CN107130521B - A kind of dell precipice section large-section beam Bailey truss hoisting die construction method - Google Patents

A kind of dell precipice section large-section beam Bailey truss hoisting die construction method Download PDF

Info

Publication number
CN107130521B
CN107130521B CN201710385016.2A CN201710385016A CN107130521B CN 107130521 B CN107130521 B CN 107130521B CN 201710385016 A CN201710385016 A CN 201710385016A CN 107130521 B CN107130521 B CN 107130521B
Authority
CN
China
Prior art keywords
steel
double flute
bailey truss
flute steel
sunpender
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710385016.2A
Other languages
Chinese (zh)
Other versions
CN107130521A (en
Inventor
何昌杰
高峰奇
曾喜安
蒋立红
林冰
吴智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Bureau Third Construction Co Ltd
Original Assignee
China Construction Fifth Bureau Third Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Bureau Third Construction Co Ltd filed Critical China Construction Fifth Bureau Third Construction Co Ltd
Priority to CN201710385016.2A priority Critical patent/CN107130521B/en
Publication of CN107130521A publication Critical patent/CN107130521A/en
Application granted granted Critical
Publication of CN107130521B publication Critical patent/CN107130521B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of dell precipice section large-section beam Bailey truss hoisting die construction method, it in turn includes the following steps, splicing lifting beret slice, making and installation top double flute steel, installation lower part channel steel, are laid with distribution beam, seating side guard rail, laydown, template at installation sunpender, the present invention, which is one, can effectively solve that because with a varied topography, height is too high a kind of Bailey truss hoisting die construction method of landing support can not be laid, the present invention adapts to that all are with a varied topography, in large-span structure engineering.

Description

A kind of dell precipice section large-section beam Bailey truss hoisting die construction method
Technical field
The present invention relates to a kind of dell precipice section large-section beam Bailey truss hoisting die construction methods.
Background technology
With building trade development and meet complex building requirement.Bridges and culverts, large-span structure, larger high ordertransfer structure Part is increasing.Used cast-in-situ steel reinforced concrete beam span is big in the construction process, height difference is big from the ground for these components.Branch The selection of support form need to meet technically feasible, reasonable in economy, ensure in safety, condition optimal on the duration.However due to Height is too high from the ground for structure, is limited by landform, geology and transportation condition, arrangement is complicated, and stress is larger, can not be by tradition Mode is arranged.Therefore use which kind of support system particularly important in the construction process.
Invention content
In view of the deficiencies of the prior art, the present invention provides one kind can not set up landing support suitable for a varied topography, The simple dell precipice section large-section beam Bailey truss hoisting die construction method of constructing operation simultaneously.
Including splicing lifting beret slice, making and top double flute steel is installed, installation sunpender, installation lower part double flute steel, is laid with Distribution beam, seating side guard rail, laydown, template, it is characterised in that:Steps are as follows for Specific construction:
(1) splicing lifting beret slice,
A certain number of beret slices are chosen according to structural span in structure design drawing, and assembled formation is carried out by connecting pin Bailey truss, Bailey truss are hung to the reinforced beam top of pouring molding by tower crane, and it is big that Bailey truss sets up length In the deck-siding equal to reinforced beam, drilling installation expansion bolt, passes through U-shaped armful by Bailey truss on reinforced beam Hoop and expansion bolt are fixed on reinforced beam;
(2) it makes and double flute steel is installed,
The making of top double flute steel and lower part double flute steel is carried out in material processing site while Bailey truss is set up, on Portion's double flute steel and lower part double flute steel are made of two same size channel steels, and hole, channel steel and channel steel are reserved between two channel steels Between using steel cushion block be welded to connect fixation, the steel cushion block of top double flute steel and lower part double flute steel be equipped with it is corresponding can For the hole that sunpender passes through, after Bailey truss is set up, top double flute steel is hoisted to Bailey truss top, top double flute It is welded and fixed between steel and Bailey truss top flange;
(3) sunpender is installed,
According to structural stress analysis, the high-strength bolt of appropriate diameter is chosen as sunpender, the length of sunpender is determined according to design Degree, indicates the installation site of top double flute steel and lower part double flute steel on sunpender, and when installation, sunpender is between the double flute steel of top Hole on steel cushion block passes through so that top double flute steel is placed in the installation marker location of sunpender, then by nut by sunpender with Top double flute steel is fixed;
(4) lower part double flute steel is installed,
After the completion of hanger erection, safe steel cat ladder is installed from Bailey truss as easy operation platform, then carries out Lower part double flute steel is transported to the lower part of Bailey truss by tower crane, using hawser so that sunpender is passed through by the installation of lower part double flute steel Hole between the double flute steel of lower part on steel cushion block so that lower part double flute steel is placed in the installation marker location of sunpender, then passes through nut Sunpender and lower part double flute steel are fixed;
(5) it is laid with distribution beam,
After all lower part double flute steel are installed in place, in lower part, the upside of double flute steel is laid with distribution beam;
(6) seating side guard rail,
On distribution beam top, scaffold is set up, and set up and go along with sb. to guard him, all go along with sb. to guard him is closed using Dense mesh screen, and is going along with sb. to guard him Upper setting anti-drop net;
(7) laydown, template,
Cast-in-situ Beam position, laydown installation form are made in distribution beam.
In step (1), it is 3 meters long, 1.5 meters of height that Bailey truss, which uses 321 beret slices, beret slice sectional dimension,.
In step (2), the steel cushion block is laid along channel steel extending direction and arranges that spacing is 1m~1.5m.
In step (5), distribution beam is made up of the laying of I-steel, and the I-steel is welded and fixed with lower part double flute steel.
In step (6), sets up 1.2 meters high of skirt of facing and protect, steel pipe cat ladder is set up in scaffold, and be laid with step plate, foot Hand cradle completely spreads bamboo fragrant plant piece, and one of anti-drop net vertically is being arranged every 10 meters as construction operation platform.
The present invention by using Bailey truss hoisting die construction technology solves that landing frame body can not be used due to a varied topography The case where being.The Bailey truss that hoisting die construction is formed by connecting using beret slice by pin as upper support structure, adopt by substructure With double flute steel.Up-down structure is attached using high-strength bolt as sunpender by bolt.Finally consolidate using steel plate as baffle plate is hung It is scheduled on and constitutes stable Bailey truss on channel steel and hang mould support system.It is mainly characterized by reducing that lower support system, progress are fast, throw Relatively small, guarantee construction quality is provided, is solved well because of the construction difficult problem with a varied topography that can not arrange landing support.Due to group It is processed in factory floor at the accessory of Bailey truss, dimensional discrepancy very little, and itself has prodigious rigidity, is transported to construction Scene, which carries out assembling, can become Bailey truss, and length is determined according to cast-in-place beam length.For this purpose, this hoisting die construction method safety Reliably, easy for construction.
In conclusion the present invention is one can effectively solve that because with a varied topography, height is too high landing support can not be laid A kind of Bailey truss hoisting die construction method, the present invention adapt to that all are with a varied topography, in large-span structure engineering.
Description of the drawings
Fig. 1 is the positive facade overall schematic of Bailey truss formed using this construction method.
Fig. 2 is the Bailey truss side elevation overall schematic formed using this construction method.
Fig. 3 is Bailey truss of the present invention, sunpender, double flute steel connection diagram.
Fig. 4 is screw rod of the present invention and double flute steel connection diagram.
Fig. 5 is double flute steel schematic diagram of the present invention;
Each label indicates in figure:1, high-strength bolt;2, nut;3, steel cushion block;4, double flute steel;5, Bailey truss;6, Bei Lei Holder bearing;7, crosshead;8, distribution beam;9, template;10, cast-in-situ concrete beam;11, steel pipe frame column support system.
Specific implementation mode
The present invention will be further described with reference to the accompanying drawings and examples.Following circumferential directions refer to the week along tunnel To, axially refer to along tunnel axial direction.
Fig. 1 to Fig. 5 shows the implementation figure of the dell precipice section large-section beam Bailey truss hoisting die construction method of the present invention, It includes the following steps:
(1) splicing lifting beret slice,
It is 3 meters long, 1.5 meters of height that hoisting die construction, which uses 321 beret slices (reinforced), standard beret slice sectional dimension,.Foundation Structural span chooses a certain number of beret slices and carries out assembly by connecting pin in structure design drawing.Referring to Fig. 1, will finally spell The Bailey truss 5 installed is hung to 6 top of reinforced beam of pouring molding by tower crane, and reinforced beam 6 is supported on On steel pipe frame column support system 11, Bailey truss sets up length and is more than or equal to deck-siding, in advance the drilling installation expanding screw on beam Bailey truss is fixed on by U-shaped anchor ear and expansion bolt on beam by bolt.
(2) it makes and double flute steel 4 is installed,
The system of top double flute steel 41 and lower part double flute steel 42 is carried out in material processing site while Bailey truss is set up Make, referring to Fig. 5, top double flute steel 41 and lower part double flute steel 42 are made of two same size channel steels, pre- between two channel steels It boxes out gap, is reliably welded using steel cushion block 3 between channel steel and channel steel, steel cushion block arranges that spacing is 1m~1.5m.Steel cushion block On reserve the hole passed through for sunpender in advance using drilling machine.It, will after Bailey truss erection finishes and double flute steel performs Double flute steel is hoisted to Bailey truss top, and double flute steel 4 and Bailey truss are welded and fixed between 5 top flange.
(3) sunpender is installed,
According to structural stress analysis, the high-strength bolt 1 for choosing appropriate diameter is used as sunpender, field technician to measure It calculates, determines the length of sunpender.The specific location for indicating upper and lower channel steel with red paint on sunpender in advance, is lifted later. When installation, referring to Fig. 3, the hole that sunpender 1 is reserved across top double flute steel 41 in steel cushion block 3 uses on steel cushion block top Nut 2 is fixed.
(4) lower part double flute steel 42 is installed,
Referring to Fig. 1, after installation is complete in sunpender 1, safe steel cat ladder is installed from the Bailey truss of top as easily applying Work platform carries out the installation of lower part double flute steel 42, lower part double flute steel 42 is transported to 5 lower part of Bailey truss, work using tower crane first Make personnel and double flute steel is fixed on technical staff by double flute steel both sides referring to Fig. 4 across screw rod by nut 2 using hawser The position indicated in advance.
(5) it is laid with distribution beam,
Referring to Fig. 2, after all lower part double flute steel 42 are installed in place, it is allocated work as required on 4 top of double flute steel The laying of word steel 8 is fixed between I-steel 8 and lower part double flute steel 42 in the form of welding.
(6) seating side guard rail,
Referring to Fig. 2, on 8 top of distribution beam, foot hand is set up in structural beams both sides, and 7, steel pipe cat ladder is set up in scaffold, and is spread If step plate facilitates construction personnel to walk up and down, scaffold completely spreads bamboo fragrant plant piece, and take using steel pipe as construction operation platform If 1.2 meters of height face skirt shield, all go along with sb. to guard him is closed using Dense mesh screen, and one of anti-drop net vertically is being arranged every 10 meters.
(7) laydown, laying template,
Referring to Fig. 2, unwrapping wire makes the position of Cast-in-situ Beam 10 in distribution beam 8, and laydown installation form 9 finally carries out Beams of concrete 10 pours.

