel reinforcement cage by the operating platform One end be connected with the top of the column steel reinforcement cage, the other end is fixed on ground.
10. the construction method of overhead box beam concrete column according to claim 9, it is characterised in that in the column Every side of steel reinforcement cage respectively sets an at least cable wind rope.
CN201711387525.5A 2017-12-20 2017-12-20 The construction method of overhead box beam concrete column Pending CN108018782A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711387525.5A CN108018782A (en) 2017-12-20 2017-12-20 The construction method of overhead box beam concrete column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711387525.5A CN108018782A (en) 2017-12-20 2017-12-20 The construction method of overhead box beam concrete column

Publications (1)

Publication Number Publication Date
CN108018782A true CN108018782A (en) 2018-05-11

Family

ID=62074385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711387525.5A Pending CN108018782A (en) 2017-12-20 2017-12-20 The construction method of overhead box beam concrete column

Country Status (1)

Country Link
CN (1) CN108018782A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554070A (en) * 2020-12-15 2021-03-26 浙江交工集团股份有限公司 Bridge upright post bracket-free construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06193016A (en) * 1992-12-28 1994-07-12 Taisei Corp Build-in construction method of steel framed pillar leg part
JP2009264036A (en) * 2008-04-28 2009-11-12 East Japan Railway Co Method for reinforcing bridge pier or the like
CN102011368A (en) * 2010-11-10 2011-04-13 中国一冶集团有限公司 One-time molding construction method for vase-shaped columnar pier of viaduct
CN105178199A (en) * 2015-10-19 2015-12-23 中亿丰建设集团股份有限公司 Pier column construction method and pier column template
CN105256948A (en) * 2015-09-07 2016-01-20 中交第一公路工程局有限公司 Construction method and molding bed of square reinforced concrete pier
CN106012811A (en) * 2016-06-14 2016-10-12 江苏燕宁建设工程有限公司 Construction method for integrally binding and hoisting reinforcing bars for pier body of vase type bridge pier

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06193016A (en) * 1992-12-28 1994-07-12 Taisei Corp Build-in construction method of steel framed pillar leg part
JP2009264036A (en) * 2008-04-28 2009-11-12 East Japan Railway Co Method for reinforcing bridge pier or the like
CN102011368A (en) * 2010-11-10 2011-04-13 中国一冶集团有限公司 One-time molding construction method for vase-shaped columnar pier of viaduct
CN105256948A (en) * 2015-09-07 2016-01-20 中交第一公路工程局有限公司 Construction method and molding bed of square reinforced concrete pier
CN105178199A (en) * 2015-10-19 2015-12-23 中亿丰建设集团股份有限公司 Pier column construction method and pier column template
CN106012811A (en) * 2016-06-14 2016-10-12 江苏燕宁建设工程有限公司 Construction method for integrally binding and hoisting reinforcing bars for pier body of vase type bridge pier

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李灏等: "立柱无支架施工技术在桥梁工程中的应用_", 《公路交通科技》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554070A (en) * 2020-12-15 2021-03-26 浙江交工集团股份有限公司 Bridge upright post bracket-free construction method

Similar Documents

Publication Publication Date Title
CN106758790B (en) A kind of precast construction and construction method of bridge substructure construction
CN105908902B (en) Precast Pier Columns steel reinforcement cage locating rack and pier stud steel reinforcement cage construction method
CN105839536A (en) Construction method of cable-stayed bridge pylon
CN207177303U (en) Rail mounted vibrating spear
CN103114681A (en) To-be-poured structure and construction method of high-altitude large-span reinforced concrete beam
CN206267422U (en) A kind of assembly concrete superposed column
CN209114332U (en) A kind of long big section bent cap bracket system of overhanging
CN103498425A (en) Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof
CN106948276A (en) A kind of method of cast-in-place box beam bracket integral demounting
CN107806019A (en) Large-span suspension bridge gate Sarasota construction method
CN114770706B (en) Light T-beam prefabrication equipment and prefabrication installation construction method
CN207863507U (en) A kind of vertical member displacement apparatus for skyscraper floor
CN206599919U (en) A kind of integral prefabricated reinforcing bar web frame of shear wall
CN105484165B (en) Integrated prestress tensioning frame structure and manufacturing and using methods thereof
CN206800800U (en) Horizontal reinforcement distance piece
CN108018782A (en) The construction method of overhead box beam concrete column
CN106836255B (en) The integral prefabricated structure of basement bottom board catch pit steel mesh and method of construction
CN205889488U (en) Steel sleeve box's precast reinforced concrete back cover template and hoist device thereof
CN107130521B (en) A kind of dell precipice section large-section beam Bailey truss hoisting die construction method
CN208534069U (en) The assembled support device of steel bar truss floor support plate composite floor system
CN106638645A (en) Layering prefabricated structure and building method of basement bottom board water collection pit reinforcing mesh
CN205617664U (en) Prefabricated pier stud locating rack for steel reinforcement cage
CN205369044U (en) Integration prestressing force stretch -draw frame construction
CN212176590U (en) Outer frame safety protection structure is exempted from to assembled building
CN206418512U (en) Basement bottom board catch pit bar-mat reinforcement is layered precast construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180511

WD01 Invention patent application deemed withdrawn after publication