CN107270881A - A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point - Google Patents

A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point Download PDF

Info

Publication number
CN107270881A
CN107270881A CN201710564429.7A CN201710564429A CN107270881A CN 107270881 A CN107270881 A CN 107270881A CN 201710564429 A CN201710564429 A CN 201710564429A CN 107270881 A CN107270881 A CN 107270881A
Authority
CN
China
Prior art keywords
control point
surface layer
layer control
wind
tunnel body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710564429.7A
Other languages
Chinese (zh)
Other versions
CN107270881B (en
Inventor
李博平
张笈玮
刘波
王坤
吕明
白联锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
UNIT 63926 OF PLA
Original Assignee
UNIT 63926 OF PLA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by UNIT 63926 OF PLA filed Critical UNIT 63926 OF PLA
Priority to CN201710564429.7A priority Critical patent/CN107270881B/en
Publication of CN107270881A publication Critical patent/CN107270881A/en
Application granted granted Critical
Publication of CN107270881B publication Critical patent/CN107270881B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • G01C15/02Means for marking measuring points

Abstract

The invention discloses a kind of efficient setting out method in tunnel body for wind inner mold surface construction control point, comprise the following steps:Tunnel body for wind BIM is set up with BIM technology, obtain characteristic cross-section position coordinate data;Project hole body closed-loop path central axis projection benchmark control point;Fishing line suspension wire enciphered method lays surface layer control point;The detection of surface layer control point is checked.Present invention fusion BIM BIM technologies, ten hundreds of complex space coordinates is passed through into Rational Simplification in the limited scope of operation at the construction field (site), by suspension wire encryption projection setting-out on enclosed structure, easy construction, efficiency high, solve the problem such as big, setting-out time length of profile measurement workload in tunnel body for wind.

Description

A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point
Technical field
The present invention relates to tunnel body for wind inner mold surface construction field of measuring technique, certain more particularly to a kind of type concrete tunnel body for wind gradual change is empty Between inner mold surface construction control point setting out method.
Background technology
Certain type acoustic wind tunnel is domestic cast-in-place concrete structure+terrazzo inner mold face hole body complete first, hole wall inner surface flatness It is required that≤3mm/2m, axis coaxle degree≤4mm.After the completion of the phosphor bodies construction of hole, survey crew is controlled by surface layer control point The construction in wind-tunnel inner mold face, the quantity at inner mold face control point and distribution will with can meet surface layer dividing strip installation primary condition. Because the developed area in wind-tunnel inner mold face is larger(14930㎡), in order to ensure inner mold face precision, it is necessary to which nearly 10,000 surface layers are controlled Point, and the space hole body of a closing is formed after the completion of main structure construction, if survey crew is according to conventional coordinate staking out method Surface layer control point setting-out is carried out one by one, it is necessary to take the scope of operation for a long time, other specialties will be unable to construction, directly influence wind The duration of hole engineering construction.Restricted by the human resources balance factor of project, job site can not possibly be equipped with many instruments and survey Teams and groups are measured, to accelerate setting-out speed, while ensureing surveying setting-out precision, it is necessary to study a kind of efficient quick, reliable and stable survey Measure control point line-putting method.
The content of the invention
It is an object of the invention to provide a kind of efficient setting out method in tunnel body for wind inner mold surface construction control point, and then it is generalized to any Gradual change, complex space type surface construction survey unwrapping wire process, above-mentioned purpose are achieved by the following technical solution.
A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point, comprises the following steps:
1)Tunnel body for wind BIM is set up with BIM technology, obtain characteristic cross-section position coordinate data:
According to characteristic cross-section is divided on the basis of the slope variation and subsiding crack of tunnel body for wind each several part, with BIM three Dimension space coordinate system extracts each side boundary point of characteristic cross-section, middle point coordinate data, imports total powerstation and obtains characteristic cross-section point position seat Mark data;
2)Project hole body closed-loop path central axis projection benchmark control point;
3)Suspension wire enciphered method lays surface layer control point:
Suspension wire encryption is carried out by the way of first horizontal encryption, rear longitudinal direction encryption;Believe during horizontal surface layer control points layout according to BIM The coordinate data of model extraction is ceased, is come out the horizontal surface layer control point setting-out in characteristic cross-section with total powerstation, characteristic cross-section one As take each side boundary point, midpoint as characteristic point and paste horizontal surface layer control point, it is big that the spacing at horizontal surface layer control point regards type face It is small to determine(1.5m~4m);During longitudinal surface layer control points layout, on the basis of the horizontal surface layer control point of setting-out, no more than Encryption suspension wire is tensed between two horizontal surface layer control points in the range of 6m, suspension wire is concordant with horizontal surface layer control point absolute altitude; Span between two crosswise joint points, the suspension wire according to 1.5m~2m spacing distance in tunnel body for wind structural plane along tension is pasted 2~3 longitudinal surface layer control points, longitudinal surface layer control point center adjusts longitudinal surface layer control point absolute altitude just to suspension wire, after stickup Suspension wire with tension is concordant;Said process is repeated between each characteristic cross-section until whole surveying and locatings are completed.
4)The detection of surface layer control point is checked.
Further, sampling Detection is checked checks method detection vertical, horizontal surface layer control point absolute altitude using staggered cross, after Suspension wire, which is tightened, on the basis of longitudinal surface layer control point that survey is set checks the horizontal surface layer control point absolute altitude first surveyed and set, edge or other portions Position control point can directly be checked using steel tape.
Tunnel body for wind of the present invention is a series of symmetrical octets, asymmetric octet, shuttle table type circular hole body, Fang Dong The closed space grading structure that the combination of the type such as body, box-like body body is constituted, tunnel body for wind closed-loop path central axis is a virtual axis.
Suspension wire of the present invention needs smaller diameter, moderate strength, sag of chain small, and suspension wire sag of chain is not in 6m length ranges Surveying setting-out requirement can be met more than 1.0mm side.Preferably fishing line.
The beneficial effect of patent of the present invention is:
BIM BIM technologies are merged, at the construction field (site) by ten hundreds of complex space coordinates in the limited scope of operation By Rational Simplification, by suspension wire encryption projection setting-out on enclosed structure, easy construction, efficiency high solve tunnel body for wind The problems such as interior profile measurement workload is big, setting-out time length, it is ensured that layout point meets the harsh design and work in gradually-changed space type face Skill requirement, and promoted development and application of the BIM technology in engineering construction.Measuring method of the present invention can reduce prior art three / bis- measurement workload.
Brief description of the drawings
Fig. 1 is tunnel body for wind BIM sketch of the present invention.
Fig. 2 is the anistree hole body characteristicses sectional view of tunnel body for wind of the present invention.
Fig. 3 is certain anistree hole body section suspension wire enciphered method schematic diagram of the invention.
In figure:1. tunnel body for wind stable section, 2. the first diffusers of hole body, are hole body contraction section, test section, 3. between 1 and 2 Hole body thin wall concrete section(150mm is thick), beam, 5. virtual hole body closed-loop path central axis are returned in 4. holes in vitro;A1. Horizontal surface layer control point, A2. longitudinal directions surface layer control point, B. suspension wires;C. tunnel body for wind structural plane, D. terrazzo inner mold face(45mm It is thick).
Embodiment
A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point, comprises the following steps:
1)Tunnel body for wind BIM is set up with BIM technology, obtain characteristic cross-section position coordinate data:
According to characteristic cross-section is divided on the basis of the slope variation and subsiding crack of tunnel body for wind each several part, with BIM three Dimension space coordinate system extracts each side boundary point of characteristic cross-section, middle point coordinate data, imports total powerstation and obtains characteristic cross-section point position seat Mark data;
2)Project hole body closed-loop path central axis projection benchmark control point;
3)Suspension wire enciphered method lays surface layer control point:
Suspension wire encryption is carried out by the way of first horizontal encryption, rear longitudinal direction encryption;Believe during horizontal surface layer control points layout according to BIM The coordinate data of model extraction is ceased, is come out the horizontal surface layer control point setting-out in characteristic cross-section with total powerstation, characteristic cross-section one As take each side boundary point, midpoint as characteristic point and paste horizontal surface layer control point, it is big that the spacing at horizontal surface layer control point regards type face It is small to determine(1.5m~4m);During longitudinal surface layer control points layout, on the basis of the horizontal surface layer control point of setting-out, no more than Encryption suspension wire is tensed between two horizontal surface layer control points in the range of 6m, suspension wire is concordant with horizontal surface layer control point absolute altitude; Between the two crosswise joint points, with the dipstick metering of the convention amount such as steel tape away from according to 1.5m~2m spacing distance in tunnel body for wind Suspension wire of the structural plane along tension pastes 2~3 longitudinal surface layer control points, and longitudinal surface layer control point center is pasted just to suspension wire Adjust longitudinal direction surface layer control point absolute altitude afterwards concordant with the suspension wire tensed, reach the interpolation encryption between two horizontal surface layer control points Purpose,
Said process is repeated between each characteristic cross-section until whole surveying and locatings are completed.
4)The detection of surface layer control point is checked:
Sampling Detection is checked checks method detection vertical, horizontal surface layer control point absolute altitude using staggered cross, and the longitudinal surface set is surveyed after Suspension wire is tightened on the basis of layer control point and checks the horizontal surface layer control point absolute altitude first surveyed and set, and edge or other position control points can be adopted Directly checked with steel tape.
Described tunnel body for wind is a series of symmetrical octets, asymmetric octet, shuttle table type circular hole body, Fang Dongti, box-shaped The closed space grading structure that the combination of the type such as body body is constituted, tunnel body for wind closed-loop path central axis is a virtual axis.Suspension wire is selected It is selected as fishing line, preferably No. 1.5 fishing lines or No. 2 fishing lines.
Embodiment 1
Below in conjunction with example, accompanying drawing, the present invention is described in further detail.As shown in Fig. 1 ~ 3,
1)Tunnel body for wind BIM is set up with BIM technology, obtain characteristic cross-section position coordinate data
Using CAD diagram paper, for each section structural plane C-shape of hole body and size, pass through the professional softwares such as SketchUp, Revit BIM is set up, high-precision section thin-walled tunnel body for wind terrazzo inner mold face D accurate three-dimensional space coordinates are obtained;
Slope variation and subsiding crack according to tunnel body for wind each several part etc. divide measurement section, if tunnel body for wind is divided into stem portion, Straightway or oblique line section are typically divided with 4m, 6m, and the larger region of tunnel body for wind change in shape goes out to be characterized section to change place; Each side boundary point of characteristic cross-section, middle point coordinate data are extracted with the BIM three-dimensional coordinate system of foundation, is imported Total powerstation obtains characteristic cross-section position coordinate data;
2)Project hole body closed-loop path central axis projection benchmark control point
Utilize the three-level benchmark control point reserved when tunnel body for wind structure base slab is constructed(Spacing 20m~30m), thrown with total powerstation Plane projection control level Four datum mark, the datum line for setting up closed-loop path central axis 5 on tunnel body for wind structure base slab are penetrated, as The foundation at setting-out surface layer control point and reference;
3)Fishing line suspension wire enciphered method lays surface layer control point
Horizontal surface layer control point A1 is laid:The coordinate data extracted according to BIM information models, with total powerstation in closing tunnel body for wind The intersection point point for measuring characteristic cross-section and closed-loop path central axis 5 is thrown on inner bottom plating by 4m~6m spacing of division, in intersection point point Upper erection total powerstation, sights three-level axial reference control point farther out, then 90 ° of rotary apparatus, is cut feature using total powerstation The whole setting-outs of horizontal surface layer control point A1 in face come out, and characteristic cross-section typically takes each side midpoint or boundary point to be characterized a stickup Surface layer control point A1, characteristic cross-section transverse direction surface layer control point A1 spacing is determined regarding type face size(1.5m~4m).
Longitudinal surface layer control point A2 is laid:Treat the horizontal surface layer control point A1 of setting-out(Three axially adjustable devices, end is It is pointed)Cement in after tunnel body for wind structural plane C, between two horizontal surface layer control point A1 of the workmen in the range of no more than 6m Encryption suspension wire B, suspension wire B is tensed in structural plane basic unit on the outside of the horizontal surface layer control point A1, to hang using cement nail colligation, stickfast Line is concordant with horizontal surface layer control point A1 absolute altitudes;Between the two crosswise joint points A1, with the convention amount dipstick metering such as steel tape Away from the suspension wire B according to 1.5m~2m spacing distance in tunnel body for wind structural plane C along tension pastes 2~3 longitudinal surface layers and controlled Point A2, longitudinal surface layer control point A2 centers just to suspension wire B, adjust longitudinal surface layer control point A2 absolute altitudes and the suspension wire tensed after stickup B is concordant, reaches and is repeated in said process between the purpose that interpolation is encrypted between two horizontal surface layer control point A1, each characteristic cross-section Until whole surface layer control point A1, A2 surveying and locatings are completed.
By investigating experiment, three kinds of encryption suspension wires, respectively cotton thread, finer wire, fishing line are chosen.Tightened under 6m length outstanding Line, cotton thread is softer, and sag of chain is 1.0-1.2mm, but is relatively large in diameter, and measurement error is big;Finer wire sag of chain is 1.2-1.4mm, And it is inconvenient for use;2.0# fishing line diameters are small, and sag of chain is 0.8-1.0mm;It is final to determine that encryption suspension wire uses 1.5# or 2.0# fishes Line.
4)The detection of surface layer control point is checked
It should sample and be checked after the completion of A1, A2 coordinate projection of surface layer control point(Ratio desirable 3%~5%), detection, which is checked, preferably to exist Longitudinal surface layer control point A2 is carried out after fixing, in same slope section section, and sampling Detection is checked checks method using staggered cross Vertical, horizontal surface layer control point A1, A2 absolute altitude is detected, is surveyed after on the basis of the longitudinal surface layer control point A2 set and is tightened suspension wire and check elder generation The horizontal surface layer control point A1 absolute altitudes set are surveyed, edge or other position control points can be checked using steel tape, be that subsequent construction is carried For accurately controlling foundation.

Claims (7)

1. a kind of efficient setting out method in tunnel body for wind inner mold surface construction control point, it is characterised in that:Comprise the following steps:
1)Tunnel body for wind BIM is set up with BIM technology, obtain characteristic cross-section position coordinate data:
According to characteristic cross-section is divided on the basis of the slope variation and subsiding crack of tunnel body for wind each several part, with BIM three Dimension space coordinate system extracts each side boundary point of characteristic cross-section, middle point coordinate data, imports total powerstation and obtains characteristic cross-section point position seat Mark data;
2)Project hole body closed-loop path central axis projection benchmark control point;
3)Suspension wire enciphered method lays surface layer control point:
Suspension wire encryption is carried out by the way of first horizontal encryption, rear longitudinal direction encryption;Believe during horizontal surface layer control points layout according to BIM The coordinate data of model extraction is ceased, is come out the horizontal surface layer control point setting-out in characteristic cross-section with total powerstation, and paste transverse direction Surface layer control point, pasting the characteristic point at horizontal surface layer control point includes each side boundary point of characteristic cross-section, midpoint, horizontal surface layer control The spacing of point regards type face size as 1.5m~4m;During longitudinal surface layer control points layout, using the horizontal surface layer control point of setting-out as Encryption suspension wire is tensed between benchmark, two horizontal surface layer control points in the range of no more than 6m, suspension wire is controlled with horizontal surface layer Point absolute altitude is concordant;
The span between two crosswise joint points, according to 1.5m~2m spacing distance in tunnel body for wind structural plane along the outstanding of tension Line pastes 2~3 longitudinal surface layer control points, and longitudinal surface layer control point center adjusts longitudinal surface layer control just to suspension wire, after stickup Point absolute altitude is concordant with the suspension wire tensed;Said process is repeated between each characteristic cross-section until whole surveying and locatings are completed;
4)The detection of surface layer control point is checked.
2. the efficient setting out method in tunnel body for wind inner mold surface construction control point according to claim 1, it is characterised in that:Step 4) Middle sampling Detection is checked checks method detection vertical, horizontal surface layer control point absolute altitude using staggered cross, and the longitudinal surface layer set is surveyed after Suspension wire is tightened on the basis of control point and checks the horizontal surface layer control point absolute altitude first surveyed and set, edge or other position control points use steel Tape measure is directly checked.
3. the efficient setting out method in tunnel body for wind inner mold surface construction control point according to claim 1, it is characterised in that:The wind Hole body is that a series of type bodies combine the closed space grading structure constituted, and tunnel body for wind closed-loop path central axis is an imaginary axis Line.
4. the efficient setting out method in tunnel body for wind inner mold surface construction control point according to claim 3, it is characterised in that:Described one Series type body includes symmetrical octet, asymmetric octet, shuttle table type circular hole body, Fang Dongti, box-like body.
5. the efficient setting out method in tunnel body for wind inner mold surface construction control point according to claim 1, it is characterised in that:It is described outstanding Line suspension wire sag of chain in 6m length ranges is not more than 1.0mm.
6. the efficient setting out method in tunnel body for wind inner mold surface construction control point according to claim 1, it is characterised in that:It is described outstanding Line is fishing line.
7. the efficient setting out method in tunnel body for wind inner mold surface construction control point according to claim 6, it is characterised in that:It is described outstanding Line is No. 1.5 fishing lines or No. 2 fishing lines.
CN201710564429.7A 2017-07-12 2017-07-12 A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point Active CN107270881B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710564429.7A CN107270881B (en) 2017-07-12 2017-07-12 A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710564429.7A CN107270881B (en) 2017-07-12 2017-07-12 A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point

Publications (2)

Publication Number Publication Date
CN107270881A true CN107270881A (en) 2017-10-20
CN107270881B CN107270881B (en) 2019-07-05

Family

ID=60071959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710564429.7A Active CN107270881B (en) 2017-07-12 2017-07-12 A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point

Country Status (1)

Country Link
CN (1) CN107270881B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110646159A (en) * 2019-10-18 2020-01-03 中国建筑第八工程局有限公司 Construction method for high-precision control and measurement of cast-in-place bare concrete wind tunnel

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004351450A (en) * 2003-05-28 2004-12-16 Yaskawa Electric Corp Calibration device for laser beam machining head with rotary mechanism and method for using it
CN103486984A (en) * 2013-10-12 2014-01-01 中国人民解放军63926部队 Detection method for coaxiality of inner molded surface of wind tunnel
CN104899378A (en) * 2015-06-10 2015-09-09 上海大学 Digital installation method for high-rise steel structure based on BIM and three-dimensional measurement

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004351450A (en) * 2003-05-28 2004-12-16 Yaskawa Electric Corp Calibration device for laser beam machining head with rotary mechanism and method for using it
CN103486984A (en) * 2013-10-12 2014-01-01 中国人民解放军63926部队 Detection method for coaxiality of inner molded surface of wind tunnel
CN104899378A (en) * 2015-06-10 2015-09-09 上海大学 Digital installation method for high-rise steel structure based on BIM and three-dimensional measurement

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
张桃: "结冰风洞现场制作安装技术", 《安装》 *
张笈玮: "BIM 在异形薄壁混凝土风洞工程施工中的应用研究", 《施工技术》 *
李博平: "施工应用背景下混凝土风洞工程BIM模型创建研究", 《施工技术》 *
李博平: "风洞内型面顶面水磨石施工工艺与抗拉试验研究", 《施工技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110646159A (en) * 2019-10-18 2020-01-03 中国建筑第八工程局有限公司 Construction method for high-precision control and measurement of cast-in-place bare concrete wind tunnel

Also Published As

Publication number Publication date
CN107270881B (en) 2019-07-05

Similar Documents

Publication Publication Date Title
CN104792274B (en) A kind of measuring method of circular tunnel convergent deformation
CN106320707B (en) A kind of full projection line-putting method
CN104499714B (en) Hydromechanical installer engineering construction method based on BIM platforms and robot measurement
CN103806478B (en) A kind of measuring method of Deformation of Diaphragm Wall
CN103292748B (en) A kind of split of many substrates based on laser measurement detection method
CN107869249B (en) Arcuate structure high-formwork construction method
CN108871268B (en) Tunnel under-excavation numerical calculation method based on laser point cloud
CN103542820B (en) A kind of method detecting wind-tunnel inside surface flatness
CN103486984B (en) The detection method of profile right alignment in a kind of wind-tunnel
CN101957343B (en) Novel acoustic-emission ground-stress-field measuring technology based on plane stress condition
CN106638318A (en) Method for positioning anchor point of beam end of cable stayed bridge and installation method of cable guide pipe
CN102680942A (en) Blast furnace frame measuring positioning method based on total station
CN102966041A (en) Spatial stay-cable positioning method of multispan continuous S-shaped landscape bridge
CN102953552A (en) Method for positioning through hole of pipe truss
CN104848838A (en) Method for observing rock and soil sample shear band inclination angle evolution rules under two types of formation conditions
CN106289195A (en) The method for building up of plateau distance heavy construction Measurement and Control System
CN104674860B (en) Wire holing through survey method in seabed tunnel
CN111691691A (en) Method for installing, measuring and positioning box body bending and twisting component and drum node
CN107270881A (en) A kind of efficient setting out method in tunnel body for wind inner mold surface construction control point
CN103344214B (en) 1.6-degree parabolic extralarge pier measuring and pier body linear control method
CN106289125B (en) A kind of ship closes up greatly the measurement method of step simulations carrying
CN109649683A (en) A kind of radome test load(ing) point determines method
CN109580164B (en) Experimental device and method for influence of wind load on large-chassis double-tower structure
CN206459587U (en) A kind of survey tool
CN111337000B (en) Rotating curved surface building construction measurement lofting method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant