CN107743746A CN201711160599.5A CN201711160599A CN107743746A CN 107743746 A CN107743746 A CN 107743746A CN 201711160599 A CN201711160599 A CN 201711160599A CN 107743746 A CN107743746 A CN 107743746A
Authority
CN
China
Prior art keywords
hydraulic reclamation
open ground
construction method
fast construction
alkali
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711160599.5A
Other languages
Chinese (zh)
Inventor
赵秀芳
张涛
王振宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN TEDA GREENING GROUP Co Ltd
Original Assignee
TIANJIN TEDA GREENING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN TEDA GREENING GROUP Co Ltd filed Critical TIANJIN TEDA GREENING GROUP Co Ltd
Priority to CN201711160599.5A priority Critical patent/CN107743746A/en
Publication of CN107743746A publication Critical patent/CN107743746A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01BSOIL WORKING IN AGRICULTURE OR FORESTRY; PARTS, DETAILS, OR ACCESSORIES OF AGRICULTURAL MACHINES OR IMPLEMENTS, IN GENERAL
    • A01B79/00Methods for working soil
    • A01B79/02Methods for working soil combined with other agricultural processing, e.g. fertilising, planting

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental Sciences (AREA)
  • Cultivation Of Plants (AREA)

Abstract

The present invention relates to a kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method, this method comprises the following steps:(1), prepartion of land;(2) crushing straw of 0.5 2.0cm length, is laid, 5 8cm stalks is often laid, is rolled back and forth 24 times using 10 15t weight real machines, spray water, repeat laying crushing straw and roll spray water, untill stalk thickness reaches 8 15cm after the compacting, spray water, stop laying;(3), by 120 150g/m2Amount, the fluffy seed of alkali is mixed thoroughly with fine sand or sieving fine earth, broadcasted sowing;(4) 1.0 2.0cm fine sands, are laid.The application of achievement of the present invention rapid build vegetation system, this season vegetation coverage can may be up to more than 60% on the geavy salt alkali open ground of hydraulic reclamation then, and Second Year can reach more than 80%, greatly shorten the alkali fluffy invasion time.

Description

A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method
Technical field
The present invention relates to a kind of vegetation fast construction method, more particularly to a kind of strand hydraulic reclamation geavy salt alkali open ground vegetation is fast Fast construction method.
Background technology
Strand barged-in fill is the warp that is formed using the seabed mud that offshore dredging comes out by waterpower hydraulic reclamation.By seawater Environment influences, and barged-in fill salt content height (>=10g/kg), alkalescence is strong (pH >=8.0), and particle is thin (based on sticking grain), water-holding capacity Greatly, invalid hole water content is high, and quality clings, and plant is difficult to survive.Because vegetation is rare, earth's surface is exposed, airborne dust takes place frequently, to area The ecological environment and health in domain bring great destruction.Existing original soil improvement and soil moved in improve the original planting technique cost height, cycle Long, maintenance task weight, is not suitable for the reserved hydraulic reclamation open ground restoration of the ecosystem construction of provisional urban construction.Therefore, strand hydraulic reclamation weight Saline and alkaline open ground needs a kind of technical method of inexpensive, quick vegetation construction badly.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of strand hydraulic reclamation geavy salt alkali open ground vegetation rapid build side Method, especially salt content >=20g/kg geavy salt alkali hydraulic reclamation open ground vegetation fast construction methods, mainly by hydraulic reclamation open ground Earth's surface " ground levelling-laying stalk-roll-spray water-sow-cover sand " pattern, realize that strand hydraulic reclamation open ground vegetation is fast Fast construction method.
To solve above-mentioned technical problem, the technical scheme is that:
A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method, comprises the following steps:
(1), prepartion of land;
(2) crushing straw of 0.5-2.0cm length, is laid, often lays 5-8cm stalks, using 10-15t weight real machine back and forth Roll 2-4 times, spray water, repeat laying crushing straw-roll-spray water, stalk thickness reaches 8- after compacting Untill 15cm, spray water, stop laying;
(3), by 120-150g/m2Amount, the fluffy seed of alkali is mixed thoroughly with fine sand or sieving fine earth, broadcasted sowing;
(4) 1.0-2.0cm fine sands, are laid.
In the above method, stalk described in step (2) is maize straw.
In the above method, rolling compaction machine described in step (2) is steel wheel formula, and it is 5-10m/min to roll gait of march.
In the above method, spray water described in step (2) is sprayed for artificial or machinery, amount of application:Terminate last before laying Water-spraying amount is 20-45L/m2, each layer laying fountain height is 10-15L/m under remaining2
In the above method, fluffy alkali described in step (3) is Suaeda salsa.
In the above method, fine sand described in step (4) is 40-70 mesh river sands.
Present invention also offers the above method in salt content >=20g/kg geavy salt alkali hydraulic reclamation open ground vegetation rapid builds Application.
Beneficial effect possessed by the present invention:
Strand barged-in fill salt content is high, alkalescence is strong, and quality clings, and structural difference, typically at least to deposit more than 3 years, first Cutting edge of a knife or a sword plant Suaeda salsa just starts to invade, but biomass is extremely low, and the application of achievement of the present invention can be naked in the geavy salt alkali of hydraulic reclamation then Rapid build vegetation system on open country, this season vegetation coverage may be up to more than 60%, and Second Year can reach more than 80%, greatly Shorten the alkali fluffy invasion time, enhance the restoration of the ecosystem of hydraulic reclamation open ground, easy construction, strong operability, cost is cheap, The extensive application of agricultural stalk simultaneously, decrease maize straw and burn the heavily contaminated problem brought, realize agricultural stalk Recycling, environment, social and economic benefits are notable.
Embodiment
With reference to specific embodiment, the present invention will be further described, but does not limit protection scope of the present invention.
A kind of technical method of strand hydraulic reclamation geavy salt alkali open ground vegetation rapid build, mainly by hydraulic reclamation open ground Table " ground levelling-laying stalk-roll-spray water-sow-cover sand " pattern, realize that strand hydraulic reclamation open ground vegetation is quick The technical method of structure.
Embodiment:
Case Experiments On A is in mid-April, 2016, the industrial area Taida greening group original soil greening examination at Tianjin Southern port Test on study base and deploy, be experimental field the deposition strand reclaimed land of 3 years, area 900m2(30m × 30m), 0-40cm tables soil Layer salt content average is 33.7g/kg, pH value 8.27, open ground, no plant life.
A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method, specific implementation step are:
Experimental field prepartion of land;The crush maize stalk of 0.5-1.5cm length is laid, often lays 5-6cm thickness stalks, is used 12t weight steel drum compactors roll 3 times back and forth, and it is 6m/min to roll gait of march, artificial spray water, repeats laying and crushes Stalk-roll-spray water, untill stalk thickness reaches 10cm after the compacting, stop laying, wherein, terminate last before laying Water-spraying amount is 35L/m2, each layer laying fountain height is 12L/m under remaining2;By 135g/m2Amount, by the fluffy seed of alkali with Fine sand is mixed thoroughly, broadcasted sowing;Lay 1.0cm thickness 40-70 mesh river sands.
In mid-May, 2016, experimental field earth's surface be covered with the blocks of glossy and green fluffy seedling of alkali, mid-August, experimental field earth's surface plant Reach 62.8% by cover degree, do not done the check plot of experimental test processing, earth's surface is exposed, one layer of salt efflorescence of earth's surface;In in Augusts, 2017 Ten days, experimental field alkali it is fluffy plantation processing coverage reach 86.3%, check plot still earth's surface is exposed, without any plant growth.This skill Art is in face significant effect.
The above described is only a preferred embodiment of the present invention, not make any form to technical scheme On limitation, any simple modification that every technical spirit according to the present invention is made to above example, equivalent variations are with repairing Decorations, in the range of still falling within technical scheme.

Claims (7)

  1. A kind of 1. strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method, it is characterised in that:Comprise the following steps:
    (1), prepartion of land;
    (2) crushing straw of 0.5-2.0cm length, is laid, 5-8cm stalks is often laid, is rolled back and forth using 10-15t weight real machine 2-4 times, spray water, laying crushing straw-roll-spray water is repeated, stalk thickness reaches 8-15cm and is after compacting Only, spray water, laying is stopped;
    (3), by 120-150g/m2Amount, the fluffy seed of alkali is mixed thoroughly with fine sand or sieving fine earth, broadcasted sowing;
    (4) 1.0-2.0cm fine sands, are laid.
  2. A kind of 2. strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method according to claim 1, it is characterised in that:Step Suddenly stalk described in (2) is maize straw.
  3. A kind of 3. strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method according to claim 1, it is characterised in that:Step Suddenly rolling compaction machine described in (2) is steel wheel formula, and it is 5-10m/min to roll gait of march.
  4. A kind of 4. strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method according to claim 1, it is characterised in that:Step Suddenly spray water described in (2) is sprayed for artificial or machinery, amount of application:Last time water-spraying amount is 20-45L/ before terminating laying m2, each layer laying fountain height is 10-15L/m under remaining2
  5. A kind of 5. strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method according to claim 1, it is characterised in that:Step Suddenly it is Suaeda salsa that alkali described in (3) is fluffy.
  6. A kind of 6. strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method according to claim 1, it is characterised in that:Step Suddenly fine sand described in (4) is 40-70 mesh river sands.
  7. 7. any one of claim 1-6 methods described is in salt content >=20g/kg geavy salt alkali hydraulic reclamation open ground vegetation rapid builds Application.
CN201711160599.5A 2017-11-20 2017-11-20 A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method Pending CN107743746A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711160599.5A CN107743746A (en) 2017-11-20 2017-11-20 A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711160599.5A CN107743746A (en) 2017-11-20 2017-11-20 A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method

Publications (1)

Publication Number Publication Date
CN107743746A true CN107743746A (en) 2018-03-02

Family

ID=61251578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711160599.5A Pending CN107743746A (en) 2017-11-20 2017-11-20 A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method

Country Status (1)

Country Link
CN (1) CN107743746A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109769596A (en) * 2019-02-26 2019-05-21 天津泰达绿化集团有限公司 A kind of geavy salt alkali open ground ecology covering improvement salt dust collecting method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101828477A (en) * 2010-04-27 2010-09-15 中国科学院武汉植物园 Method of planting lawn in saline-alkali soil
CN101946573A (en) * 2010-08-17 2011-01-19 北京师范大学 Method for ameliorating saline and alkaline land
CN104285533A (en) * 2014-10-22 2015-01-21 赵俊瑞 Method for using agricultural straw to improve saline-alkali soil
CN105993276A (en) * 2016-06-30 2016-10-12 山东胜伟园林科技有限公司 Root salinity controlling method achieved by adopting sisal fiber-based biomass charcoal infiltration layer and application of method in saline and alkaline land suaeda salsa planting

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101828477A (en) * 2010-04-27 2010-09-15 中国科学院武汉植物园 Method of planting lawn in saline-alkali soil
CN101946573A (en) * 2010-08-17 2011-01-19 北京师范大学 Method for ameliorating saline and alkaline land
CN104285533A (en) * 2014-10-22 2015-01-21 赵俊瑞 Method for using agricultural straw to improve saline-alkali soil
CN105993276A (en) * 2016-06-30 2016-10-12 山东胜伟园林科技有限公司 Root salinity controlling method achieved by adopting sisal fiber-based biomass charcoal infiltration layer and application of method in saline and alkaline land suaeda salsa planting

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109769596A (en) * 2019-02-26 2019-05-21 天津泰达绿化集团有限公司 A kind of geavy salt alkali open ground ecology covering improvement salt dust collecting method

Similar Documents

Publication Publication Date Title
CN108605460B (en) Vegetation recovery method and ecological recovery method for open pit coal mine waste dump in grassland area
CN108124632B (en) greening method suitable for high and steep shale slope
CN102138428A (en) Vegetation restoration method adopting plant fiber blanket with assist of slurry spraying
KR101224632B1 (en) The environment-friendly vegetative soil composition and method of slope afforestantion using thereof
CN106718602B (en) Seedling planting method on coral sand for hydraulic filling of island reef in newly built tropical zone
CN104686003A (en) Reconstruction method of reclaimed soil profile in coal mining subsidence area
CN107237334B (en) A kind of road foundation execavated rockmass frame gird type slope protection code builds the construction method of plant biological bag greening
CN101507404B (en) Method for increasing calligonum drought stress resistance recovered by manpower on arid desert
CN106385843A (en) Method for increasing leaching efficiency of soil salinity in plough layer
CN104294830A (en) Side slope ecological protection and recovery method and arrangement structure
CN106605469A (en) Coastal reclamation land ecological restoration and greening method
CN1912256A (en) Method of vegetation slope pavement of level fluctuation zone
KR101283514B1 (en) Restoration method based on reinforecment and organic vegetation material
CN105210648A (en) A kind of plant Li implantation methods of intercepting dike water conservation drought resisting high yield
CN109354313B (en) Method for constructing near-natural complex water bank ecological zone by combining sludge/waste residues
CN107743746A (en) A kind of strand hydraulic reclamation geavy salt alkali open ground vegetation fast construction method
CN109429605A (en) A kind of salt-soda soil and desertification administering method
CN110574518A (en) Method for improving and planting shrubs in severe viscous saline-alkali soil and application of method
CN106134560A (en) A kind of improve beach saline-alkali ground the polymerization that plants economic crops
CN110786196A (en) Method for improving and planting arbor in severe viscous saline-alkali soil and application
CN116114546A (en) Water and soil conservation and re-greening method for alpine region
CN206895159U (en) A kind of saline soil area is locally isolated device
CN108677973A (en) A kind of climing combination bank protecting method of celluar concrete grass
CN204298833U (en) Protecting slope ecology and recovery arrangement
CN114175884A (en) Ecological restoration method in reclamation of mining area land in alpine region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180302