CN107700519A - One kind lifting tower crane installation method - Google Patents
One kind lifting tower crane installation method Download PDFInfo
- Publication number
- CN107700519A CN107700519A CN201710934960.9A CN201710934960A CN107700519A CN 107700519 A CN107700519 A CN 107700519A CN 201710934960 A CN201710934960 A CN 201710934960A CN 107700519 A CN107700519 A CN 107700519A
- Authority
- CN
- China
- Prior art keywords
- tower crane
- lifting
- installation method
- foundation ditch
- framework
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses one kind to lift tower crane installation method, including following construction procedure:First one piece of bearing plate is made in tower crane bottom of foundation ditch to be installed, one lifting framework being made up of beam column is set according to the height at foundation ditch bottom to natural ground on bearing plate top again, lifting framework is preferably higher by nature ground, tower crane positioning pedestal is set in lifting frame upper surface, the standard knot of tower crane is finally directly installed on lifting framework according to positioning pedestal.Present invention lifting tower crane installation method can directly be seated the supporting course of bottom of foundation ditch, caving in for foundation ditch is easily caused without being seated in foundation ditch periphery, the tower body of the installation method is more than natural ground simultaneously, basement will not be backfilled and impacted, without doing earth-retaining enclosure wall again around tower crane, and tower crane section is also not in have ponding to invade bubble, thoroughly solving is having bottom of foundation ditch to have ponding to need situation about being drawn water with suction pump to tower crane.
Description
Technical field
The present invention relates to the realm of building construction, particularly belongs to a kind of lifting tower crane installation method.
Background technology
Tower crane is a kind of indispensable crane gear in Building Construction.In work progress, the peace of tower crane
It is the area coverage in ground storehouse according to building to put, economy and carry out after lifting that weight of material etc. is many-sided and considering it is reasonable
Arrangement, tower crane in the presence of many risks, has plenty of because tower crane is near basis when installation, to the excavation on basis
Cause landslide to produce displacement, or uneven sedimentation etc. is produced due to ponding, it is such, it can all cause serious peace
Full accident, while the tower crane having is seated bottom of foundation ditch, periphery needs to make a circle retaining wall, influences the basement earthwork and integrally return
Fill out, continual when bottom of foundation ditch produces ponding tower crane can also be drawn water.A kind of therefore, lifting tower crane base of invention
Plinth installation method is to solve problems.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of lifting tower crane installation method, by using the installation
Method, can solve the problem that because tower crane is on foundation ditch side, excavation of foundation pit and cause foundation ditch the risk caved in occur, tower crane is located
The backfill of the basement earthwork is not interfered with bottom of foundation ditch, while tower crane can be directly installed on more than nature ground, will not be gone out
Existing pit water accumulation influences tower crane and drawn water with suction pump.
In order to solve the above technical problems, the technical solution adopted by the present invention is as follows:
One kind lifting tower crane installation method, includes following construction technology:Foundation ditch 1 is excavated first, hole bottom 2 is smooth
After-pouring concrete cushion, the position of repositioning pre-installation tower crane, release the position line of tower crane bearing plate 3, then formwork,
Plate is wire-tie, and the reinforcing bar for four frame columns 4 for lifting framework 11 is previously inserted in bearing plate 3, then casting concrete;Work as tower crane
After basis reaches form removal condition, the lifting framework 11 on top is started from, lifting framework 11 is rectangular configuration, and by four frameworks
4, four Vierendeel girders 6 of post are formed, and determine that the absolute altitude on nature ground, then plate prick the reinforcing bar of four frame columns 4, and formwork supporting plate, then
The reinforcing bar of four Vierendeel girders 6 is made, the upper surface of lifting framework 11 is embedded into after tower crane section posting 5 is positioned, then is poured mixed
It is solidifying native, after form removal condition to be achieved, form removal;Tower crane of the standard knot 7 of last tower crane directly with lifting framework 11 upper surface
Section posting 5 is connected with high-strength bolt, that is, completes tower crane installation.
Described bearing plate 3 is poured by armored concrete to be formed, and is directly poured in the supporting course of the bottom of foundation ditch 1.
Described lifting framework 11 is made up of reinforced concrete beam column, is poured on bearing plate 3.
The described lifting height of framework 11 is chosen according to the absolute altitude of bearing plate 3 to natural ground, and lifting framework 11 is higher than certainly
Right ground.
After the completion of the underground component 8 at hole bottom 2 is constructed, it can directly carry out the earthwork 9 and backfill, then carry out upper component 10
Construction.
The positioning pedestal of described lifting framework 11 upper surface setting tower crane tower body, positioning pedestal are relative with tower crane tower body
Should.
The invention enables tower crane can directly be seated in bottom of foundation ditch, then directly be lifted tower crane by lifting framework
To more than natural ground, tower crane is avoided near basis, and foundation pit collapse caused by foundation excavation, tower crane is from foundation ditch bottom directly quilt
The influence eliminated after the completion of basement construction to basement backfilling of earthwork is given rise to more than nature ground, will not also allow tower crane
Underground water or the erosion of other ponding are received, eliminates the work drawn water with suction pump to its basis.The tower crane of the present invention
Installation method, it is simple to operate, easily implement, tower crane can be directly cast in the supporting course of bottom of foundation ditch, avoided in base
The operating procedure driven piles is needed in the case of hole periphery geology is bad, while has prevented the risk that tower crane causes foundation pit collapse,
It can adapt to, in most Deep Foundation Pit situation, reduce the security risk in engineering construction, the method has larger
Development prospect.
Brief description of the drawings
Fig. 1 is the foundation ditch schematic diagram of the present invention.
Fig. 2 is the tower crane and lifting block schematic illustration of the present invention.
Fig. 3 is invention tower crane scheme of installation.
Fig. 4 is tower crane schematic diagram after backfilling of earthwork of the present invention.
Fig. 5 is present invention lifting circuit theory schematic diagram.
Embodiment
Referring to accompanying drawing, one kind lifting tower crane installation method, include following construction technology:Foundation ditch 1 is carried out first
Excavate, cheat the smooth after-pouring concrete cushion in bottom 2, the position of repositioning pre-installation tower crane, release determining for tower crane bearing plate 3
Bit line, then formwork, plate wire-tie, the reinforcing bar of four frame columns 4 for lifting framework 11 is previously inserted in bearing plate 3, then is poured
Build concrete;After tower crane reaches form removal condition, the lifting framework 11 on top is started from, lifting framework 11 is rectangle knot
Structure, and be made up of four frame columns, 4, four Vierendeel girders 6, determine that the absolute altitude on nature ground, then plate prick the steel of four frame columns 4
Muscle, and formwork supporting plate, the reinforcing bar of four Vierendeel girders 6 is then made, lifting framework 11 is embedded into after tower crane section posting 5 is positioned
Upper surface, then casting concrete, after form removal condition to be achieved, form removal;The standard knot 7 of last tower crane is directly with lifting framework
The tower crane section posting 5 of 11 upper surfaces is connected with high-strength bolt, that is, completes tower crane installation.
Bearing plate 3 is poured by armored concrete to be formed, and is directly poured in the supporting course of the bottom of foundation ditch 1;Lift framework 11 by
Reinforced concrete beam column forms, and pours on bearing plate 3;Lift absolute altitude of the height of framework 11 according to bearing plate 3 to natural ground
Choose, lifting framework 11 is higher than nature ground;After the completion of the underground component 8 at hole bottom 2 is constructed, it can directly carry out the earthwork 9 and return
Fill out, then carry out upper component 10 and construct;Lift the positioning pedestal that the upper surface of framework 11 sets tower crane tower body, positioning pedestal and tower
Tower crane body is corresponding.
Claims (6)
1. one kind lifting tower crane installation method, it is characterised in that include following construction technology:First to foundation ditch(1)Enter
Row excavates, and cheats bottom(2)Smooth after-pouring concrete cushion, the position of repositioning pre-installation tower crane, releases tower crane bearing plate
(3)Position line, then formwork, plate wire-tie, framework will be lifted(11)Four frame columns(4)Reinforcing bar be previously inserted pressure-bearing
Plate(3)It is interior, then casting concrete;After tower crane reaches form removal condition, the lifting framework on top is started from(11), lifting
Framework(11)For rectangular configuration, and by four frame columns(4), four pieces Vierendeel girders(6)Form, determine the absolute altitude on nature ground, then
Plate pricks four frame columns(4)Reinforcing bar, and formwork supporting plate, then make four Vierendeel girders(6)Reinforcing bar, by tower crane section posting
(5)Lifting framework is embedded into after positioning(11)Upper surface, then casting concrete, after form removal condition to be achieved, form removal;Most
The standard knot of tower crane afterwards(7)Directly with lifting framework(11)The tower crane section posting of upper surface(5)Connected with high-strength bolt, i.e., it is complete
Installed into tower crane.
2. lifting tower crane installation method according to claim 1, it is characterised in that described bearing plate(3)By steel
Reinforced concrete, which pours, to be formed, and is directly poured in foundation ditch(1)The supporting course of bottom.
3. lifting tower crane installation method according to claim 1, it is characterised in that described lifting framework(11)By
Reinforced concrete beam column forms, and pours in bearing plate(3)On.
4. lifting tower crane installation method according to claim 1, it is characterised in that described lifting framework(11)It is high
Degree is according to bearing plate(3)Absolute altitude to natural ground is chosen, and lifts framework(11)Higher than nature ground.
5. lifting tower crane installation method according to claim 1, it is characterised in that positioned at hole bottom(2)Subterranean
Part(8)After the completion of construction, the earthwork can be directly carried out(9)Backfill, then carries out upper component(10)Construction.
6. lifting tower crane installation method according to claim 1, it is characterised in that described lifting framework(11)On
The positioning pedestal of surface setting tower crane tower body, positioning pedestal are corresponding with tower crane tower body.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710934960.9A CN107700519A (en) | 2017-10-10 | 2017-10-10 | One kind lifting tower crane installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710934960.9A CN107700519A (en) | 2017-10-10 | 2017-10-10 | One kind lifting tower crane installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107700519A true CN107700519A (en) | 2018-02-16 |
Family
ID=61183931
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710934960.9A Pending CN107700519A (en) | 2017-10-10 | 2017-10-10 | One kind lifting tower crane installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107700519A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111608195A (en) * | 2020-06-01 | 2020-09-01 | 中国二十冶集团有限公司 | Construction method for foundation of frame-structured water pump house |
CN111733863A (en) * | 2020-06-24 | 2020-10-02 | 江苏省宁强建设有限公司 | Tower crane foundation for foundation pit and construction method thereof |
CN112227405A (en) * | 2020-09-29 | 2021-01-15 | 上海建工七建集团有限公司 | Tower crane foundation located on foundation pit slope and construction method thereof |
CN112227408A (en) * | 2020-10-14 | 2021-01-15 | 上海建工七建集团有限公司 | Tower crane foundation located on foundation pit slope and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704504A (en) * | 2012-06-26 | 2012-10-03 | 南通华新建工集团有限公司 | Method for constructing tower crane foundation |
CN102912810A (en) * | 2012-11-22 | 2013-02-06 | 北京城乡建设集团有限责任公司 | Tower crane base structure in range of base bottom plate and construction method thereof |
CN104032767A (en) * | 2014-06-20 | 2014-09-10 | 天津二十冶建设有限公司 | Tower crane foundation in deep foundation pit and construction method of tower crane foundation |
CN205975658U (en) * | 2016-08-18 | 2017-02-22 | 中国建筑第八工程局有限公司 | Steel platform tower crane foundation |
-
2017
- 2017-10-10 CN CN201710934960.9A patent/CN107700519A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704504A (en) * | 2012-06-26 | 2012-10-03 | 南通华新建工集团有限公司 | Method for constructing tower crane foundation |
CN102912810A (en) * | 2012-11-22 | 2013-02-06 | 北京城乡建设集团有限责任公司 | Tower crane base structure in range of base bottom plate and construction method thereof |
CN104032767A (en) * | 2014-06-20 | 2014-09-10 | 天津二十冶建设有限公司 | Tower crane foundation in deep foundation pit and construction method of tower crane foundation |
CN205975658U (en) * | 2016-08-18 | 2017-02-22 | 中国建筑第八工程局有限公司 | Steel platform tower crane foundation |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111608195A (en) * | 2020-06-01 | 2020-09-01 | 中国二十冶集团有限公司 | Construction method for foundation of frame-structured water pump house |
CN111733863A (en) * | 2020-06-24 | 2020-10-02 | 江苏省宁强建设有限公司 | Tower crane foundation for foundation pit and construction method thereof |
CN112227405A (en) * | 2020-09-29 | 2021-01-15 | 上海建工七建集团有限公司 | Tower crane foundation located on foundation pit slope and construction method thereof |
CN112227408A (en) * | 2020-10-14 | 2021-01-15 | 上海建工七建集团有限公司 | Tower crane foundation located on foundation pit slope and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
CN102094425B (en) | Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam | |
CN103031839B (en) | Construction method of hand-dug piles | |
CN107700519A (en) | One kind lifting tower crane installation method | |
CN207003499U (en) | A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit | |
CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
CN106638640A (en) | Modular coffer construction method for concrete without subsealing in the geologic condition of stratum | |
CN105239578B (en) | Water-rich sand layer deep foundation pit underwater construction method | |
CN110106919A (en) | A kind of lid digs the building enclosure and its construction method at station | |
CN108532586A (en) | A kind of construction method of garage parking diaphram wall | |
CN102864780A (en) | Supporting structure and supporting method of foundation pit | |
CN205742216U (en) | A kind of Unfavorable geology foundation ditch that is used for puts slope excavation combined bearing structure | |
CN113550322A (en) | Enclosure system next to deep and shallow foundation pit and construction method | |
CN207003421U (en) | A kind of steel plate pilework for being seated hard rock top surface | |
CN204590059U (en) | A kind of combined type tower-crane foundation structure | |
CN102220764B (en) | Construction method of deep foundation pit bracing system | |
CN109440779A (en) | Active X-shaped foundation pit supporting method with double rows of piles | |
CN206448285U (en) | Without bottom concrete combined type cofferdam under the conditions of formation geology | |
CN103215965A (en) | Laminate type high-rise platform pile tower crane foundation and construction method | |
CN108755702A (en) | A kind of higher soft soil foundation foundation ditch strengthening processing method of level of ground water | |
CN110700270B (en) | Construction method for non-drainage earthwork excavation of ultra-deep foundation pit | |
CN108035360A (en) | A kind of method for pattern foundation pit supporting structure | |
CN106013174A (en) | Oblique supporting method for foundation pit shoring and oblique supporting structure | |
CN216515701U (en) | Miniature stake raft board combination foundation structure | |
CN102605801A (en) | Suspension semi-reverse-construction method for underground circular water tank |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180216 |
|
RJ01 | Rejection of invention patent application after publication |