CN103938875A - Ground single body tensioning lifting construction method of single layer suspendome - Google Patents
Ground single body tensioning lifting construction method of single layer suspendome Download PDFInfo
- Publication number
- CN103938875A CN103938875A CN201310026825.6A CN201310026825A CN103938875A CN 103938875 A CN103938875 A CN 103938875A CN 201310026825 A CN201310026825 A CN 201310026825A CN 103938875 A CN103938875 A CN 103938875A
- Authority
- CN
- China
- Prior art keywords
- construction
- lifting
- dome
- ground
- suspendome
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The invention relates to suspendome lifting, in particular to a ground single body tensioning lifting construction method of a single layer suspendome. The method comprises the steps that after an outer ring truss structure shell-shaped roof is constructed, according to the construction of a center area suspendome structure, a splicing operation platform is built at the position under the designing position of a dome structure, key work such as splicing welding of a reticulated dome and laying and tensing of a prestressed cable are all completed on the operation platform; meanwhile, lower anchor points for improving construction are arranged on nodes surrounding the dome structure, upper improving anchor points are designed and mounted on the completed truss roof over the improving lower anchor points, and lifting equipment steel stranded wires are arranged. Through a synchronous technology, the suspendome structure which is tensioned by ground single bodies is lifted in place. The difficult problem of project construction is solved, and construction tasks are achieved economically, safely and reliably. The ground single body tensioning lifting construction method of the single suspendome is the best construction method for mounting the suspendome structure of the type of working station, and is economic, saving in construction period, safe and reliable.
Description
Technical field
The present invention relates to a dome and promote, relate in particular to a kind of individual layer string and prop up vault ground monomer stretch-draw lifting construction method.
Background technology
In many sports centers sports palace project, sports palace central area individual layer string props up dome and surrounding vault type room connects into entirety, and difficulty of construction is very big.After surrounding vault type trussed roof has been constructed, now outside loop wheel machine no operatton condition (outside loop wheel machine operating radius does not reach construction requirement), inner because construction plant does not possess loop wheel machine entry condition, therefore propping up after dome can only adopt ground monomer stretch-draw, this central area string promotes form construction in place.
The suspended-dome structure of venue central area in the past, all adopts and lays long-armed tower crane outside the Olympic venues, in, set up to structural base exceed load-bearing full hall scaffold, suspended-dome structure is technique in bulk in position.If this Study of Support engineering adopts traditional construction technology, in current tower crane design project limit of power, need the quantity of tower crane many, and the task that cannot 100% fulfils assignment.
Summary of the invention
The object of the invention is to overcome the defect of prior art, provide a kind of individual layer string to prop up dome ground monomer stretch-draw lifting construction method.Construction cost of the present invention is cheap, safe and reliable, short construction period.
In order to achieve the above object, the present invention is achieved in that
A kind of individual layer string props up dome ground monomer stretch-draw lifting construction method, it is characterized in that, it comprises:
Step 1, the trussed construction system of construction roof system outer ring, after treating outer ring roof structure construction, the upper anchor point hoisting frame promoting is installed on the node location being connected with cantilever frame at interior ring truss, and installation promotes power set;
Step 2, the installation on ground of net shell: set up consolidation service platform under net shell, set up out the job platform of ladder moulding according to the shape of net shell, in support platform, carry out the assembled assembled work such as point, temporary supporting moulding bed, component assembly welding of putting of net shell;
Step 3, net shell is assembled complete after, install and promote anchorage and the distribution beam that may need, and wear and join steel strand, the debugging work before lifting means is tentatively used;
Step 4, the laying of prestressed cable and ground stretch-draw: according to the calculative determination construction stretching value of design stretch-draw value, the operating mode of constructing, formulate the construction stretching value of each position drag-line in stretch-draw step and every step, in guaranteeing to promote, suspended-dome structure distortion, in design allowed band, is guaranteed structure construction safety;
Step 5, Synchronous lifting;
Step 6, installs string and props up the embedding benefit rod member between dome and the interior ring of outer ring roof system truss, discharges lifter active force, and the support force that makes string prop up dome is all transferred to outside roof system support system;
Step 7, the dismountings such as lifting means, measure for improvement, support jig.
Described individual layer string props up dome ground monomer stretch-draw lifting construction method, and step 1 also comprises: described hoisting frame ensures the safe distance on vertical and horizontal space in lifting construction, for promoting the reserved necessary usage space of steel strand of use; In addition, note also rigidity and the stability of hoisting frame.
Described individual layer string props up dome ground monomer stretch-draw lifting construction method, and step 2 also comprises: the necessary reserved passageway setting such as strut, prestressed cable in described platform for lining; Quality control in assembled process, prevents that structure from, because of the malformation that assembled, construction factor, welding etc. bring, affecting construction quality.Key is to control three-dimensional space position, the integral assembling size Control of net shell node, and the relative position while ensureing installation on ground is correct.
Described individual layer string props up dome ground monomer stretch-draw lifting construction method, and in step 3, in described lifting, anchorage, on a vertical line, in be controlled at ± 20mm of the error of perpendicularity, and ensures that steel strand cabling is smooth and easy
After outer ring of the present invention trussed construction shell mould roof construction completes, the construction of central area suspended-dome structure, adopt position under the design attitude of dome structure to set up consolidation service platform, the key jobs such as the assembled welding of net shell and the laying stretch-draw of prestressed cable have all been constructed on job platform.Meanwhile, arrange the anchorage of lifting construction on the surrounding grid node of dome structure, on the completed trussed roof directly over lifting anchorage, design and installation promotes anchor point and lays lifting means and steel strand.Suspended-dome structure ground monomer stretch-draw being completed by Synchronous lifting technology promotes in place.Both the project construction difficult problem having solved, again economic, the safe and reliable construction task that completed.Fact proved, this construction method is the best construction method that the suspended-dome structure of this type operating mode is installed, not only economical, saves the duration and safe and reliable.The present invention, by the improvement of construction method, has solved the insurmountable construction difficult problem of conventional construction method, and work progress is safe and reliable, and whole efficiency significantly promotes; Realize automation control and simulation analysis in conjunction with operation, improved construction safety and reliability; Save tall and big bearing frame measure and Large-scale Hoisting equipment investment, saved material, reduced installation cost.
Detailed description of the invention
Below in conjunction with detailed description of the invention, the present invention is further illustrated:
The present invention is taking center stadium engineering in Huludao City's physical culture as example: its suspended-dome structure form as: suspended-dome structure is connected on the ring truss of outer ring roof system, string prop up dome self by single layer welding ball-receiving net shell, prestressed cable and the strut that links between the two be connected otic placode etc., suspended-dome structure prestressed cable is made up of three ring ropes and corresponding radial cable, structure construction difficulty is very big, is mainly assembled, the laying stretch-draw of drag-line and the problem of suspended-dome structure installation in position that solves net shell.According to this design feature, on the surrounding grid node of dome structure, arrange the anchorage of lifting construction, on the completed trussed roof directly over lifting anchorage, design and installation promotes anchor point and lays Synchronous lifting lifting means and steel strand.Suspended-dome structure ground monomer stretch-draw being completed by Synchronous lifting technology promotes in place.Specific construction step is as follows:
First, the trussed construction system of construction roof system outer ring, after treating outer ring roof structure construction, on interior ring truss, (Nodes being connected with cantilever frame) installs the upper anchor point hoisting frame promoting, and installation promotes power set.Technical essential is: the design of the setting of anchor point, hoisting frame in lifting.Noting hoisting frame safe distance vertically and on horizontal space in lifting construction, is the reserved necessary usage space of steel strand that promotes use; In addition, note also rigidity and the stability of hoisting frame.
The installation on ground of net shell.Set up consolidation service platform, set up out the job platform of ladder moulding according to the shape of net shell, in support platform, carry out the assembled assembled work such as point, temporary supporting moulding bed, component assembly welding of putting of net shell and show.Technical essential: the necessary reserved passageway setting such as strut, prestressed cable in platform for lining; Quality control in assembled process, prevents that structure from, because of the malformation that assembled, construction factor, welding etc. bring, affecting construction quality.Key is to control three-dimensional space position, the integral assembling size Control of net shell node, and the relative position while ensureing installation on ground is correct;
Net shell is assembled complete after, install and promote anchorage and the distribution beam that may need, and wear and join steel strand, debugging work before lifting means is tentatively used, key problem in technology: in lifting, anchorage, on a vertical line, in be controlled at ± 20mm of the error of perpendicularity, ensures that steel strand cabling is smooth and easy;
The laying of prestressed cable and ground stretch-draw.Technical essential: design stretch-draw value, construction stretching value, according to the calculative determination of construction operating mode, are formulated the construction stretching value of each position drag-line in stretch-draw step and every step, and in guaranteeing to promote, suspended-dome structure distortion, in design allowed band, is guaranteed structure construction safety.
Synchronous lifting, key technology: hoisting frame, promote up and down the design of anchor point and distribution beam;
String is installed and is propped up the embedding benefit rod member between ring truss in dome and outer ring roof system;
Discharge lifter active force, the support force that makes string prop up dome is all transferred to outside roof system support system;
The dismountings such as lifting means, measure for improvement, support jig.
By facts have proved, this construction method has solved construction difficult problem, with high content of technology, safe and reliable, construction precision is high, construction quality is good, and saves tall and big bearing frame measure and Large-scale Hoisting equipment, operation automation, intellectuality, improve technology content, significantly reduced installation cost.
Claims (4)
1. individual layer string props up a dome ground monomer stretch-draw lifting construction method, it is characterized in that, it comprises:
Step 1, the trussed construction system of construction roof system outer ring, after treating outer ring roof structure construction, the upper anchor point hoisting frame promoting is installed on the node location being connected with cantilever frame at interior ring truss, and installation promotes power set;
Step 2, the installation on ground of net shell: set up consolidation service platform under net shell, set up out the job platform of ladder moulding according to the shape of net shell, in support platform, carry out the assembled assembled work such as point, temporary supporting moulding bed, component assembly welding of putting of net shell;
Step 3, net shell is assembled complete after, install and promote anchorage and the distribution beam that may need, and wear and join steel strand, the debugging work before lifting means is tentatively used;
Step 4, the laying of prestressed cable and ground stretch-draw: according to the simulation calculation of design stretch-draw value, the operating mode of constructing, determine construction stretching value, formulate the construction stretching value of each position drag-line in stretch-draw step and every step, in guaranteeing to promote, suspended-dome structure distortion, in design allowed band, is guaranteed structure construction safety;
Step 5, Synchronous lifting;
Step 6, installs string and props up the embedding benefit rod member between dome and the interior ring of outer ring roof system truss, discharges lifter active force, and the support force that makes string prop up dome is all transferred to outside roof system support system;
Step 7, the dismountings such as lifting means, measure for improvement, support jig.
2. individual layer string according to claim 1 props up dome ground monomer stretch-draw lifting construction method, it is characterized in that: step 1 also comprises: described hoisting frame ensures the safe distance on vertical and horizontal space in lifting construction, for promoting the reserved necessary usage space of steel strand of use; In addition, note also rigidity and the stability of hoisting frame.
3. individual layer string according to claim 1 props up dome ground monomer stretch-draw lifting construction method, it is characterized in that: described step 2 also comprises: the necessary reserved passageway setting such as strut, prestressed cable in described platform for lining; Quality control in assembled process, prevents that structure from, because of the malformation that assembled, construction factor, welding etc. bring, affecting construction quality; Control three-dimensional space position, the integral assembling size Control of net shell node, the relative position while ensureing installation on ground is correct.
4. individual layer string according to claim 1 props up dome ground monomer stretch-draw lifting construction method, it is characterized in that, in described step 3, in described lifting, anchorage, on a vertical line, in be controlled at ± 20mm of the error of perpendicularity, and ensures that steel strand cabling is smooth and easy.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310026825.6A CN103938875A (en) | 2013-01-18 | 2013-01-18 | Ground single body tensioning lifting construction method of single layer suspendome |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310026825.6A CN103938875A (en) | 2013-01-18 | 2013-01-18 | Ground single body tensioning lifting construction method of single layer suspendome |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103938875A true CN103938875A (en) | 2014-07-23 |
Family
ID=51186725
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310026825.6A Pending CN103938875A (en) | 2013-01-18 | 2013-01-18 | Ground single body tensioning lifting construction method of single layer suspendome |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103938875A (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105046001A (en) * | 2015-07-21 | 2015-11-11 | 上海海勃膜结构有限公司 | Whole construction process simulation analysis method for prestressed suspended cable membrane dome structure |
CN105113778A (en) * | 2015-07-15 | 2015-12-02 | 安徽跨宇钢结构网架工程有限公司 | Hydraulic lifting platform |
CN105822071A (en) * | 2016-03-29 | 2016-08-03 | 浙江中南建设集团钢结构有限公司 | Peripheral bearing bidirectional intersected spatial steel truss structure one-way lifting installing process |
CN106499193A (en) * | 2016-10-30 | 2017-03-15 | 上海二十冶建设有限公司 | A kind of installation method of Ecology umbrella single-layer lattice shell steel construction |
CN108571075A (en) * | 2017-03-10 | 2018-09-25 | 五冶集团上海有限公司 | A kind of large-span shell assembling jig frame staged Platforms Construct Method of Super |
CN109763568A (en) * | 2019-01-17 | 2019-05-17 | 中建七局安装工程有限公司 | A kind of suspen-shell structure network construction method |
CN109868902A (en) * | 2019-02-25 | 2019-06-11 | 中建四局第一建筑工程有限公司 | A kind of large span steel structure roof entirety lift structure |
CN111719757A (en) * | 2020-06-18 | 2020-09-29 | 中国建筑第八工程局有限公司 | Method and system for integrally lifting asymmetric inner ring truss and cable dome |
CN111733978A (en) * | 2020-06-30 | 2020-10-02 | 中国建筑一局(集团)有限公司 | Large-span arc-shaped steel structure without support in middle and construction method |
CN112982669A (en) * | 2021-02-09 | 2021-06-18 | 清华大学建筑设计研究院有限公司 | Eccentric annular large-cantilever prestressed steel structural system and construction method thereof |
CN115030386A (en) * | 2022-05-19 | 2022-09-09 | 中建钢构工程有限公司 | Construction method of endless cable chord support latticed shell structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06180029A (en) * | 1992-12-15 | 1994-06-28 | Takenaka Komuten Co Ltd | Lift-up construction method of single layer truss roof |
CN101519913A (en) * | 2008-12-29 | 2009-09-02 | 青建集团股份公司 | Construction method for lifting whole steel structural roof with large span and complicated design |
CN101852019A (en) * | 2010-06-11 | 2010-10-06 | 北京市机械施工有限公司 | Lifting mounting method for inclined steel roof |
CN101858149A (en) * | 2009-04-08 | 2010-10-13 | 上海市机械施工有限公司 | Large-sized steel structure integral translation and hoisting combination construction process |
CN102808519A (en) * | 2012-08-16 | 2012-12-05 | 上海通用金属结构工程有限公司 | Large-span integral lifting method for roof frame |
-
2013
- 2013-01-18 CN CN201310026825.6A patent/CN103938875A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06180029A (en) * | 1992-12-15 | 1994-06-28 | Takenaka Komuten Co Ltd | Lift-up construction method of single layer truss roof |
CN101519913A (en) * | 2008-12-29 | 2009-09-02 | 青建集团股份公司 | Construction method for lifting whole steel structural roof with large span and complicated design |
CN101858149A (en) * | 2009-04-08 | 2010-10-13 | 上海市机械施工有限公司 | Large-sized steel structure integral translation and hoisting combination construction process |
CN101852019A (en) * | 2010-06-11 | 2010-10-06 | 北京市机械施工有限公司 | Lifting mounting method for inclined steel roof |
CN102808519A (en) * | 2012-08-16 | 2012-12-05 | 上海通用金属结构工程有限公司 | Large-span integral lifting method for roof frame |
Non-Patent Citations (1)
Title |
---|
曹云巧: "葫芦岛体育馆屋盖整体提升技术应用", 《2012中国钢结构行业大会论文集》 * |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105113778A (en) * | 2015-07-15 | 2015-12-02 | 安徽跨宇钢结构网架工程有限公司 | Hydraulic lifting platform |
CN105046001B (en) * | 2015-07-21 | 2018-02-27 | 上海海勃膜结构股份有限公司 | The construction overall process analogue simulation analysis method of prestressing force string guy film dome structure |
CN105046001A (en) * | 2015-07-21 | 2015-11-11 | 上海海勃膜结构有限公司 | Whole construction process simulation analysis method for prestressed suspended cable membrane dome structure |
CN105822071A (en) * | 2016-03-29 | 2016-08-03 | 浙江中南建设集团钢结构有限公司 | Peripheral bearing bidirectional intersected spatial steel truss structure one-way lifting installing process |
CN105822071B (en) * | 2016-03-29 | 2017-11-28 | 浙江中南建设集团钢结构有限公司 | The bidirectional crossed Steel Space Truss structure one-way lift and erection technique of periphery supporting |
CN106499193A (en) * | 2016-10-30 | 2017-03-15 | 上海二十冶建设有限公司 | A kind of installation method of Ecology umbrella single-layer lattice shell steel construction |
CN108571075B (en) * | 2017-03-10 | 2019-12-03 | 五冶集团上海有限公司 | A kind of large-span shell assembling jig frame staged Platforms Construct Method of Super |
CN108571075A (en) * | 2017-03-10 | 2018-09-25 | 五冶集团上海有限公司 | A kind of large-span shell assembling jig frame staged Platforms Construct Method of Super |
CN109763568A (en) * | 2019-01-17 | 2019-05-17 | 中建七局安装工程有限公司 | A kind of suspen-shell structure network construction method |
CN109868902A (en) * | 2019-02-25 | 2019-06-11 | 中建四局第一建筑工程有限公司 | A kind of large span steel structure roof entirety lift structure |
CN111719757A (en) * | 2020-06-18 | 2020-09-29 | 中国建筑第八工程局有限公司 | Method and system for integrally lifting asymmetric inner ring truss and cable dome |
CN111719757B (en) * | 2020-06-18 | 2022-01-21 | 中国建筑第八工程局有限公司 | Method and system for integrally lifting asymmetric inner ring truss and cable dome |
CN111733978A (en) * | 2020-06-30 | 2020-10-02 | 中国建筑一局(集团)有限公司 | Large-span arc-shaped steel structure without support in middle and construction method |
CN112982669A (en) * | 2021-02-09 | 2021-06-18 | 清华大学建筑设计研究院有限公司 | Eccentric annular large-cantilever prestressed steel structural system and construction method thereof |
CN112982669B (en) * | 2021-02-09 | 2022-09-16 | 清华大学建筑设计研究院有限公司 | Eccentric annular large-cantilever prestressed steel structural system and construction method thereof |
CN115030386A (en) * | 2022-05-19 | 2022-09-09 | 中建钢构工程有限公司 | Construction method of endless cable chord support latticed shell structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103938875A (en) | Ground single body tensioning lifting construction method of single layer suspendome | |
CN104141383B (en) | A kind of Bailey beam pendent form support system and construction thereof | |
CN107090932B (en) | Construction method of large-span thin-wall plane arch truss based on stiff ring beam | |
CN102535845A (en) | Construction method of bearing frame of corridor structure | |
CN103556836B (en) | Spherical reticulated shells assembling and construction method under restricted clearance condition | |
CN203947771U (en) | A kind of Bailey beam pendent form support system | |
CN105298100A (en) | Construction method of cantilever construction platform with ultrahigh cast-in-place flaring structure in cylindrical building | |
CN104100090B (en) | High-altitude comprehensive construction method of big-cantilever steel truss structure | |
CN104695715A (en) | Construction method of beam string structure of roof | |
CN206692235U (en) | A kind of steel structure dome lifts by crane erecting device | |
CN105804400A (en) | Hoisting construction method of curved truss | |
CN103485574B (en) | A kind of granulation tower tower top structure of reinforced concrete method | |
CN208899886U (en) | Cantilever frame platform | |
CN109138454A (en) | A kind of installation method of super high-rise building outline border bandy truss | |
CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
CN114182647B (en) | Construction method for lifting and turning weak arch | |
CN102777044B (en) | Hoisting method of steel-structured spraying layer of urea prilling tower | |
CN102691267A (en) | High pier construction method for external whole operation platform | |
CN109853964A (en) | A kind of construction method for steel construction armored concrete mixed structure | |
CN110616706B (en) | Construction method for layering binding in large-diameter pile foundation reinforcing steel bar hole | |
CN105625732B (en) | Superelevation overhanging steel structure truss support free construction method | |
CN201714056U (en) | Truss-type operating platform | |
CN109440942B (en) | Installation structure and construction process of factory building roof grid | |
CN107130521B (en) | A kind of dell precipice section large-section beam Bailey truss hoisting die construction method | |
CN116290905A (en) | Roof steel structure reconstruction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20140723 |