CN107130521A - A kind of dell precipice section large-section beam Bailey truss hoisting die construction method - Google Patents
A kind of dell precipice section large-section beam Bailey truss hoisting die construction method Download PDFInfo
- Publication number
- CN107130521A CN107130521A CN201710385016.2A CN201710385016A CN107130521A CN 107130521 A CN107130521 A CN 107130521A CN 201710385016 A CN201710385016 A CN 201710385016A CN 107130521 A CN107130521 A CN 107130521A
- Authority
- CN
- China
- Prior art keywords
- steel
- double flute
- section
- flute steel
- bailey truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of dell precipice section large-section beam Bailey truss hoisting die construction method, in turn include the following steps, splicing lifts beret truss, made with installing top double flute steel, installing suspension rod, installation bottom channel-section steel, laying distribution beam, seating side guard rail, laydown, template, the present invention, which is one, can effectively solve that because with a varied topography, height is too high a kind of Bailey truss hoisting die construction method of landing support can not be laid, the present invention adapts to that all are with a varied topography, in large-span structure engineering.
Description
Technical field
The present invention relates to a kind of dell precipice section large-section beam Bailey truss hoisting die construction method.
Background technology
With building trade development and meet complex building requirement.Bridges and culverts, large-span structure, larger high ordertransfer structure
Part is increasing.The discrepancy in elevation is big greatly, from the ground for cast-in-situ steel reinforced concrete beam span of these components employed in work progress.Branch
The selection of support form need to meet technically feasible, reasonable in economy, ensure in safety, condition optimal on the duration.Yet with
Height is too high from the ground for structure, is limited by landform, geology and transportation condition, arrangement is complicated, stress is larger, it is impossible to by tradition
Mode is arranged.Therefore it is particularly important using which kind of support system in work progress.
The content of the invention
In view of the shortcomings of the prior art, the present invention provides one kind and can be applied to a varied topography and can not set up landing support,
While the simple dell precipice section large-section beam Bailey truss hoisting die construction method of constructing operation.
Beret truss is lifted including splicing, made with installing top double flute steel, installing suspension rod, installation bottom channel-section steel, laying point
With beam, seating side guard rail, laydown, template, it is characterised in that:Specific construction step is as follows:
(1) splicing lifting beret truss,
A number of beret truss, which is chosen, according to structural span in structure design drawing passes through the assembled formation of connecting pin progress
Bailey truss, Bailey truss is hung to the reinforced beam top for having poured shaping by tower crane, and it is big that Bailey truss sets up length
In the deck-siding equal to reinforced beam, expansion bolt is installed in drilling on reinforced beam, and Bailey truss is passed through into U-shaped armful
Hoop and expansion bolt are fixed on reinforced beam;
(2) make with installing double flute steel,
The making that place carries out top double flute steel and bottom double flute steel is processed in material while Bailey truss is set up, on
Portion's double flute steel and bottom double flute steel are constituted by two same size channel-section steels, and hole, channel-section steel and channel-section steel are reserved between two channel-section steels
Between carry out being welded to connect fixation using steel plate washer, the steel cushion block of top double flute steel and bottom double flute steel can provided with corresponding
The hole passed through for suspension rod, after Bailey truss sets up and finished, Bailey truss top, top double flute are hoisted to by top double flute steel
It is welded and fixed between steel and Bailey truss top flange;
(3) suspension rod is installed,
According to structural stress analysis, the high-strength bolt of appropriate diameter is chosen as suspension rod, the length of suspension rod is determined according to design
Degree, indicates the installation site of top double flute steel and bottom double flute steel, during installation, suspension rod is between the double flute steel of top on suspension rod
Hole on steel cushion block is passed through so that top double flute steel is placed in the installation marker location of suspension rod, then by nut by suspension rod with
Top double flute steel is fixed;
(4) bottom double flute steel is installed,
After the completion of hanger erection, safe steel cat ladder is installed at Bailey truss as easy operation platform, then carried out
Bottom double flute steel, the bottom of Bailey truss is transported to by tower crane, using hawser so that suspension rod is passed through by the installation of bottom double flute steel
Hole between the double flute steel of bottom on steel cushion block so that bottom double flute steel is placed in the installation marker location of suspension rod, then passes through nut
Suspension rod is fixed with bottom double flute steel;
(5) distribution beam is laid,
After all bottom double flute steel are installed in place, the upside laying distribution beam of double flute steel in bottom;
(6) seating side guard rail,
On distribution beam top, scaffold is set up, and sets up and goes along with sb. to guard him, all go along with sb. to guard him is closed using Dense mesh screen, and is going along with sb. to guard him
Upper setting anti-drop net;
(7) laydown, template,
Cast-in-situ Beam position, laydown installation form are made in distribution beam.
In step (1), Bailey truss uses 321 beret truss, and beret truss sectional dimension is 1.5 meters high to be 3 meters long.
In step (2), the steel plate washer is laid along channel-section steel bearing of trend and arranges that spacing is 1m~1.5m.
In step (5), distribution beam is made up of the laying of I-steel, and the I-steel is welded and fixed with bottom double flute steel.
In step (6), set up 1.2 meters high facing and steel pipe cat ladder, and laying step plate, pin are set up in skirt shield, scaffold
Hand cradle completely spreads bamboo fragrant plant piece, and vertically setting one of anti-drop net every 10 meters as construction operation platform.
The present invention solves that because with a varied topography landing support body can not be used by using Bailey truss hoisting die construction technology
The situation of system.The Bailey truss that hoisting die construction is formed by connecting by pin using beret truss is upper support structure, and substructure is adopted
Use double flute steel.Up-down structure is attached using high-strength bolt as suspension rod by bolt.Finally steel plate is consolidated as baffle plate is hung
It is scheduled on and stable Bailey truss is constituted on channel-section steel hangs mould support system.It is mainly characterized by reducing that lower support system, progress are fast, throw
Money is relatively small, ensure construction quality, and the construction difficult problem of landing support can not be arranged well because with a varied topography by solving.Due to group
Accessory into Bailey truss is processed in factory floor, dimensional discrepancy very little, and itself has very big rigidity, is transported to construction
Scene, which is assembled, can just turn into Bailey truss, and length is determined according to cast-in-place beam length.Therefore, this hoisting die construction method safety
Reliably, easy construction.
In summary, the present invention, which is one, can effectively solve that because with a varied topography, height is too high landing support can not be laid
A kind of Bailey truss hoisting die construction method, the present invention adapts to that all are with a varied topography, in large-span structure engineering.
Brief description of the drawings
Fig. 1 is the positive facade overall schematic of Bailey truss using the formation of this construction method.
Fig. 2 is the Bailey truss side elevation overall schematic using the formation of this construction method.
Fig. 3 is Bailey truss of the present invention, suspension rod, double flute steel connection diagram.
Fig. 4 is screw rod of the present invention and double flute steel connection diagram.
Fig. 5 is double flute steel schematic diagram of the present invention;
Each label is represented in figure:1st, high-strength bolt;2nd, nut;3rd, steel cushion block;4th, double flute steel;5th, Bailey truss;6th, Bei Lei
Support bearing;7th, crosshead;8th, distribution beam;9th, template;10th, cast-in-situ concrete beam;11st, steel pipe frame column support system.
Embodiment
The present invention will be further described with reference to the accompanying drawings and examples.Following circumferences refer to the week along tunnel
To, axially refer to along tunnel axial direction.
Fig. 1 to Fig. 5 shows the implementation figure of the dell precipice section large-section beam Bailey truss hoisting die construction method of the present invention,
It comprises the following steps:
(1) splicing lifting beret truss,
Hoisting die construction uses 321 beret truss (reinforced), and standard beret truss sectional dimension is 1.5 meters high to be 3 meters long.Foundation
Structural span chooses a number of beret truss and carries out assembly by connecting pin in structure design drawing.Referring to Fig. 1, it will finally spell
The Bailey truss 5 installed is hung to the top of reinforced beam 6 for having poured shaping by tower crane, and reinforced beam 6 is supported on
On steel pipe frame column support system 11, Bailey truss sets up length more than or equal to deck-siding, and expanding screw is installed in drilling on beam in advance
Bolt, Bailey truss is fixed on beam by U-shaped anchor ear and expansion bolt.
(2) make with installing double flute steel,
While Bailey truss is set up the making that place carries out double flute steel is processed in material.Referring to Fig. 5, double flute steel 4 is by two
Root same size channel-section steel is constituted, and hole is reserved between two channel-section steels, is reliably welded using steel cushion block 3 between channel-section steel and channel-section steel
Connect, steel cushion block arrangement spacing is 1m~1.5m.The hole for being available for suspension rod to pass through is reserved using rig in advance on steel cushion block.In shellfish thunder
Support, which is set up, to be finished and after double flute steel performs, and double flute steel is hoisted into Bailey truss top, double flute steel 4 and Bailey truss 5
It is welded and fixed between top flange.
(3) suspension rod is installed,
According to structural stress analysis, the high-strength bolt 1 of appropriate diameter is chosen as suspension rod, field technician measures
Calculate, determine the length of suspension rod.In advance on suspension rod with it is red paint indicate above and below channel-section steel particular location, lifted afterwards.
During installation, referring to Fig. 3, the hole that suspension rod 1 is reserved through top double flute steel 4 in steel cushion block 5 uses spiral shell on steel cushion block top
Mother 2 is fixed.
(4) bottom channel-section steel is installed,
Referring to Fig. 1, after the installation of suspension rod 1, safe steel cat ladder is installed at the Bailey truss of top as easily applying
Work platform, carries out the installation of bottom double flute steel, and double flute steel 4 is transported into the bottom of Bailey truss 5, staff's profit using tower crane first
Double flute steel is passed through into screw rod with hawser, referring to Fig. 4, technical staff is fixed on by nut 2 by double flute steel both sides and indicated in advance
Good position.
(5) distribution beam is laid,
Referring to Fig. 2, after all bottom double flute steel are installed in place, I-shaped is allocated on request on the top of double flute steel 4
The laying of steel 8, is fixed between I-steel 8 and bottom double flute steel 4 in the form of welding.
(6) seating side guard rail,
Referring to Fig. 2, on the top of distribution beam 8, pin hand is set up in structural beams both sides, and 7, steel pipe cat ladder, and paving are set up in scaffold
If step plate, convenient construction personnel walk up and down, and scaffold completely spreads bamboo fragrant plant piece, and take using steel pipe as construction operation platform
If 1.2 meters high face skirt shield, all go along with sb. to guard him is closed using Dense mesh screen, and is vertically setting one of anti-drop net every 10 meters.
(7) laydown, laying template,
Referring to Fig. 2, unwrapping wire makes the position of Cast-in-situ Beam 10 in distribution beam 8, and laydown installation form 9 is finally carried out
Beams of concrete 10 is poured.
Claims (5)
1. a kind of dell precipice section large-section beam Bailey truss hoisting die construction method, including splicing lifting beret truss, making and peace
Portion's double flute steel is loaded onto, suspension rod is installed, bottom channel-section steel, laying distribution beam, seating side guard rail, laydown, template are installed,
It is characterized in that:Specific construction step is as follows:
(1) splicing lifting beret truss,
A number of beret truss, which is chosen, according to structural span in structure design drawing passes through the assembled formation shellfish thunder of connecting pin progress
Support, Bailey truss is hung to the reinforced beam top for having poured shaping by tower crane, and drill peace on reinforced beam
Expansion bolt is filled, Bailey truss is fixed on reinforced beam;
(2) make with installing double flute steel,
The making that place carries out top double flute steel and bottom double flute steel is processed in material while Bailey truss is set up, top is double
Channel-section steel and bottom double flute steel are constituted by two same size channel-section steels, hole are reserved between two channel-section steels, between channel-section steel and channel-section steel
Carry out being welded to connect fixation using steel plate washer, the steel cushion block of top double flute steel and bottom double flute steel is available for hanging provided with corresponding
The hole that bar is passed through, after Bailey truss sets up and finished, Bailey truss top is hoisted to by top double flute steel, top double flute steel with
Bailey truss is welded and fixed between top flange;
(3) suspension rod is installed,
According to structural stress analysis, the high-strength bolt of appropriate diameter is chosen as suspension rod, the length of suspension rod is determined according to design,
The installation site of top double flute steel and bottom double flute steel is indicated on suspension rod, during installation, suspension rod is from steel pad between the double flute steel of top
Hole on block is passed through so that top double flute steel is placed in the installation marker location of suspension rod, then by nut by suspension rod and top
Double flute steel is fixed;
(4) bottom double flute steel is installed,
After the completion of hanger erection, safe steel cat ladder is installed at Bailey truss as easy operation platform, bottom is then carried out
Bottom double flute steel, the bottom of Bailey truss is transported to by tower crane by the installation of double flute steel, using hawser so that suspension rod passes through bottom
Hole between double flute steel on steel cushion block so that bottom double flute steel is placed in the installation marker location of suspension rod, then will be hung by nut
Bar is fixed with bottom double flute steel;
(5) distribution beam is laid,
After all bottom double flute steel are installed in place, the upside laying distribution beam of double flute steel in bottom;
(6) seating side guard rail,
On distribution beam top, scaffold is set up, and sets up and goes along with sb. to guard him, all go along with sb. to guard him is closed using Dense mesh screen, and is set on going along with sb. to guard him
Put anti-drop net;
(7) laydown, template,
Cast-in-situ Beam position, laydown installation form are made in distribution beam.
2. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step
Suddenly in (1), Bailey truss uses 321 beret truss, and beret truss sectional dimension is 1.5 meters high to be 3 meters long.
3. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step
Suddenly in (2), the steel plate washer is laid along channel-section steel bearing of trend and arranges that spacing is 1m~1.5m.
4. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step
Suddenly in (5), distribution beam is made up of the laying of I-steel, and the I-steel is welded and fixed with bottom double flute steel.
5. dell precipice section large-section beam Bailey truss hoisting die construction method according to claim 1, it is characterised in that:Step
Suddenly in (6), set up it is 1.2 meters high face steel pipe cat ladder is set up in skirt shield, scaffold, and laying step plate, scaffold is as applying
Work operating platform, completely spreads bamboo fragrant plant piece, and vertically setting one of anti-drop net every 10 meters.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710385016.2A CN107130521B (en) | 2017-05-26 | 2017-05-26 | A kind of dell precipice section large-section beam Bailey truss hoisting die construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710385016.2A CN107130521B (en) | 2017-05-26 | 2017-05-26 | A kind of dell precipice section large-section beam Bailey truss hoisting die construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107130521A true CN107130521A (en) | 2017-09-05 |
CN107130521B CN107130521B (en) | 2018-10-19 |
Family
ID=59734028
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710385016.2A Active CN107130521B (en) | 2017-05-26 | 2017-05-26 | A kind of dell precipice section large-section beam Bailey truss hoisting die construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107130521B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108005114A (en) * | 2017-12-11 | 2018-05-08 | 贵州中昇东浩科技有限公司 | A kind of piping lane pours mould |
CN109457814A (en) * | 2018-11-15 | 2019-03-12 | 李延敏 | Towering and major diameter building top cover construction method based on Bailey bracket structure |
CN112093704A (en) * | 2020-09-09 | 2020-12-18 | 厦门安科科技有限公司 | Hanging device for jacking formwork system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20080099543A (en) * | 2007-05-09 | 2008-11-13 | 동명공영건설(주) | Formwork assembly for a bridge |
CN202688888U (en) * | 2012-07-17 | 2013-01-23 | 中交第二公路工程局有限公司 | Deck type reversely hung template hanging frame |
CN103835238A (en) * | 2014-02-21 | 2014-06-04 | 中铁大桥局股份有限公司 | High-pier cable-stayed bridge zero-number block non-bracket construction method and structure in construction process |
CN104141383A (en) * | 2014-07-16 | 2014-11-12 | 北京万兴建筑集团有限公司 | Bailey beam suspension formwork supporting system and construction method thereof |
CN105133497A (en) * | 2015-07-21 | 2015-12-09 | 杭州江润科技有限公司 | Construction method for diagonal-span low-clearance road-on-duty multi-azimuth adjustable cast-in-place box beam support system |
-
2017
- 2017-05-26 CN CN201710385016.2A patent/CN107130521B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20080099543A (en) * | 2007-05-09 | 2008-11-13 | 동명공영건설(주) | Formwork assembly for a bridge |
CN202688888U (en) * | 2012-07-17 | 2013-01-23 | 中交第二公路工程局有限公司 | Deck type reversely hung template hanging frame |
CN103835238A (en) * | 2014-02-21 | 2014-06-04 | 中铁大桥局股份有限公司 | High-pier cable-stayed bridge zero-number block non-bracket construction method and structure in construction process |
CN104141383A (en) * | 2014-07-16 | 2014-11-12 | 北京万兴建筑集团有限公司 | Bailey beam suspension formwork supporting system and construction method thereof |
CN105133497A (en) * | 2015-07-21 | 2015-12-09 | 杭州江润科技有限公司 | Construction method for diagonal-span low-clearance road-on-duty multi-azimuth adjustable cast-in-place box beam support system |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108005114A (en) * | 2017-12-11 | 2018-05-08 | 贵州中昇东浩科技有限公司 | A kind of piping lane pours mould |
CN109457814A (en) * | 2018-11-15 | 2019-03-12 | 李延敏 | Towering and major diameter building top cover construction method based on Bailey bracket structure |
CN112093704A (en) * | 2020-09-09 | 2020-12-18 | 厦门安科科技有限公司 | Hanging device for jacking formwork system |
Also Published As
Publication number | Publication date |
---|---|
CN107130521B (en) | 2018-10-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105926448B (en) | A kind of construction method of the Cable stayed Bridge Main Tower in the double rope faces of the only tower of curve | |
CN106894639B (en) | The hanging reverse construction method of installation of steel construction under a kind of | |
CN101781879B (en) | Construction method of single-pylon cable-stayed bridge without dorsal cables | |
CN106677070A (en) | Construction support and method for overhead large-span heavy-duty cross beam | |
CN106702910A (en) | Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes | |
CN102535845A (en) | Construction method of bearing frame of corridor structure | |
CN208586936U (en) | A kind of control protects brick mixed building joist and demolishes walls constructing device | |
CN106337555A (en) | Method for constructing triangular steel support for cantilever structure of outer wall of building | |
CN109025295A (en) | A kind of high-altitude long-span steel reinforced concrete corridor construction method | |
CN107130521B (en) | A kind of dell precipice section large-section beam Bailey truss hoisting die construction method | |
CN106436573A (en) | Construction method of corbel and steel truss bracket of wide-span upper crossbeam of extra-high cable bent tower | |
CN206352391U (en) | Socket joint type key slot type Quick Release support system | |
CN106948276A (en) | A kind of method of cast-in-place box beam bracket integral demounting | |
CN105804400A (en) | Hoisting construction method of curved truss | |
CN107227814A (en) | A kind of large cantilever concrete structure section construction method | |
CN100460613C (en) | Suspension holder construction method | |
CN108979131A (en) | A kind of high-building construction steel form and operation frame integral hoisting stage apparatus | |
CN206692235U (en) | A kind of steel structure dome lifts by crane erecting device | |
CN206267309U (en) | A kind of assembled steel concrete frame core wall structure system | |
CN114775881A (en) | Dome structure hoisting construction method and mounting and connecting structure | |
CN211949510U (en) | Annular cantilever platform construction supporting system | |
CN110616706B (en) | Construction method for layering binding in large-diameter pile foundation reinforcing steel bar hole | |
CN203034799U (en) | Tower hoist standard knot bearing overhead support formwork steel platform structure | |
CN201714056U (en) | Truss-type operating platform | |
CN105625732B (en) | Superelevation overhanging steel structure truss support free construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |