CN107784444A - A kind of production schedule performs tracking - Google Patents

A kind of production schedule performs tracking Download PDF

Info

Publication number
CN107784444A
CN107784444A CN201711040628.4A CN201711040628A CN107784444A CN 107784444 A CN107784444 A CN 107784444A CN 201711040628 A CN201711040628 A CN 201711040628A CN 107784444 A CN107784444 A CN 107784444A
Authority
CN
China
Prior art keywords
production
time
completion
difference
bar code
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711040628.4A
Other languages
Chinese (zh)
Inventor
刘平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN MORESOFT Co Ltd
Original Assignee
FUJIAN MORESOFT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN MORESOFT Co Ltd filed Critical FUJIAN MORESOFT Co Ltd
Priority to CN201711040628.4A priority Critical patent/CN107784444A/en
Publication of CN107784444A publication Critical patent/CN107784444A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of production schedule and performs tracking, step S1, pre-establishes the production schedule in system, sets the scheduled time difference of the scheduled time of going into operation, the scheduled time of completion, operation and completion, and sets corresponding delay early warning threshold values respectively;Step S2, in process of production, system terminates bar code to producers by the operation bar code and production for scanning current work order, respectively obtains the actual production time of work order, actual completion date, and poor by the way that the real time gone into operation and completed is calculated;Step S3, the system-computed actual production time and the difference for the scheduled time of going into operation, actual completion date and the difference of the scheduled time of completion, and the real time poor difference with preset time difference, and compared with corresponding delay early warning threshold values, early warning is made if necessary, and warning information is informed into related personnel, work order production is tracked so as to realize.

Description

A kind of production schedule performs tracking
Technical field
The present invention relates to the management method of production line, more particularly to a kind of production schedule to perform tracking.
Background technology
Nowadays it is exactly artificial tracing that the production schedule that mainly uses, which performs tracking, in production, such manager Formula, not only labor intensive, and efficiency is low;This traditional and original production schedule performs tracking far can not meet Instantly information system management and the demand of fine-grained management.
Disclosed in 2014-03-05, Publication No. 103616853A Chinese invention discloses a kind of turnout production plan and held Row system, by bar code printing device, terminal computer, sub- computer, track switch processing subsystem, bar code data collection device and local Network is formed, and bar code printing device is that each rail member in track switch process of manufacture puts up a bar code, and in bar code The serial number of each rail member is recorded, production task is directly issued to the terminal electricity of every equipment by sub- computer and LAN On brain, terminal computer exports Machining Instruction to track switch processing subsystem, track switch processing subsystem and is exported and processed according to terminal computer After instructing process finishing, bar code data collection device realizes production report work, while quality inspection by scanning the serial number on rail member Personnel complete the inspection work of the rail member by bar code data collection device scanning barcode after the assay was approved.Advantage:Track switch is given birth to An extension of the plan manufacturing execution system as ERP system is produced, is responsible for holding plan according to workshop actual conditions progress science OK, fine-grained management.The invention provides more general production management, but not to specific production meter on actual production line Implementation status is drawn to be tracked.
Disclosed in 2014-07-30, Publication No. 103955790A Chinese invention disclose it is a kind of based on PDA device with The operation flow execution system of enterprise resource planning instant messaging.Carried out according to the steps:Step 1, provided in enterprise According to arrival situation in the planning system of source, material storage list is created, and prints material storage list of the generation with bar code, it is former Material storage single cross warehouse keeper;Step 2, warehouse keeper obtain enterprise using the bar code on PDA device scanning material storage list Resource planning end material storage information, after the completion of material storage, warehouse keeper sends print label order in a pda, is raw material weight It is new to paste the label with two-dimensional bar code;Step 3, Sales and Planning Staff create customer sales in enterprise resource planning and ordered Single, scheduler creates production order in enterprise resource planning according to sales order and storage raw material information, and raw Into production and construction list, production and construction list is printed, production and construction single cross production operational staff, operational staff is according to production and construction for production It is single to complete raw material neck material;Production operational staff clicks on raw material and fed intake in a pda, bar code in production and construction list is scanned, from enterprise Production is obtained in industry resource planning system to feed intake information, scans the two-dimensional bar code of band on raw material label, and from Enterprise Resources Plan The information comparison that feeds intake is obtained in system, operational staff is after machining for generation, clicks on finished product in PDA and receives, scanning production is applied Bar code in work order obtains information of receiving from enterprise resource planning;Step 4, the material being particularly shown in a pda The actual information that finished product is received is inputted in batch information, submits enterprise resource planning, band is printed according to the voucher number received There is the finished product label of two-dimensional bar code, and paste and complete finished product storage, Sales and Planning Staff is in enterprise resource planning according to pin Order creation delivery order is sold, and prints delivery outbound list of the generation with bar code;Deliver goods outbound single cross finished product warehouse keeper and Dispatch from the factory verifier;Step 5, warehouse keeper are scanned bar code in delivery outbound list with PDA, obtained from enterprise resource planning Detailed outbound information, warehouse keeper scans in warehouse for finished product two-dimensional bar code on finished product label with PDA, with being obtained from enterprise resource planning The information taken is matched, and enterprise resource planning is submitted after all matching, and is completed the delivery posting of delivery order, is dispatched from the factory Verifier scans the bar code on delivery outbound list with PDA, and delivery order outbound information is obtained from enterprise resource planning, Verifier dispatch from the factory in the two-dimensional bar code with Product labelling on PDA scanning cars, is carried out with obtaining information from enterprise resource planning Matching, product is not matched if all had after the completion of scanning, warning message is prompted, forbids dispatching from the factory, as all matched, is then permitted Permitted to dispatch from the factory.Equally the invention provides more general production management, but not to the specific production schedule on actual production line Implementation status is tracked.
The content of the invention
The technical problem to be solved in the present invention, it is that providing a kind of production schedule performs tracking, draws by retouching code Planned production time and actual production time, scheduled completion time and actual completion date, then calculate actual operation automatically With the time difference of planned production, and early warning is made, work order production is tracked so as to realize.
What the present invention was realized in:A kind of production schedule performs tracking, including:
Step S1, pre-establish the production schedule in system, set the scheduled time of going into operation, completion the scheduled time, go into operation and The scheduled time difference of completion, and the scheduled time of the scheduled time of going into operation, the scheduled time of completion, operation and completion is set respectively The delay early warning threshold values of difference;
Step S2, in process of production, the operation bar code and production for scanning current work order terminate bar code, system to producers Gather respectively obtain work order after the sweep time obtain actual production time, actual completion date, and thrown by being calculated The real time of production and completion is poor;
Step S3, the system-computed actual production time and the difference for the scheduled time of going into operation, actual completion date and completion The scheduled time difference, and the difference of the real time poor difference with the preset time, if some difference be on the occasion of and be more than Corresponding delay early warning threshold values, then make early warning, and warning information is informed into related personnel, otherwise illustrates to hold by the production schedule OK.
Further, the operation bar code is the bar code on first product of first process of the current work order of production;The life Production terminates bar code to produce the bar code on the last process of current work order last product.
The invention has the advantages that:The present invention draws planned production time and actual production time, plan by retouching code Completion date and actual completion date, then calculate the time difference of actual operation and planned production automatically, and make early warning, from And realize and the manufacturing schedule of work order on production line is tracked.
Brief description of the drawings
The present invention is further illustrated in conjunction with the embodiments with reference to the accompanying drawings.
Fig. 1 is the inventive method execution flow chart.
Embodiment
Referring to shown in Fig. 1, the production schedule of the invention performs tracking, including:
Step S1, pre-establish the production schedule in system, set the scheduled time of going into operation, completion the scheduled time, go into operation and The scheduled time difference of completion, and the scheduled time of the scheduled time of going into operation, the scheduled time of completion, operation and completion is set respectively The delay early warning threshold values of difference;
Step S2, in process of production, the operation bar code and production for scanning current work order terminate bar code, system to producers Gather respectively obtain work order after the sweep time obtain actual production time, actual completion date, and thrown by being calculated The real time of production and completion is poor;Wherein, the operation bar code is the bar on first product of first process of the current work order of production Code;The production terminates bar code to produce the bar code on the last process of current work order last product.
Step S3, the system-computed actual production time and the difference for the scheduled time of going into operation, actual completion date and completion The scheduled time difference, and the difference of the real time poor difference with the preset time, if some difference be on the occasion of and be more than Corresponding delay early warning threshold values, then make early warning, and warning information is informed into related personnel, such as organizes squad leader, workshop supervisor, no Then explanation is performed by the production schedule, without alarm.
The present invention is described in detail as one example below:
Step S1, the production schedule is pre-established in system, certain work order production schedule is set as follows:
The operation scheduled time is 9:00, delay early warning threshold values is 20 minutes;
The scheduled time of completion is 10:00, delay early warning threshold values is 10 minutes;
Go into operation and the scheduled time difference of completion is 1 hour, delay early warning threshold values is 30 minutes;
Step S2, in process of production, the operation bar code and production for scanning current work order terminate bar code, system to producers Obtained after gathering the sweep time:
Actual production time is 9:10;
Actual completion date is 10:50;
And by be calculated go into operation and the real time of completion poor it is 1 small 40 points;
Step S3, system-computed obtains:
Actual production time and the difference A=9 for the scheduled time of going into operation:10-9:00=10 minutes;
Actual completion date and the difference B=10 of the scheduled time of completion:50-10:00=50 minutes;
And the real time poor difference with the preset time difference C=1 it is small 40 points -1 hour=40 minutes,
System judges to obtain:
Due to A=10 minute≤20 minute, illustrate to perform by the production schedule, without alarm;
Due to B=50 minutes>10 minutes, illustrate to be more than corresponding delay early warning threshold values, then make early warning;And early warning is believed Breath informs related personnel in real time;
Due to C=40 minutes>30 minutes, illustrate to be more than corresponding delay early warning threshold values, then make early warning;And early warning is believed Breath informs related personnel in real time.The condition of production of specific work order on production line is grasped in time so as to realize, real-time tracking.
Although the foregoing describing the embodiment of the present invention, those familiar with the art should manage Solution, the specific embodiment described by us are merely exemplary, rather than for the restriction to the scope of the present invention, are familiar with this The equivalent modification and change that the technical staff in field is made in the spirit according to the present invention, should all cover the present invention's In scope of the claimed protection.

Claims (2)

1. a kind of production schedule performs tracking, it is characterised in that:Including:
Step S1, the production schedule is pre-established in system, the scheduled time of going into operation, the scheduled time, operation and the completion of completion is set Scheduled time difference, and the scheduled time of going into operation, the scheduled time of completion, the scheduled time difference of operation and completion are set respectively Delay early warning threshold values;
Step S2, in process of production, the operation bar code and production for scanning current work order terminate bar code, system acquisition to producers The actual production time of work order, actual completion date are respectively obtained after the sweep time, and goes into operation and completes by being calculated Real time it is poor;
Step S3, the system-computed actual production time and the difference for the scheduled time of going into operation, actual completion date are pre- with completion The difference fixed time, and the real time poor difference with preset time difference, if some difference is on the occasion of and more than corresponding Delay early warning threshold values, then make early warning, and warning information is informed into related personnel, otherwise explanation is performed by the production schedule.
2. a kind of production schedule according to claim 1 performs tracking, it is characterised in that:The operation bar code is made a living Produce the bar code on first product of first process of current work order;The production terminates bar code to produce the last process of current work order most Bar code on the latter product.
CN201711040628.4A 2017-10-31 2017-10-31 A kind of production schedule performs tracking Pending CN107784444A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711040628.4A CN107784444A (en) 2017-10-31 2017-10-31 A kind of production schedule performs tracking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711040628.4A CN107784444A (en) 2017-10-31 2017-10-31 A kind of production schedule performs tracking

Publications (1)

Publication Number Publication Date
CN107784444A true CN107784444A (en) 2018-03-09

Family

ID=61432358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711040628.4A Pending CN107784444A (en) 2017-10-31 2017-10-31 A kind of production schedule performs tracking

Country Status (1)

Country Link
CN (1) CN107784444A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109388116A (en) * 2018-10-31 2019-02-26 金蝶软件(中国)有限公司 A kind of production management method, management system for internet of things and relevant device
CN110038805A (en) * 2019-04-16 2019-07-23 浙江国自智能装备有限公司 Tracking and controlling method, device, equipment and the readable storage medium storing program for executing of production logistics
CN110361994A (en) * 2018-03-26 2019-10-22 深圳中集智能科技有限公司 Realize method and device, the readable storage medium storing program for executing of production process visual control
CN112758633A (en) * 2020-12-02 2021-05-07 深圳市宏讯实业有限公司 Feeding control method, feeding control device, feeding system and storage medium
CN113537941A (en) * 2021-07-22 2021-10-22 重庆电子工程职业学院 Real-time dynamic progress control method and device for engineering management
CN113935853A (en) * 2021-10-29 2022-01-14 广东三扬网络科技有限公司 Production progress tracking management method, module, system and storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07325860A (en) * 1994-05-30 1995-12-12 Mitsubishi Denki Toubu Computer Syst Kk Production control system
CN104778502A (en) * 2015-03-16 2015-07-15 上海市建筑装饰工程集团有限公司 Digitalized monitoring method suitable for building decoration members
CN105335828A (en) * 2015-11-20 2016-02-17 中山领创网络科技有限公司 Operation method of production management
CN105741034A (en) * 2016-01-27 2016-07-06 浪潮电子信息产业股份有限公司 Assembly test production man hour calculation method of server product

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07325860A (en) * 1994-05-30 1995-12-12 Mitsubishi Denki Toubu Computer Syst Kk Production control system
CN104778502A (en) * 2015-03-16 2015-07-15 上海市建筑装饰工程集团有限公司 Digitalized monitoring method suitable for building decoration members
CN105335828A (en) * 2015-11-20 2016-02-17 中山领创网络科技有限公司 Operation method of production management
CN105741034A (en) * 2016-01-27 2016-07-06 浪潮电子信息产业股份有限公司 Assembly test production man hour calculation method of server product

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110361994A (en) * 2018-03-26 2019-10-22 深圳中集智能科技有限公司 Realize method and device, the readable storage medium storing program for executing of production process visual control
CN109388116A (en) * 2018-10-31 2019-02-26 金蝶软件(中国)有限公司 A kind of production management method, management system for internet of things and relevant device
CN109388116B (en) * 2018-10-31 2021-08-20 金蝶软件(中国)有限公司 Production management method, Internet of things management system and related equipment
CN110038805A (en) * 2019-04-16 2019-07-23 浙江国自智能装备有限公司 Tracking and controlling method, device, equipment and the readable storage medium storing program for executing of production logistics
CN112758633A (en) * 2020-12-02 2021-05-07 深圳市宏讯实业有限公司 Feeding control method, feeding control device, feeding system and storage medium
CN113537941A (en) * 2021-07-22 2021-10-22 重庆电子工程职业学院 Real-time dynamic progress control method and device for engineering management
CN113935853A (en) * 2021-10-29 2022-01-14 广东三扬网络科技有限公司 Production progress tracking management method, module, system and storage medium

Similar Documents

Publication Publication Date Title
CN107784444A (en) A kind of production schedule performs tracking
CN107844108B (en) Board watching method for automatic material matching and feeding based on MES
CN109634229A (en) A kind of intelligent plant manufacturing management system based on big data
CN108320069A (en) A kind of manufacturing execution system
CN103116821A (en) Whole course tracking method and whole course tracking system of discrete manufacturing workshop production process quality
CN107527154A (en) A kind of management planning and scheduling and executing system for being used for the scene of manufacturing
CN108681878A (en) The acquisition of intelligent plant production line data and billboard management system and method
CN103208054A (en) Fine monitoring method and system for discrete workshop production process work-in-process inventory
CN103106617A (en) Method and system for monitoring overall process of finished vehicle productive task executive condition
CN110516936A (en) A kind of intelligence production line mixing system
CN108335027A (en) A kind of wisdom interconnection manufacture execution managing and control system
CN107833028A (en) A kind of project logistics traceability system and method for tracing
CN103955790A (en) Material management system based on PDA device and enterprise resource planning system
CN109034618A (en) A kind of clothes processing intelligent flexible process streaming system
CN110232504A (en) A kind of quality manufacturing execution system platform and terminal
CN109711695A (en) A kind of MES dynamic job shop scheduling manufacturing execution system
CN109872038A (en) A kind of manufacture executes Visualized management system and method
CN112053252A (en) Wire harness production management system
CN106934528A (en) A kind of discrete type manufacture process management system
CN103699984A (en) In-order synchronous distribution system of commercial vehicle module production line
CN109597382A (en) Coal machine and manufactures intelligence blanking production system
CN109523205A (en) A kind of warehouse management method
CN205762407U (en) A kind of electric automatic Picking System of business based on barcode scanner
CN111126877B (en) Chemical fiber industry planning and scheduling method and system
CN110119925A (en) A kind of shower room glass production flowing water shipment system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180309