Claims (5)

1. a kind of dell precipice section large-section beam Bailey truss hoisting die construction method, including splicing lifting beret slice, making and peace It loads onto portion's double flute steel, installation sunpender, installation lower part double flute steel, be laid with distribution beam, seating side guard rail, laydown, mould Plate, it is characterised in that:Steps are as follows for Specific construction:
(1) splicing lifting beret slice,
A certain number of beret slices are chosen according to structural span in structure design drawing, and assembled formation shellfish thunder is carried out by connecting pin Holder, Bailey truss are hung to the reinforced beam top of pouring molding by tower crane, and drill peace on reinforced beam Expansion bolt is filled, Bailey truss is fixed on reinforced beam;
(2) it makes and double flute steel is installed,
The making of top double flute steel and lower part double flute steel is carried out in material processing site while Bailey truss is set up, top is double Channel steel and lower part double flute steel are made of two same size channel steels, hole are reserved between two channel steels, between channel steel and channel steel Be welded to connect fixation using steel cushion block, the steel cushion block of top double flute steel and lower part double flute steel is equipped with corresponding for hanging Top double flute steel is hoisted to Bailey truss top by the hole that bar passes through after Bailey truss is set up, top double flute steel with Bailey truss is welded and fixed between top flange;
(3) sunpender is installed,
According to structural stress analysis, the high-strength bolt of appropriate diameter is chosen as sunpender, the length of sunpender is determined according to design, Indicate the installation site of top double flute steel and lower part double flute steel on sunpender, when installation, sunpender is from steel pad between the double flute steel of top Hole on block passes through so that top double flute steel is placed in the installation marker location of sunpender, then by nut by sunpender and top Double flute steel is fixed;
(4) lower part double flute steel is installed,
After the completion of hanger erection, safe steel cat ladder is installed from Bailey truss as easy operation platform, then carries out lower part Lower part double flute steel is transported to the lower part of Bailey truss by tower crane by the installation of double flute steel, using hawser so that sunpender passes through lower part Hole between double flute steel on steel cushion block so that lower part double flute steel is placed in the installation marker location of sunpender, then will be hung by nut Bar is fixed with lower part double flute steel;
(5) it is laid with distribution beam,
After all lower part double flute steel are installed in place, in lower part, the upside of double flute steel is laid with distribution beam;
(6) seating side guard rail,
On distribution beam top, scaffold is set up, and set up and go along with sb. to guard him, all go along with sb. to guard him is closed using Dense mesh screen, and is set on going along with sb. to guard him Set anti-drop net;
(7) laydown, template,
Cast-in-situ Beam position, laydown installation form are made in distribution beam.
2. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step Suddenly in (1), it is 3 meters long, 1.5 meters of height that Bailey truss, which uses 321 beret slices, beret slice sectional dimension,.
3. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step Suddenly in (2), the steel cushion block is laid along channel steel extending direction and arranges that spacing is 1m~1.5m.
4. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step Suddenly in (5), distribution beam is made up of the laying of I-steel, and the I-steel is welded and fixed with lower part double flute steel.
5. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step Suddenly it in (6), sets up 1.2 meters high of skirt of facing and protects, steel pipe cat ladder is set up in scaffold, and be laid with step plate, scaffold is used as and applies Work operating platform completely spreads bamboo fragrant plant piece, and one of anti-drop net vertically is being arranged every 10 meters.
CN201710385016.2A 2017-05-26 2017-05-26 A kind of dell precipice section large-section beam Bailey truss hoisting die construction method Active CN107130521B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710385016.2A CN107130521B (en) 2017-05-26 2017-05-26 A kind of dell precipice section large-section beam Bailey truss hoisting die construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710385016.2A CN107130521B (en) 2017-05-26 2017-05-26 A kind of dell precipice section large-section beam Bailey truss hoisting die construction method

Publications (2)

Publication Number Publication Date
CN107130521A CN107130521A (en) 2017-09-05
CN107130521B true CN107130521B (en) 2018-10-19

Family

ID=59734028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710385016.2A Active CN107130521B (en) 2017-05-26 2017-05-26 A kind of dell precipice section large-section beam Bailey truss hoisting die construction method

Country Status (1)

Country Link
CN (1) CN107130521B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108005114A (en) * 2017-12-11 2018-05-08 贵州中昇东浩科技有限公司 A kind of piping lane pours mould
CN109457814B (en) * 2018-11-15 2020-07-07 李延敏 Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN112093704B (en) * 2020-09-09 2021-11-16 厦门安科科技有限公司 Hanging device for jacking formwork system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080099543A (en) * 2007-05-09 2008-11-13 동명공영건설(주) Formwork assembly for a bridge
CN202688888U (en) * 2012-07-17 2013-01-23 中交第二公路工程局有限公司 Deck type reversely hung template hanging frame
CN103835238B (en) * 2014-02-21 2015-11-18 中铁大桥局集团有限公司 A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN104141383B (en) * 2014-07-16 2016-06-01 北京万兴建筑集团有限公司 A kind of Bailey beam pendent form support system and construction thereof
CN105133497B (en) * 2015-07-21 2016-08-24 杭州江润科技有限公司 A kind of construction method being inclined cross low clearance active service highway multi-azimuth adjustable cast-in-place box beam bracket system

Also Published As

Publication number Publication date
CN107130521A (en) 2017-09-05

Similar Documents

Publication Publication Date Title
CN105926448B (en) A kind of construction method of the Cable stayed Bridge Main Tower in the double rope faces of the only tower of curve
CN106677070B (en) A kind of high-altitude long-span heavy duty construction of beam bracket and construction method
CN101781879B (en) Construction method of single-pylon cable-stayed bridge without dorsal cables
CN100545363C (en) Structure conversion layer type steel concrete girder mould suspension construction method
CN102535845A (en) Construction method of bearing frame of corridor structure
CN106702910A (en) Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes
CN106436573B (en) Superelevation Sarasota large span upper beam bracket steel truss stand construction method
CN107130521B (en) A kind of dell precipice section large-section beam Bailey truss hoisting die construction method
CN107090975A (en) A kind of big across the cast-in-situ concrete beam Bailey bracket formwork construction method of superelevation
CN103498425A (en) Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof
CN109025295A (en) A kind of high-altitude long-span steel reinforced concrete corridor construction method
CN103938875A (en) Ground single body tensioning lifting construction method of single layer suspendome
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN109267493A (en) A kind of construction method installed across river steel lid beam
CN103938871B (en) A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint
CN108643572A (en) Concrete crossbeam support, shellfish thunder platform construction and steel strand wires combined installation method
CN102777044B (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN110409624A (en) A kind of installation of large scale equipment and main structure be inverse to be made to calculate and construction method
CN106381810B (en) With the cast-in-place outstanding method for filling beam of beam-column type bracket
CN110616706B (en) Construction method for layering binding in large-diameter pile foundation reinforcing steel bar hole
CN201714056U (en) Truss-type operating platform
CN102635234A (en) Construction method for controlling thickness of upper-layer steel bar protection layer and board thickness of floorboard
CN106245531B (en) Steel structural bridge installation method is hung under bilateral derrick type

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant